    Introduction

    EastLink: largest urban infrastructure project in Australia

    $2.5 billion, 45 km toll road project

    PB and Hyder Joint Venture

    71 of 84 bridges in original scope

    Currently under construction

    Hyder Consulting Pty Ltd4

    Introduction contd

    45 km toll road from Mitcham to Frankston

  • 8/10/2019 Warren - Eastlink Super T Bridges

    3/23

    Hyder Consulting Pty Ltd5

    Introduction contd

    71 Bridges over 5 regions

    Hyder Consulting Pty Ltd6

    Precast Planning

    Standard Precast Units

    Super-T to AS5100 profile

  • 8/10/2019 Warren - Eastlink Super T Bridges

    4/23

    Hyder Consulting Pty Ltd7

    Detailed Design

    Standard Precast Units

    1800mm Deep Super-T Beams

    Can span up to 38m long and weigh over 80 tonnes

    Reduced the number of spans required for each bridge

    Hyder Consulting Pty Ltd8

    Precast Planning

    Standard Precast Units

    Precast Pier

    & Crosshead Construction

    close to movingtraffic

    Reduce site costs

  • 8/10/2019 Warren - Eastlink Super T Bridges

    5/23

    Hyder Consulting Pty Ltd9

    Precast Planning

    Standard Precast Units

    Barrier Unit

    Hyder Consulting Pty Ltd10

    Precast Planning

    Standard Precast Units

    Wingwalls and Fenderwalls

  • 8/10/2019 Warren - Eastlink Super T Bridges

    6/23

    Hyder Consulting Pty Ltd11

    Precast Planning

    Standard Precast Units

    Noise WallPanels

    Hyder Consulting Pty Ltd12

    Detailed Design

    D&C Contract O&M Contract

    Concessionaire

    Southern & Eastern

    Integrated Transport

    Authority (SEITA)

    ConnectEast

    Independent Review (IR)

    SKM/Maunsell/Davis

    Langdon

    Environmental ManagementRepresentative

    Financier EngineerURS/Evans & Peck

    Thiess John Holland

    (TJH)Transfield Services

    (TSL)

    Proof Engineer/

    Construction Verifier

    SMEC/KBR

    Independent Quality

    Auditor

    Tolling

    SICE ConstructionDesign

    Parsons Brinckerhoff

    Hyder JV

    Wood Marsh

    UGR

    Connell Wagner

    Road Safety

    Auditor

    Design

    Consultant

    Review Process:

  • 8/10/2019 Warren - Eastlink Super T Bridges

    7/23

    Hyder Consulting Pty Ltd13

    Detailed Design

    Standardised approach used in design

    Details of connections of precast critical to design

    Lifting of precast incorporated in design

    Inclusion of Urban Design features

    Safety in design was considered

    Value Engineering process continued duringdetailed design

    Hyder Consulting Pty Ltd14

    Detailed Design

    Super T beams

    PBHyder designed58 Super-T bridges

  • 8/10/2019 Warren - Eastlink Super T Bridges

    8/23

    Hyder Consulting Pty Ltd15

    Detailed Design

    Super T beam Design involved:

    Standardising Super-T beam sizes toensure 24 hour turn around inproduction

    Allowing for long periods of storagebefore erection

    Using integral abutments for bridgesgiving greater tolerance during erection

    Hyder Consulting Pty Ltd16

    Detailed Design

    Super T beam Design

  • 8/10/2019 Warren - Eastlink Super T Bridges

    9/23

    Hyder Consulting Pty Ltd17

    Detailed Design

    Precast Segmental Pier Design

    Hyder Consulting Pty Ltd18

    Detailed Design

    Detailing incorporating Urban Design features

    Pier constructionwith falsework

    Precast Segmental Pier Design

  • 8/10/2019 Warren - Eastlink Super T Bridges

    10/23

    Hyder Consulting Pty Ltd19

    Detailed Design

    Precast Wing Walls

    Wingwall Lifted into place

    Abutment beam poured

    Insitu concrete fenderwall pouredconnecting to wingwall

    Hyder Consulting Pty Ltd20

    Detailed Design

    Barriers

    Designed for Highand MediumContainment Levels

    (High 1000 kN) Connection using

    stitch joint to deckand pin joint forcontinutiy

    Incorporating UrbanDesign patterning

  • 8/10/2019 Warren - Eastlink Super T Bridges

    11/23

    Hyder Consulting Pty Ltd21

    Detailed Design

    Precast Components designed using 3D CAD

    Hyder Consulting Pty Ltd22

    Detailed Design

    Precast Components designed using 3D CAD

  • 8/10/2019 Warren - Eastlink Super T Bridges

    12/23

    Hyder Consulting Pty Ltd23

    Precast Facility

    Site selected in Morwell

    with following benefits: Using an established

    Plant (Di Fabro)

    Availability of Labour

    Close to concrete supplierand other resources

    Established TransportRoutes to Eastlink

    Hyder Consulting Pty Ltd24

    Precast Facility

    Steel Super-TMoulds

    Fabricated inChina

    750 2 beamcapacity mould

    1350 2 beamcapacity mould

    1500 2 beamcapacity mould

    1800 1 beamcapacity mould

  • 8/10/2019 Warren - Eastlink Super T Bridges

    13/23

    Hyder Consulting Pty Ltd25

    Flat Beds for Wingwalls & Fenderwalls

    Precast Facility

    Hyder Consulting Pty Ltd26

    Precast Facility

    Standard Precast Pier Mould

  • 8/10/2019 Warren - Eastlink Super T Bridges

    14/23

    Hyder Consulting Pty Ltd27

    Precast Facility

    Barrier moulds designed for

    upside down casting

    Hyder Consulting Pty Ltd28

    Precast Production

    Super-T Beams

    Radiant Heat curing

    24 Hour turn-around

    Double stacking

  • 8/10/2019 Warren - Eastlink Super T Bridges

    15/23

    Hyder Consulting Pty Ltd29

    Precast Production

    Barriers

    Standard lengthsto maximiseoutput

    Developing aPin ConnectionDetail

    Hyder Consulting Pty Ltd30

    Precast Production

    Noise Walls

    Post & Panel Wall units castvertically in Battery Moulds

    Rock Face template for cantilever walls

  • 8/10/2019 Warren - Eastlink Super T Bridges

    16/23

    Hyder Consulting Pty Ltd31

    Construction

    Transportation

    Super-T beams:

    87 tonnes

    40 m long

    Transport studyundertaken

    Hyder Consulting Pty Ltd32

    Construction

    Lifting

    500 tonne crane

    Snow Whitepurchasedspecifically for project

  • 8/10/2019 Warren - Eastlink Super T Bridges

    17/23

    Hyder Consulting Pty Ltd33

    Construction

    Lifting

    Flexibility in lifting(end to - end)

    Hyder Consulting Pty Ltd34

    Construction

    Installation

    Placement &Levelling

    Connected byStitch Joints,BoltedConnections orStressed anchors

  • 8/10/2019 Warren - Eastlink Super T Bridges

    18/23

    Hyder Consulting Pty Ltd35

    Additional Structures

    Other Precast Elements include:

    Noise walls

    Precast soil wall facing

    Humedeck units

    Culverts and Pits

    Hyder Consulting Pty Ltd36

    EastLink Bridges 17 EastLink bridges over local roads

    EastLink over Railway Parade

    38m spans, 1800mm deep Super-T beams

  • 8/10/2019 Warren - Eastlink Super T Bridges

    19/23

    Hyder Consulting Pty Ltd37

    EastLink Bridges

    16 EastLink bridges over waterways

    Bored piles and columns at pier

    Hyder Consulting Pty Ltd38

    EastLink BridgesMonash Interchange 3rd largest interchange in Southern Hemisphere

    Nine bridges

    Aerial view ofinterchange

    Under construction

    EastLink N/B Entry Ramp

    128m, 4 span Trouser Leg

    bifurcation for multiple access

  • 8/10/2019 Warren - Eastlink Super T Bridges

    20/23

  • 8/10/2019 Warren - Eastlink Super T Bridges

    21/23

    Hyder Consulting Pty Ltd41

    Construction Progress(cont.)

    Hyder Consulting Pty Ltd42

    Construction Progress(cont.)

  • 8/10/2019 Warren - Eastlink Super T Bridges

    22/23

    Hyder Consulting Pty Ltd43

    Construction Progress(cont.)

    Hyder Consulting Pty Ltd44

    Construction Progress(cont.)

  • 8/10/2019 Warren - Eastlink Super T Bridges

    23/23

    Hyder Consulting Pty Ltd45

    TJH / PBHyder

    Thank You