Belize Municipal Development Project (P111928) Mid-term Review Mission – June 10 – 14, 2013 Aide Memoire I. Introduction 1. A World Bank team led by Yoonhee Kim (Team Leader and Sr. Urban Economist) and comprised of Maritza Rodriguez (Sr. Financial Management Specialist), Noreen Beg (Sr. Environmental Safeguards Specialist), Yingwei Wu (Sr. Procurement Specialist), Kimberly Vilar (Social Development Specialist), Anna Okola (Transport Specialist) and Keren Charles (Operations Analyst Consultant) undertook the Mid- term Review (MTR) Mission of the Project from June 10 – 14, 2013. 2. The mission team held discussions with Ms. Yvonne Hyde (CEO, Ministry of Finance and Economic Development), Ms. Candelaria Morter (CEO, Local Government), Mr. Eugene Palacio (Director, Local Government), Mr. Errol Gentle (CEO, Ministry of Works and Transport), Mr. Lawrence Sylvester (CEO, Ministry of Housing and Urban Development) Ms. Beverly Castillo (CEO, Ministry of Natural Resources and Agriculture, MNRA) and Ms. Gina Young (MNRA), the Mayors and Town Council representatives of Belmopan, Benque Viejo del Carmen, Corozal, Dangriga, Orange Walk, Punta Gorda, and Santa Elena/San Ignacio, as well as Daniel Cano (Executive Director, Belize Social Investment Fund, SIF) and the Project Implementation Unit (PIU). 3. The mission carried out site visits for Phase 1 and Phase 2 works in all seven Town Councils as part of the Mid-term Review Mission. The mission expresses appreciation for the kind support extended to the Bank team during the mission (a detailed list of people met is provided in Annex 2). A wrap-up meeting was held with the Project Steering Committee (PSC) to discuss the key findings of the mission. In particular, the mission focused on reflecting lessons learnt and experiences from the Project’s implementation up to date and the completion of the Phase 1 program. 4. This aide-memoire summarizes the findings, recommendations and agreements reached during the mission and it is subject to confirmation by World Bank management. The aide-memoire will be publicly disclosed once finalized. 1

Upload: others

Post on 22-Mar-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Belize Municipal Development Project (P111928)Mid-term Review Mission – June 10 – 14, 2013

Aide Memoire

I. Introduction

1. A World Bank team led by Yoonhee Kim (Team Leader and Sr. Urban Economist) and comprised of Maritza Rodriguez (Sr. Financial Management Specialist), Noreen Beg (Sr. Environmental Safeguards Specialist), Yingwei Wu (Sr. Procurement Specialist), Kimberly Vilar (Social Development Specialist), Anna Okola (Transport Specialist) and Keren Charles (Operations Analyst Consultant) undertook the Mid-term Review (MTR) Mission of the Project from June 10 – 14, 2013.

2. The mission team held discussions with Ms. Yvonne Hyde (CEO, Ministry of Finance and Economic Development), Ms. Candelaria Morter (CEO, Local Government), Mr. Eugene Palacio (Director, Local Government), Mr. Errol Gentle (CEO, Ministry of Works and Transport), Mr. Lawrence Sylvester (CEO, Ministry of Housing and Urban Development) Ms. Beverly Castillo (CEO, Ministry of Natural Resources and Agriculture, MNRA) and Ms. Gina Young (MNRA), the Mayors and Town Council representatives of Belmopan, Benque Viejo del Carmen, Corozal, Dangriga, Orange Walk, Punta Gorda, and Santa Elena/San Ignacio, as well as Daniel Cano (Executive Director, Belize Social Investment Fund, SIF) and the Project Implementation Unit (PIU).

3. The mission carried out site visits for Phase 1 and Phase 2 works in all seven Town Councils as part of the Mid-term Review Mission. The mission expresses appreciation for the kind support extended to the Bank team during the mission (a detailed list of people met is provided in Annex 2). A wrap-up meeting was held with the Project Steering Committee (PSC) to discuss the key findings of the mission. In particular, the mission focused on reflecting lessons learnt and experiences from the Project’s implementation up to date and the completion of the Phase 1 program.

4. This aide-memoire summarizes the findings, recommendations and agreements reached during the mission and it is subject to confirmation by World Bank management. The aide-memoire will be publicly disclosed once finalized.

5. Key Project Data and Performance Rating

Key Project Data Key Performance RatingPrevious Current

Board Approval Date

September 16, 2010

Progress towards achievement of Project Development Objectives

Satisfactory Satisfactory

Effectiveness Date

January 25, 2011

Overall Implementation Progress

Moderately Satisfactory

Satisfactory

Closing Date November 30, 2015

Disbursed US$ 2.6 million US$ 4.7 million

Loan Amount US$ 15 million % Disbursed 17% 31%

II. Implementation Status Overview

6. As of May 31, 2013, the Project has disbursed about US$ 4.7 million, equivalent to approximately 31% of the loan amount. Since the last supervision mission in December 2013, the PIU has disbursed

1

Page 2: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

US$ 2.1 million. Another US$ 2.2 million (including US$ 0.46 million operating cost) has been committed for the implementation of Phase 1 sub-Projects, consisting of 50% of the total loan.

III. Key Findings from Mid-Term Review Mission

7. Main Achievement of the Project up to date: The mission was pleased to note the following achievement up to date.

a. The project is well underway to achieve its development objective (to improve access to basic municipal infrastructure and to enhance municipal management in selected town and city councils of Belize).

b. The project has completed all Phase 1 investment (except Dangriga market sub-component), resulting in the rehabilitation of 19 streets (some 7.3 km) and refurbishment of the Punta Gorda Town Hall

c. Mobilization and implementation of five TA components: Revenue Enhancement, Financial Management, Asset Management and Maintenance Plan, Urban Development Plan, Communication Strategy, and Road Safety and Public Awareness. The TA programs have begun to demonstrate tangible results and benefits to enhance TCC’s capacity for municipal management. Some examples include: a) color coded land use maps was developed for the seven (7) municipalities under the BMDP to assist with the consultancy to prepare the municipal development plans; b) diagnostic report on the performance of their revenue sources including a comparative analysis of the performance and administration of revenue sources including property tax and trade license fees; and c) the participation of Mayors, Deputy Mayors and Administrators of all TCCs in a two-day peer sharing workshop on Best Practices for revenue collection and management, among others.

d. Phase 2 preparation is well underway according to the implementation plan including meeting the requirements of the second phase eligibility criteria and counterpart contribution

e. Enhanced project implementation capacity of the PIU in all aspects (technical, financial, procurement, project management, safeguards policies) and continued institutional efforts to maintain high level of transparency (e.g. FM disclosure, website, etc). The Bank also acknowledges guidance and oversight provided by the Project Steering Committee

f. Overall project’s ratings for Progress towards Project Development Objective and Implementation Progress are satisfactory.

8. Key Recommendations and Lessons Learnt for the Remaining Project Implementation:

a. Phase 2 Project Appraisal and Investment Prioritization: the mission noted that while investment prioritization was adequately carried out following a consultative and participatory process, some of the proposed investments appear to lack technical, economic, and financial assessment. In particular, the proposed project appraisal documents should strengthen alternative investments that were considered and document better social, economic, technical, and environmental justification for the proposed investment for TCCs.

2

Page 3: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

b. Design Review: the mission recommends carrying out a thorough design review including: a) site visits to validate the adequacy of design; b) sharing site designs with the TCs for review; c) utilizing external peer review is encouraged to ensure the best quality of designs.

c. Contract/construction Management: the mission stressed the importance of enhancing contract and construction management by the PIU. Based on the review of Dangriga market sub-component, the mission recommends adequate documentation of any issues raised during the site visits by the PIU technical staff; proactive communication and clarification of any contractual issues by the PIU; and maintaining signed minutes of the discussion between the PIU, contractors and TCs. In particular, while SIF retains supervision and project management roles (Dangriga, small works), it is important to maintain logs of instructions to contractors. Such records are critical not only for the determination of delays in future, if relevant, but also importantly to ensure compliance and implementation by contractor, and aid in subsequent follow up visits.

d. Capacity building and technical assistance components for TCCs: there is a need to build a closer dialogue and policy linkage with the Ministry of Local Government and the Ministry of Natural Resources and Agriculture. In particular, important progress has been made for revenue enhancement TA (with the support from international and local consultants) and MLG can play a significant leadership towards accomplishing the objective of the TA and ensuring that the project’s support for revenue enhancement can be sustained and continued. In addition, an interim protocol for information sharing relating to land ownership between TCCs and the MNRA was agreed and the mission recommends following upon and monitoring this during the project implementation.

e. Ensuring participatory project implementation throughout the entire project cycle : the mission stressed that the key development impact that the Project aims to achieve is enhanced transparency and accountability for TCCs. The Project has built several mechanisms to allow this (e.g. investment prioritization through participatory process, establishing project monitoring committee and grievance mechanisms, and making financial statement public). The remaining project implementation should continue to support participatory process and transparency and the Bank team will provide adequate support as needed.

IV. Implementation Status by Project Component

Component 1: Municipal Infrastructure Investments

9. Completed and ongoing Phase 1 works. The mission visited Phase 1 Project sites under implementation in all seven TCs (Annex 3 includes a detailed list of site visit locations and dates and Annex 4 provides implementation status of Phase 1 works.) During the site visits the mission met with mayors, Town Council representatives, as well as affected stakeholders. The mission found the quality of construction generally satisfactory and suggested a few minor areas of improvement in safety measures (such as pavements) and quality of materials used (such as paint for street markings). Key discussion and issues raised during the site visit are:

a. Belmopan –The Bank concurs with TC Mayor’s recommendation that the SIF shares the site designs with the Belmopan TCC’s engineer.

b. Belmopan, Benque Viejo del Carmen – The paint on some streets started to fade away, which indicate that the PIU should evaluate and determine the best paint options for street rehabilitation works. The Bank recommends following up with contractors and/or putting

3

Page 4: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

corrective measures for all streets supported under Phase 1. In addition, maintenance options could be considered to have the roads re-painted regularly.

c. Punta Gorda – The site visit to the proposed Phase 2 streets revealed room for improvement in the vetting process for sub-Projects. In particular, the selection and prioritization of Hopeville road, which is expected to benefit directly 86 households, was not clear. Meanwhile, the West St (VOA Sts), which was considered during the public participation process, was not included in the prioritized list. The mission emphasized the importance of carrying out economic, social and technical evaluation, along with community interests and overall public good in the weighting and final prioritization of sub-Projects.

d. The mission noted some complementary works for Phase 1 street rehabilitation envisaged under Phase 2, such as sidewalk and additional drainage along the street. The mission recommended the PIU proceed with the complementary works under a separate shopping package.

10. Dangriga Market Sub-Component. The mission discussed with the PIU both supervision and ongoing work contracts in great detail. Site visits to ongoing works for rehabilitation and expansion of existing market highlighted that no engineer is on site to supervise works and there has been considerable delay in project construction (40% completion rate as estimated by SIF). The contractor reports that his team has been working full time with a crew of about 21 men; however, due to ongoing issues related to non-payment, the crew size is variable. The mission discussed options available for SIF to successfully complete works without more delay, including possible contract termination and the status-quo. In order to decide on a way forward, it was agreed that SIF will assess the feasibility and likelihood of the existing contractor to complete construction without further delay (e.g. assessing financial condition, credit arrangement, quality of ongoing construction, and revised work plan for completion) by June, 21, 2013, consult with the PSC and the mayor, and inform the Bank of the proposed steps to take and solution by the end of June, 2013. With no supervision firm for last several months and concerns regarding the contractor’s capacity, the mission also noted there is potential that quality of the works may have been compromised. At the present time, with no supervision firm on board, SIF has been performing the supervision functions as well as Project Management, leading to potential contentious scenarios in the attribution of delays between the contractor and SIF.

11. The mission discussed a long pending issue of supervision contract for Dangriga Market. After the review by the Bank’s team, it was decided that while 100% payments of the contract had been made to ATA by PIU, deliverables had been only partially made under Interim Report #3 for Dangriga. Furthermore, it was decided that the PIU had overpaid the supervision firm at the amount of BZ$21,641 with BZ$11,656 overpaid for Interim #3 and BZ$9,985 for final payment. It was further agreed that SIF will determine any deduction to be applied to the refund taking into account additional visit by the firm and communicate to the Bank the justification for the final amount for the refund by Friday, June 21, 2013. The case of supervision contact for Dangriga Market highlights the importance of understanding the difference between time-based and lump sum contracts and improving the SIF’s contract management.

12. Selection of Phase 2 investments: The mission noted that while investment prioritization was adequately carried out following consultative and participatory process, some of the proposed investments appear to lack technical, economic, and financial appraisal. In particular, the proposed project appraisal documents should strengthen alternative investments that were considered and document better technical, economic, and environmental justification for the proposed investment. The mission recommended the PIU review all the selected sub-projects, carry out additional assessment that would justify all the proposed subprojects (e.g. value for money), document social, economic, environmental benefits of the

4

Page 5: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

proposed projects, adjust sub-projects prioritization following the analysis, and carry out another public consultation process as needed to close the loop on the final investment programs. It was noted that enhanced project appraisal document and investment prioritization would ensure greater level of legitimacy and transparency for the project. It was agreed that the PIU will provide a revised phase 2 project appraisal documents reflecting earlier comments by the Bank communicated by email and observations made during the mission by July 31, 2013 for the Bank’s no objection.

13. Eligibility Criteria for 2nd Phase Investment; the mission was informed that all the TCCs have met the required eligibility criteria for the 2nd phase investment. They include:

a. That the process for the formal adoption of a Municipal Growth Plan by the Town or City Council after a conducting a series of prior public meetings have been initiated. That the process for the preparation of a physical asset maintenance plan and corresponding budget and incorporation of maintenance budget in the Annual Town or City Council budget have been initiatedb. Conduct monthly Council meetings of which at least one should be open to the general public every two months starting from October 2012 c. Conduct public Town meetings at least once every six months as required by law starting from October 2012d. Submission of monthly financial reports to MLLGRDINEM and the publication of such reports as required by law starting October 2012.Reduction in the overdraft facility maintained by the Town or City Council to within 90% of the overdraft limit as approved by the Ministry of Finance by Q3 2011 and for any investment applied for after July 31, 2012 a further reduction to within 75%; ande. Hiring of a qualified accountant using a transparent selection process based on clearly defined qualifications and experience and using Terms of Reference previously agreed with BSIF and the WB.

It was agreed that the PIU will provide the Bank team with the evidence of meeting all the 2 nd phase investment criteria by June 28, 2013. It was reiterated that no sub-project can proceed without meeting the eligibility criteria.

14. Lump-sum based supervision –The mission noted the recommended approach for Phase 2 supervision is time based contracting method. SIF noted difficulties, mainly capacity constraints for the oversight of such contracts. SIF confirmed that to date, the majority of contracts are implemented lump sum given the relatively small size of contracts (typically under ½ million). The mission agreed that recognizing the concerns of SIF, and the relatively small contracts envisioned, lump sum may be considered. In this scenario, the mission recommended more detailed estimates on the part of SIF to have better comfort on the expected supervision effort and thus manage better upfront costs estimates, which may also revise upwards to reflect risk transfer to consultant (who assumes full risk for construction delays, which could be caused by any number of factors).

Component 2: Technical Assistance and Capacity Building for TCCs, MLLGRDN and MNRA

15. Revenue Enhancement (RESP) and Financial Management: The Revenue Enhancement TA has advanced well and has made a satisfactory progress. Some specific achievements up to date are:

LGO and UPO are located in the Ministries of Local Government and Natural Resources: Terms of Reference and Memorandum of Understanding between BSIF and the Government Ministries have been agreed to. Agreements include office accommodation and sharing of transportation and accommodation during field work.

5

Page 6: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

LGO worked closely with TCCs, MLG, SIF and Consultants to implement the following capacity building initiatives between April 2011 and May 2013: Revenue Enhancement Support Program, Computer and Information Technology Network Upgrade Support, Training in QuickBooks Usage and Municipal Development Plans.

LGO Terms of Reference revised at the request of the Ministry of Local Government in March 2013 to reflect greater alignment with specific project related activities.

Terms of Reference developed for the procurement of the technical expertise necessary to develop the Municipal Development Plans.

Color coded land use maps developed for the seven (7) municipalities under the BMDP to assist with the consultancy to prepare the municipal development plans.

Activities coordinated with consultants, government agencies, Non-Governmental Organizational and other relevant stakeholders involved in developing the Municipal Development Plans.

16. The mission was informed that final reports on the progress and outcome under the TA consultancy is under preparation and the team will support an international expert during the final consultation and dissemination of the final report scheduled end July, 2013. In addition, the team noted that the training for the use of QuickBooks for accounting has improved financial management for the TCs. The Bank noted, however, a need to integrate revenue side management together with expense side and proposed working during the remaining project implementation to ensure the interface and integration of the financial system in TCCs. Furthermore, the mission was informed that the MLG is planning to carry out a strategic review of the Ministry’s roles and work plan to support TCCs in enhancing municipal management capacity. The mission highlighted the importance of institutionalizing revenue enhancement efforts within the Ministry and agreed that the Bank team will have a follow-up discussion with the Ministry end July, 2013. Lastly, the mission was informed of the ongoing efforts by MNRA to update the quality of property registration and cadastral information for town councils. Following the discussion, the mission agreed with the MNRA on the interim protocol to allow sharing relevant information with TCCs for revenue enhancement efforts. It was agreed that Urban Planner under the project will follow up and communicate with the TCCs on the interim protocol.

17. Municipal Growth Plan, Asset Maintenance Plan and Traffic Management: the consultancies have been just mobilized and the mission highlighted that the PIU send all the main deliverables for the Bank’s technical review and comments. The mission was pleased to note that the TA activity is well under way with formulation of local working group consisting of town councils members, civil society and private sector.

Component 3: Project Management

18. Contract Management – the mission recommends hiring additional staff to focus on contract compliance aspects, working closely with Project Coordinator and Project Engineers. SIF noted a previous attempt to hire personnel, but due to the stringent requirements (a legal background was stipulated) the advertisement did not yield interest or responses. The mission recommends reviewing the ToR and selection criteria to allow more flexibility. The mission recognizes that there may be few local staff with in depth experience in procurement in multi-lateral funded projects. A more general profile is strongly recommended, allowing for on-the-job training on specific WB policies. In the opinion of the mission, a legal background should not be a requisite, but rather focus on the profile of the person for example attention to detail, organization skills, assertiveness, and effective oral and written communication skills, in addition to basic qualifications/education/experience that permits adequate performance.

6

Page 7: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

19. Monitoring and Evaluation – the mission reviewed the existing framework for M&E including revising baseline and target values and adjusting indicators. The detailed M&E indicators are provided in Annex 6.

Financial Management (FM)

20. Internal Controls. The Project FM Unit continues to be well staffed with experienced, competent and accredited accountant professionals, who exercise due diligence and care keeping in mind key internal control features, including segregation of duties for key processes.

21. Budget and Interim Unaudited Financial Reports (IUFRs) The mission appreciates that the Project’s IUFRs until March 2013 were submitted to the Bank on time and included comprehensive information. The submitted figures have been reconciled with Bank account records in Client Connection and banking statements. SIF periodically prepares easy-to-read summaries of FM reports of the Project to provide to its major stakeholders, such as TCs and PSC. The summary reports highlight the Project’s progress in terms of financial indicators and disbursement as well as compares projections with actual figures. SIF continues to post and update Project financial information on the SIF website, openly disclosing key data in line with the Project transparency requirements established in the Bank’s Access to Information Policy.

22. External Audits. The mission reviewed internal control issues highlighted by auditors in the management letter for the period April 2011/March 2012 and was pleased to note that SIF resolved and closed all of the items. The mission met with the external audit team. The audit work for the current period, as of March 2013 is in advanced stage and no delay in report submission is foreseen. As of the date of the mission, no material weakness has come to the auditor’s attention, although they flagged the need to improve contract projections to reduce instances for contract amendments changing the total cost of a specific consulting firm. SIF and the Bank have found the performance of the audit firm as satisfactory; consequently, since the firm audits SIF as an entity, SIF management will present a motion to the Board to approve an extension for next audit period, with the corresponding adjustments in the inflation rate.

23. Disbursement. The mission was pleased to note that the Project disbursement rate has accelerated to a perfect match of 50% for this mid-term review disbursed and committed. The mission randomly reviewed payment documentation and files, which were complete and orderly archived. It was noted that payment clauses should be reviewed by the Finance Officers and clearly understood by the Project Team, to mitigate risks of improper payments. The mission discussed the format of the table to include in the request restructuring for reallocation among disbursement categories.

Procurement Management

24. Procurement Capacity. The mission reviewed the capacity of the SIF implementing the Project procurement. In January 2013 SIF recruited a new Procurement Officer responsible for all procurement activities including identification and selection of contractors, and oversight of the bidding process for the Project. The Bank procurement mission in February 2013 conducted a thorough capacity assessment of procurement staff and made recommendations to ensure technical quality reassurance in procurement implementation. Besides intensive job training by the Bank’s senior procurement specialist, the Procurement Assistant participated in the procurement workshops in the region for 2013. The Procurement Officer should take formal procurement training within the year of 2013. As an action to further strengthen the capacity of procurement, the hiring of contract management staff has been agreed upon by SIF.

7

Page 8: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

25. Procurement Plan (PP). The mission reviewed the progress of the procurement plan and agreed with the proposed updates by SIF based on the need for the implementation of the Project for Phase 2. The updated PP incorporating the agreements shall be submitted to the Bank by July 14, 2013 for no-objection and publication.

26. Procurement Supervision: The mission reviewed the on-going and completed procurement processes and contracts under Phase 1, which made substantial contribution to the robust improvement in the Project’s disbursement. The planning for Phase 2 was discussed reflecting the experience and lessons learnt. Detailed discussion on procurement supervision is attached in Annex 7.

27. Procurement Post-review: The procurement post-review (PPR) was conducted during the mission of February 11-14, 2013. The civil works for street rehabilitation contracts via shopping were post reviewed by the Bank with sample of three contracts at the total amount of US$ 165,734.58 equivalent. The MTR mission conducted the physical inspection. The review has concluded that procurement activities carried out under the Project are in compliance with arrangements agreed in the Project financing agreement and no major issue were found regarding procurement.

Social Safeguards

28. Resettlement Plans:

a. Lessons learnt: The location of the temporary relocation, both in Dangriga and Corozal, seemed during the preparation of the plan, to be adequate to maintain the same level of income; all three plans would have benefited from more supervision and hands-on intervention.   SIF’s delegation of decision-making to the municipalities was too early in the process, for example, leaving communication with Project-affected people mainly in the hands of the town council with minimal supervision or delegating to the Belmopan town council the resolution of the taxi relocation.  

b. Area of Development for Second Half of Project Implementation: To carry out an analysis regarding the income lost by the Project –affected people and the present and future fees they have to pay the Town Council as rent as well as user fees to devise an income restoration program within the Dangriga Abbreviated Resettlement Plan; to use the analysis to define an Income Restoration Program to be consulted with the Project-affected people and town council within the Plan and update it accordingly ; Regular visits by SIF’s social officer will be carried out to all sites with active works; updates on the implementation of the plans will be prepared and documented by SIF.  

29. Social accountability - Project Monitoring Committees (PMCs):

a. Lessons learnt: During Phase One, the PMCs were effective, to a certain extent, in being the SIF’s contact person from the community to give third party reports on the progress of the works.   However, they did not completely fulfill the original monitoring function, given that they did not close the accountability loop by reporting back to the community members who they represent after their visits to the site and meetings with SIF or the Town Council; (ii) Project Monitoring Committees need to be strengthened and more closely supervised by SIF.

b. Area of Development for Second Half of Project Implementation: During the second phase of the Project, the SIF will develop and implement a strengthening proposal for the Project Monitoring Committees (PMC), with World Bank support and guidance.   Increased supervision from SIF’s social officer is also recommended.  

8

Page 9: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

30. Grievance Redress Mechanism:

a. Lessons learnt: The first tier of the sub-Projects’ grievance redress mechanism can only be the PMC if they have been strengthened and have a good working relationship (in the appropriate language) with the Project-affected people.

b. Area of Development for Second Half of Project Implementation: A new first tier mechanism will be devised for Dangriga’s current plan and Phase Two’s plans.   A bilingual contact person, preferably a social worker, will be assigned to the Dangriga market to communicate with the affected people on a regular basis.    Similarly, in the other towns, a contact person will be assigned.   When appropriate, bilingual contact persons will be assigned.  Moreover, the SIF will contact the Ombudsman and Legal Office to brief him/her on the Project and possible grievances he/she might receive.    

31. Indigenous Peoples Framework:

a. Lessons learnt: Culturally appropriate consultation was not carried out consistently.    The Project’s framework is broad in scope and mostly emphasizes the importance of the cultural aspects of communication and consultation.   However, consultations with Project-affected people as well as broader community during participatory governance activities were not necessarily carried out in the most culturally appropriate manner.   For example, bilingual staff was not hired to ease communication with Project-affected people whose first language is not English.   Also, in one case, the mission noted that consultations for second phase Projects could have been more culturally appropriate.

b. Area of Development for Second Half of Project Implementation: These responsibilities should be championed by SIF and not delegated to the municipalities.   The SIF will safeguard that communication is provided in a culturally appropriate manner, according to the Project’s Indigenous Peoples Framework.   In the same manner, town hall meetings and other participatory events within the MDP’s activities will follow the framework.

32. Communication strategy:

a. Lessons learnt: Citizen participation in local decision-making is in its beginning stages under the Project due to several factors.  

b. Area of Development for Second Half of Project Implementation: Communications strategy will be adapted to focus on strengthening the municipalities’ accountability mechanisms.

33. Participatory decision-making processes:

a. Lessons learnt: With the exception of Belmopan, all other Town Councils reported that their town hall meetings participation could have been better; therefore the decisions resulting from these meetings could have relied on a more robust participatory exercise.  

b. Area of Development for Second Half of Project Implementation: SIF will supervise these participatory processes more closely, to ensure that participation is meaningful.

Environmental Safeguards

34. Compliance with Bank safeguard policies is satisfactory.

9

Page 10: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

35. The mission reviewed compliance with the Belize Municipal Development Plan Environmental Management Framework, dated June 2010, and followed up on progress since the previous implementation mission in December 2012. Sub-Projects that require oversight of safeguard compliance include:

a. Road and pavement rehabilitation works (including associated drainage) in Belmopan, San Ignacio/Santa Elena, Orange Walk, Corozal, Dangriga, Benque Viejo, and Punta Gorda.

b. Market construction including provision of wastewater disposal for sanitary block and solid and liquid waste management for fish market waste at Dangriga.

c. Construction of town hall building in Punta Gorda.

36. The mission commends the Project Engineers tasked with monitoring environmental management. As requested during the last mission, monitoring reports of environmental management of civil works Projects that are currently under implementation have been included in the overall progress reports. A separate detailed EMP has been prepared for the market construction at Dangriga Market and will be disclosed in the Bank InfoShop and on the SIF website. For Phase 2 Projects, the follow-up screening form in the ESMF will be completed for each sub-Project prior to the start of civil works, and where required, an EMP checklist will be prepared (utilizing the format followed for the Dangriga Market EMP).

37. Phase 1 road and pavement rehabilitation. On the whole, adequate health and safety measures have been adopted (provision of Personal Protective Equipment and adequate road signage and notification of roadworks). Dust control spraying is undertaken on a daily basis. Construction waste has been disposed of promptly and in an appropriate manner. No trees were removed as a result of the roadworks.

38. The mission commends the Project Team for its excellent initiative in consulting the Institute of Archaeology/National Institute of Culture and History with regard to the gun turrets, which had formed part of Fort Barlee (adjacent to the roadworks in Corozal). This led to the turrets being protected and fortified, and signposted as a Heritage Landmark. (The cavities identified under the turrets are a natural geological formation, and are confirmed to be of no historic or cultural significance.

39. The mission recommends the PIU to take the following actions:a. Ensure that where relevant, drains are covered with grilles, both for pedestrian safety, and to

prevent accumulation of solid waste leading to blockage and backup from silt traps at the shoreline.

b. Reduce the height of the inverts in the flat slope drain running towards the sea from Corozal market to ensure smooth flow and disposal of wastewater. When corrective works are completed, flush the drain (using water from the fire station pump) and cover the drain with grilles.

c. Upon completion of all sub-Projects in Phase 1, prepare a summarized completion report of environmental mitigation measures followed, lessons learned (e.g., ensure that drains are tested by contractors to ensure that effluent waters flow through to the outtakes.)

40. Market construction at Dangriga. The new market is still under construction. The sanitary block under construction will have a biological filtration system (solid waste will be collected in a septic tank and appropriately disposed of, and aggregates will filter liquid waste, which will drain into a tile pond). The solid waste from the fish market will be collected in a depository for regular collection for use as composting. The liquid waste from the fish market will be sent to a soak-away system, before biological filtration to the soil. The design of the building (roof and floor drains) incorporates adequate rainwater drainage measures. Stainless steel has been utilized in food stall design, instead of tiles, for

10

Page 11: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

sanitary purposes (no cracks harboring bacteria, etc.). The temporary toilet drains into a self-contained impermeable septic tank, which will be removed upon completion of the Project. In terms of environmental measures, sheet siding has been placed along the banks of the adjacent canal to prevent erosion. A detailed EMP has been prepared for this sub-Project and will be disclosed in the World Bank InfoShop and in-country on the SIF website (a copy will also be given to the Town Council and made available to the public).

41. The mission recommends the PIU to take the following actions:a. Ensure that installation of soak-aways, grease traps, and septic tank are properly installed, by

on-site supervision during the process. b. Undertake a baseline water quality analysis of the ambient water quality in Dangriga Canal and

upstream. Samples will be analyzed for coliforms and Ph-level, and follow-up samplings will be taken three months after the market is operational, and again six months thereafter.

c. Install siltation barrier to prevent solid waste in the canal from entering the open sea.

42. Construction of town hall building in Punta Gorda (completed). The building meets all environmental compliance standards, but the mission recommends that the PIU replace the wooden covers currently placed on drain entry points with grilles as soon as feasible to allow for rainwater to enter the drains, thereby preventing stagnation with resultant health risks.

43. Phase 2 Investments. Going forward, the mission recommends the PIU to take the following action during Phase 2 of the Project:

a. Future sub-Projects must have a brief EIA (where required by Government of Belize (GoB) environmental regulations and/or World Bank OPs) and/or an EMP checklist prepared and disclosed prior to the start of works. Consultation with local stakeholders on the EIA/EMP must take place and be documented in an annex to the EIA/EMP. Given that this is a Category B Project (with limited environmental impact), preparation of environmental documentation and periodic progress reports can be included in the TOR for the design consultant/supervision engineer.

___________________________ ____________________________Yvonne S. Hyde Yoonhee Kim

CEO Ministry of Finance and Task Team Leader, World Bank Economic Development

11

Page 12: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 1a: Action Plan

Relevant Activities Recommendation/Action Responsible Agency

Due Date

1 Project Management – Dangriga Market

The SIF will communicate to the Bank the justification for the final amount for the refund for the supervision works at the Dangriga Market.

PIU By June 21, 2013

2 Project Management – Dangriga Market

Regarding the Dangriga Market contractors, the SIF will confer with legal professionals and the Project Steering Committee (PSC) on the next steps and inform the Bank of the decision.

PIU By June 28, 2013

3 FM: Request for reallocation among disbursement categories

Prepare Table with Disbursement Categories for Reallocation.

PIU By June 21, 2013

Second Phase Investment Prioritization and Appraisal

Provide a revised phase 2 project appraisal documents for the Bank’s no objection

PIU By July 31, 2013

Second Phase Investment Prioritization and Appraisal

Provide the Bank team with the evidence of meeting all the 2nd

phase investment criteria

PIU June 28, 2013

6 Procurement The updated procurement plan incorporating the agreements shall be submitted to the Bank for no-objection and publication.

By July 14, 2013

7 Procurement C14: Traffic Management Training Module (QCBS-Lump sum): Swedish National Road Consulting AB (SWEROAD) contract to start.

By end of June, 2013

8 Procurement C32-33: Preparation of Designs, Technical Specifications, Cost Estimates and supervision for Structures (Small Works) in Corozal, Orange Walk and Benque Viejo (CQS): to open. The consultancy is advertised in the local press with a deadline.

By June 14, 2013 (opening date)

By June 28, 2013 (deadline for

advertisement)

9 Procurement C34-35: Preparation of Designs, Technical Specification, Cost Estimates and Supervision of Municipal Streets Rehabilitation (Small Works) in Corozal, Orange Walk, Benque Viejo & San

By June 14, 2013

12

Page 13: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Ignacio/Santa Elena and Belmopan (CQS): to open

10 Procurement C36: Preparation of Designs, Technical Specifications and Cost Estimates for the Rehabilitation of Municipal streets in Belmopan, Punta Gorda, Dangriga, Corozal, Orange Walk, Benque Viejo & San Ignacio/Santa Elena (LCS): to open.

By June 14, 2013

11 Social Safeguards Conduct Income Restoration analysis and submit to the Bank. The new Income Restoration Program will be in effect by August 1st (the original works completion deadline).

PIU By June 28, 2013

12 Social Safeguards Update the Plan to reflect the new provisions for the first tier of grievance redress mechanism and the income restoration plan.

PIU By June 28, 2013

13 Social Safeguards Propose a work plan for phase two incorporating lessons learned covering resettlement, culturally appropriate consultation, accountability/participation, and grievance redress mechanisms.

PIU By June 28, 2013

14 Environmental Safeguards

Ensure that where relevant, drains are covered with grilles.

PIU By end of Phase 1 Project

Commissioning

15 Environmental Safeguards

Reduce the height of the inverts in the flat slope drain running towards the sea from Corozal market to ensure smooth flow and disposal of wastewater. When corrective works are completed, flush the drain (using water from the fire station pump) and cover the drain with grilles.

PIU By end-July

16 Environmental Safeguards

Upon completion of all sub-Projects in Phase 1, prepare a summarized completion report of environmental mitigation measures followed and any lessons learned

PIU Upon Phase 1 Project Commissioning

17 Environmental Safeguards

Provide details on next available Safeguards training workshop for Project engineers (or approve environmental management training courses)

WB By end-July

13

Page 14: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

18 Environmental Safeguards

Dangriga Market: Ensure that installation of soak-aways, grease traps, and septic tank are properly installed, by on-site supervision during the process.Undertake a baseline water quality analysis of the ambient water quality in Dangriga Canal and upstream.Install siltation barrier to prevent solid waste in the canal from entering the open sea.

PIU Timing dependent on construction schedule

First sampling by end-July

Prior to completion of civil works

19 Environmental Safeguards - Phase 2 sub-Projects

Future sub-Projects must have a brief EIA (where required by GoB environmental regulations and/or World Bank OPs) and/or an EMP checklist prepared and disclosed prior to the start of works. Consultation with local stakeholders on the EIA/EMP must take place and be documented in an annex to the EIA/EMP.

PIU Prior to commencement of

civil works on Phase 2 sub-Projects

14

Page 15: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 1b: Action Plan Update from Last Mission (December 2012)

Relevant Activities

Recommendation/Action Responsible Agency

Due Date Status

1 Environmental Safeguards

Ensure that road crews at Corozal are provided with protective headwear by the contractor, and with protective footwear for those operating heavy machinery (e.g., drills)

PIU By end of December

2012

Done

2 Environmental Safeguards

Confirm that the cavity under 1st North Street in Corozal is not culturally or historically important; Check with the Department of Archaeology that there is no concern about filling the cavity with concrete

PIU By end of December

2012

Done

3 Environmental Safeguards

Provide brief environmental compliance progress reports for Phase 1 roads Projects, and provide a completion report upon completion of subProjects

PIU By end of March 2012

Done (Summarized completion report to be

prepared upon completion of

ALL sub-Projects)

4 Environmental Safeguards

Advise on progress of the initiative to plant Bermuda grass along earth-lined drains for erosion control

PIU At PIU’s discretion

At PIU’s discretion

5 Environmental Safeguards

Provide brief environmental compliance progress reports for Dangriga market

PIU By mid-January

2013, mid-May 2013, and in July

2013

Detailed EMP prepared, and

will be disclosed by end-June

6 Environmental Safeguards

Undertake a baseline water quality analysis of the ambient water quality in Dangriga Canal; upon completion of the works, periodically assess the point source water quality at the sanitary block and soak-away

PIU/TC By end of February

2013

Baseline assessment to be

conducted by end- July.

Periodic testing to follow upon

market becoming

operational7 Environmental

SafeguardsPrepare and disclose brief EIA (where required) and EMP for future subProjects

PIU Upon selection of

Phase 2 subProjects

Upon selection of Phase 2 subProjects

8 Environmental Safeguards

Provide details on next available Safeguards training workshop for

WB By end of December

Pending (timing of workshop

15

Page 16: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Project engineers 2012 was during Project mission)

16

Page 17: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 2: List of People Met

Belize Social Investment FundDaniel Cano Executive DirectorErnest Raymond Project CoordinatorNellie Trench Finance Unit CoordinatorChristine Lopez-King Senior Accounts OfficerEvan Dakers Social SpecialistCarolyn Crawford Procurement SpecialistKeisha Rodriguez Urban PlannerLionel Jiminez EngineerFrancisco Gonzalez EngineerClifford King Local Government Officer

Ministry of Finance and Economic DevelopmentYvonne Hyde CEO

Ministry of Natural Resources and AgricultureBeverly Castillo CEOGina Young Physical Planner

Ministry of Local GovernmentCandelaria Morter CEOEugene Palacio Director

Project Steering Committee (PSC)Yvette Alvarez Ministry of Finance RepresentativeLawrence Sylvester CEO, Ministry of Housing and Urban DevelopmentErrol Gentle CEO, Ministry of Works and Transport

MayorsSimeon Lopez Mayor of BelmopanMiguel Velasquez Mayor of Benque Viejo del CarmenHilberto Campos Mayor of CorozalH. Gilbert Swaso Mayor of DangrigaKevin Bernard Mayor of Orange WalkAnthony Fuentes Mayor of Punta GordaJohn August Jr. Mayor of Santa Elena/San Ignacio

Town CouncilsEnrique Carballo Executive Secretary, Belize Mayors’ AssociationJavier Novelo Engineering Assistant, Belmopan TCAngela Wade City Administrator, Belmopan TCSebastian Morales Revenue Manager, Belmopan TCCarolene Arzu Accountant, Belmopan TCJohukeoui Jones Traffic Manager, Belmopan TCCarmencita Sosa Accountant, Benque Viejo del Carmen TCMelly Coyol Town Administrator, Benque Viejo del Carmen TCElva Perez Deputy Mayor, Corozal TC

17

Page 18: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Rafael Castillo Councilor, Corozal TCGilroy Howard Flores Deputy Mayor, Dangriga TCTimothy Westley PME, Dangriga TCPaul S. Francisco Ag. Town Administrator, Dangriga TCSimon Paulino Deputy Mayor Punta Gorda TCLudwig Palacio Town Administrator, Punta Gorda TCWilfredo Wina Traffic Management, Santa Elena/San Ignacio TCKaren Fernandez Town Administrator, Santa Elena/San Ignacio TCMelanie Danilezyk Revenue Manager, Santa Elena/San Ignacio TC

Horwath Belize, LLPLisa Zayden Audit Team LeaderJessie Huang Audit Team MemberCatherine Castillo Audit Team Member

18

Page 19: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 3: List of Site Visit Locations and Dates

June 10, 2013- Belmopan: Easter Bus Terminal one-way street and Taxi Parking, Nimli Punit Street,

Hummingbird Extension, Raccoon Street

June 11, 2013- Benque Viejo del Carmen: Church Street, Church Hill Street, Burns Street, Independence Street,

Juanito Pongorast Capital Park- Santa Elena/San Ignacio: West Street, Eden Street- Orange Walk: Aviles Street, Santa Familia, Central Park- Corozal: 1st North Street (Police Station), Punta Gorda Street, Zuzuc Street, 1st South Street

June 12, 2013- Dangriga: Market Rehabilitation/Extension- Punta Gorda: Pampana Street, Robert Pennell Street, Town Hall/Administrative Building

Rehabilitation, Hopeville Street, West Street

19

Page 20: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 4: Status of Phase 1 Projects

Component 1, Phase 1 Sub-Project Status

Project SitesLength

Designed (m)

Length Constructed

(m)Town/City Contractor

Percent Completed

(%)

Start Date of the Contract

(NTP)

Completion Date

Bus Terminal Area 308 195*1 Belmopan Belize Roadway Construction 100 8/13/12 12/11/1218th St 497 260 San Ignacio Castillo Equipment 100 8/20/12

Avilez Lane 137 110 Orange Walk M&R Construction 100 8/20/12 11/19/12Tangerine St 134 160Zuzuc St 201 280 Corozal Imer Hernandez Dev. Co. Ltd. 100 8/20/12 11/19/12Church St 750 750 Benque Viejo del

Carmen

Imer Hernandez Dev. Co. Ltd. 100

10/3/13 10/4/13Churchill St 750 750Burns St 450 450Eden St 627 280 San Ignacio/Santa

ElenaWest St 237 584Robert Pennell St 274 160 Punta GordaPampana St 375 375

San Ignacio St 349 350 Orange Walk De' Mars Construction 100 9/24/12 12/23/12Nim Li Punit St 272 250*2

Belmopan

A&N Construction

10010/4/12 3/3/13Hummingbird Dr 76 180 100

Raccoon St 435 325*3 100Punta Gorda St 402 500

Corozal100

1st North St 195 195*4 100Santa Familia St 776 615*5 Orange Walk 40

Notes:1. Sidewalks were added on both sides.2. 1/2 length paved with HMA, other half with 2-layer 1/2" chip seal.3. Shorten to adjust for additional drains added to Nim Li Punit St and Hummingbird Drive.4. Added some 200m of 0.6m wide lined drains and some 240m of 1m wide lined drains.5. Portion of Audinette Alley not in Orange walk Town therefore, this portion was eliminated,

only 200m paved, 160m of 0.6m wide lined drain added on both sides,sub-base & base added over 615m length.

20

Page 21: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 5: Proposed Phase 2 Projects

The proposed phase 2 Projects and lengths in order of north to south, west to east are:1.       Corozal:

- Market (1,500m2) Expansion and Rehabilitation- 6th Ave (85m) and 1st St South (180m) Rehabilitation- Fort Barlee south turrets (2) Rehabilitation- Sport Complex (12,000m2) Expansion and Rehabilitation

2.       Orange Walk:- Central Park (2,400 m2) Rehabilitation- Park Streets (1,800 m2) (North Park St/80m, South Park St/80m and Lover’s Lane/70M)

Rehabilitation- Santa Familia St Rehabilitation

3.       Benque Viejo del Carmen:- Juanito Gongora St (545m), Independence St (530m) Rehabilitation- 1,100m long by 1.2m wide Sidewalks (1,320m2)

4.       San Ignacio/Santa Elena:- Carmelita St (312m), Bishop Edmund St (45m), Martin Galvez St, and Cahal Pech St

(428m) Rehabilitation- Salazar St (548m), Eden St (480m) Rehabilitation

5.       Belmopan:- Water Reservoir Streets (Barton Creek St/370m, Blue Creek St/290m, Garbutt

Creek/440m, Haulover Creek/380m, Mussel Creek/450m, and Roaring Creek/520m) Rehabilitation

- Chiquibul St (240m) and Almond Blvd (280m) Rehabilitation6.       Dangriga:

- Trucking Blvd (355m) and Gadsby Ramos St (732m) Rehabilitation7.       Punta Gorda:

- Melendrez Blvd (350m), R. K. Pennell Blvd (320m), Mangrove St (310m), Wild Cane St (350m) Rehabilitation

21

Page 22: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 6: Monitoring and Evaluation

Data Collection MatrixProject / Intermediate Outcome Indicators

Base-line

Target Values Data Collection and Reporting

CommentsYR 1 YR 2 YR 3 YR 4 YR 5Frequency

and Reports

Data Collection

Instruments

Responsibility for Data

Collection

Number of beneficiaries with access to improved quality of basic municipal infrastructure (direct and indirect Project beneficiaries (number), of which is female (percentage).

0

Direct Direct Direct Direct Direct

AnnualSub-Projects completion

reportsPIU-SIF

The data collected in year 1 is for the two (2)

Pilot Projects in Belmopan and San

Ignacio/Santa Elena. The data for year 2 has

not been revised for population increases over the past 6 month

period

Male

Female

Male

Female

Male

Female

Male

Female

Male

Female

49% 51% 49

% 51%

3,500 -

-

-Indirect Indirect Indirect Indirect Indirect

Male

Female

Male

Female

Male

Female

Male

Female

Male

Female

49% 51% 49

% 51%

146,172 153,683 -

- -

Number of towns successfully completing investments in first and second phases

0 0 6.00 - - -

End of phase 1

and end of the Project

Project Completion

ReportsPIU-SIF

Six (6) TCCs have successfully completed investments in phase 1 (Belmopan, Benque,

Corozal, Orange Walk, Punta Gorda, and

SI/SE). Phase 2 is to commence in year 3

At least four TCC’s each have achieved four out of seven intermediate outcome indicators of component 2

0 0 4.00 - -

- Annual Compilation of different

progress reports such as financial

reports submitted to

PIU-SIF The four (4) TCCs that achieved at least four

out of the seven intermediate outcome

indicators of component 2 are:

Corozal, Belmopan,

22

Page 23: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

MLLGRD Benque, and Dangriga.

Intermediate Outcome Indicators

Baseline YR 1 YR 2 YR 3 YR 4 YR 5Frequency

and Reports

Data Collection

Instruments

Responsibility for Data

CollectionComments

Km of drainage financed under the Project

0 0 10.1 - - - Semi-

annual

Sub-Projects completion

reportsPIU-SIF

Km of rehabilitated roads under the Project

0 0 5.18 - - - Semi-

annual

Sub-Projects completion

reportsPIU-SIF

Number of improved intersections under the Project

0 58 - - - Semi-

annual

Sub-Projects completion

reportsPIU-SIF

Number of traffic signs financed under the Project

0 107 - - - Semi-

annual

Sub-Projects completion

reportsPIU-SIF

Number of towns and cities that comply with terms and conditions of sub-Project agreement

0 7 7 -

- - Semi-annual

Sub-Projects completion

reportsPIU-SIF

Number of towns and cities that have adopted MGP

0 0 0 - -

- Semi-annual

Minutes of Town Hall Meetings

MLLGRD

Number of towns increasing own revenue collection

Local revenue collected in 2009

0 0 - -

- Semi-annual

Financial Reports

submitted to MLLGRD

MLLGRD Belize City and San Pedro Town have been included. The period (April to July) will be

compared for 2011/2012 and 2012/2013 as

recommended by

23

Page 24: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

consultant

Number of towns with qualified accountants on staff

0 7

9 - -

- Semi-annual

Towns and Councils submit

information to

MLLGRD

MLLGRDBelize City and San

Pedro Town have been included

Number of towns submitting required financial reports

0 9 9 -

- - Semi-annual

Financial Reports

submitted to MLLGRD

MLLGRDBelize City and San

Pedro Town have been included

Number of towns using a computerized financial reporting system

0 1 9 -

- - Semi-annual

Reports submitted to

PIU PCMLLGRD

Belize City and San Pedro Town have been

included.

Number of towns with a physical asset maintenance plan and corresponding budgets

0 0 0 - - - Semi-

annual

Financial Reports

submitted to MLLGRD

MLLGRD

Number of towns with roads and safety procedures

0 0 0 - - - Semi-

annual

Reports submitted to

PIU PCNumber of towns and city councils that have received training from the Local Government and Urban Planning Officers

0 9 9 - - - Semi-

annual

Reports submitted to

PIU PC

MLLGRD and MNRE

Belize City and San Pedro Town have been

included

Number of TCC’s provided with spatial data sets showing land

0 7

7 - -

- Semi-annual

MNRE Internal Reports

MNRE

24

Page 25: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

parcelsPercentage of sub-Projects that meet SIF’s service standards in accordance with the OM

0 100% 100% - -

- Semi-annual

SIF PIU Internal reports

PIU-SIF

Procurement and FM duties are executed in accordance with national and World Bank guidelines

0 yes yes - - - Semi-

annual

SIF PIU Internal reports/

Financial Audits

PIU-SIF

25

Page 26: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Annex 7: Procurement Review Phase 1For contracts of major TA packages under Component 2:

i. C11: Municipal Growth Plan (QCBS-Lump sum): Contract was signed in December 2012 with a proposed completion date of December 2013. Technical Assistance to prepare the Municipal Development Plans is being provided by the firm, Institute for International Urban Development (I2UD). Commencing their work on January 2, 2013, I2UD submitted their Draft Inception Report on February 4, 2013 and the Final Inception Report on March 1, 2013 that incorporated stakeholder comments. The consultants submitted the draft Municipal Development Plan Strategy for review on Thursday, April 4, 2013 and the final document was submitted on May 6, 2013.

ii. The preparation of the Municipal Development Plans was launched on May 9, 2013 at the First National Workshop. Module 1 - Municipal Assessment commenced in all seven (7) municipalities on May 13, 2013 with cluster workshops and follow-up sessions conducted by the consultants. The total amount for this Project is BZD$687,359.72. The total outstanding amount left of this contract is BZD$494,939.79.

iii. C14: Traffic Management Training Module (QCBS-Lump sum): Swedish National Road Consulting AB (SWEROAD) was selected as consultant for this Project. Matters relating to the association were clarified during contract negotiation and contract went for signature. The contract is to start by the end of June 2013. The total contract amount is BZD$729,630.50.

iv. Physical Asset Maintenance Plan (QCBS-Lump sum): The contract was signed in April 2013 total contract amount is BZD$432,415.00, with the consulting firm Hydroplan. The first payment of BZD$37,432.50 has been paid to the consultant with the submission of the first draft Inception Report. The consultant has recently submitted the final Inception Report to the PIU for their review. This contract has not had any contractual issues thus far. The procurement method used was QCBS. Outstanding balance left on this contract is BZD$394,982.50

b. Project activities related to “Refurbishment of Buildings”:i. C2-3: Consulting services for design and technical inspection for buildings signed

with ATA in lump-sum contract was reviewed by Mission, given the non-compliance with the contract conditions. While 100% payments of the contract had been made to ATA by PIU, deliverables had been only partially made under Interim Report #3 for Dangriga. It was agreed that the 20% payment for Interim Report #3 be split between PG and Dangriga based on supervision of civil works contracts, based on which the overpaid amount was calculated as BZ$21,641 with BZ$11,656 overpaid for Interim #3 and BZ$9,985 for final payment. The refund decision is subject to the fiduciary consideration by PIU’s Financial Management team. The lessons from ATA contract were discussed to avoid similar contract management issues.

ii. W-3: Civil works contract for PG under NCB procedures was signed on March 22, 2012 at US$ 212,575, and completed in September 2012, on schedule.

iii. W-5: Civil works for Dangriga under NCB procedures was reviewed by the mission in April 2012, especially on the post qualification for the lowest evaluated bid, K & G

26

Page 27: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

Construction. Bank gave no-objection to the contract award to K & G issued on May 4 and contract was signed on May 24, 2012 at US$ 668,675 (BZ1,377,349.50). The contract has been delayed substantially. Though GCC46.1 for the liquidity penalty could be applied not exceeding the total liquidity of 5% of the contract price, the reason causing the delay has not been agreed. The Project is assessing the contract status from technical and contractual point of view and will decide the next steps by the end of June.

c. Project activities related to “Rehabilitation of Streets”:i. C5-10: Preparation of Designs, Technical Specifications and Cost Estimates for

Rehabilitation of Municipal Streets: Contract was signed November 2011 with Anthony Thurton & Associates at total contract sum was BZ$299,757.94. The contract has been completed.

ii. C5-10: Supervision of Municipal Street Rehabilitation of street works: Contract was signed in July 2012 with TECHNIPLAN at the total contract amount is BZ $774,519.00. The contract is time-based and managed within the ceiling of the contract. There is an outstanding balance of BZ$108,542.74 for reimbursable expenses.

d. Civil works for the street were tendered under NCB (2 packages) and shopping (5 packages) procedures, based on design and supervision under C5-10 consulting services. The PIU has requested that the Bank increases the thresholds for both NCB and shopping for works, from US$ 1.0 million per NCB tender to US$ 1.5 million per NCB tender, and for shopping from US$ 100,000 to US$ 150,000. The Bank provided no-objection to the increase threshold in May, 2012, which has accelerated the implementation of the Phase 1 construction works. The following NCB packages were reviewed at the mission:

i. W 9: Rehabilitation of streets in Benque Viejo, San Ignacio and Punta Gorda Town (NCB): The contractor Imer Hernandez Development Company signed contract on the August 16, 2012 with a start date of September 2, 2012, at the total contract price is BZ$2, 320, 630.65. An amendment totaling US$49,562.51 was added to the contract for adjustment to rebuild existing concrete lined drains, to replace a culvert in Benque and primer for asphalt coat to streets.

ii. W 11: Rehabilitation of streets in Benque Viejo, San Ignacio and Punta Gorda Town (NCB): The contract was signed in September 2012 with A & N Construction at the total contract amount of BZ$2,183,809.65. The contract is 97% completed with works to be concluded in August 2013. An amendment totaling BZ$99,125.02 was approved for additional works for drains in Orange Walk and Corozal due to poor designs by the Design Consultant. The outstanding balance for payment is BZ$504,220.95.

Phase 2e. C32-33: Preparation of Designs, Technical Specifications, Cost Estimates and

supervision for Structures (Small Works) in Corozal, Orange Walk and Benque Viejo (CQS): The consultancy is advertised in the local press with a deadline of June 28, 2013. The deadline was extended an additional week due to limited amount of EOIs received. The proposed opening date is June 14, 2013.

f. C34-35: Preparation of Designs, Technical Specification, Cost Estimates and Supervision of Municipal Streets Rehabilitation (Small Works) in Corozal, Orange Walk, Benque Viejo & San Ignacio/Santa Elena and Belmopan (CQS): The consultancy was

27

Page 28: documents.worldbank.orgdocuments.worldbank.org/curated/en/644791486155885089/... · Web view–The mission noted the recommended approach for Phase 2 supervision is time based contracting

advertised starting May 17, 2013 with a deadline of June 3, 2013. The proposed opening is June 14, 2013.

g. C36: Preparation of Designs, Technical Specifications and Cost Estimates for the Rehabilitation of Municipal streets in Belmopan, Punta Gorda, Dangriga, Corozal, Orange Walk, Benque Viejo & San Ignacio/Santa Elena (LCS): The consultancy was advertised starting May 1st, 2013 with a deadline of May 31st, 2013. The deadline was extended an additional week due to limited amount of EOIs received. The proposed opening date is June 14, 2013.

28