wayne bag get t 112105

Upload: shazz28

Post on 05-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Wayne Bag Get t 112105

    1/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 1

    Earned Value Management:An Introduction and Short

    Tutorial

    Wayne Baggett

  • 7/31/2019 Wayne Bag Get t 112105

    2/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 2

    Outline

    What is Earned Value?

    Government Requirements

    Small Project Usage

    Why Use Earned Value?

    Earned Value in a NutshellConclusions

  • 7/31/2019 Wayne Bag Get t 112105

    3/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 3

    What is Earned Value?

    How does

    Dilbert knowthis?

  • 7/31/2019 Wayne Bag Get t 112105

    4/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 4

    What is Earned Value?

    Project Management Technique Integrates technical performance requirements,

    resource planning, and cost accounting withschedule

    Provides insight into project status

    Provides early warning signals for problems

    Provides a disciplined means ofmanaging the project

  • 7/31/2019 Wayne Bag Get t 112105

    5/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 5

    Government Requirements

    OMB Circular A-11, Exhibit 300 (2004)

    Requires EVMS for allmajor acquisitions

    Agencies must have ANSI-compliant EVMS in placeby December 31, 2005

    EVMS data must be used to identify problems and

    provide realistic final cost estimates as a part of

    decision packages Federal Acquisition Regulations (2005) amended

    to require contractor-maintained EVMS

  • 7/31/2019 Wayne Bag Get t 112105

    6/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 6

    Government RequirementsThese requirements apply to large projects or

    programs; DOD requires

    Contract Value $50M: validated ANSI-compliant

    EVMS, structured reports and reviews, ongoing

    surveillance

    $50M > Contract Value $20M: ANSI-compliant

    EVMS (validation not required), tailored reports and

    reviews, ongoing surveillance

    Contract Value < $20M: EVMS optional, ongoing

    surveillance

    Very rigid, heavily constrained system at this level

  • 7/31/2019 Wayne Bag Get t 112105

    7/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 7

    Small Project Usage

    Small projects provide the bestopportunities for earned-value employment Consider its use for all in-house funded

    developmental projects where a firmcommitment is made to management.

    Software projects can especially benefit fromthe employment of a simple earned-valueapproach.

    (Fleming and Koppelman, Earned Value Project Management: APowerful Tool for Software Projects, Crosstalk, July, 1998, p.19.)

  • 7/31/2019 Wayne Bag Get t 112105

    8/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 8

    Small Project Usage

    The Personal Software Process (PSPSM) and TeamSoftware Process (TSPSM) use EVM PSP has practitioners estimate task efforts and track

    their actual effortsTasks estimated are very smallabout 10 hours each

    Data are used to improve future estimates

    TSP expands the use of EVM to the project level

    Use of PSP and TSP helps projects meet theircommitments (Tuma, D. and Webb, D., Personal Earned Value:Why Projects Using the Team Software Process Consistently MeetSchedule Commitments, Crosstalk, March 2005, p. 17.)

    PSP and TSP are registered service marks of Carnegie Mellon University

  • 7/31/2019 Wayne Bag Get t 112105

    9/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 9

    Small Project Usage

    Several projects at STScI have used EVM:

    Most used a tailored version of EVM

    JWST S&OC development

    FOS, PPS, PRDS

    JWST FITS Writer development

    INS Master Schedule development DMS Automated Test System development

  • 7/31/2019 Wayne Bag Get t 112105

    10/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 10

    Why Use Earned Value?

    Obligates planning to the level of taskmanagement

    Less likely to overlook workProvidesobjective measures of progress

    Allows early detection of budget and

    schedule problemsAllows anobjective projection of eventual

    project cost and schedule

  • 7/31/2019 Wayne Bag Get t 112105

    11/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 11

    Key to Earned Value

    Determine the value for every taskprior to starting work!

  • 7/31/2019 Wayne Bag Get t 112105

    12/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 12

    Guidelines for Setting/Earning Value

    Use a consistent unit of measurement that makes

    sense for the project

    Dollarsrequired for large govt projects

    Hoursuseful on small projects; PSPSM

    Arbitrary numbernot recommended, but still used

    Consider task duration

    Select Earned Value Methods that are as objectiveas possible

  • 7/31/2019 Wayne Bag Get t 112105

    13/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 13

    Earned Value MethodsMethod Usage Examples

    Equivalent

    Units

    Value based on completed portion of a large number

    of completed activities

    S/W Implementation, H/W

    Production

    0-100 Value earned upon completing work that starts and

    ends within one status period

    Outlines, Document Preparation,

    Formal Reviews

    50-50 Part of value earned when work starts and remainder

    when it ends, usually when work straddles tworeporting periods; percentages are determined by the

    manager

    Short Engineering Analyses,

    System Design, Build andAcceptance Tests

    Interim

    Milestones

    Value earned at the completion of objective

    milestones; usually for work that straddles several

    consecutive status periods

    Long-Term Analyses, System

    Design, Requirements Definition

    Apportioned

    Effort

    Value earned is prorated based on a portion earned for

    another unit of work

    QA, Configuration Management,

    Database Management

    Percent

    Complete

    Value earned based on subjective estimate; usually

    for work that has no objective measure of

    completeness

    Long-Term Studies, Maintenance

    and Operations

    Level of

    Effort

    Value based on passage of time; usually for work that

    cannot be defined or measured

    Project Management,

    Receptionist, Help Desk

    Objectivity

  • 7/31/2019 Wayne Bag Get t 112105

    14/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 14

    $-

    $50

    $100

    $150

    $200

    $250

    10/1/2005

    11/26/2005

    1/21/2006

    3/18/2006

    5/13/2006

    7/8/2006

    9/2/2006

    10/28/2006

    12/23/2006

    2/17/2007

    4/14/2007

    6/9/2007

    8/4/2007

    9/29/2007

    11/24/2007

    1/19/2008

    3/15/2008

    5/10/2008

    Date

    Value($1000s)

    Planned

    Actual

    Example: Planned vs. Actuals

    $13,000 under budget!

    Current Date

  • 7/31/2019 Wayne Bag Get t 112105

    15/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 15

    $-

    $50

    $100

    $150

    $200

    $250

    10/1/2005

    11/26/2005

    1/21/2006

    3/18/2006

    5/13/2006

    7/8/2006

    9/2/2006

    10/28/2006

    12/23/2006

    2/17/2007

    4/14/2007

    6/9/2007

    8/4/2007

    9/29/2007

    11/24/2007

    1/19/2008

    3/15/2008

    5/10/2008

    Date

    Value($1

    000s)

    PV

    EV

    AC

    Example: Earned ValueBAC=$200

    SV=EV-PV=($30) CV=EV-AC=($17)

    PMB

    PV

    EVAC

  • 7/31/2019 Wayne Bag Get t 112105

    16/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 16

    Earned Value Concepts

    Planned Value (PV)planned cost of doingthe scheduled work(formerly BCWS)

    Earned Value (EV)plannedcost of the

    work completed (formerly BCWP)

    Actual Cost (AC)actual cost of the work

    completed (formerly ACWP)

    Performance Measurement Baseline (PMB)the time-phased budget plan against

    which performance is measured

  • 7/31/2019 Wayne Bag Get t 112105

    17/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 17

    Earned Value Concepts (cont.)

    Schedule Variance (SV)measures how

    project is doing relative to the schedule

    SV = EVPVPositive Ahead of Sched., Negative Behind Sched.

    Cost Variance (CV)measures how project

    is performing; productivity measureCV = EVAC

    PositiveEfficient, Negative Inefficient

  • 7/31/2019 Wayne Bag Get t 112105

    18/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 18

    Earned Value Concepts (cont.)

    Budget Variance (BV)measures how

    project is doing against the budget

    BV = PVACPositive Under Budget, Negative Over Budget

    Budget At Completion (BAC)sum of the

    planned value plus the UndistributedBudget

  • 7/31/2019 Wayne Bag Get t 112105

    19/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 19

    $-

    $50

    $100

    $150

    $200

    $250

    10/1/2005

    11/26/2005

    1/21/2006

    3/18/2006

    5/13/2006

    7/8/2006

    9/2/2006

    10/28/2006

    12/23/2006

    2/17/2007

    4/14/2007

    6/9/2007

    8/4/2007

    9/29/2007

    11/24/2007

    1/19/2008

    3/15/2008

    5/10/2008

    Date

    Value($1

    000s)

    PV

    EVAC

    ETC

    Example: Earned Value

    VAC=BAC-EAC=($33)

    EAC=AC + ETC=$233

    ETC=(BAC-EV)/CPI=$146

    SPI=EV/PV=0.70

    CPI=EV/AC=0.81

  • 7/31/2019 Wayne Bag Get t 112105

    20/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 20

    Earned Value Concepts (cont.)Schedule Performance Index (SPI)

    measure of schedule compliance: is workbeing done at the planned rate?

    SPI = EV/PV1 Faster than planned

    Cost Performance Index (CPI)productivity measure: is the work costing

    what was expected?

    CPI = EV/AC< 1Inefficient, > 1 Efficient

  • 7/31/2019 Wayne Bag Get t 112105

    21/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 21

    Earned Value Concepts (cont.)

    Estimate To Complete (ETC)estimate of

    the effort required to complete the project

    from the current dateETC = (BACEV)/CPI

    Estimate At Completion (EAC)the

    estimated total cost of the project

    EAC = AC + ETC

  • 7/31/2019 Wayne Bag Get t 112105

    22/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 22

    Earned Value Concept SummaryAcronym Definition Equation Interpretation

    PV Budgeted cost of task (none)

    EV Earned value for task (none)

    AC Actual cost of task (none)

    SV Schedule Variance SV=EV - PV>0 = Ahead, 0 = Under, 0 = Productive, 1 = Faster, 1 = Efficient, < 1 = Inefficient

    ETC Estimate to Complete ETC=(BAC-EV) /CPI

    EAC Estimate At Completion EAC=AC+ETC

    VAC Variance at Completion VAC = BAC - EAC >0 = Under,

  • 7/31/2019 Wayne Bag Get t 112105

    23/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 23

    Costs of EVMS

    Marginal cost of using EVMS is estimated at lessthan 1% to a few% of total contract cost Based mainly on large DOD contracts with

    experienced EVMS users

    Some costs are unnecessary according to EVMScriteria, but effort is put into those activities anyway

    Expect costs to be higher at STScI due toinexperience in using EVM and our culture Mitigated by our implementation

    Christensen, David S., The Costs and Benefits of the Earned Value ManagementProcess, Acquisition review Quarterly, Fall, 1998, p. 373.

  • 7/31/2019 Wayne Bag Get t 112105

    24/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 24

    Benefits of Earned Value

    It is a single management control system thatprovides reliable data.

    It integrates work, schedule, and cost using a workbreakdown structure.

    The associated database of completed projects isuseful for comparative analysis.

    The cumulative cost performance index (CPI)provides an early warning signal.

    The schedule performance index provides an earlywarning signal.

    Christensen, David S., The Costs and Benefits of the Earned Value ManagementProcess, Acquisition review Quarterly, Fall, 1998, p. 373.

  • 7/31/2019 Wayne Bag Get t 112105

    25/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 25

    Benefits of Earned Value

    The CPI is a predictor for the final cost of theproject.

    It uses an index-based method to forecast the finalcost of the project.

    The to-complete performance index allowsevaluation of the forecasted final cost.

    The periodic (e.g., weekly or monthly) CPI is abenchmark.

    The management by exception principle canreduce information overload.

    Christensen, David S., The Costs and Benefits of the Earned Value ManagementProcess, Acquisition Review Quarterly, Fall, 1998, p. 373.

  • 7/31/2019 Wayne Bag Get t 112105

    26/26

    GSET Technical Seminar SeriesSpace Telescope

    Science Institute

    November 21, 2005 26

    The most common problem product teams face is

    unreasonable schedule pressure. When teams areforced to work to unreasonable schedules, they areunable to make useful plans. Every plan they

    produce misses managements edicted schedule and

    is therefore unacceptable. As a result, they mustwork without the guidance of an orderly plan. Underthese conditions, the team will generally take muchlonger to complete the project than they otherwisewould.

    Watts Humphrey, Pathways to Process Maturity: The Personal Software Processand Team Software Process, SEI Interactive, June 1999.