w10 not every bore is boring - sciandra
DESCRIPTION
TRANSCRIPT
HORIZONTAL DIRECTIONAL DRILLING NOT EVERY BORE IS BORING
Florida Chapter APWA - 2013 Annual Meeting and Trade Show
April 24, 2013
Jason Sciandra, P.E.
Pipe Pullback
Outline
• Overview of HDD
• Overview of case study
• Design considerations
• Geotechnical investigation and laboratory testing program
• Contract specifications
• Submittal process
• Critical factors during construction
Horizontal Directional Drilling Overview
• Surface conflicts (e.g., waterways, major road, buildings)
• Subsurface conflicts (e.g., existing utilities and infrastructure)
• Environmental regulation (e.g., wetlands)
Case Study Overview
Intake
WWTP
Difficult
Property
Owner
Environmentally
Sensitive Areas
Two HDDs
Weir
Case Study Overview (Cont.)
Entry Pit
Exit Pit
Case Study Overview (Cont.)
Exit Pit
Pipe Laydown Area
Blocked Off
Staging Area
Design Considerations
• Preliminary pull-back calculations – contractor should confirm
– Tensile stress, stretching
– Type of machine required
– Pipe material
• External force on the pipe (soil pressure) – contractor should confirm
• Pipe material – HDPE vs. Fusible PVC vs. other
Design Considerations – Pipe Material Selection
Design Considerations – Pipe Material Selection
Geotechnical Investigations
• Number and type of soil borings
• Types of soil borings
– Shallow land borings
– Deep land borings
– Deep water borings
Geotechnical Investigations (Cont.)
• Key findings:
– Mixed face
– Weathered, fractured limestone
• Store samples until project completion
Contract Specifications
• Competitive procurement – can’t just choose best contractor
• Specifications can be used to establish minimum experience criteria
– Project Example:
Submittal Process
• Two Objectives:
– Document the contractor’s equipment and approach
– Engage contractor in the thought process of completing the work
Submittal Process (Cont.)
Typical submittals:
1. Contact Grouting Plan
2. Contingency Plan for Remediation of Potential Problems
3. Disposal of Spoils and Drilling Fluids Plan
Submittal Process (Cont.)
4. Equipment Layout Plan
Submittal Process (Cont.)
4. Equipment Layout Plan
Submittal Process (Cont.)
4. Equipment Layout Plan
Submittal Process (Cont.)
5. Inadvertent Return and Surface Spill Contingency Plan
6. Horizontal Directional Drilling Work Plan
Maximum Allowable Mud Pressure for Hydraulic Fracture
Submittal Process (Cont.)
7. Maximum Allowable Drilling Fluid Pressure Calculations
Maximum Allowable Mud Pressure for Shear Failure
Submittal Process (Cont.)
8. Methods, Equipment, and Materials Description Plan
9. Pipe Filling Methods and Testing
10. Protection of Adjacent Structures and Facilities Plan
11. Pipe Stress Calculations
Submittal Process (Cont.)
10. Protection of Adjacent Structures and Facilities Plan
Preconstruction
Survey
Submittal Process (Cont.)
12. Pullback Calculations
Pull-back Force and Hyrdokinetic Force
Submittal Process (Cont.)
13. Qualifications
5 Years Experience
Specified Material
Experience
Submittal Process (Cont.)
13. Qualifications
Field
Supervisor
Experience
Submittal Process (Cont.)
14. Radius of Curvature Confirmation
Submittal Process (Cont.)
15. Rig Capacity Plan
16. Safety Plan
17. Schedule
18. Soil Separation Plan
19. Surveying Equipment and Procedures
20. As-built pilot bore profile
21. Daily logs and records
Critical Factors during Construction
• Communication
• Risk mitigation meetings
• Daily bore logs and as-built submittals
Communication
• Keep lines of communication open between:
– Contractor and engineer
– Contractor and owner
– Contractor and subcontractor (if applicable)
– Contractor and property owners
Risk Mitigation Meetings
• Specification requirement: “At least 15 working days prior to each major operations milestone, the CONTRACTOR and HDD superintendent shall attend a risk mitigation meeting with representatives of the ENGINEER and OWNER for each HDD crossing.”
• Milestones can include: – Rig mobilization and setup.
– Pilot bore drilling.
– Pre-reaming and reaming.
– Layout and thermal butt-fusing of pipe.
– Pressure testing of pipe prior to pullback.
– Final reaming and pullback of pipe.
– Pressure testing of pipe after installation.
– Mandrel/pig test to confirm deformations of pipe are within allowable tolerances.
Daily Logs and As-Built Submittals
Plan View
Profile View
Construction Videos – Pipe Layout Side
Construction Videos – Ballast Water
Construction Videos – Drill Rig Side
Construction Photos – Pull Head
Construction Photos – Ream Head
Construction Photos – Pipe Fusing Machine
Conclusion
• Design considerations
• Geotechnical investigation and laboratory testing program
• Contract specifications
• Contractor selection
• Submittal process
• Critical factors during installation
Questions