vote no. 11 annual report 2014/2015 financial year...flisp financed-linked individual subsidy...
TRANSCRIPT
-
1
VOTE NO. 11
ANNUAL REPORT
2014/2015 FINANCIAL YEAR
-
2
Contents
PART A: GENERAL INFORMATION ................................................................................................... 4
1. DEPARTMENT GENERAL INFORMATION .............................................................................. 5
2. LIST OF ABBREVIATIONS/ACRONYMS .................................................................................. 6
3. FOREWORD BY THE MEC ....................................................................................................... 8
4. REPORT OF THE ACCOUNTING OFFICER .......................................................................... 11
5. STATEMENT OF RESPONSIBILITY AND CONFIRMATION OF ACCURACY OF THE ANNUAL REPORT ............................................................................................................................... 15
6. STRATEGIC OVERVIEW ......................................................................................................... 16
6.1 Vision ................................................................................................................................ 16
6.2 Mission .............................................................................................................................. 16
6.3 Values ............................................................................................................................... 16
7. LEGISLATIVE AND OTHER MANDATES ............................................................................... 17
8. ORGANISATIONAL STRUCTURE .......................................................................................... 19
PART B: PERFORMANCE INFORMATION ....................................................................................... 20
1. AUDITOR GENERAL’S REPORT: PREDETERMINED OBJECTIVES ................................... 21
2. OVERVIEW OF DEPARTMENTAL PERFORMANCE ............................................................. 21
2.1 Service Delivery Environment .......................................................................................... 21
2.2 Service Delivery Improvement Plan ................................................................................. 22
2.3 Organisational environment .............................................................................................. 23
3. STRATEGIC OUTCOME ORIENTED GOALS ........................................................................ 23
4. PERFORMANCE INFORMATION BY PROGRAMME ............................................................ 26
4.1 Programme 1: Administration ........................................................................................... 26
4.2 Programme 2: Human Settlements .................................................................................. 31
4.3 Programme 3: Cooperative Governance .......................................................................... 38
4.4 Programme 4: Traditional Affairs ...................................................................................... 44
5. TRANSFER PAYMENTS ......................................................................................................... 47
5.1. Transfer payments to public entities ................................................................................. 47
5.2. Transfer payments to all organisations other than public entities .................................... 47
6. CONDITIONAL GRANTS ......................................................................................................... 47
6.1. Conditional grants and earmarked funds paid .................................................................. 47
6.2. Conditional grants and earmarked funds received ........................................................... 47
7. DONOR FUNDS ....................................................................................................................... 48
7.1. Donor Funds Received ..................................................................................................... 48
8. CAPITAL INVESTMENT .......................................................................................................... 48
8.1. Capital investment, maintenance and asset management plan ....................................... 48
-
3
PART C: GOVERNANCE .................................................................................................................... 49
1. RISK MANAGEMENT............................................................................................................... 50
2. FRAUD AND CORRUPTION ................................................................................................... 51
3. MINIMISING CONFLICT OF INTEREST ................................................................................. 51
4. CODE OF CONDUCT .............................................................................................................. 52
5. HEALTH SAFETY AND ENVIRONMENTAL ISSUES ............................................................. 52
6. PORTFOLIO COMMITTEES .................................................................................................... 53
7. SCOPA RESOLUTIONS .......................................................................................................... 53
8. PRIOR MODIFICATIONS TO AUDIT REPORTS .................................................................... 60
9. INTERNAL CONTROL UNIT .................................................................................................... 60
10. INTERNAL AUDIT AND AUDIT COMMITTEES ...................................................................... 62
11. AUDIT COMMITTEE REPORT ................................................................................................ 65
PART D: HUMAN RESOURCE MANAGEMENT ................................................................................ 69
1. INTRODUCTION ...................................................................................................................... 70
2. OVERVIEW OF HUMAN RESOURCES .................................................................................. 70
3. HUMAN RESOURCES OVERSIGHT STATISTICS ................................................................ 71
PART E: FINANCIAL INFORMATION .............................................................................................. 103
1. REPORT OF THE AUDITOR GENERAL ....................................................................................... 104
2. ANNUAL FINANCIAL STATEMENTS .................................................................................... 109
-
4
PART A: GENERAL INFORMATION
-
5
1. DEPARTMENT GENERAL INFORMATION
PHYSICAL ADDRESS: 20 Rabe Street
Polokwane
0699
POSTAL ADDRESS: Private Bag X9485
Polokwane
0700
TELEPHONE NUMBER/S: +27 15 284 5000
FAX NUMBER: +27 15 293 1520
EMAIL ADDRESS: [email protected]
WEBSITE ADDRESS : www.coghsta.limpopo.gov.za
mailto:[email protected]
-
6
2. LIST OF ABBREVIATIONS/ACRONYMS
AFS Annual Financial Statements
AGSA Auditor General of South Africa
BBBEE Broad Based Black Economic Empowerment
CDP Community Development Programme
CDW Community Development Worker
CFO Chief Financial Officer
CoGHSTA Cooperative Governance Human Settlements and Traditional Affairs
CRU Community Residential Units
DORA Division of Revenue Act
EAP Employee Assistance Programme
EU European Union
EXCO Executive Council
FLISP Financed-Linked Individual Subsidy Programme
GITO Government Information Technology Office
HDA Housing Development Agency
HOD Head of Department
HSDG Human Settlements Development Grant
HSS Housing Subsidy System
IDP Integrated Development Plan
IGR Intergovernmental Relations
ISHS Integrated Sustainable Human Settlements
LED Local Economic Development
LGTAS Local Government Turnaround Strategy
LUMS Land Use Management Scheme
MEC Member of the Executive Council
-
7
MIG Municipal Infrastructure Grant
MPAC Municipal Public Accounts Committee
MTEF Medium Term Expenditure Framework
NDoHS National Department of Human Settlements
NHFC National Housing Finance Corporation
NUSP National Upgrading Support Programme
PFMA Public Finance Management Act
PGP Provincial Growth Points
PMU Project Management Unit
POA Programme of Action
SISP Strategic Information Systems Plan
SDF Spatial Development Framework
SCM Supply Chain Management
SMME Small Medium and Micro Enterprises
SAIGA Southern African Institute of Government Auditors
SCOPA Standing Committee on Public Accounts
SDIP Service Delivery Improvement Plan
SIU Special Investigations Unit
SITA State Information Technology Agency
SLA Service Level Agreement
TR Treasury Regulations
USDG Urban Settlement Development Grant
CWP Community Works Programme
WSP Workplace Skills Plan
-
8
3. FOREWORD BY THE MEC
Name: Ms. MG Makhurupetje
Title: Member of the Executive Committee
The second year of the current Administration coincides with the 60th anniversary of the
Freedom Charter, the ruling African National Congress’s Bible founded in Kilptown in
1955. The Freedom Charter is more relevant today as it was then for its call for a just
society based on the bill of rights which is enshrined in the country’s Constitution. As we
move forward with the actualisation of the Freedom Charter, ours is to ensure that we
sustain the good work of the past 21 years as we make our due contribution towards
changing the living conditions of our people, mindful of the fact that we must do things
differently and faster because a better life for all cannot be delayed any longer. In moving
forward to restoring the dignity of our people, we must at all times refer to our core
mandates which are:
Outcome Eight: “Create Sustainable Human Settlements and Improve the Quality of
Household Life” and
Outcome Nine: “A Responsive, Accountable, Effective and Efficient Local Government
System”.
Human Settlements
The Freedom Charter is unequivocal in its expression that “there shall be houses,
security and comfort”, and as the Department we declare that this shall be our rallying
song throughout.
In addition to the Freedom Charter, we allude to the following:
All people shall have the right to live where they choose, be decently housed, and to
bring up their families in comfort and security;
Unused housing space will be made available to the people to build their own houses;
Rent shall be lowered;
-
9
Slums shall be demolished, and new suburbs built where there shall be adequate
transport, roads, lighting, playing fields, crèches and social centres;
Fenced locations and ghettoes shall be abolished, and laws which break up families shall
be repealed.
As a Department we are committed to building on the progress achieved in the 21years
of democracy, while recognising that more still needs to be done, particularly with the
implementation of the National Development Plan, Vision 2030.
We shall make strides in developing our housing infrastructure that supports the
development of human capital, including access to water, sanitation and that supports
economic growth and development as well as quality of life of citizens.
Human settlement must be understood in the context of social development and radical
economic transformation as well as meeting the objectives of rolling back the quagmire of
underdevelopment.
Currently 9 000 units are at construction stage, and we have committed the entire budget
for the rural housing projects. By March 2015 over 1900 units were completed while
others were at foundation, wall plate and roof level.
We are planning to transfer 3 700 housing units to beneficiaries through the Enhanced
Extended Discount Benefit Scheme and Registration and Endorsement Programme.
Our Department is undoubtedly poised for a development trajectory that reflects the
steady progress in infrastructure investment. It is within this context that of the R1,385
billion allocated to the programme, R1,285 billion is the Human Settlements Development
Grant earmarked for funding the human settlement programme, as guided by the
Outcome 8 of the Medium Term Strategic Framework.
Co-operative Governance
The Department recommits itself to the 10 high-level developments targets as presented
by the Premier during the State of the Province Address. Key amongst these
development plans to the Department is:
Increased access to basic water to 90% by 2020;
Increased access to electricity to 90% by 2020;
Increased access to sanitation to 50% by 2020.
In this regard we are delighted with some of the developments regarding provision of
water in the Province.
We continue to regard Local Government as an important sphere of government as they
are very close to the people. We will continue to support this sphere so that it discharges
its duties, mainly through the Back to Basics programme in order to:
-
10
provide democratic and accountable government for local communities;
provide services to communities in a sustainable manner;
promote social and economic development;
encourage the involvement of communities and community organisations in
matters of local government.
Be that as it may, here and there we come across challenges as we discharge our duties.
As a Province we are experiencing a decline in housing delivery from the previous two
financial years which resulted from the withholding of the Human Settlements
Development Grant, and the subsequent housing pilot procurement project by the
Section 100 Intervention Task Team which could not yield the expected results on the
appointment of contractors to build 10 500 units.
I take this opportunity to express my sincere gratitude to the Premier of our Province,
Honourable Chupu Mathabatha for entrusting me with the Department of Cooperative
Governance, Human Settlements and Traditional Affairs. As we celebrate the 60th
anniversary of the Freedom Charter, we are mindful of the task that lies ahead, and we
declare that until the people of Limpopo are liberated from all forms of social and
economic oppression, we shall never give up.
It is my utmost honour and privilege to present this Annual Report of the Department of
Cooperative Governance, Human Settlements and Traditional Affairs for the 2014/15
Financial Year.
Ms. MG Makhurupetje MEC: Co-operative Governance, Human Settlements and Traditional Affairs Date: 31 July 2015
-
11
4. REPORT OF THE ACCOUNTING OFFICER
Name: Mr. M.G. Makoko
Title: Acting Head of Department
Overview of the operations of the Department:
The 2014/15 Annual Report presents the performance of the Department in its efforts to fulfil its
constitutional mandate and its vision for integrated, sustainable human settlements in line with
outcome 8, 9 and 12. The Department has recorded significant progress on improving financial
management in municipalities through continuous capacitation initiatives as well as monitoring
and evaluation of this important sphere of government.
In support to initiatives of job opportunities created, the Province has received additional funding
from CoGTA on CWP, which provided about 21 000 job opportunities to participants.
The institutions of Traditional Leadership have been supported through coordination of
stakeholders to participate in the initiation schools management. Additional compensation for
Traditional Leaders has been streamlined with the pronouncement made by the President.
The Human Settlements sector has had its fair share of challenges for the past two financial
years. However the Department is ready to turn the situation around to ensure that services are
delivered to the people of Limpopo as expected.
The system of governance and accountability has matured in the Department, which is congruent
to the expectations by the public at large. This is credited to the management team of the
Department as well as oversight institutions who quality-check the Departments’ obligations
initiatives regularly.
-
12
Overview of the financial results of the Department:
Departmental receipts
Departmental receipts
2014/2015 2013/2014
Estimate Actual Amount
Collected
(Over)/Under Collection
Estimate
Actual Amount
Collected
(Over)/Under Collection
R’000 R’000 R’000 R’000 R’000 R’000
Sale of goods and services other than capital assets
1 274 1 273 1 988 1 083 (94)
Transfers received - - - 2 000 (2 000)
Fines, penalties and forfeits - - - 11 - 11
Interest, dividends and rent on land 129 93 36 61 231 (170)
Sale of capital assets 268 268 - 225 - 225
Financial transactions in assets and liabilities
1 254 1 501 (247) 1 215 1 247 (32)
Total 2 925 3 135 (210) 2 500 4 561 (2 060)
The Department has collected R3.135 million (2013/14: R4.561 million) which is 7.15% more than
planned. The better than anticipated performance is mainly due to money received from the
National Department Human Settlements in respect of debt recoveries by the SIU.
Revenue Tariff policy
The Department has implemented transversal tariffs as determined and approved by the
Provincial Treasury during the year under review.
Irrecoverable debts written off
A total of R6.5 million was written off as irrecoverable debts in terms of the transversal debt
management policy approved by Provincial Treasury.
No new measures were instituted during the course of the year to raise additional revenue.
However, the transversal revenue management policy was implemented to ensure more
efficient/effective revenue collection.
Capital assets amounting to R268 000 were sold during the year under review.
Programme Expenditure
Programme Name
2014/2015 2013/2014
Final Appropriation
Actual Expenditure
(Over)/ Under
Expenditure
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
R’000 R’000 R’000 R’000 R’000 R’000
Administration 276 838 274 729 2 109 261 201 256 757 4 444
Human Settlements (verify) 923 829 676 932 246 897 776 695 394 695 382 000
Co-Operative Governance 232 805 232 313 492 239 642 233 880 5 762
Traditional Institutional Development 342 044 341 498 546 311 455 301 306 10 149
Total 1 775 516 1 525 470 250 046 1 588 993 1 186 638 402 355
The Department spent R1.525 billion (2013/14: R1.187 billion) of the total allocation of R1.776
million which represents 85.9% (2013/14: 74.7%). The spending trend at programme level has
been depicted in the table above.
-
13
The expenditure of R1.525 billion includes R66 million which was defrayed from prepayments
made to ESKOM in prior years.
The underspending is mainly in the Human Settlements programme due to late appointment of
service providers for low cost housing projects. The underspent amount is committed to the
existing housing projects and the roll-over of these funds has since been approved.
Virements
Reason for the virement
The virements were effected for the defrayment of excess expenditure in respect of leave
gratuities as well as transport costs within Goods and Services. Savings realised were
utilised to write off irrecoverable debts.
Unauthorised, fruitless and wasteful expenditure
The Department incurred fruitless and wasteful expenditure of R4m during the year under review
as disclosed in the Annual Financial Statements.
Future plans of the Department
Regular monitoring of service providers to ensure compliance with the service contracts with the
Department as well as close monitoring and support of municipalities and traditional leadership
institutions to ensure continued improvements in service delivery.
Supply chain management
o The major challenge experienced in SCM was late procurement of low cost houses as
already stated
o The SCM processes and systems are in place to prevent irregular expenditure and there is
strict adherence to legislation and policies.
Programme Name
2014/2015
Adjusted Appropriation
Virements Final Appropriation
Actual Expenditure
Available Budget
R’000 R’000 R’000 R’000
Administration 277 537 (699) 276 838 274 729 2 109
Human Settlements 923 130 699 923 829 676 932 246 897
Co-operative Governance 232 755 50 232 805 232 313 492
Traditional Institutional Development 342 092 (50) 342 094 341 498 546
Total 1 775 516 - 1 775 516 1 525 470 250 046
-
14
Events after the reporting date
There were no events (adjusting and non-adjusting), favourable and unfavourable that occurred
after the reporting date and the date of approval of the Annual Financial Statements.
Makoko M.G. Accounting Officer Department of Co-operative Governance, Human Settlements and Traditional Affairs Date: 31 May 2015
-
15
5. STATEMENT OF RESPONSIBILITY AND CONFIRMATION OF
ACCURACY OF THE ANNUAL REPORT
To the best of my knowledge and belief, I confirm the following:
All information and amounts disclosed throughout the Annual Report are consistent.
The Annual Report is complete, accurate and is free from any omissions.
The Annual Report has been prepared in accordance with the guidelines on the Annual
Report as issued by National Treasury.
The Annual Financial Statements (Part E) have been prepared in accordance with the
modified cash standard and the relevant frameworks and guidelines issued by the
National Treasury.
The Accounting Officer is responsible for the preparation of the Annual Financial
Statements and for the judgements made in this information.
The Accounting Officer is responsible for establishing, and implementing a system of
internal control that has been designed to provide reasonable assurance as to the
integrity and reliability of the performance information, the human resources information
and the Annual Financial Statements.
The external auditors are engaged to express an independent opinion on the Annual
Financial Statements.
In my opinion, the Annual Report fairly reflects the operations, the performance
information, the human resources information and the financial affairs of the Department
for the financial year ended 31 March 2015.
Yours faithfully
Accounting Officer
Name: Makoko M.G.
Date: 31 May 2015
-
16
6. STRATEGIC OVERVIEW
6.1 Vision
Integrated Sustainable Human Settlements
6.2 Mission
To be effective agent of change that delivers quality services to citizens of Limpopo
through:
i. Promoting developmental cooperative governance,
ii. Supporting municipalities and traditional leadership institutions, and
iii. Optimally deliver integrated and sustainable human settlements
6.3 Values
Our values are underpinned by the Batho Pele Principles.
Service Excellence:
We shall strive to attain recognized standards of service quality, and maintain continuous improvement in service delivery.
Innovation:
We shall toil in the pursuit of excellence and innovation on the use of information and communication technology to enhance public service delivery.
Integrity:
We shall conduct our business with integrity at all times to inculcate a culture of
honesty and accountability among all our employees. Prudence:
We shall exercise prudence and economy in running the business of the Department
and in pursuance of its goals and the objectives of government.
Transparency:
We shall always ensure transparency in everything we do in order to build trust and confidence with all our stakeholders.
Fairness and consistency:
We shall treat all our beneficiaries, suppliers and employees with fairness and equity at all times.
-
17
Professionalism
We shall ensure that employees demonstrate high level of professionalism when interacting with all stakeholders
7. LEGISLATIVE AND OTHER MANDATES
Constitutional Mandates
Section of the Constitution
Direct responsibility in ensuring compliance
Chapter 2, section 26
This section puts direct responsibility on the Department in ensuring that everyone has access to adequate housing, which is carried out through the ISHS programme
Chapter 7, section 154
The section directs the Provincial Government to support and strengthen the capacity of municipalities to manage their own affairs, to exercise their powers and to perform their functions.
Legislative Mandates
Relevant Act Key Responsibilities
A. The Public Service Act of 1994 as amended and regulations
To provide for the organization and administration of the public service of the Republic, the regulation of the conditions of employment, terms of office, discipline, retirement and discharge of members of the public service.
B. The Public Finance Management Act 1 of 1999 (as amended) and Regulations
To regulate financial management in the national government and provincial government, to ensure all revenue, expenditure , assets and liabilities of those governments are managed efficiently
C. The Housing Act of 1997
To promote and facilitate the provision of adequate housing within the framework of national housing policy.
D. The Local Government Municipal Structures Act of 1998
The MEC for local government in a Province, by notice in the Provincial Gazette must establish a municipality in each municipal area which the Demarcation Board demarcates in the Province in terms of the Demarcation Act.
E. The Local Government Municipal Systems Act of 2000
The MEC for local government in the Province may, subject to any other law regulating provincial supervision of local government – assist a municipality with the planning, drafting, and adoption of mid review of its 5 year integrated development plan.
F. The Disaster Management Act 2002
To provide for an integrated and coordinated disaster management policy that focuses on preventing or reducing the risk and mitigating the severity of disasters, emergency preparedness, rapid and effective response to disasters and post-disaster recovery; the establishment of national, provincial and municipal disaster management centres, disaster management volunteers, and matters incidental thereto.
-
18
Relevant Act Key Responsibilities
G. Spatial Planning and Land Use Management Act of 2013
To provide a framework for spatial planning and land use management in the Republic; to specify the relationship between the spatial planning and the land use management system and other kinds of planning; to provide for the inclusive, developmental, equitable and efficient spatial planning at the different spheres of government.
H. Traditional Leadership and Governance Framework Act 41 of 2003
To provide for the recognition of traditional communities; to provide for the establishment and recognition of traditional councils; to provide a statutory framework for leadership positions within the institution of traditional leadership.
-
19
8. ORGANISATIONAL STRUCTURE
-
20
PART B: PERFORMANCE INFORMATION
-
21
1. AUDITOR GENERAL’S REPORT: PREDETERMINED OBJECTIVES
Refer to part E
2. OVERVIEW OF DEPARTMENTAL PERFORMANCE
2.1 Service Delivery Environment
The Department is charged with the responsibility of ensuring that citizens are sheltered,
municipalities are able to provide services in accordance with their constitutional
mandate, promote co-operative governance and providing support to traditional
leadership and their communities.
2.1.1 Human settlements
As a sector there are vast issues from the economy that can affect the delivery of
services. The years 2013/14 and 2014/15 have been rather challenging for the
Department. Although the economic environment did not have huge impact on the
delivery of services, the organizational environment had a huge impact. In the medium
and long term the situation will have an impact on issues of addressing housing demand,
human settlements planning, reduction of housing backlog, and promotion of economic
opportunities.
2.1.2 Co-operative Governance
Back to Basics
In response to the launch of the Back to Basics approach by the Minister of CoGTA, the
Department has facilitated the adoption of the approach in the Province. As a result an
assessment was conducted in all municipalities. This assessment has assisted in
determining the state of municipalities to inform direct interventions
2.1.3 Traditional Leadership Institutions
Traditional Leaders continue to play an important role in the development of communities. To date the number of recognised Headmen/Headwomen has increased from 1480 to 1509. The Department has processed the outstanding arrear payments of Headmen/Headwomen, adjusted their salaries and simultaneously exploring all the available avenues to ensure that all challenges regarding tools of trade are addressed. The Province is inundated with teething problems of Traditional Leadership claims and disputes, hence the Kgatla Commission was established to adjudicate over these disputes. The Commission has to date received 508 and has finalised 175 cases.
-
22
2.2 Service Delivery Improvement Plan
The Department has completed a service delivery improvement plan. The tables below
highlight the service delivery plan and the achievements to date.
Main services and standards
Main services Beneficiaries Current/actual standard of
service
Desired standard of
service
Actual achievement
Installation of
services in
Lephalale for
rental units
(CRU)
Hostel dwellers
and community
members
514 services 514 services Bulk services
installed,
reticulation
phase to
commence
during
2015/16
Improve
compliance on
all governance
issues in 30
municipalities
Municipalities 5 unqualified
reports and 2
clean audits
30 clean audits 12
municipalities
achieved
unqualified
audit
opinions
Batho Pele arrangements with beneficiaries (Consultation access etc.)
Current/actual arrangements
Desired arrangements
Actual achievements
Community participation meetings
One public participation
3 events held at Motetema, Bloodriver and Lebowakgomo Zone S
Service delivery information tool
Current/actual information tools
Desired information tools
Actual achievements
CoGHSTA news, brochures Print media, Electronic media
COGHSTA newsletter X2
Brochures: 5 X Disaster management and social housing
Electronic newsletters: 8 issues of CoGHSTA online published
-
23
Complaints mechanism
Current/actual complaints mechanism Desired complaints mechanism
Actual achievements
Departmental toll free number: 0800687432
Short message system
Not implemented, complaints were dealt with manually e.g. 225 walk ins received & resolved
2.3 Organisational environment
In the year under review the Department fully implemented the new organogram and the
establishment is updated.
3. STRATEGIC OUTCOME ORIENTED GOALS
The Department has considered the strategic direction of the Human Settlements, Co-operative
Governance and Traditional Affairs sectors to align and contribute to national imperatives.
Furthermore, the strategic intent of the Department was reviewed during 2013/14 in preparation
for the new electoral cycle which has commenced during the year under review. These goals
have taken into account the socio-economic environment of the Province.
Goal Goal Statement Outputs Progress
1. A professional
public service
that is proactive,
responsive and
geared towards
the realisation of
a developmental
state
To ensure continuous
professional support and
an enabling environment
for efficient and effective
service delivery
1.1 Implemented
Performance Management
Systems in the Department
annually
67% (47 of 70) of
organisational targets
achieved.
1 816 employees received
performance awards
All queries lodged through
Departmental, Premier and
Presidential hotlines have
been resolved
1.2 Financial management
support and advisory
services for effective
accountability
Achieved unqualified audit
outcome without matters of
emphasis for 2013/14
financial year, an
improvement from 2012/13.
Voted budget expenditure
improved from 74% in
2013/14 to 86% in 2014/15
All undisputed invoices paid
within 30 days as per
standard
2. Integrated Eradicate informal 2.1 Housing development Multi-Year Housing
-
24
Goal Goal Statement Outputs Progress
human
settlements with
socio-economic
opportunities
settlements and facilitate
equitable access to
adequate housing in an
integrated and sustainable
manner.
properly planned by October
each year
Development Plan
reviewed in accordance
with the new priorities of the
MTSF
10 000 sites identified for
development
4 informal settlements in
mining towns of
Fetakgomo, Greater
Tubatse, Lephalale and
Elias Motsoaledi have been
identified for formalisation
to enable implementation of
various projects of human
settlements. In addition
Elias Motsoaledi and
Greater Tubatse
municipalities have been
supported through NUSP
2.2 Housing backlog
reduced by 80,000 units
through implementation of
different housing
programmes by 2019
2 125 houses completed in
the Province
10 232 subsidies approved
for qualifying beneficiaries
2.3 Security of tenure
promoted through effecting
transfer of 3,500 housing
properties annually to
qualifying beneficiaries
497 housing properties
transferred to beneficiaries
3 properties devolved to
municipalities
3. Sustainable
Cooperative
Governance
system
• Monitor and play
oversight role in all
municipalities in order
to improve
performance and good
governance
• Co-ordinate and
provide support to
Traditional Leadership
Institutions in order to
enhance Local
Governance.
3.1 Strengthened
institutional capacity of all
municipalities by monitoring
compliance with local
government legislation
annually
Municipal IDP’s assessed
annually
Intervened in Ba-
Phalaborwa municipality to
ensure compliance with
legislation
Monitored and support
municipalities with MIG
compliance and
implementation
Supported municipalities to
improve financial
management and
-
25
Goal Goal Statement Outputs Progress
accountability
Continued implementation
of Traditional Affairs
Framework
-
26
4. PERFORMANCE INFORMATION BY PROGRAMME
4.1 Programme 1: Administration
Purpose: To provide effective leadership, management and administrative support to core functions of the Department. This is ensured through continuous refinement of corporate policies,
skills development, efficient and effective financial management, structures and systems in
compliance with legislation and best practice and championing Batho Pele principles and service
delivery.
Sub-programmes
Administration
Strategic objectives
Financial management support and advisory services for effective accountability
Efficient business processes and back office systems
Strategic objectives, performance indicators, planned targets and actual achievements
This programme has managed to achieve most of its planned targets as summarised below: Maintaining Service Excellence: With the aim of providing excellent services as enshrined in our values, the Department was recognized for its performance on vast programmes as indicated below
Award category Award Institution
Provincial Government Departments
doing most to Accelerate Service Delivery
In Limpopo Province
Diamond Arrow Award PMR Africa
Departments that achieved highest score
on financial reporting ending March 2013
Annual Public Reporting Awards
Pyramid shaped glass
trophy
SAIGA
Innovative Enhancement of Internal
Systems of Government
1st Runner up for - GITO
Branch
Centre for Public
Service Innovation
The awards are motivating achievements for the Department to strive for excellence despite its challenges. Human Resources Management:
The Department filled a total of 69 vacant posts on the organogram
-
27
Human resources development has facilitated training programmes aiming to empower and capacitate employees to perform their duties more effectively
Internship programme has trained a total of 110 graduates and offered learnerships to individuals who require work experience for completion of qualifications.
There is a reasonable and mutual and harmonious relationship between the employer and employees due to the consistent interaction between the parties in the form of Labour Management Forum as well as bi-lateral meetings with organised labour
Communication Services: The Department has received positive media coverage as a result of implementation of the reviewed communication plan. A new weekly online newsletter has been launched during the year. Other activities implemented include:
Successfully hosted and branded fifty six (56) strategic events for the enhancement of CoGHSTA’s image
During the Back to Basics indaba, CoGHSTA received maximum publicity through eight (8) Community, Local and national Media, and gave access to audience in excess of 4 million with almost 70% of listeners within LSM 5-8, resulting to a lasting footprint for the Department.
Continuously maintained good relations with Media by hosting Media Networking session
which brought all strategic partners, politicians and media fraternity under one roof in the
4th quarter.
Strategic objectives:
Programme 1: Administration
Strategic objectives Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation
from planned
target to
Actual
Achievement
for 2014/2015
Comment on
deviations
1. Efficient business
processes and back
office systems
99% 100% 100 % None None
2. Financial management
support and advisory
services for effective
accountability
100% Process 100%
of completed
claims/vouchers
within 30 days
100% None None
-
28
Performance indicators
Programme 1: Administration
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target to
Actual
Achievement for
2014/2015
Comment on
deviations
1. Number of posts
filled
20 posts filled 30 69 posts filled 39 posts filled Moratorium on
filling of post was
lifted
2. Number of training sessions conducted as per statutory requirement WSP
1 300 training
sessions
conducted
1 200 1858 658 Additional training conducted for Traditional Affairs Branch
3. Percentage of
gender and disability
representation
54% Female 46% Male 0.61% people with disability
50% Gender
2% people with
Disability
55% Women
0,67% people with disability
45% Women 1,33% People with disability
Some of
applicants with
disabilities did
not meet the
requirements
4. Percentage of
targets met
N/A 100% 67% 33% Programme 2: Human Settlements achieved less than 50% of planned targets
5. Percentage of
resolved queries
logged through the
Departmental toll free,
Premier and
Presidential hotlines
Resolved 99%
of queries
lodged
100% 100% None None
6. Percentage of anti-
fraud and corruption
cases reported and
investigated
85% (40 of 47
cases)
100% 100% None None
7. Percentage of
undisputed invoices
paid within 30 days
100% 100% 100% None None
8. Type of audit opinion Unqualified
opinion
without
matters of
emphasis
Achieve
unqualified
opinion without
matters of
emphasis
Achieved
unqualified
opinion with
matters of
emphasis
Completeness
of human
settlements
performance
information
Improvement
in monitoring
of
performance
reporting
-
29
Programme 1: Administration
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target to
Actual
Achievement for
2014/2015
Comment on
deviations
Performance
of
remunerative
work by
officials
without
permission
Misstatement
of balances in
the AFS
corrected
during the
audit
More staff
awareness
training
Improve
monitoring of
reporting
9. Percentage of
allocated budget spent
74.7% 100% 82% 18% Significant
underspending
in Programme 2:
Human
Settlements
Reasons for all deviations
The lifting of section 100 (1) (b) in the Province has informed the uplifting on the moratorium
on filling of posts as the Provincial HRM Task Team has been discontinued.
Delay in procurement processes has impacted on implementation of programmes and
spending thereof.
Applicants did not meet requirements specifically people with disabilities
Additional training programmes implemented at Traditional Affairs Branch for the Admin
officers and Accounting clerks due to gaps identified.
Change of management staff impacted negatively on monitoring of performance reporting in
ISHS
Uncertainty in accounting treatment of expenditure out of prepaid funds let to misstatement
Staff ignorance led to remunerative work without permission (RWOPS)
-
30
Strategy to overcome areas of under performance
Posts have been identified to be filled by people with disability and women to ensure that
equity targets are met
More vigilance and monitoring should improve financial and non-financial reporting, as well
as (RWOPS)
Changes to planned targets
None
Sub-programme expenditure
Sub- Programme Name
2014/2015 2013/2014
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
R’000 R’000 R’000 R’000 R’000 R’000
Corporate Services 275,016 272,948 2,068 259,466 255,091 4,375
Office of the MEC 1,822 1,781 41 1,735 1,667 68
Total 276,838 274,729 2,109 261,201 256,758 4,443
Linking performance with budgets
The programme has successfully implemented planned projects and the budget was fully utilised
to deliver the outputs below:
o Recruitment process
o Maintenance and operations of ICT
o Communication initiatives
o Training and development
o Internal controls measures
-
31
4.2 Programme 2: Human Settlements
The purpose: To ensure provision of housing development, access to adequate accommodation
in relevant areas, access to social infrastructure and economic opportunities
To achieve the above mentioned objectives, the programme is divided into three sub-
programmes:
Sub-programme Description
Housing Needs,
Research and Planning
This programme focuses on administration, policy
initiatives and analysis, housing planning as well as
research for the sector
Housing Development,
Implementation,
Planning and Targets
This programme focuses on financial, incremental,
social, rental and rural interventions and
implementation
Housing Assets
Management and
Property Management
This programme is geared for sales and transfer of
properties to households, devolution and maintenance
of housing properties
Strategic Objective: To reduce housing backlog through integrated planning and construction,
with the main aim of promoting economic opportunities through transferring of housing properties
to beneficiaries.
Strategic objectives, performance indicators, planned targets and actual achievements
In the year under review, the Department had significant challenges that hindered recovery from the developments in the 2013/14 financial year. The main delay emanated from the procurement process for Human Settlements Development Grant (HSDG). The Department was part of the pilot project of the Chief Procurement Office from National Treasury. The process of procurement took approximately 7 months to complete. As a result the Department underspent the budget significantly. Subsequently, the HSDG allocation was reduced with an amount of R559 million during February/March 2015. This has impacted on the achievement of targets for the year under review as detailed below, since the procurement process had an effect on all programmes of Human Settlements.
Human settlements planning were successfully implemented, with the exception of land acquisition during the year. Other programmes including rural housing, disaster/emergency housing, and enhanced people’s housing, rental stock, transferring of housing properties and connection to basic services were affected by the prolonged procurement process during the year. This programme has achieved 21% of its planned targets.
-
32
Strategic objectives:
Programme 2: Integrated Sustainable Human Settlements
Strategic objectives Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
3. Housing
development properly
planned by October
each year
Not achieved Formalise 4
settlements
Not achieved None None
4. Reduced housing
backlog by 80 000 by
2019
2 877 10 500 2 065 8 435 The pilot procurement project delayed the process of appointment of contractors
5. Transferred 50 000
housing properties to
beneficiaries by 2019
767 3 150 497 2 653 The pilot procurement project delayed the process of appointment of contractors
Performance indicators
1
2
Programme 2: Integrated Sustainable Human Settlements
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
1. A Multi-Year
Housing Development
Plan/APP developed by
October
Multi-Year Housing Development Plan reviewed
Reviewed Multi–year Human Settlement development plan
Multi-Year
Housing
Development
Plan reviewed
None None
2. Number of informal
settlements formalised
through township
establishment
Not achieved
4 settlements formalised
0 4 The three service providers appointed in March 2015 for a period of 2 years.
1 Customised Indicators
2 Provincial Specific Indicators
-
33
Programme 2: Integrated Sustainable Human Settlements
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
3. Number of Hectares
of land acquired
0 50ha 0 50ha Identified land
was overpriced
4. Number of planned
human settlement
(housing) development
based on IDP’s,
National and Provincial
priorities approved
(Number of
development sites
identified)
N/A 10 000 10 000 None None
5. Number of
municipalities
accredited on housing
provision
Prepared one
municipality for
level two
Accreditation
Confirm one municipality for level 2 Accreditation
0 1 Municipality Municipality has not improved the audit outcomes
6. Number of capacity
building workshops
conducted
35 35 38 3 The additional
three workshops
were requested
by Presidency in
Muyexe
7. Number of
municipalities
capacitated and
supported with regard
to human settlement
(housing) development
planning
2 (Elias
Motsoaledi &
Tubatse
supported)
2 Municipality
supported
through NUSP
2 None None
8. Number of Acts
passed and/or policy
guidelines approved
Draft provincial
housing
allocation policy
available
Informal
settlement Bill still
with the
Provincial
Legislature for
gazetting
Pass1 Policy/
Act
0 1 Draft policy on
Provincial
Housing
Allocation
available
-
34
Programme 2: Integrated Sustainable Human Settlements
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
9. Number of research
papers completed
None 1 0 1 Research paper
on Housing
Cooperatives still
at Draft stage
10. Number of new
housing units
completed in the
Province across all
housing programmes
being utilized by the
Province
2 877 10 500 2 065 8 435 The pilot procurement project delayed the process of appointment of contractors
11. Number of Housing
stock/RDP rectified
95
700 60 640 The pilot procurement project delayed the process of appointment of contractors
12. Number of
households connected
to basic services as
part of the informal
Settlement Upgrading
Programme
N/A 3 000 0 3 000 The pilot procurement project delayed the process of appointment of contractors
13. Number of rental
units built (CRU) and
(SH)
N/A 250 0 250 The pilot procurement project delayed the process of appointment of contractors
14. Number of new
sites connected to
basic water and
sanitation services as
part of the Integrated
Residential
Development
Programme
N/A 500 0 500 Polokwane Ext.
121 and 86 –
service provider
was delayed due
to outstanding
power of attorney
from DPW.
15. Number of
Enhanced Peoples
Housing Process units
N/A 150 0 150 The pilot procurement project delayed the process of appointment of
-
35
Programme 2: Integrated Sustainable Human Settlements
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
completed contractors
16. Number of units
transferred through the
Enhanced Extended
Discount Benefit
Scheme
135 150 188 38 Carryover
projects from
2013/14
17. Number of rental
units sold to
beneficiaries
N/A N/A N/A N/A N/A
18. Number of rental
units transferred
N/A N/A N/A N/A N/A
19. Number of units
registered and
endorsed
767 3 000 309 2 691 The pilot procurement project delayed the process of appointment of contractors
20. Number of debtors
reduced per financial
year
N/A N/A N/A N/A N/A
21. Number of rental
units devolved to
municipalities in terms
of section 15 of the
housing Act, 97
None 3 3 None None
22. Number of projects
approved
80 80 32 48 Outcome of SCM
yielded fewer
contractors than
expected.
23. Number of job
opportunities created
466 5 500 392 5 108 The pilot procurement project delayed the process of appointment of contractors
24. Number of
beneficiaries/ subsidies
approved on HSS
N/A 10 500 10 171 329 Some applicants
for subsidies did
not qualify in
identified areas
-
36
Programme 2: Integrated Sustainable Human Settlements
Performance
Indicator
Actual
Achievement
2013/2014
Planned Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
25. Percentage of
disputes/cases
resolved
89% (189 of
213)
100% 91% (273 of
301)
9% Non-availability of
parties
26. Number of Reports
submitted (MEC
advisory panel)
1 1 0 1 New advisory
panel was
constituted in the
4th quarter.
27. Number of Finance-
Linked Individual
Subsidy Programme
(FLISP) units
completed
N/A 300 60 240 Applicants failing National Credit Act requirements.
Note: Performance Indicator 11 has been funded under blocked projects
Reasons for all deviations
The National Treasury pilot on procurement for Human Settlements delayed appointment of
service providers to implement Housing projects for the year
Beneficiaries for rural housing programme saturated in Lephalale and others failing searches
In accordance with FLISP criteria, applicants did not fulfil all requirements
Affected parties to disputes not adhering to the procedure of case management therefore delaying
conclusion.
Strategy to overcome areas of under performance
Extension of contract period granted for contractors appointed in 2014/15 financial year.
-
37
Sub-programme expenditure
2014/2015 2013/2014
Sub- Programme Name Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
R’000 R’000 R’000 R’000 R’000 R’000
Housing needs, research
and planning
16,875
14,898
1,977
22,432
22,384
48
Housing development ,
implementation ,
planning and targets
874,201
629 462
244 739
716,363
338,014
378,349
Housing asset
management and
property management
32,753
32,572
181
37,900
34,297
3,603
Total 923,829 676 932 246 897 776,695 394,695 382,000
Linking performance with budgets
Significant underspending in programme 2 is from transfers and subsidies, which funds the
implementation of human settlements development. Expenditure and performance recorded is
lower than planned. This is attributed mainly to delayed appointment of contractors.
file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!V331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!V331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AK331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AK331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AK331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AZ331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AZ331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AZ331
-
38
4.3 Programme 3: Cooperative Governance
The purpose: The programme aims at capacitating municipalities to implement their legal
mandates through the following sub-programme:
List of the sub-programmes
Sub-programme Description
Local Government
Support
To support municipalities with administration
requirements and compliance, financial management
and accountability, public participation, capacity
development as well as perform monitoring and
evaluation
Development Planning To support and monitor municipalities on spatial
planning, disaster management, land use
management, municipalities infrastructure delivery,
local economic development and IDP coordination
Strategic Objective: The objective of this programme focuses on capacity development in municipalities. Municipalities require constant monitoring and evaluation with the purpose of implementation on corrective actions to ensure service delivery. Governance in municipalities has improved in the past five years. This is evident in the:
Professionalisation of the recruitment of senior managers in municipalities
Development and implementation of valuation rolls in all 25 local municipalities
Compliance with the Municipal Systems Act by installing controls to ensure proper and effective governance systems
Development and implementation of credible IDP’s
Strategic oversight on financial management programme
Strategic objectives, performance indicators, planned targets and actual achievements
The Sub-Department has monitored the performance of municipalities in compliance with relevant legislation. Concurrently, provided support to municipalities to ensure continued service delivery. This is done to ensure that municipalities are functional and able to perform their constitutional mandate of providing services to citizens timeously. Financial management in municipalities The improvement of financial management in municipalities has been a cornerstone of our intervention for immediate impact and preservation of long term goals to enhance municipal efficiency and viability. Through targeted and focused intervention there has been a remarkable progress on the audit outcomes of 2013/14 as depicted on the table below:
Municipal Audit Outcomes
Audit opinion 2012/13 2013/14
Unqualified 0 12
Qualified 18 11
-
39
Audit opinion 2012/13 2013/14
Adverse 3 1
Disclaimers 9 6
It is imperative that systems have to be established and maintained to ensure effective, efficient and economic use of resources and to prevent fruitless and wasteful expenditure by this important sphere of government.
The system of local government is maturing in the Province. The Provincial Executive Council (EXCO) has evoked section 139(4)(b) in Ba-Phalaborwa in order to assist in compliance with Municipal Property Rates Act and to ensure that maximum revenue is collected for the interest of both government and community. Implementation of the Operation Clean Audit Plan
Twenty seven (27) municipalities have developed and submitted the audit remedial action plans to address issues raised by the Auditor General in respect of the 2013/14 municipal audit. The following three (3) municipalities have not yet submitted the audit remedial action plans in respect of the 2013/14 municipal audit namely: Aganang, Mogalakwena, and Ba-Phalaborwa.
The reasons for non-compliance are that Ba-Phalaborwa municipality is disputing the audit outcomes, and Aganang municipality submitted the Annual Financial Statements late and received the audit opinion late in February 2015. Several engagements were done at Mogalakwena municipality to be assisted to develop remedial plans. However, to date, the municipality has neither provided an action plan nor availed themselves to be assisted by the Department. The Department has assessed twenty one (21) audit remedial action plans and provided written feedback.
SPLUMA implementation
The Spatial Planning and Land Use Management Act, (SPLUMA) was enacted during 2013. The Province has finalised Regulations to the Act implementation is 1 July 2015. The Action plan with key tasks to be undertaken by the Municipalities has been developed and coupled with the generic Modalities on Agreements for the Joint District Municipal Tribunal format. The Department of Rural Development and Land Reform has also appointed a Service Provider to assist municipalities in the development of modalities regarding, by-laws, delegations, tariffs and the drafting of the Memorandum of Understanding in preparation for the implementation of the Act.
Strategic objectives
Programme 3 : Co-operative Governance
Strategic objectives Actual
Achievement
2013/2014
Planned
Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
6. Improved support
and oversight in all
municipalities by
2015
4 Reports on
implementation
of municipal
capacity
development
plan
4 None None
-
40
Performance indicators
3
4
Programme 3 : Co-operative Governance
Performance Indicator Actual Achievement
2013/2014
Planned Target
2014/2015
Actual Achievement
2014/2015
Deviation from planned target
to Actual Achievement
2014/2015
Comment on deviations
1. Number of municipal performance reports compiled as per the requirements of Section 47 of the MSA
N/A 1 1 None None
2. Number of municipalities supported to improve audit outcomes
5 30 30 None None
3. Number of
municipalities with
functional performance
audit committees
30 30 30 None None
4. Number of
municipalities with
functional Performance
Management System
(PMS)
N/A 30 30 None None
5. Number of
municipalities supported
with fraud and anti-
corruption strategy
N/A 30 8 22 Capacity challenges
6. Number of reports on
the filing of municipal
managers and section 56
4 4 4 None None
7. Number of
municipalities with HR
policies norms and
standards
30 30 30 None None
8. Number of
municipalities supported to
fill top six positions filled by
30 30 30 None None
3 Customised Indicators
4 Provincial Specific Indicators
-
41
Programme 3 : Co-operative Governance
Performance Indicator Actual Achievement
2013/2014
Planned Target
2014/2015
Actual Achievement
2014/2015
Deviation from planned target
to Actual Achievement
2014/2015
Comment on deviations
competent staff
9. Number of
municipalities capacitated
to implement individual
PMS with respect to sec
56 & 57 managers
30 30 30 None None
10. Number of
municipalities supported in
MPRA implementation
24 25
25 None None
11. Number of
municipalities with MPAC
30 30 30 None None
12. Number of reports on
government debts
reduction
4 4 4 None None
13. Number of reports on
the implementation of
clean audit plan
4 4 4 None None
14. Number of
municipalities supported to
establish audit committees
30 30 30 None None
15. Number of reports on
implementation of
Municipal capacity
development plan
4 4 4 None None
16. Number of
municipalities supported to
spend MIG
29 29 29 None None
17. Number of report
produced on households
with access to basic
services i.e. (water,
sanitation, electricity,
refuse removal) from
municipalities
1 1 1 None None
-
42
Programme 3 : Co-operative Governance
Performance Indicator Actual Achievement
2013/2014
Planned Target
2014/2015
Actual Achievement
2014/2015
Deviation from planned target
to Actual Achievement
2014/2015
Comment on deviations
18. Number of
Municipalities with
functional ward
committees
25 25 23 2 Non-submission of
reports by
Mogalakwena and
Greater Tubatse
19. Number of
municipalities with
functional IGR structures
5 5 5 None None
20. Number of Izimbizo
held by MEC, Mayors &
Councillors
4 4 4 None None
21. Number of awareness
campaign conducted for
elections
4 2 2 None None
22. Number of
municipalities where full
CDW programmes are
implemented
25 25 25 None None
23. Number of district
municipalities with disaster
management centres
supported
5 5 5 None None
24. Number of meetings of
the Intergovernmental
Disaster Management
forum
4 4 4 None None
25. Number of provincial
fire preparedness reports
compiled
1 1 1 None None
26. Number of municipalities supported to implement SDFs in term of guidelines
30 30 30 None None
27. Number of
municipalities
implementing LUMS
12 12 12 None None
-
43
Programme 3 : Co-operative Governance
Performance Indicator Actual Achievement
2013/2014
Planned Target
2014/2015
Actual Achievement
2014/2015
Deviation from planned target
to Actual Achievement
2014/2015
Comment on deviations
28. Number of reports on
the Statutory Board
(Townships Board)
4 5 5 None None
29. Number of
municipalities supported
with spatial and land use
management
N/A 30 30 None None
30. Number of demarcated
sites available for Human
Settlements
5450 5000 5130 130 Additional sites
emanates from
public parcels and
other communities
that were not
engaged during the
planning phase
31. Number of municipalities supported with the development of legally compliant IDP
30 30 30 None None
32. Number of municipalities with LED strategies assessed
N/A 30 30 None None
33. Number of District LED fora established
5 5 5 None None
34. Number of work opportunities created through the community work programme
23 969 17 000 21 496 4496 CoGTA provided
more allocation to
expand to additional
4 municipalities
Reasons for all deviations
The Sub-Department has achieved 97% of its targets and the reasons are as follows:
Additional work opportunities: Greater Tzaneen, Greater Tubatse and Greater Giyani
increased by a combined total of 2496 participants. The program expanded by 2000
participants to 4 municipalities being Musina, Greater Letaba, Elias Motsoaledi and
Polokwane municipality. Each municipality has 500 participants
Mogalakwena and Greater Tubatse municipalities are not complying with the IGR Act
-
44
Strategy to overcome areas of under performance
Accounting Officers of municipalities have been engaged
Sub-programme expenditure
2014/2015 2013/2014
Sub- Programme Name
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
R’000 R’000 R’000 R’000 R’000 R’000
Local Governance 174,796 174,443 354 173,235 173,011 224
Development
Planning 58,009 57,870 138 66,335 60,870 5,465
Total
232,805 232,313 492 239,571 233,881 5,690
Linking performance with budgets
The programme has achieved 97% of its planned targets during the year in accordance
with allocated budget.
4.4 Programme 4: Traditional Affairs
The purpose: Aims to support the institution of Traditional Leadership to operate within the
context of co-operative governance
List of the sub-programmes
Sub-programme Description
Traditional Institutional
Admin
To support Traditional Institutions with administration,
resource administration, land administration and
facilitation of rural development
Administration of
Houses of Traditional
Leaders
To support Houses of Traditional leadership with
administration of its committees and Local Houses
Strategic Objective: Ensure that provisions of Traditional Leadership legislation and policies are
implemented
Strategic objectives, performance indicators, planned targets and actual achievements
The Provincial Commission on Traditional Leadership, Disputes and Claims has
received 507 applications and 175 cases have been completed to date.
The President of the Republic has on 09 February 2014 approved salary increases
for all categories of Traditional Leaders. This has been done per Proclamation No.9
of 2014, published in Government Gazette No. 37352 dated 18 February 2014. The
file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V481file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK481file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK481
-
45
Department has paid salary adjustments for 2014/15 and arrears on Persal System
for active Traditional Leaders. The payment was made during June 2014.
In line with Framework for the Provision of Enabling Resources to Qualifying
Traditional Leaders and members of Houses of Traditional Leaders the Department
is still mobilising resources to implement some of the tools of trade such as: motor
vehicles, provisions for Kings and construction of traditional councils' offices.
Furthermore, 29 previously recognised Traditional Leaders were paid allowances
including arrears
Strategic objective
Programme 4: Traditional Institutional Development
Strategic objectives Actual
Achievement
2012/2013
Planned
Target
2013/2014
Actual
Achievement
2013/2014
Deviation from
planned target to
Actual
Achievement for
2013/2014
Comment on
deviations
7. Supported all
established
institutions of
Traditional Leaders
by 2019
12 12 12 None None
Performance indicators
Programme 4: Traditional Institutional Development
Performance
Indicator
Actual
Achievement
2013/2014
Planned
Target
2014/2015
Actual
Achievement
2014/2015
Deviation from
planned target
to Actual
Achievement
for 2014/2015
Comment on
deviations
1. Number of sittings by the Provincial House of Traditional Leaders
2 2 2 None None
2. Number of sittings by the local house of traditional leaders
10 10 10 None None
3. Number of Traditional Councils supported
184 185 185 None None
-
46
Sub-programme expenditure
2014/2015 2013/2014
Sub- Programme Name
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
Final Appropriation
Actual Expenditure
(Over)/Under Expenditure
R’000 R’000 R’000 R’000 R’000 R’000
Traditional Institutional Administration
335,056
334,654
402
304,530
294,614
9,916
Administration of Houses of Traditional Leaders
6,988
6,844
144
6,925
6,692
233
Total 342,044 341,498 545 311,455 301,306 10,149
Linking performance with budgets
The funds in this programme have been utilised towards compensation of Traditional Leaders and supporting of the functioning of Traditional Leadership institutions.
file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK631
-
47
5. TRANSFER PAYMENTS
5.1. Transfer payments to public entities
No transfer payments were made to any public entity
5.2. Transfer payments to all organisations other than public entities
No transfer payments were made to any organisations
6. CONDITIONAL GRANTS
6.1. Conditional grants and earmarked funds paid
Not Applicable to the Department
6.2. Conditional grants and earmarked funds received
The table below details the conditional grants and earmarked funds received for the period 1 April
2014 to 31 March 2015.
Conditional Grant Human Settlement Development Grant:
Department who transferred the grant
Human Settlements
Purpose of the grant To provide funding for the creation of
Sustainable human settlements.
Expected outputs of the grant
Accelerated delivery of housing
opportunities
Efficient utilisation of land for Human
Settlements development
Improved property market
Rectification
Actual outputs achieved 2065 housing units completed
497 properties transferred to beneficiaries
Amount per amended DORA (R’000)
R 825,603
Amount received (R’000) R 825,603
-
48
Reasons if amount as per DORA was not received
None
Amount spent by the Department (R’000)
R583,021
Reasons for the funds unspent by the entity
The pilot procurement project delayed the process of appointment of contractors
Reasons for deviations on performance
The pilot procurement project delayed the process of appointment of contractors
Measures taken to improve performance
Extension of contract period granted for contractors appointed in 2014/15 financial year.
Monitoring mechanism by the receiving Department
Inspections carried out during construction
process
Enhanced project management through
decentralisation in local municipal areas
Technical support through deployment of
Cuban Technical Advisors
7. DONOR FUNDS
7.1. Donor Funds Received
No donor funds were received during the year under review
8. CAPITAL INVESTMENT
8.1. Capital investment, maintenance and asset management plan
Infrastructure
projects
2014/2015 2013/2014
Final Appropriation
R’000
Actual Expenditure
R’000
(Over)/Under Expenditure
R’000
Final Appropriation
R’000
Actual Expenditure
R’000
(Over)/Under Expenditure
R’000
New and replacement assets
825,603
583 021 242 582 682,110 303,449 378,661
Total 825,603 583 021 242 582 682,110
303,449 378,661
-
49
PART C: GOVERNANCE
-
50
1. RISK MANAGEMENT
1.2 Risk management policy and strategy.
The Department has a Risk Management Strategy and policy and they are reviewed
annually and approved by the Accounting officer.
1.2 Regular risk assessments
Risk Assessment is conducted on an annual basis to identify risks that have a
potential to adversely affect achievements of Departmental Objectives and overall
efficiency and effectiveness of business processes.
1.3 Risk Management Committee
The Risk Management Committee exists in terms of the Risk Committee Charter
reviewed on an annual basis. The Risk Committee reviews the Departments system
of Risk Management and oversees implementation of recommendations relating to
risk management
1.4 Audit Committee
The Audit Committee considers the Department’s risk management report on a quarterly
basis and advises the Department on improvements of risk management.
Progress in the management of risks, whether this has transmitted into improvements in
the Department’s performance, and if not, what it plans on doing to address this problem
In the year under review, the Department mitigated 40% of the prioritized risks. Risks for
which target could not be achieved continue to be significant to the achievement of
Departmental objectives and as a result have been targeted during the 2015/16 financial
year.
For the financial year under review, a risk assessment was conducted and the following
are prioritized risks:
Risk Progress
Inability to meet equity targets Two people with disability were appointed
Theft and insecurity CCTV to be procured during 2015/16 FY.
Adverse reputation of the Department Assessment report on all social media platforms made, of which
outcome was presented to management
Loss of records at traditional councils Monitored compliance with the record management policy and
the file plan at Sekhukhune District Municipality
-
51
Risk Progress
Poor financial management in
municipalities and ineffective
implementation of Audit action plans
Assessments were conducted through Back to Basics approach
Limitations to acquire well located land Land identified in Tzaneen and Burgersfort
Inadequate bulk infrastructure Business plan finalized.
Capacity constraints in project
management and engineering skills
Continued monitoring of projects and joint inspection between
stakeholders conducted
Inaccessibility of credit to
beneficiaries(gap market)
FLISP project launched (Bendor Ext. 100)
Fraud and corruption Received 56 cases and 48 have been finalized.
Prolonged operational stoppages Service provider to develop BCP appointed on the
12/02/2015.BCP will be finalized December 2015
2. FRAUD AND CORRUPTION
Fraud prevention initiatives
Fraud Prevention Plan developed and has been implemented through developing of Anti-
Fraud &Corruption Strategy, awareness workshops and conducting investigation on
cases reported.
Mechanisms in place to report fraud and corruption
Procedure manual developed and all cases received are sanctioned by Head of Department before official investigation is conducted. Whistle blowing policy in place to guide officials on the process and management.
Procedure on handling reported cases
Cases are reported to the Head of Department office and upon findings emanating from the investigation, recommendation are forwarded to Head of Department for his/her consideration. Those which requires further referral to other units and or agencies, such referrals are done for their further handling
3. MINIMISING CONFLICT OF INTEREST
All employees are required to apply to the Executive Authority for permission to conduct
remunerative work outside the public service in terms of Section 30 of the Public Service
act. The Department has entered into an agreement with Companies and Intellectual
Property Commission (CIPC) in terms of which access has been provided for the
purposes of viewing on the CIPC database. Before an award is made to the prospective
bidder a search is performed to determine if either of the directors/members is a
governmental employee.
-
52
Where a conflict of interest is identified, disciplinary proceedings are instituted against the
affected employee.
4. CODE OF CONDUCT
Ethical practices in the Department are in line with the Code of Conduct for the Public
Service. There is a reasonable mutual and harmonious relationship between employer
and employee in the Department due to consistent interaction between the parties in the
form of Labour Management Forum as well as bilateral meetings with organised labour.
The Department regularly conducts workshops, briefing sessions, inductions and training
sessions in relation to both PSCBC Resolution 1 of 2003 and PSCBC Resolution 14 of
2002. Disciplinary Code and Procedures Policy has been approved by the Executive
Authority and is in force.
In case of breach of Code of Conduct, disciplinary proceedings will be instituted against
the affected employee.
5. HEALTH SAFETY AND ENVIRONMENTAL ISSUES
The Department has a functioning Employee Wellness Unit which addresses all the
Health Safety and Environmental issues.
The Department has a Committee that deals with Health Safety and Environment.
Audits are done on continuous basis to address issues that might pose risk to Healt