week 12 mrp july

Upload: abidah-zulkifli

Post on 14-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/27/2019 Week 12 MRP July

    1/44

    Outcome 4:Use software-generated information to make decisions at

    operational, tactical and strategic levels in an organization.

    Assessment Criteria:4.3 Prepare a spreadsheetto enable material

    requirements planning and calculate economic order

    quantities.

  • 7/27/2019 Week 12 MRP July

    2/44

    Manufacturing

    computer information

    system

    Determines quantity &

    timing of dependent

    demand items

    1 2 3 4 5

    Gross Requirements 2 20 25 15

    Scheduled Receipts 5 30

    Available 25 23 33 33 8

    Net Requirements 7

    Planned Order Receipts 7

    Planned Order Releases 7

  • 7/27/2019 Week 12 MRP July

    3/44

    Demand for one item is related to the demand for

    another item.

    Consider Ford Explorer:

    Fords demand for auto tires and radiators depend on

    the production of Explorer.

    o 4 tires and 1 radiator go into each finished Explorer.

  • 7/27/2019 Week 12 MRP July

    4/44

    Computer system

    Mainly discrete products

    Accurate bill-of-material

    Accurate inventory status

    99% inventory accuracy

    Stable lead times

  • 7/27/2019 Week 12 MRP July

    5/44

    Increased customer satisfaction due to meeting

    delivery schedules

    Faster response to market changes

    Improved labor & equipment utilization

    Better inventory planning & scheduling

    Reduced inventory levels without reduced customerservice

  • 7/27/2019 Week 12 MRP July

    6/44

    1. Master Production Schedule (MPS)

    2. Bills of Materials (BOM)

    3. Accurate Inventory Records

    4. Purchase Orders Outstanding

    5. Lead Times for Each Component

  • 7/27/2019 Week 12 MRP July

    7/44

    Specifies WHAT(No. of finished product or item) is tobe made and WHEN

    Must accordance with aproduction planwhich: sets the overall level of output in broad terms

    MPS tells what is required to satisfy demand and meet the

    production plan

    Establishes what items to make and when, in terms

    of specific products.

    Reasonable length of time time takes to produce a

    product.

  • 7/27/2019 Week 12 MRP July

    8/44

    Aggregate

    Production Plan

    Execute capacity plans

    Material Requirements

    Plan (MRP)

    Marketing:

    Customer DemandFinance:

    Cash flow

    Engineering:

    Design completion

    Human Resources:

    Manpower planning

    Production:

    Capacity Inventory

    Management:

    Return on Investment

    Capital

    Procurement:

    Supplier performance

    Master

    Production

    Schedule (MPS)

    Changeproductionplan?

  • 7/27/2019 Week 12 MRP July

    9/44

    1,2001,500

    Aggregate Production Plan(shows the total quantity ofamplifiers

    10030075 watt amplifier

    450450500500150 watt amplifier

    100100100100240 watt amplifier

    Master ProductionSchedule (Shows thespecific type and quantity ofamplifier to be produced

    87654321Weeks

    FebruaryJanuaryMonths

  • 7/27/2019 Week 12 MRP July

    10/44

    Make to Order

    (Process Focus)

    Assemble toOrder or

    Forecast

    (Repetitive)

    Stock to Forecast

    (Product Focus)

    Schedule finished

    product

    Steel, Beer,Bread Lightbulbs, Paper

    Print shopMachine shop

    Fine dining restaurant

    Examples:

    Number of end

    items

    Number of

    inputs

    Typical focus of the

    master production

    schedule Scheduleorders

    Schedule

    modules

    Motorcycles, autos,

    TVs, fast-food

    restaurant

  • 7/27/2019 Week 12 MRP July

    11/44

    List of the raw materials, sub-assemblies, intermediate

    assemblies, sub-components, components, parts and the

    quantities of each needed to manufacture an end product dovary somewhat in scope

    E.g: recipe for cake, specifying ingredients and

    quantities/amount, full set of drawings for an ambulance

  • 7/27/2019 Week 12 MRP July

    12/44

    Provides product structure (tree)

    Parents: Items above given level

    Children: Items below given level

    Shows low-level coding

    Lowest level in structure item occurs

    Top level is 0; next level is 1 etc.

  • 7/27/2019 Week 12 MRP July

    13/44

    Speaker Kits, Inc., packages high-fidelity components for mail order.

    Components for the top-of-the-line speaker kit, AiWA II (A),

    include 2 standard 12-inch speaker kits (Bs) and 3 standard 12-inch

    speaker kits with amp-booster (Cs).

    Each B consists of two 12-inch speakers (Ds) and 2 shipping boxeseach with an installation kit (E). Each of the three speaker kits with

    amp-booster kits (Cs) has 2 speaker boosters (Fs) and 2 installation

    kits (Es). Each speaker booster (F) includes two 12-inch speakers

    (Ds) and 1 amp-booster (G). The total for each AiWA II is 4 standard

    12-inch speakers and twelve 12-inch speakers with the amp-booster

    (Gs).

    As we can see, the demand for B, C, D, E, F and G is completely

    dependent on the master production schedule for A the AiWA II

    speaker kits.

  • 7/27/2019 Week 12 MRP July

    14/44

    A

    B(2) Std 12 Speaker kit C(3) Std 12 Speaker kitw/ amp-booster

    F(2)Std 12 Speaker booster

    assembly

    E(2)E(2)

    Packing box of

    installation kit of wire,

    bolts and screwsG(1)

    amp-booster

    D(2)12 speaker

    D(2)12 speaker

    Level

    0

    1

    2

    3

  • 7/27/2019 Week 12 MRP July

    15/44

    Product structure (tree) for AiWA II Speaker Kit shows

    four levels : 0, 1, 2, 3

    four parents: A, B, C, F - has at least one level below B, C, D, E, F, G are components (children) has at least

    one level above

    B, C, F are both parent and component (children)

    Number in parentheses ( ) no.of units needed to

    make the item immediately above it.

  • 7/27/2019 Week 12 MRP July

    16/44

    Determine the number of units of each item required to

    satisfy demand for a new order of 50 AiWA II speaker

    kits.

    Part A = 50 units Part B = 2 x number of As = 2 (50) = 100

    Part C = 3 x number of As = 3 (50) = 150

    Part D = 2 x number of Bs + 2 x number of Fs

    = 2 (100) + 2 (300) = 800

  • 7/27/2019 Week 12 MRP July

    17/44

    Firm should achieved at least 99% record accurate

    Should exist as a by-product of well-managed

    purchasing and inventory-control department

    Good purchasing data (purchase data execute, recordsof those orders and scheduled delivery dates available)

    good production plans effective MRP system.

  • 7/27/2019 Week 12 MRP July

    18/44

    Time required to acquire (purchase, produce or

    assemble)

    Example 3: Lead times for AiwA II Speaker

    Component Lead Time

    A 1 week

    B 2 weeks

    C 1 week

    D 1 week

    Component Lead Time

    E 2 weeks

    F 3 weeks

    G 2 weeks

  • 7/27/2019 Week 12 MRP July

    19/44

    1 2 3 4 5 6 7 8

    A

    B

    C

    D

    E

    E

    F

    G

    D

    2 weeks to

    produced

    1 week

    2 weeks

    1 week2 weeks

    2 weeks

    3 weeks

    1 week

    1 week

    Start production of

    D

    Must have D and Ecompleted here so

    production can begin on B

  • 7/27/2019 Week 12 MRP July

    20/44

    Outcome 4:

    Use software-generated information to make decisions at

    operational, tactical and strategic levels in an organization.

    Assessment Criteria:

    4.3 Prepare a spreadsheet to enable material

    requirements planning and calculate economic orderquantities.

  • 7/27/2019 Week 12 MRP July

    21/44

    Aggregate Production Plan

    Master ProductionSchedule

    Material Requirement Plan

    Set due dates for theavailability of end items NOT

    when end item will be

    manufactured

    Bill of Material(Product

    Structure Tree)

    Lead time

    Inventory level

  • 7/27/2019 Week 12 MRP July

    22/44

    WEEK LEAD TIME

    1 2 3 4 5 6 7 8

    A. Required date

    Order released date1 week

    B. Required date

    Order released date 2 weeks

    C. Required date

    Order released date1 week

    E. Required date

    Order released date2 weeks

    F. Required dateOrder released date

    3 weeks

    D. Required date

    Order released date1 week

    G. Required date

    Order released date2 weeks

    50

    100

    300

    50

    150

    200

    300

    600

    100

    150

    300200

    300

    600

    200

    200

    300

    300

    = Lead Time BOM Lead Time

  • 7/27/2019 Week 12 MRP July

    23/44

    Example 4 : Gross MRP

    - assumes that there is no inventory on hand

    If there is inventory on hand

    net requirement plan include:

    i. gross requirement ii. on-hand inventory

    ii. net requirements

    iv. planned order receipt (quantity planned to be

    received at a future date)

    v. planned order release (schedule date for an order to

    be released)

  • 7/27/2019 Week 12 MRP July

    24/44

    ITEM ON HAND

    A

    B

    C

    D

    EF

    G

    10

    15

    20

    10

    105

    0

    Constructing a netrequirements plan is similar to

    constructing a GRP.

    Stating with item A - workbackward to determine net

    requirements for all item.

  • 7/27/2019 Week 12 MRP July

    25/44

    LotSize

    LeadTime

    (weeks)

    OnHand

    SafetyStock

    Allo-cated

    Low-level

    Code

    ItemIdenti-

    fication

    Week1 2 3 4 5 6 7 8

    Gross Requirements

    Schedule Receipts

    Project On

    Hand

    Net RequirementPlanned Order

    Receipts

    Planned Order

    Releases

    Refer to product structure, on-hand inventory, and lead times.i. ITEM A:Gross requirement = 50 units (at week 8), item on-hand = 10 units

    net requirement & planned order receipt

    = 50 10 = 40 units (at week 8)

    Lead times = 1 week, so planned order release = week 7 (40 units)

  • 7/27/2019 Week 12 MRP July

    26/44

    LotSize

    LeadTime

    (weeks)

    OnHand

    SafetyStock

    Allo-cated

    Low-level

    Code

    ItemIdenti-

    fication

    Week1 2 3 4 5 6 7 8

    Gross

    Requirements

    Schedule Receipts

    Project OnHand

    Net Requirement

    Planned Order

    Receipts

    Planned Order

    Releases

    Lot-

    for-

    lot

    1 10 - - 0 A 50

    101010101010101010

    40

    40

    40

    Lead Time

    of 1 week

    B C

  • 7/27/2019 Week 12 MRP July

    27/44

    ii. ITEM B:Gross requirement = 100 units (week 7) - BA

    item on-hand = 15 units

    ** Requirement for item B depends on the net requirement of

    A:net requirement for A = 40

    Requirement for BA= 2(40) = 80 (at week 7)

    net requirement & planned order receipts for BA

    = 80 15 = 65 (at week 7)

    Lead times = 2 week, so planned order release

    = 65 (week 5)

    PT TP

  • 7/27/2019 Week 12 MRP July

    28/44

    LotSize

    LeadTime

    (weeks)

    OnHand

    SafetyStock

    Allo-cated

    Low-level

    Code

    ItemIdenti-

    fication

    Week1 2 3 4 5 6 7 8

    Gross

    Requirements

    Schedule Receipts

    Project OnHand

    Net Requirement

    Planned Order

    Receipts

    Planned Order

    Releases

    Lot-

    for-

    lot

    2 15 - - 1 B 80

    1515151515151515

    65

    65

    65

    Lead Time

    of 2 weeks

    E D

  • 7/27/2019 Week 12 MRP July

    29/44

    iii. ITEM C:Gross requirement = 150 units (week 7) - CA

    item on-hand = 20 units

    ** Requirement for item C depends on the net requirement of

    A:net requirement for A = 40

    Requirement for CA= 3(40) = 120 (at week 7)

    net requirement & planned order receipts for CA

    = 120 20 = 100 (at week 7)

    Lead times = 1 week, so planned order release

    = 100 (week 6)

  • 7/27/2019 Week 12 MRP July

    30/44

    LotSize

    Lead

    Time

    (weeks)

    OnHand

    SafetyStock

    Allo-cated

    Low-

    level

    Code

    Item

    Identi-

    fication

    Week1 2 3 4 5 6 7 8

    Gross

    Requirements

    Schedule Receipts

    Project OnHand

    Net Requirement

    Planned Order

    Receipts

    Planned Order

    Releases

    Lot-

    for-

    lot

    1 20 - - 1 C 120

    2020202020202020

    100

    100

    100

    Lead Time

    of 1 week

    E F

  • 7/27/2019 Week 12 MRP July

    31/44

  • 7/27/2019 Week 12 MRP July

    32/44

    ITEM E:Gross requirement = 300 units (week 6) - Ec

    ** Requirement for item E is also depends on the net

    requirement of C:net requirement for C = 100

    Requirement for EC = 2(100) = 200 (at week 6)

    net requirement & planned order receipts for EC

    = 200 (**no more on-hand inventory for item E, after been

    used for B)

    Lead times = 2 weeks, so planned order release

    = 200 (week 4)

    Net E

  • 7/27/2019 Week 12 MRP July

    33/44

  • 7/27/2019 Week 12 MRP July

    34/44

    v. ITEM F:Gross requirement = 300 units (week 6) - FC

    item on-hand = 5 units

    ** Requirement for item F depends on the net requirement of

    C:net requirement for C = 100

    Requirement for FC= 2(100) = 200 (at week 6)

    net requirement & planned order receipts for FC

    = 200 5 = 195 (at week 6)

    Lead times = 3 week, so planned order release

    = 195 (week 3)

  • 7/27/2019 Week 12 MRP July

    35/44

    LotSize

    Lead

    Time

    (weeks)

    OnHand

    SafetyStock

    Allo-cated

    Low-

    level

    Code

    Item

    Identi-

    fication

    Week1 2 3 4 5 6 7 8

    Gross

    Requirements

    Schedule

    Receipts

    Project On

    Hand

    Net Requirement

    Planned Order

    Receipts

    Planned OrderReleases

    Lot-

    for-

    lot

    3 5 - - 2 F 200C

    555555

    195

    195

    195

    5

    Lead Time

    of 3 weeks

    D G

  • 7/27/2019 Week 12 MRP July

    36/44

    vi. ITEM D:Gross requirement = 600 units (week 5) - DF

    = 200 units (week 6) - DB

    item on-hand = 10 units

    ** Requirement for item D depends on the netrequirement of F:

    net requirement for F = 195

    Requirement for DF = 2(195) = 390 (at week 3)

    net requirement & planned order receipts for DF

    = 390 - 10= 380 (at week 3)

    Lead times = 1 weeks, so planned order release

    = 380 (week 2)Net D

  • 7/27/2019 Week 12 MRP July

    37/44

    ITEM D:Gross requirement = 200 units (week 6) - DB

    item on-hand = 10 units

    ** Requirement for item D is also depends on the net

    requirement of B:

    net requirement for B = 65

    Requirement for DB = 2(65) = 130 (at week 5)

    net requirement & planned order receipts for DB

    = 130 (**no more on-hand inventory for item D - after been

    used for F)

    Lead times = 1 weeks, so planned order release

    = 130 (week 4)Net D

  • 7/27/2019 Week 12 MRP July

    38/44

  • 7/27/2019 Week 12 MRP July

    39/44

  • 7/27/2019 Week 12 MRP July

    40/44

    LotSize

    Lead

    Time

    (weeks)

    OnHand

    SafetyStock

    Allo-cated

    Low-

    level

    Code

    Item

    Identi-

    fication

    Week1 2 3 4 5 6 7 8

    Gross

    Requirements

    Schedule

    Receipts

    Project On

    Hand

    Net Requirement

    Planned Order

    Receipts

    Planned OrderReleases

    Lot-

    for-

    lot

    2 0 - - 3 G 195F

    0000

    195

    195

    195

    Lead Time

    of 2 weeks

    Complete MRP

    http://localhost/var/www/apps/conversion/tmp/examples%20excel/MRPtemplate.xlsxhttp://localhost/var/www/apps/conversion/tmp/examples%20excel/MRPtemplate.xlsx
  • 7/27/2019 Week 12 MRP July

    41/44

    Assessment Criteria:

    4.3 Prepare a spreadsheetto enable material

    requirements planningand calculate economic order

    quantities.

  • 7/27/2019 Week 12 MRP July

    42/44

    BOM

    Lead Times

    (Item Master File)

    Inventory Data

    Purchasing data

    Master Production

    Schedule

    MRP

    planning

    programs

    (computer

    and

    software)

    MRP by Period Report

    MRP by date report

    Planned order report

    Purchase advice

    Exception report

  • 7/27/2019 Week 12 MRP July

    43/44

    A BOM AiWAIILead

    Time1 Lot Size

    Minimum

    quantity

    Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8

    Gross Requirements 50

    Schedule Receipts

    Project OnHand

    10 10 10 10 10 10 10 10 10

    Net Requirement 40

    Planned Order Receipts 40

    Planned Order Releases 40

  • 7/27/2019 Week 12 MRP July

    44/44

    A BOM AiWAIILead

    Time1 Lot Size

    Minimum

    quantity

    Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8

    Gross Requirements=BOM!$G

    $7

    Schedule Receipts

    Project OnHand =BOM!$

    E$7=BOM!$E

    $7

    =BOM!$E

    $7

    =BOM!$E

    $7

    =BOM!$E

    $7

    =BOM!$E

    $7

    =BOM!$E

    $7

    =BOM!$E

    $7

    =BOM!$E

    $7

    Net Requirement=$L$7-

    $L$9

    Planned Order Receipts =$L$10

    Planned Order Releases =$L$11

    AiWAII Speaker Kit - MRP Excel

    http://localhost/var/www/apps/conversion/tmp/examples%20excel/MRP.xlsxhttp://localhost/var/www/apps/conversion/tmp/examples%20excel/MRP.xlsx