wayne bag get t 112105
TRANSCRIPT
-
7/31/2019 Wayne Bag Get t 112105
1/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 1
Earned Value Management:An Introduction and Short
Tutorial
Wayne Baggett
-
7/31/2019 Wayne Bag Get t 112105
2/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 2
Outline
What is Earned Value?
Government Requirements
Small Project Usage
Why Use Earned Value?
Earned Value in a NutshellConclusions
-
7/31/2019 Wayne Bag Get t 112105
3/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 3
What is Earned Value?
How does
Dilbert knowthis?
-
7/31/2019 Wayne Bag Get t 112105
4/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 4
What is Earned Value?
Project Management Technique Integrates technical performance requirements,
resource planning, and cost accounting withschedule
Provides insight into project status
Provides early warning signals for problems
Provides a disciplined means ofmanaging the project
-
7/31/2019 Wayne Bag Get t 112105
5/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 5
Government Requirements
OMB Circular A-11, Exhibit 300 (2004)
Requires EVMS for allmajor acquisitions
Agencies must have ANSI-compliant EVMS in placeby December 31, 2005
EVMS data must be used to identify problems and
provide realistic final cost estimates as a part of
decision packages Federal Acquisition Regulations (2005) amended
to require contractor-maintained EVMS
-
7/31/2019 Wayne Bag Get t 112105
6/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 6
Government RequirementsThese requirements apply to large projects or
programs; DOD requires
Contract Value $50M: validated ANSI-compliant
EVMS, structured reports and reviews, ongoing
surveillance
$50M > Contract Value $20M: ANSI-compliant
EVMS (validation not required), tailored reports and
reviews, ongoing surveillance
Contract Value < $20M: EVMS optional, ongoing
surveillance
Very rigid, heavily constrained system at this level
-
7/31/2019 Wayne Bag Get t 112105
7/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 7
Small Project Usage
Small projects provide the bestopportunities for earned-value employment Consider its use for all in-house funded
developmental projects where a firmcommitment is made to management.
Software projects can especially benefit fromthe employment of a simple earned-valueapproach.
(Fleming and Koppelman, Earned Value Project Management: APowerful Tool for Software Projects, Crosstalk, July, 1998, p.19.)
-
7/31/2019 Wayne Bag Get t 112105
8/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 8
Small Project Usage
The Personal Software Process (PSPSM) and TeamSoftware Process (TSPSM) use EVM PSP has practitioners estimate task efforts and track
their actual effortsTasks estimated are very smallabout 10 hours each
Data are used to improve future estimates
TSP expands the use of EVM to the project level
Use of PSP and TSP helps projects meet theircommitments (Tuma, D. and Webb, D., Personal Earned Value:Why Projects Using the Team Software Process Consistently MeetSchedule Commitments, Crosstalk, March 2005, p. 17.)
PSP and TSP are registered service marks of Carnegie Mellon University
-
7/31/2019 Wayne Bag Get t 112105
9/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 9
Small Project Usage
Several projects at STScI have used EVM:
Most used a tailored version of EVM
JWST S&OC development
FOS, PPS, PRDS
JWST FITS Writer development
INS Master Schedule development DMS Automated Test System development
-
7/31/2019 Wayne Bag Get t 112105
10/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 10
Why Use Earned Value?
Obligates planning to the level of taskmanagement
Less likely to overlook workProvidesobjective measures of progress
Allows early detection of budget and
schedule problemsAllows anobjective projection of eventual
project cost and schedule
-
7/31/2019 Wayne Bag Get t 112105
11/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 11
Key to Earned Value
Determine the value for every taskprior to starting work!
-
7/31/2019 Wayne Bag Get t 112105
12/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 12
Guidelines for Setting/Earning Value
Use a consistent unit of measurement that makes
sense for the project
Dollarsrequired for large govt projects
Hoursuseful on small projects; PSPSM
Arbitrary numbernot recommended, but still used
Consider task duration
Select Earned Value Methods that are as objectiveas possible
-
7/31/2019 Wayne Bag Get t 112105
13/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 13
Earned Value MethodsMethod Usage Examples
Equivalent
Units
Value based on completed portion of a large number
of completed activities
S/W Implementation, H/W
Production
0-100 Value earned upon completing work that starts and
ends within one status period
Outlines, Document Preparation,
Formal Reviews
50-50 Part of value earned when work starts and remainder
when it ends, usually when work straddles tworeporting periods; percentages are determined by the
manager
Short Engineering Analyses,
System Design, Build andAcceptance Tests
Interim
Milestones
Value earned at the completion of objective
milestones; usually for work that straddles several
consecutive status periods
Long-Term Analyses, System
Design, Requirements Definition
Apportioned
Effort
Value earned is prorated based on a portion earned for
another unit of work
QA, Configuration Management,
Database Management
Percent
Complete
Value earned based on subjective estimate; usually
for work that has no objective measure of
completeness
Long-Term Studies, Maintenance
and Operations
Level of
Effort
Value based on passage of time; usually for work that
cannot be defined or measured
Project Management,
Receptionist, Help Desk
Objectivity
-
7/31/2019 Wayne Bag Get t 112105
14/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 14
$-
$50
$100
$150
$200
$250
10/1/2005
11/26/2005
1/21/2006
3/18/2006
5/13/2006
7/8/2006
9/2/2006
10/28/2006
12/23/2006
2/17/2007
4/14/2007
6/9/2007
8/4/2007
9/29/2007
11/24/2007
1/19/2008
3/15/2008
5/10/2008
Date
Value($1000s)
Planned
Actual
Example: Planned vs. Actuals
$13,000 under budget!
Current Date
-
7/31/2019 Wayne Bag Get t 112105
15/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 15
$-
$50
$100
$150
$200
$250
10/1/2005
11/26/2005
1/21/2006
3/18/2006
5/13/2006
7/8/2006
9/2/2006
10/28/2006
12/23/2006
2/17/2007
4/14/2007
6/9/2007
8/4/2007
9/29/2007
11/24/2007
1/19/2008
3/15/2008
5/10/2008
Date
Value($1
000s)
PV
EV
AC
Example: Earned ValueBAC=$200
SV=EV-PV=($30) CV=EV-AC=($17)
PMB
PV
EVAC
-
7/31/2019 Wayne Bag Get t 112105
16/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 16
Earned Value Concepts
Planned Value (PV)planned cost of doingthe scheduled work(formerly BCWS)
Earned Value (EV)plannedcost of the
work completed (formerly BCWP)
Actual Cost (AC)actual cost of the work
completed (formerly ACWP)
Performance Measurement Baseline (PMB)the time-phased budget plan against
which performance is measured
-
7/31/2019 Wayne Bag Get t 112105
17/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 17
Earned Value Concepts (cont.)
Schedule Variance (SV)measures how
project is doing relative to the schedule
SV = EVPVPositive Ahead of Sched., Negative Behind Sched.
Cost Variance (CV)measures how project
is performing; productivity measureCV = EVAC
PositiveEfficient, Negative Inefficient
-
7/31/2019 Wayne Bag Get t 112105
18/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 18
Earned Value Concepts (cont.)
Budget Variance (BV)measures how
project is doing against the budget
BV = PVACPositive Under Budget, Negative Over Budget
Budget At Completion (BAC)sum of the
planned value plus the UndistributedBudget
-
7/31/2019 Wayne Bag Get t 112105
19/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 19
$-
$50
$100
$150
$200
$250
10/1/2005
11/26/2005
1/21/2006
3/18/2006
5/13/2006
7/8/2006
9/2/2006
10/28/2006
12/23/2006
2/17/2007
4/14/2007
6/9/2007
8/4/2007
9/29/2007
11/24/2007
1/19/2008
3/15/2008
5/10/2008
Date
Value($1
000s)
PV
EVAC
ETC
Example: Earned Value
VAC=BAC-EAC=($33)
EAC=AC + ETC=$233
ETC=(BAC-EV)/CPI=$146
SPI=EV/PV=0.70
CPI=EV/AC=0.81
-
7/31/2019 Wayne Bag Get t 112105
20/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 20
Earned Value Concepts (cont.)Schedule Performance Index (SPI)
measure of schedule compliance: is workbeing done at the planned rate?
SPI = EV/PV1 Faster than planned
Cost Performance Index (CPI)productivity measure: is the work costing
what was expected?
CPI = EV/AC< 1Inefficient, > 1 Efficient
-
7/31/2019 Wayne Bag Get t 112105
21/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 21
Earned Value Concepts (cont.)
Estimate To Complete (ETC)estimate of
the effort required to complete the project
from the current dateETC = (BACEV)/CPI
Estimate At Completion (EAC)the
estimated total cost of the project
EAC = AC + ETC
-
7/31/2019 Wayne Bag Get t 112105
22/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 22
Earned Value Concept SummaryAcronym Definition Equation Interpretation
PV Budgeted cost of task (none)
EV Earned value for task (none)
AC Actual cost of task (none)
SV Schedule Variance SV=EV - PV>0 = Ahead, 0 = Under, 0 = Productive, 1 = Faster, 1 = Efficient, < 1 = Inefficient
ETC Estimate to Complete ETC=(BAC-EV) /CPI
EAC Estimate At Completion EAC=AC+ETC
VAC Variance at Completion VAC = BAC - EAC >0 = Under,
-
7/31/2019 Wayne Bag Get t 112105
23/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 23
Costs of EVMS
Marginal cost of using EVMS is estimated at lessthan 1% to a few% of total contract cost Based mainly on large DOD contracts with
experienced EVMS users
Some costs are unnecessary according to EVMScriteria, but effort is put into those activities anyway
Expect costs to be higher at STScI due toinexperience in using EVM and our culture Mitigated by our implementation
Christensen, David S., The Costs and Benefits of the Earned Value ManagementProcess, Acquisition review Quarterly, Fall, 1998, p. 373.
-
7/31/2019 Wayne Bag Get t 112105
24/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 24
Benefits of Earned Value
It is a single management control system thatprovides reliable data.
It integrates work, schedule, and cost using a workbreakdown structure.
The associated database of completed projects isuseful for comparative analysis.
The cumulative cost performance index (CPI)provides an early warning signal.
The schedule performance index provides an earlywarning signal.
Christensen, David S., The Costs and Benefits of the Earned Value ManagementProcess, Acquisition review Quarterly, Fall, 1998, p. 373.
-
7/31/2019 Wayne Bag Get t 112105
25/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 25
Benefits of Earned Value
The CPI is a predictor for the final cost of theproject.
It uses an index-based method to forecast the finalcost of the project.
The to-complete performance index allowsevaluation of the forecasted final cost.
The periodic (e.g., weekly or monthly) CPI is abenchmark.
The management by exception principle canreduce information overload.
Christensen, David S., The Costs and Benefits of the Earned Value ManagementProcess, Acquisition Review Quarterly, Fall, 1998, p. 373.
-
7/31/2019 Wayne Bag Get t 112105
26/26
GSET Technical Seminar SeriesSpace Telescope
Science Institute
November 21, 2005 26
The most common problem product teams face is
unreasonable schedule pressure. When teams areforced to work to unreasonable schedules, they areunable to make useful plans. Every plan they
produce misses managements edicted schedule and
is therefore unacceptable. As a result, they mustwork without the guidance of an orderly plan. Underthese conditions, the team will generally take muchlonger to complete the project than they otherwisewould.
Watts Humphrey, Pathways to Process Maturity: The Personal Software Processand Team Software Process, SEI Interactive, June 1999.