well test report january 3 - 18, 1980 · well test report january 3 - 18, 1980 ... to verify the...
TRANSCRIPT
HGP-A
HELLHEAD GENERATOR PROJECT
WELL TEST REPORT
JANUARY 3 - 18, 1980
Department of Energy Contract
DE-AC03-78ET28420
HGP-A JANUARY 3-18, 1980 vJELL TEST REPORT Engineering Group
University of Hawaii Hawaii Geothermal Project
I. Introduction
The HGP-A well at Puna, Hawaii underwent a two-week flow test in
January, 1980:
1) To verify the quantity of steam flow for a 3-MW power plant.
2) To verify the quantity of non-condensible gases and percentage
of H2S, which are critical in the design of condensers and H2S
abatement system.
3) To prove out the effectivenesses of the caustic/peroxide H2S
abatement system and the noise abatement system of the rock pit.
4) To check out the steam collection system which will be used in
the final power plant operating system.
The test is judged to be a success because it has accomplished most
of our objectives. The following summarizes the Engineering Group's effort
of the well test. Separate reports will cover the results of the
reservoi r fl ui d chemi stry. and H2S abatement experiments.
II. Responsibilities of the Hawaii Geothermal Project
The Hawaii Geothermal Project (HGP) staff was responsible for the
operation of the well test under the direction of the well test manager.
Figure 1 shO\oJs the organization of the \1ell test.
Specifically the Engineering Group of the HGP "'Jas responsible for:
A.. Providing a test supervisor and a test data recorder 24 hours
per day throughout' the test period. The test supervisor had
the overall responsibility of maintaining the operation of the
well test under the direction of the well test manager.
-2-
B. Maintaining a record of all well flow, pressure and temperature
data.
C. Maintaining a well test log including any complaints from the
residents.
D. Maintaining a chemical injection log including caustic dilution
records.
E. Checking the performance of the separator by steam calorimeter.
F. Implementing the safety plan.
G. Conducting downhole temperature and pressure measurements prior
to the well test and after the well test.
H. Monitoring the noise level to measure the effectiveness of the
rock pit muffler.
I I 1. Resul ts
A. Hell flow vs. wellhead pressure
Due to the incorrect sizing of the steam control valve, it was
not possible to control a steady flow much beyond 161 psig at the
separator, therefore we were not able to obtain meaningful data
beyond that point. Table 1 summarizes the well flow data vs. the
sepa rator pressure. Tab 1 e 2 is an abbrevi ated version of the \'Ie 11
flow data performed in 1977 duplicated here for comparison purposes.
In general, the wellhead pressure is approximately 10 to 15 psi
higher than the separator due to line loss and higher separator
elevation. Notice that the steam flow rate does not differ much
from the previous flow test but water flow rate is much higher.
This is due partially to the improper design of the weir measuring
methods employed in the previous test measurements.
-3-
The final plant design calls for approximately 160 psig at the
separator. The metered steam flow will adequately generate 3 MH
of electricity.
B. Calorimeter I
An Ellison U-Path Steam Calorimeter was used to check the
effectiveness of the separator by measuring the steam quality of the
separated steam. Due to the placement of the calorimeter, there was
a 10 ft. length of inlet pipe between the steam line and the
calorimeter, It was very difficult to insure adiabatic condition in
the inlet pipe even though the pipe was insulated.
Nevertheless, calorimeter measurements \'1ere attempted and no
better than 96% quality was consistently obtained. These data do
not match up to the results of the chemistry chloride method
employed by the HGP Chemi stry Group. Thei r measurements consistently
show very little chloride in the steam and showed better than 99.9%
steam quality. Thus, we feel that the separator is performing
adequately and the performance of 99.9% separation is satisfactory.
C. Chemical Injection Rates
Throughout the test, we were able to maintain very constant
peroxide injection rate but were unable to maintain very constant
caustic injection rate without constant adjustment. The caustic
metering pump and its air actuator must be repaired. A separate
report covers the results of the H2S abatement experiments.
D. Noi se
Sound level measurements were taken to test the efficiency of
the newly installed rock muffler system. The measurements were
taken at various stations around the well site, 1/2 mile up and
-4-
down the adjacent Pohoiki Bay Road and 1/2 mile up into the Leilani
Estates area. Initial measurements were obtained with the well
flashing through the twin stacks only. Later sound level measure
ments were obtained with the rock muffler in operation.
The muffler system consisted of an earthen pit upon which rocks
were placed. Steam from the H2S treatment system was discharged
into the pit. Some of the steam condensed in the earthen pit and
emptied into the percolation pond. The uncondensed steam rose up
through the rock pile and disbursed into the atmosphere.
The rock muffler proved to be an effective noise abatement system.
At many stations over 30% noise level reductions were. experienced.
Figure 2 is a diagram of the well site and indicates the stations at
which noise level readings were taken. Table 3 lists the noise level
measurements obtained at each station. As added information, noise
level readings of previous flashings are included in Table 3.
E. Temperature and Pressure Profiles
Prior to the start of the two week flow test at HGP-A in
January 1980, a temperature-pressure profile was taken where the
temperature profile showed high temperatures at 4300 and 6250 feet
in the order of 320°C. Th~ temperature and pressure plots are shown
in Figures 3 and 4. No other downhole tests were conducted during
the flow test until after the well was shut-in.
The HGP-A well was reworked in September, 1979 to restore the
casing cement competency. The original 9 5/811 casing was set from
the surface to ~2200 ft. below casing head flange. Before the
repair work the well temperature profile showed high temperatures
all the way up to ~1500 ft. During rework several attempts were
-5-
made to squeeze off zones around 2200 ft. and 1500 ft. The cement
bond logs showed only approximately 80% bond at best. Subsequently,
a new string of ]I' casing was run from surface to 3000 ft. The
temperature peaks at 1500 ft. and 2200 ft. on the temperature
profile prior to flashing reflect the zones where the conduction
of heat from outside of the casing exists.
Since the well shutdown, five temperature profiles have been
conducted. Two profiles taken immediately. after shutdown have shown
the flashing profile characteristics (semi-vertical straight-line),
while five days later, the temperature profile started to show
similarities to the preflash profile, The ten and thirty-one day
profiles display, in general, cooling in the upper sections and
heating in the lower sections. These plots are presented in Figure 3.
F. Water Level Recovery
Water level recovery after the two week flow test followed
similar patterns of other recoveries after production flow. This is
shown in Figure 5. Approximately twenty-three days after shutdown,
the water level was at ground level. This recovery was faster than
previous recoveries following production flows of similar time'
length. It is thought that the lengthening of the casing of HGP-A
to 3000 feet, thus closing the suspected cooler water influx, may
have increased the recovery rate.
G. Other Results
1. During the two-week test, Hawaii was hit by a severe storm and
the well site suffered numerous and long power outages. During
these periods, it was not always possible to chemically treat
the steam to remove hydrogen sulfide and to operate the equipment
-6-
in the normal noise suppression mode. The final power plant
must have adequate stand-by power for noise and odor suppression
in the event of power outages.
2. During these periods where noise and odor were not suppressed,
we received several complaints from the nearby residents.
However, after the power was restored and the normal test
operation with full odor and noise abatement resumed, no further
complaints were received,
3. During the two-week·test, several weaknesses in the instrumen
tation were discovered. These are:
a. Defective separator water level indicator and level
controller.
b. Continuous plugging of the venturi pressure sensing ports.
c. Defective badgemeters for mixing caustics.
d. Lack of weatherproofing of instruments and gages.
4. The maximum growth of the wellhead during flow is approximately
5 inches.
1 Mechanical
Data Recorder
1 Process
Engineer (Rogers)
J.T. Kuwada
TEST fi4.ANAGER
James T. Kuwada.
1 TEST SUPERVISOR
Bill Chen Paul Yuen
Deane .Kihara Art Seki
Process Engineer
(FMC)
Harry Castrantas
I Chemistry
Supervisor Don Thomas
Chemistry Data
Analyzers
.. Sampl e Takers Gas Analyzer Water Analyzer
Figurel
I Pi pe f'i tter E 1 ec t/ Ins t r .
Laborer
I "'-J I
• • FIGURE 2 DIAGRAM SHOWING STATIONS FOR NOISE LEVEL READINGS
33 0 (Property Line)
12 11 1
0 27 percolation 0 percolation
pond 26 pond
22 23
2 l,'l~ 1e: 10
21]29 31 '. 30
instrument shed
3 4
WIND DIRECTION
12/28/79 t 1/3/80 ./
10:00 - 10:30A 11 :00 - 11 :30A ./'
2:25 - 2:55P ~ 6:00 - 6:30P
10
'.of
sparger pit
5
9
11/3/76 1/26/77 1/7/80
t I::"" /
6
8
7.f-- about 100 ft. ~
I 00
(diagram is not to scale)· I
1000
2000
3000 .... w w u.. .. :J:.
li: 4000 w o·
5000
6000
-9-
100
Before Start-up • • 12/13/79
After Shut-in . o 0 1118180 8 A 1/18/80 E1 0 1/23/80 5 days after shut-in ",?---:t.l 1/28/80. 10 days after shut-in @---® 2/25/80 38 days after shut-in
"r", •
. ,' .
7000~------~--------~------~--------~------~--------~~-----
Figura 3
"
o 50
-10-
PRESSURE. kg/cm2 100 150
Ore--~--r-~--~--~--~---r---r---r--'---~--~--~--~--~--~~
1000
·2000
IIJJ IJJ lL.
...
3000
~ 4000 a...
·w o
5000
6000
o 012/13/79
Figure 4
... • KO~ SEMI-LOGARITHMIC.2 CYCLES X 70 DIVISIONS Foe 464972 .J l) KEUF"F"EL & ESSER CO. MACE 'N U.S .•.
t~ " l) 19ure 5 TIME (days) :::.. --'. - i'.) w (J'I en "'-I 00 '.0 0
i'.) W -I=> (J'I en "'-I 00 '.0 p. co
~:. <-> -: . :~I :. :::: :W~TER '~EVEL RECdVERV.:JTE~.h,!;~R .. !IF;J. AJ!.H~~~:fl!j.! ~~!,dltt-U-I.L!J&~r JM~;c~/~:a~ +r~:J~!:1 ~'77 :::: (4~ :·J~)s:rI .. : :.: .:. J ........ ...... . '1 .. ......... "'1 .. ):/!~': -r=·-I-~-h-h;·.!.li~·I'i.: L ." i·:·· ... 1.,: 6" .... (14· dl '. )1::1·· ·1· ""
-.---------... ---.- .. -.-... -.---- .--".--'-f------... ~. --- ,,--~-.. - ..... i ...... -. r' '''''. ",:' .:i: .... ..:: .... : .~: ; I .. "-~~. -lNovember. Tes t ... ,.g -f-_.. ays , __ ! .. _ .. _ ....... _
~ :=~-~: : .. : ::: :: ::::::. _:'-:.~~.i ,.i .. : :.:.i : q~ i i;: : .:; iiii U :lil ill! :::.! •. ::11 ::;:::!/:: ~ll·:=l=.I-i+tt±t tl.JG{3: ~'Dece~ber Test: 1976:: :i:.( 7 days ti.:. :: ... :: l:' ::::::: .: ':':: .. :l;~ ::l: :::: :il\ ;'1i::):' :1:: ::hl!!ii:::!::i!j:~I:i--ftlltL~~J00 -=rjan I;F'eb Te~;~:1977~ ~::: (lSdays)I:::;· .. ·:··:·· '00 ! ""!; oj I:;' \'11 , ',' Iltl .) ",;" I _~ ___ L! 1] ::r_~.. :' t -il_.-+-+--
. . .... !. ....... . ,::;:: I' 'f;' ::j: ll!l .. :.::;: ·il, ;:': ii:. ;.::: .. ;::: .. -~+- H~.~-I..i+-+!-!. .'. -·1- -: r .~, 'j'. . .... ( ' .. ~'-s)\l' 1--....... , ...... " .. : .1 ... ,., , •• : .:, ..... " .. ,·:i .... ,.1 .... ·"" .. · .. ·1::; - ,--1-- -I-l ... -".~ -:January est .. 1980 .... 14c y ...
. . "' ... ~......... ..~ .;.~.;- -·;-:··;··f· 1-1;; ;1·;· !;;. ":!"!';ji ·11!'!.!:::·":;;·'·"·i;;;· --~ .... l-t--1-J.4--~-~i;f.;l. '-r-" ~ ~ .... , ... , ... ····1·· , 1" ......... I ... , . -, . . ..i, , .. :,-,. Ii .;, r: ::!; :::. '''j .. i;li;, ,I:· ,:., ,I ... ::: 'i"\t,:,: - -1-1- 1-l-~";- +·..., .. 1 ! i··- _l_:_.; I . !,,-... :--d ... " ... -- .-- .... i" ,..., ..
--...... : : ::. : ',' : :::::;: ::~'i.' ·;:·ITt.t::j Fi! ! i;: ::;: ":1 ::;: ::~i :~~'i~: j: r '1::',:: =~t+-t+'~l t~+li::~ l;· ~~';"'~+ ~H:~T -i·~·;j :.i" ... -- ...... -:~r~ ~~t:·t--·-t----+·-,-......... ,.... .. .. j ..... , .••.. ,.\ '1 1 ' ", ........ , ....... , .. , ..... i .. •• .. ", ...... --TT-::t:r-t~ I·I·I·I--I·l'-!-·-· .... ·-, .. ·,··--· .. -·,",·", -'.. "1 ... 1 .. .
·1··'······ .. : .. '::'1; II: :;i. ,;1: ... ! :.: .. ,I .. ;: .. !.II!. :':";";.:! .. -!'j"HIU -- -1--- l·r:·I·,1·1·; .. 1..:'11.1 t' :.1- _L~~.: :::. .. ....... I....·,· . . ':! ' • I . 'I I I I,!' I:' " I I L I' I:, t 1 ! I! I ", I ' I
)00 I . . i .;:.: .... ; .! I· ,:.. ..: ' .. : .1'1: .',! il:·: .. jl •. ~ .. ::; -- i·++-L+ -;-""1;,,,-.\.:.: L ... ;_ '··r-i .. -i.L;':U-i'; ;;: .. ~ .................. , ........ ;" , .... , .... .. ......... ... , ... !.; :"j il,: :jl' 'J ,.! ":'i::.i1·,:lII,I;.:,;; .. ::: "+J-·--l-tj-L-Ji+;itt .. =tL .. I-I-d·-~~-t'" :j~ .. :;.; .::: .................. i. ...... : ... .
. ---- .. ::~::::: ::.:: :~:: :--·:·~t ~:+j.~~ .'Lq~:' tH~!·:r:. [1:1 Ii!' 1:11 ill! III! 1::[ !!:, ::!! !C·~L:. - 1',1 Tf J1++i'>l ~fH+ =~t~ fH:'~i-rf:1~~ :~::: ::::, ::::,::::(:: ::::i:'~L~~ ----.---- .• - ....... •••• .. ·- .. e~· .. • .. ~··-·J:-~·--W-"+~+· ·,..-t'··~·, .III ".,I!.!. 11""""'''1 11 ... ,-1.. .1 I I I!I·~-W-W--t-ri+·:-'-T-i--"· ---"j--' ·_ .. I ...... --!-.. -.. , ...... --.. -.---.. _" ..... -...... -" ... " -.: ..... ! . .1- ... :- -t·"I'--·H+1- .i-l ·t1 H,! HH Hi Hil ii.jlj ! rid Ifll'; :1'1111 il!;ili:iij~l. , "f-I II J :r:: ' r 1 :lHtJ±J+·ti!-~ i-H' +':'-:., .. _-. '~--I--" .... I ..... "'i ..... ;". --,,---- .... -...... - ..... --- ... ; .. -.... . •. - I .. ,. -:.. -r-t ... .J.. "I' -- .,.,. i 1"11 't·· ::1 j', i ,,' I'" I'.' :.,' j''' ,-". • - - ... - -' -I!' --+T -·1- -"-1+' --'1"1 I I" T T '11"; ~-.. , , .•..•. , -.. " ................... , .. " .. : .. . . _-- ....... - ......... ,-.-..;~.-..; ..• _i_._ ... · ._.J+ ..!-·HJ-·T I" '1·11 +IL: i.! Ii 11.1 ·11; ri;lij!,ld1h;.iL. - 1- I ~.+l- I-!-' -l-r"r-'~--- l+r~.i.-LL: .. :.";.!. .. ,: '· .. 1·:" .... 1 ..... j ..... : ... 300 " .: .' ! i I. 1~,1 rijl Ill,:, II I:: I.!I~:I nil!!::'!! I t I II: 1 !Ill it,; !::~ ;1 I' :.'
---- . ""-" ., ..... :.: ...... j~MJ N' ~i ~=t /---! 'II! i11 ,1 !I! li!lllil'II:, i il! Il:~ :11 11 il":I;,;I! ~ .. -- --j._-- - 1+ ··1·· .+ -+t..JH· -I++- $·!J!t+!iHf'W: :.,: ...... "I' ........ 1·· · .. -:-· .. ; .. ·.1 ~ ------.. -------...... _" ... :;. :-'---1' " .:-. '['lllr1, II:!' iil'l: lilil'li:iil'lq:r:-'W'-lll' .. ,'" 1- ·lr~·rtrn::··;-· .. ·; .. · .... · .. T .... : .. ·: .. --'
==~------~=~.:- ~~~~j:~~~~'~ ~I';~~~-=ttt&~; : t~.! .. ; I: ~-:~ bit+l,l:mljl:-rTI~ifl LI'!I.rll~Jll:I:~illll:;ltll:1 :11;;I:nI~II::!:i:I:'I;:I:irl!:;:I:;I~ ~Pb±-:' ;\" ' ': ,-' H· :+~ ':'~~i1h:~:~ ~·!I~: ~-:i"·-·::·::~·L --------.. - . :'--"~'T- :'j . '~~----1' ;J' , 1 !_. i I .• IT iii', II j I II j'l I '1'1'1'1'; 1""- ''''\' -. "'-1:-1 i I -l' I mtt-r; -;.:----.......... '-T" .... 1-.. ..
~---- -:----;-7--; ," "'7-........ ~ I':' : ,·tJ .; i' "', I r jt i I 111 Iii Ili l : I' i 1,'11 Ii' I-\ --f- I -'j-; ;'1";" :-::-' .. :' .. : ............ 1 .. "";"'" '''1 ~""""'~-+"'''-~T''1'h' ---r-T'T -- -i- -I TN r i' .: Ii' , 1',1- tIT -It, iii 11 I! <II ,I: .111'11; II It' 1-; I, 11' rrtt Til. ~I ._ .... -- .... -; ... '--'1''' .. r'J
600 , . .\.+.±!=t. 'I:} 1 , '1n:'I;":~"'Llillllilnl!'11'1I'11""I'ill'1111' ,,' , Irtt"iIIU' '" " I J : '=I -_.-:--' --~-'7,,-. '8' ~-. "1 t'1"T 'fill' i: i ',.,jll!1 i 11111:1 11'11! '.1] II II IX I! ,'1 -T-'l '!iT "'1' --;- .-- .... -.. - .... ·-'1" .... --1----.----,,- _._-:.J...'7 ..... ," - ~"+r -r1'1 i II ;';j' ~,li:I,'li, i i'III"'!'ill:':I':I'!' ---f·i"r\!.. -- , 1!1 '---;-.1 ·r ...... • r~, ._ .. -.. - .. ·T .. · .. '!" .. '''!'''' --;---'-' .. -.-.--..... "'---:--,;' '-li""'-- T;~Jj7 r 1 'J :! . ;! i· . 'I" ;,1; II ' i' I ". 'iii ;"; :ii'I;\; --,TI ~". - -I I-t- in...! t· n' : ; .... i ~: .... : ........ , ........ ;... .... . ;.-i---.--.. ~. - -'-:-Ti7TF ,TTTTj- Tl-if -1 i j ~4t+ _ ..... _~ ~lllillll: ::1: :\' 'in!!il' =tt II - H' Ii. "itT in-: ·r;. ---;-...... ;-- .. J .... '''T'' ''''1'=
!~---.--;-.. ; 4 1 ; rH- ..lJ~. -d-r-tt-l--!- r~·f.~~J. ·~fHI·~al~il&.' :!, f1l11 ·~q:'r:1%!illll:I!Jllljllllllillll· ~+ I ~ i; ~i++h4t .~ .,.:; 7"- ~" ·-+ ...... ·1 .. - .+--I--. __ ...!_-' -=- :.~rrp ---+---"~- -~++ f: ~ - 't' r.tl 11 i L'I" Nilil: ., ql:L)i~r ,i'll il!! 1!!~:1.' ·tI-~~ =H II :L.lJ -L..0' ~-T~t :2:':::: ~:: ::: ::::1:::' :::. :::: :::['
400 -----r-'if'C" ~"-,- OIl ~ t: I ;ji i ,:,: H:' I' ij(~~"':'f~i':ii ~! , ~ eC ~'H n .L~ft' : I ,:: ::, : ~ '~T7 :irLr~ c!,e e+ _~='~:'=~~-:~~~el ~~~~ ~: ~T:~ rn jJlj ItiHl:; I~#.i.!~i. !:!1
i l:m:;!liilif!'jl~! ~d~I"IIIII~.~)f~,·::j::·r~t~'l)s~lil!~T; 'e re:i;;:lj #h~f8~;: ~~ ~~ .#ti,ffi'~f! :::';~l .~:llij: ;i,'~·t= , , -.. 1H .. ']l@ " d. + hI· . I I I I I T1 ..... ' r'" ~~ , -.. ,_. -_.!- "'r
..;....:...J.....J I ! , _1._, I I I I! I! I I J". + . r I' '!'r 1 i 1.11 I:; i iild .. , I' UZ. -, . ~ll" .Lllii·l+h-' ·~+l ,S ;41'- .:...IC, .. ..:,~ ___ tj "!~:~ 1\1~!·1 1,1 j II, ,11:',;IJ11 I,., ~~ Ill.' _1'(·l,I.LLrrrI.!:'!I"j I -------... -- ......... -- •• -----.- -- ----.-•.. :-. T"', " ,. " L ". '."', ""1" .. ~. '. 0 .'C±!~. ,,' "t· 1 ,. - f-... - "T"--X--:- -rrr -l-'rr ... , .. -, ... -" ......... - .... "-I''' ....... - . '1"-------.-.-. - .. --.-- ..... _-:--+-_. i--:-[· +'-i'+ IT ! i'~f !Ii ;'jI :.;: i',· ;i;; :.:::: ; .. : ... j . 0 i ~~.! IT' t\, -j--:"-H· '-i ,- .~,.t+ t-Lh- ._1.;_ :.;.!~ .-.:.. -... ,,-- .. - .. --,,, ...... ;.- ... ,-
200 . ,.: ' ... : ,;t;·I,:,':il·. ,i·.i":f'!t·~:·'i"-:'-;-· '-'~' ".', : 'r;* i'j T'~:' .'. ': :. .. . -.-.. ------- ..... ! ............ -.-.--~ .. I---t·t;· l~ll iI' +t Jlt'l 'll·j .il l :':i iii: :iJ! '::'11':: ,;;; ;." '1: '1 ", i . 0 I~':: Ii -'--t;+r Tree' ·~H "c· ·"m·~ c: ............ ··T -, .... ~ ----.-----~.-.~. ~ t· ~ ..• ---... ......: -~-:·---i- -:-t-r-r I j I ttl' 1 t prj Ihllit! II!! !Itl di. d: :I'!I:i:l!1';i; --1-: 1 l • I'll -- rt1 11-11--, '71 -T1T~ "-rT: lrr -~t~"7' ''''j_.r. ···'t'· -;'·"1'·;-"---j- .. ---,. -'-.. -.-,- -'-t-;-t -1ft· 'if 11d :-It! IIi' ,I!! ;!:: ,P! i!t; Hi' 1.1:
1:' r· ',': ! -r -:. 1 0
0 ~- T ";-1 ~ .. -- .' ~~ .. ,'" - ........ -- ..... " .. :. 'm""" .. -.. ~ ... -.- : : :(~.~~: :.: ~.~:=-:~:. ';Ti-:' ~~j: r11;: ~~;. ;;i;l~~ ~jii iifij:;:b: )'i:'::';;I;~ -l"~ .. i:+·jn! I: . i. i'· " '~~~-~'!':"~=~~-~~~f~7~~ ::-~~f:. ~~ .. : .. ; ... :.;.:.i .. ;.~
• n I· ................ ---..... -+--[.;.. ·-1--'-."1" "'111., ., "-1 '\1'1 "'1'111. 01 • 1"1'1'1' "'illli'" i'j'I'!]' ii,' Hi""l-'''I--l--'''J'''t'''' .. · .. 1' "~-r'''FI-~'T'r;' I,~~:r.\'.""~' .... "." .... \.-. "''1''-".;-.. :::..... ;. ";'c"I- ;-~ +i-h-til'ti rtJ \'111 HI liP !iiI! j 1111II1I Ill: I!li'li',il1i: i;!II!11 ·.~-·t· ./.++ . ·il il!! i I:!; . . ~J.. .. ·1·-I--h+·1.1·:r!··j I, ~p"J,I.':. : .... ',. "~l'''T' +". I" ... j" .. - .. -- , ...... i'" "'-'j'" .,. ·+ .... r .. · .1 .... ,.·1 h "'1 ., '1'/ lilli" "I III 'II' "1 11 ""Ililio>' .... ~- --i' .. -~-i. - ·'·I·I-r·tl·· I'; .... • .. , .. .,.~ M'" - .-r--. . '-r'" 'P" .... , .. " ., .. "" ""r'''T'' I ........ -. o :. '; ! 1 ! I I I I lill : It.lil ,II J il II !J:!i I ,I ",JI)!,l . .J I ~_ '- '" w.....L.i..l!1 ~ I :l-'-:t.> II.! 1.11 I;ii "'; it,· ;! .. ~l' ,
- ..... ~: DAYS
, '.
-12-
Table I Throttled Flow Data 1/3/80-1/18/80
Separator Total Mass Steam Flow Water Flow . Steam Pressure Flow Rate Rate Rate Quality (PSIG) (Klb/hr) (Klb/hr) (Klb/hr) (% )
56 111 .5 70.9 40.6 63.6
110 110.3 64.7 45.6 58.7
132 108.0 61.0 47.0 56.5
'161 105.9 56.6 49.3 53.4
Table 2 Throttled Flow Data 1/26/77-2/10/77
Wellhead Total Mass Steam Flow Water Flow Steam Pressure Flow Rate Rate Rate Qual ity (PSIG) (KlbLhr) (Klb/hr) (Klb/hr) (%)
\. '
54 99 65 34 66
100 93 57 36 64
165 89 54 35 60
-t
-13- .
TABLE 3
NOISE LEVEL READINGS ON DBA SCALE
STATION NO ABATEr.1ENT PARTIAL ABATEMENT PREVIOUS FLASHING ABATEr~ENT
12/28/79 1/3/80 1/3/80 11/3/76 1/26/77 1/7/80 10:00-10:30A 11 :00-11 :30A 2:25-2:551' 6:00-6:30P
1 93 91 94 75 73 100 96 57 2 99 100 99-100 82 78 104 100 66 3 84 83 82 65 75 98 93 51 4 7r:; -- 84-85 70 70 98 96 64 ,oJ
5 86 -- -- -- -- 97 -- --6 79 -- 76 64 63 98 89 50 7 88 -- 82 67 64 96 90 52 8 75 83 78 63 80 98 91 46 9 82 -- 76-78 67 67 99 93 52
10 81 -- 91 71 80 98 94 57 11 86 -- -- -- -- 99 96 --12 88 -- -- -- -- 100 90 --13 100 -- 100 . 84 82 107 100 69
14 101 -- 102 85 83 110 103 60 .. 15 98 96 98-99 81 79 107 100 56
16 100 98/99 103 -- -- 106 102 --17 102 100 103 83 82 104 101 71
18 102 -- -- 84 80 110 103 68
19 104 -- -- -- -- 110 101 --20 99 -- -- -- -- -- -- --21 98 94 -- -- -- 103 99 -- .
22 98 -- 96 82 80 104 98 67
23 93 92 73 71 100 94 63 , -- , . 24 91 94 94 76 75 99 95 69
25 97 -- 99 82 80 106 95 74
26 94 -- 94 74 73 106 93 58
27 93 -- -- -- -- 100 96 --28 97 -- 96 81 -- 106 100 68
29 98 97 97 80 -- 110 102 70
30 96 92 83 77 -- 96 91 72
31 94 -- 93-94 75 -- 108 101 66
. 32 79 83 83 60-62 -- 87 80 44
33 -- 94-95 94 73 -- -- -- 56
34 -- 41-42 42 41 -. ~~ ~. 37
35 -- 50 48 40 .- -- -- 34
36 -- 40-42 38 36 -- ~- -. 42