WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Upload: calvin-greene

Post on 27-Dec-2015

254 views

Category:

Documents


7 download

TRANSCRIPT

Page 1: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

WATER & WASTEWATER ENGINEERING Water Supply Engineering

Lecture No. 3

Surface Water Collection Works

Page 2: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Water Supply System

• Components1. Collection Works 2. Purification Works3. Distribution Works

Page 3: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

River

LLP Intake

Mixing Flocculation

Sedimentation Filtration

Disinfection

Pipe Network

HLP

Water Treatment

Plant (WTP)

Page 4: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Collection Works• 1. Intake Structure The basic function of the

intake structure is to help in safely withdrawing water from the source and then to discharge this water into the withdrawal conduit (normally called intake conduit), through which it flows up to water treatment plant(WTP).

• 2. Sump In which water is collected to be pumped to water treatment plant.

• 3. Pump Through which water is pumped to water treatment plant.

Page 5: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Collection Works

• Intakes consist of the opening, strainer and the conduit conveying the water , usually by gravity, to a well sump.

• From the well the water is pumped to the treatment plant

Page 6: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Intake Types

Factors affecting choice of intake type: 1. Water width 2. Water depth 3. Navigation 4. Fluctuation in water level

Page 7: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Intake Types

1- shore intake2- pipe intake3- Tower intake4- submerged intake

Page 8: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Factors Governing Location of Intake

1. At a straight part of the canal to avoid silting and scouring zones.

2. Upstream any source of pollution. 3. Fix a prohibited area 150 m upstream and 50

m downstream the intake location.4. Away from the surface to avoid floating

materials and away from the bottom to avoid fine materials.

Page 9: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works
Page 10: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works
Page 11: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works
Page 12: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works
Page 13: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works
Page 14: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Design of Shore Intake

• Design capacity: pop. × qav. × 1.4 × 1.1Qd = 1000 × working hrs of LLP × 60 × 60Design of intake conduit:Qd = A × V × no

Assume V = 1 m/sec.

Then, Qd = (ΠD2/4) × 1 × no Get D, V actual

No. of intake conduits < 2

Page 15: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Design of Shore Intake

• Design of sump:Qd = V / T Assume T = 5 - 15 min.V = Qd × T Get V V = L × B × d Assume d = 1 . 0 - 3 . 0 m L = n × S

Get B

n: no. of pumps S = 2 - 3 m

B < 2 m

Page 16: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Design of Shore Intake

Design of Pump House: Dimensions • L1 = L + 2 m

• B1 = L1 / 2

Pumps • HP = γ × Qd × Hm

75 × η • Hm = Hd + Hs

γ = 1 Q= Lit γ = 1 Q= m3/sec

Qd= 1.4 Qavg

Page 17: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Design of Shore Intake

• Hd is the height from mixing tank W.L to the axis of the pump

• Hs is the height from the axis of the pump to the W.L of the sump

Hm ≈ 3m at least

Page 18: WATER & WASTEWATER ENGINEERING Water Supply Engineering Lecture No. 3 Surface Water Collection Works

Design of Shore Intake

• Σ losses = Screen losses + Hfriction + inlet & outlet losses

• Screen losses = 0.1 m • Hfriction = 4 × f × L × Vact

2 ( Intake conduit)

2 × g × Dcom

• Inlet & outlet losses = 1.5 × Vact2 2 × g

L= (30-70) cm