  • 1

    VOTE NO. 11

    ANNUAL REPORT

    2014/2015 FINANCIAL YEAR

  • 2

    Contents

    PART A: GENERAL INFORMATION ................................................................................................... 4

    1. DEPARTMENT GENERAL INFORMATION .............................................................................. 5

    2. LIST OF ABBREVIATIONS/ACRONYMS .................................................................................. 6

    3. FOREWORD BY THE MEC ....................................................................................................... 8

    4. REPORT OF THE ACCOUNTING OFFICER .......................................................................... 11

    5. STATEMENT OF RESPONSIBILITY AND CONFIRMATION OF ACCURACY OF THE ANNUAL REPORT ............................................................................................................................... 15

    6. STRATEGIC OVERVIEW ......................................................................................................... 16

    6.1 Vision ................................................................................................................................ 16

    6.2 Mission .............................................................................................................................. 16

    6.3 Values ............................................................................................................................... 16

    7. LEGISLATIVE AND OTHER MANDATES ............................................................................... 17

    8. ORGANISATIONAL STRUCTURE .......................................................................................... 19

    PART B: PERFORMANCE INFORMATION ....................................................................................... 20

    1. AUDITOR GENERAL’S REPORT: PREDETERMINED OBJECTIVES ................................... 21

    2. OVERVIEW OF DEPARTMENTAL PERFORMANCE ............................................................. 21

    2.1 Service Delivery Environment .......................................................................................... 21

    2.2 Service Delivery Improvement Plan ................................................................................. 22

    2.3 Organisational environment .............................................................................................. 23

    3. STRATEGIC OUTCOME ORIENTED GOALS ........................................................................ 23

    4. PERFORMANCE INFORMATION BY PROGRAMME ............................................................ 26

    4.1 Programme 1: Administration ........................................................................................... 26

    4.2 Programme 2: Human Settlements .................................................................................. 31

    4.3 Programme 3: Cooperative Governance .......................................................................... 38

    4.4 Programme 4: Traditional Affairs ...................................................................................... 44

    5. TRANSFER PAYMENTS ......................................................................................................... 47

    5.1. Transfer payments to public entities ................................................................................. 47

    5.2. Transfer payments to all organisations other than public entities .................................... 47

    6. CONDITIONAL GRANTS ......................................................................................................... 47

    6.1. Conditional grants and earmarked funds paid .................................................................. 47

    6.2. Conditional grants and earmarked funds received ........................................................... 47

    7. DONOR FUNDS ....................................................................................................................... 48

    7.1. Donor Funds Received ..................................................................................................... 48

    8. CAPITAL INVESTMENT .......................................................................................................... 48

    8.1. Capital investment, maintenance and asset management plan ....................................... 48

  • 3

    PART C: GOVERNANCE .................................................................................................................... 49

    1. RISK MANAGEMENT............................................................................................................... 50

    2. FRAUD AND CORRUPTION ................................................................................................... 51

    3. MINIMISING CONFLICT OF INTEREST ................................................................................. 51

    4. CODE OF CONDUCT .............................................................................................................. 52

    5. HEALTH SAFETY AND ENVIRONMENTAL ISSUES ............................................................. 52

    6. PORTFOLIO COMMITTEES .................................................................................................... 53

    7. SCOPA RESOLUTIONS .......................................................................................................... 53

    8. PRIOR MODIFICATIONS TO AUDIT REPORTS .................................................................... 60

    9. INTERNAL CONTROL UNIT .................................................................................................... 60

    10. INTERNAL AUDIT AND AUDIT COMMITTEES ...................................................................... 62

    11. AUDIT COMMITTEE REPORT ................................................................................................ 65

    PART D: HUMAN RESOURCE MANAGEMENT ................................................................................ 69

    1. INTRODUCTION ...................................................................................................................... 70

    2. OVERVIEW OF HUMAN RESOURCES .................................................................................. 70

    3. HUMAN RESOURCES OVERSIGHT STATISTICS ................................................................ 71

    PART E: FINANCIAL INFORMATION .............................................................................................. 103

    1. REPORT OF THE AUDITOR GENERAL ....................................................................................... 104

    2. ANNUAL FINANCIAL STATEMENTS .................................................................................... 109

  • 4

    PART A: GENERAL INFORMATION

  • 5

    1. DEPARTMENT GENERAL INFORMATION

    PHYSICAL ADDRESS: 20 Rabe Street

    Polokwane

    0699

    POSTAL ADDRESS: Private Bag X9485

    Polokwane

    0700

    TELEPHONE NUMBER/S: +27 15 284 5000

    FAX NUMBER: +27 15 293 1520

    EMAIL ADDRESS: [email protected]

    WEBSITE ADDRESS : www.coghsta.limpopo.gov.za

    mailto:[email protected]

  • 6

    2. LIST OF ABBREVIATIONS/ACRONYMS

    AFS Annual Financial Statements

    AGSA Auditor General of South Africa

    BBBEE Broad Based Black Economic Empowerment

    CDP Community Development Programme

    CDW Community Development Worker

    CFO Chief Financial Officer

    CoGHSTA Cooperative Governance Human Settlements and Traditional Affairs

    CRU Community Residential Units

    DORA Division of Revenue Act

    EAP Employee Assistance Programme

    EU European Union

    EXCO Executive Council

    FLISP Financed-Linked Individual Subsidy Programme

    GITO Government Information Technology Office

    HDA Housing Development Agency

    HOD Head of Department

    HSDG Human Settlements Development Grant

    HSS Housing Subsidy System

    IDP Integrated Development Plan

    IGR Intergovernmental Relations

    ISHS Integrated Sustainable Human Settlements

    LED Local Economic Development

    LGTAS Local Government Turnaround Strategy

    LUMS Land Use Management Scheme

    MEC Member of the Executive Council

  • 7

    MIG Municipal Infrastructure Grant

    MPAC Municipal Public Accounts Committee

    MTEF Medium Term Expenditure Framework

    NDoHS National Department of Human Settlements

    NHFC National Housing Finance Corporation

    NUSP National Upgrading Support Programme

    PFMA Public Finance Management Act

    PGP Provincial Growth Points

    PMU Project Management Unit

    POA Programme of Action

    SISP Strategic Information Systems Plan

    SDF Spatial Development Framework

    SCM Supply Chain Management

    SMME Small Medium and Micro Enterprises

    SAIGA Southern African Institute of Government Auditors

    SCOPA Standing Committee on Public Accounts

    SDIP Service Delivery Improvement Plan

    SIU Special Investigations Unit

    SITA State Information Technology Agency

    SLA Service Level Agreement

    TR Treasury Regulations

    USDG Urban Settlement Development Grant

    CWP Community Works Programme

    WSP Workplace Skills Plan

  • 8

    3. FOREWORD BY THE MEC

    Name: Ms. MG Makhurupetje

    Title: Member of the Executive Committee

    The second year of the current Administration coincides with the 60th anniversary of the

    Freedom Charter, the ruling African National Congress’s Bible founded in Kilptown in

    1955. The Freedom Charter is more relevant today as it was then for its call for a just

    society based on the bill of rights which is enshrined in the country’s Constitution. As we

    move forward with the actualisation of the Freedom Charter, ours is to ensure that we

    sustain the good work of the past 21 years as we make our due contribution towards

    changing the living conditions of our people, mindful of the fact that we must do things

    differently and faster because a better life for all cannot be delayed any longer. In moving

    forward to restoring the dignity of our people, we must at all times refer to our core

    mandates which are:

    Outcome Eight: “Create Sustainable Human Settlements and Improve the Quality of

    Household Life” and

    Outcome Nine: “A Responsive, Accountable, Effective and Efficient Local Government

    System”.

    Human Settlements

    The Freedom Charter is unequivocal in its expression that “there shall be houses,

    security and comfort”, and as the Department we declare that this shall be our rallying

    song throughout.

    In addition to the Freedom Charter, we allude to the following:

    All people shall have the right to live where they choose, be decently housed, and to

    bring up their families in comfort and security;

    Unused housing space will be made available to the people to build their own houses;

    Rent shall be lowered;

  • 9

    Slums shall be demolished, and new suburbs built where there shall be adequate

    transport, roads, lighting, playing fields, crèches and social centres;

    Fenced locations and ghettoes shall be abolished, and laws which break up families shall

    be repealed.

    As a Department we are committed to building on the progress achieved in the 21years

    of democracy, while recognising that more still needs to be done, particularly with the

    implementation of the National Development Plan, Vision 2030.

    We shall make strides in developing our housing infrastructure that supports the

    development of human capital, including access to water, sanitation and that supports

    economic growth and development as well as quality of life of citizens.

    Human settlement must be understood in the context of social development and radical

    economic transformation as well as meeting the objectives of rolling back the quagmire of

    underdevelopment.

    Currently 9 000 units are at construction stage, and we have committed the entire budget

    for the rural housing projects. By March 2015 over 1900 units were completed while

    others were at foundation, wall plate and roof level.

    We are planning to transfer 3 700 housing units to beneficiaries through the Enhanced

    Extended Discount Benefit Scheme and Registration and Endorsement Programme.

    Our Department is undoubtedly poised for a development trajectory that reflects the

    steady progress in infrastructure investment. It is within this context that of the R1,385

    billion allocated to the programme, R1,285 billion is the Human Settlements Development

    Grant earmarked for funding the human settlement programme, as guided by the

    Outcome 8 of the Medium Term Strategic Framework.

    Co-operative Governance

    The Department recommits itself to the 10 high-level developments targets as presented

    by the Premier during the State of the Province Address. Key amongst these

    development plans to the Department is:

    Increased access to basic water to 90% by 2020;

    Increased access to electricity to 90% by 2020;

    Increased access to sanitation to 50% by 2020.

    In this regard we are delighted with some of the developments regarding provision of

    water in the Province.

    We continue to regard Local Government as an important sphere of government as they

    are very close to the people. We will continue to support this sphere so that it discharges

    its duties, mainly through the Back to Basics programme in order to:

  • 10

    provide democratic and accountable government for local communities;

    provide services to communities in a sustainable manner;

    promote social and economic development;

    encourage the involvement of communities and community organisations in

    matters of local government.

    Be that as it may, here and there we come across challenges as we discharge our duties.

    As a Province we are experiencing a decline in housing delivery from the previous two

    financial years which resulted from the withholding of the Human Settlements

    Development Grant, and the subsequent housing pilot procurement project by the

    Section 100 Intervention Task Team which could not yield the expected results on the

    appointment of contractors to build 10 500 units.

    I take this opportunity to express my sincere gratitude to the Premier of our Province,

    Honourable Chupu Mathabatha for entrusting me with the Department of Cooperative

    Governance, Human Settlements and Traditional Affairs. As we celebrate the 60th

    anniversary of the Freedom Charter, we are mindful of the task that lies ahead, and we

    declare that until the people of Limpopo are liberated from all forms of social and

    economic oppression, we shall never give up.

    It is my utmost honour and privilege to present this Annual Report of the Department of

    Cooperative Governance, Human Settlements and Traditional Affairs for the 2014/15

    Financial Year.

    Ms. MG Makhurupetje MEC: Co-operative Governance, Human Settlements and Traditional Affairs Date: 31 July 2015

  • 11

    4. REPORT OF THE ACCOUNTING OFFICER

    Name: Mr. M.G. Makoko

    Title: Acting Head of Department

    Overview of the operations of the Department:

    The 2014/15 Annual Report presents the performance of the Department in its efforts to fulfil its

    constitutional mandate and its vision for integrated, sustainable human settlements in line with

    outcome 8, 9 and 12. The Department has recorded significant progress on improving financial

    management in municipalities through continuous capacitation initiatives as well as monitoring

    and evaluation of this important sphere of government.

    In support to initiatives of job opportunities created, the Province has received additional funding

    from CoGTA on CWP, which provided about 21 000 job opportunities to participants.

    The institutions of Traditional Leadership have been supported through coordination of

    stakeholders to participate in the initiation schools management. Additional compensation for

    Traditional Leaders has been streamlined with the pronouncement made by the President.

    The Human Settlements sector has had its fair share of challenges for the past two financial

    years. However the Department is ready to turn the situation around to ensure that services are

    delivered to the people of Limpopo as expected.

    The system of governance and accountability has matured in the Department, which is congruent

    to the expectations by the public at large. This is credited to the management team of the

    Department as well as oversight institutions who quality-check the Departments’ obligations

    initiatives regularly.

  • 12

    Overview of the financial results of the Department:

    Departmental receipts

    Departmental receipts

    2014/2015 2013/2014

    Estimate Actual Amount

    Collected

    (Over)/Under Collection

    Estimate

    Actual Amount

    Collected

    (Over)/Under Collection

    R’000 R’000 R’000 R’000 R’000 R’000

    Sale of goods and services other than capital assets

    1 274 1 273 1 988 1 083 (94)

    Transfers received - - - 2 000 (2 000)

    Fines, penalties and forfeits - - - 11 - 11

    Interest, dividends and rent on land 129 93 36 61 231 (170)

    Sale of capital assets 268 268 - 225 - 225

    Financial transactions in assets and liabilities

    1 254 1 501 (247) 1 215 1 247 (32)

    Total 2 925 3 135 (210) 2 500 4 561 (2 060)

    The Department has collected R3.135 million (2013/14: R4.561 million) which is 7.15% more than

    planned. The better than anticipated performance is mainly due to money received from the

    National Department Human Settlements in respect of debt recoveries by the SIU.

    Revenue Tariff policy

    The Department has implemented transversal tariffs as determined and approved by the

    Provincial Treasury during the year under review.

    Irrecoverable debts written off

    A total of R6.5 million was written off as irrecoverable debts in terms of the transversal debt

    management policy approved by Provincial Treasury.

    No new measures were instituted during the course of the year to raise additional revenue.

    However, the transversal revenue management policy was implemented to ensure more

    efficient/effective revenue collection.

    Capital assets amounting to R268 000 were sold during the year under review.

    Programme Expenditure

    Programme Name

    2014/2015 2013/2014

    Final Appropriation

    Actual Expenditure

    (Over)/ Under

    Expenditure

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    R’000 R’000 R’000 R’000 R’000 R’000

    Administration 276 838 274 729 2 109 261 201 256 757 4 444

    Human Settlements (verify) 923 829 676 932 246 897 776 695 394 695 382 000

    Co-Operative Governance 232 805 232 313 492 239 642 233 880 5 762

    Traditional Institutional Development 342 044 341 498 546 311 455 301 306 10 149

    Total 1 775 516 1 525 470 250 046 1 588 993 1 186 638 402 355

    The Department spent R1.525 billion (2013/14: R1.187 billion) of the total allocation of R1.776

    million which represents 85.9% (2013/14: 74.7%). The spending trend at programme level has

    been depicted in the table above.

  • 13

    The expenditure of R1.525 billion includes R66 million which was defrayed from prepayments

    made to ESKOM in prior years.

    The underspending is mainly in the Human Settlements programme due to late appointment of

    service providers for low cost housing projects. The underspent amount is committed to the

    existing housing projects and the roll-over of these funds has since been approved.

    Virements

    Reason for the virement

    The virements were effected for the defrayment of excess expenditure in respect of leave

    gratuities as well as transport costs within Goods and Services. Savings realised were

    utilised to write off irrecoverable debts.

    Unauthorised, fruitless and wasteful expenditure

    The Department incurred fruitless and wasteful expenditure of R4m during the year under review

    as disclosed in the Annual Financial Statements.

    Future plans of the Department

    Regular monitoring of service providers to ensure compliance with the service contracts with the

    Department as well as close monitoring and support of municipalities and traditional leadership

    institutions to ensure continued improvements in service delivery.

    Supply chain management

    o The major challenge experienced in SCM was late procurement of low cost houses as

    already stated

    o The SCM processes and systems are in place to prevent irregular expenditure and there is

    strict adherence to legislation and policies.

    Programme Name

    2014/2015

    Adjusted Appropriation

    Virements Final Appropriation

    Actual Expenditure

    Available Budget

    R’000 R’000 R’000 R’000

    Administration 277 537 (699) 276 838 274 729 2 109

    Human Settlements 923 130 699 923 829 676 932 246 897

    Co-operative Governance 232 755 50 232 805 232 313 492

    Traditional Institutional Development 342 092 (50) 342 094 341 498 546

    Total 1 775 516 - 1 775 516 1 525 470 250 046

  • 14

    Events after the reporting date

    There were no events (adjusting and non-adjusting), favourable and unfavourable that occurred

    after the reporting date and the date of approval of the Annual Financial Statements.

    Makoko M.G. Accounting Officer Department of Co-operative Governance, Human Settlements and Traditional Affairs Date: 31 May 2015

  • 15

    5. STATEMENT OF RESPONSIBILITY AND CONFIRMATION OF

    ACCURACY OF THE ANNUAL REPORT

    To the best of my knowledge and belief, I confirm the following:

    All information and amounts disclosed throughout the Annual Report are consistent.

    The Annual Report is complete, accurate and is free from any omissions.

    The Annual Report has been prepared in accordance with the guidelines on the Annual

    Report as issued by National Treasury.

    The Annual Financial Statements (Part E) have been prepared in accordance with the

    modified cash standard and the relevant frameworks and guidelines issued by the

    National Treasury.

    The Accounting Officer is responsible for the preparation of the Annual Financial

    Statements and for the judgements made in this information.

    The Accounting Officer is responsible for establishing, and implementing a system of

    internal control that has been designed to provide reasonable assurance as to the

    integrity and reliability of the performance information, the human resources information

    and the Annual Financial Statements.

    The external auditors are engaged to express an independent opinion on the Annual

    Financial Statements.

    In my opinion, the Annual Report fairly reflects the operations, the performance

    information, the human resources information and the financial affairs of the Department

    for the financial year ended 31 March 2015.

    Yours faithfully

    Accounting Officer

    Name: Makoko M.G.

    Date: 31 May 2015

  • 16

    6. STRATEGIC OVERVIEW

    6.1 Vision

    Integrated Sustainable Human Settlements

    6.2 Mission

    To be effective agent of change that delivers quality services to citizens of Limpopo

    through:

    i. Promoting developmental cooperative governance,

    ii. Supporting municipalities and traditional leadership institutions, and

    iii. Optimally deliver integrated and sustainable human settlements

    6.3 Values

    Our values are underpinned by the Batho Pele Principles.

    Service Excellence:

    We shall strive to attain recognized standards of service quality, and maintain continuous improvement in service delivery.

    Innovation:

    We shall toil in the pursuit of excellence and innovation on the use of information and communication technology to enhance public service delivery.

    Integrity:

    We shall conduct our business with integrity at all times to inculcate a culture of

    honesty and accountability among all our employees. Prudence:

    We shall exercise prudence and economy in running the business of the Department

    and in pursuance of its goals and the objectives of government.

    Transparency:

    We shall always ensure transparency in everything we do in order to build trust and confidence with all our stakeholders.

    Fairness and consistency:

    We shall treat all our beneficiaries, suppliers and employees with fairness and equity at all times.

  • 17

    Professionalism

    We shall ensure that employees demonstrate high level of professionalism when interacting with all stakeholders

    7. LEGISLATIVE AND OTHER MANDATES

    Constitutional Mandates

    Section of the Constitution

    Direct responsibility in ensuring compliance

    Chapter 2, section 26

    This section puts direct responsibility on the Department in ensuring that everyone has access to adequate housing, which is carried out through the ISHS programme

    Chapter 7, section 154

    The section directs the Provincial Government to support and strengthen the capacity of municipalities to manage their own affairs, to exercise their powers and to perform their functions.

    Legislative Mandates

    Relevant Act Key Responsibilities

    A. The Public Service Act of 1994 as amended and regulations

    To provide for the organization and administration of the public service of the Republic, the regulation of the conditions of employment, terms of office, discipline, retirement and discharge of members of the public service.

    B. The Public Finance Management Act 1 of 1999 (as amended) and Regulations

    To regulate financial management in the national government and provincial government, to ensure all revenue, expenditure , assets and liabilities of those governments are managed efficiently

    C. The Housing Act of 1997

    To promote and facilitate the provision of adequate housing within the framework of national housing policy.

    D. The Local Government Municipal Structures Act of 1998

    The MEC for local government in a Province, by notice in the Provincial Gazette must establish a municipality in each municipal area which the Demarcation Board demarcates in the Province in terms of the Demarcation Act.

    E. The Local Government Municipal Systems Act of 2000

    The MEC for local government in the Province may, subject to any other law regulating provincial supervision of local government – assist a municipality with the planning, drafting, and adoption of mid review of its 5 year integrated development plan.

    F. The Disaster Management Act 2002

    To provide for an integrated and coordinated disaster management policy that focuses on preventing or reducing the risk and mitigating the severity of disasters, emergency preparedness, rapid and effective response to disasters and post-disaster recovery; the establishment of national, provincial and municipal disaster management centres, disaster management volunteers, and matters incidental thereto.

  • 18

    Relevant Act Key Responsibilities

    G. Spatial Planning and Land Use Management Act of 2013

    To provide a framework for spatial planning and land use management in the Republic; to specify the relationship between the spatial planning and the land use management system and other kinds of planning; to provide for the inclusive, developmental, equitable and efficient spatial planning at the different spheres of government.

    H. Traditional Leadership and Governance Framework Act 41 of 2003

    To provide for the recognition of traditional communities; to provide for the establishment and recognition of traditional councils; to provide a statutory framework for leadership positions within the institution of traditional leadership.

  • 19

    8. ORGANISATIONAL STRUCTURE

  • 20

    PART B: PERFORMANCE INFORMATION

  • 21

    1. AUDITOR GENERAL’S REPORT: PREDETERMINED OBJECTIVES

    Refer to part E

    2. OVERVIEW OF DEPARTMENTAL PERFORMANCE

    2.1 Service Delivery Environment

    The Department is charged with the responsibility of ensuring that citizens are sheltered,

    municipalities are able to provide services in accordance with their constitutional

    mandate, promote co-operative governance and providing support to traditional

    leadership and their communities.

    2.1.1 Human settlements

    As a sector there are vast issues from the economy that can affect the delivery of

    services. The years 2013/14 and 2014/15 have been rather challenging for the

    Department. Although the economic environment did not have huge impact on the

    delivery of services, the organizational environment had a huge impact. In the medium

    and long term the situation will have an impact on issues of addressing housing demand,

    human settlements planning, reduction of housing backlog, and promotion of economic

    opportunities.

    2.1.2 Co-operative Governance

    Back to Basics

    In response to the launch of the Back to Basics approach by the Minister of CoGTA, the

    Department has facilitated the adoption of the approach in the Province. As a result an

    assessment was conducted in all municipalities. This assessment has assisted in

    determining the state of municipalities to inform direct interventions

    2.1.3 Traditional Leadership Institutions

    Traditional Leaders continue to play an important role in the development of communities. To date the number of recognised Headmen/Headwomen has increased from 1480 to 1509. The Department has processed the outstanding arrear payments of Headmen/Headwomen, adjusted their salaries and simultaneously exploring all the available avenues to ensure that all challenges regarding tools of trade are addressed. The Province is inundated with teething problems of Traditional Leadership claims and disputes, hence the Kgatla Commission was established to adjudicate over these disputes. The Commission has to date received 508 and has finalised 175 cases.

  • 22

    2.2 Service Delivery Improvement Plan

    The Department has completed a service delivery improvement plan. The tables below

    highlight the service delivery plan and the achievements to date.

    Main services and standards

    Main services Beneficiaries Current/actual standard of

    service

    Desired standard of

    service

    Actual achievement

    Installation of

    services in

    Lephalale for

    rental units

    (CRU)

    Hostel dwellers

    and community

    members

    514 services 514 services Bulk services

    installed,

    reticulation

    phase to

    commence

    during

    2015/16

    Improve

    compliance on

    all governance

    issues in 30

    municipalities

    Municipalities 5 unqualified

    reports and 2

    clean audits

    30 clean audits 12

    municipalities

    achieved

    unqualified

    audit

    opinions

    Batho Pele arrangements with beneficiaries (Consultation access etc.)

    Current/actual arrangements

    Desired arrangements

    Actual achievements

    Community participation meetings

    One public participation

    3 events held at Motetema, Bloodriver and Lebowakgomo Zone S

    Service delivery information tool

    Current/actual information tools

    Desired information tools

    Actual achievements

    CoGHSTA news, brochures Print media, Electronic media

    COGHSTA newsletter X2

    Brochures: 5 X Disaster management and social housing

    Electronic newsletters: 8 issues of CoGHSTA online published

  • 23

    Complaints mechanism

    Current/actual complaints mechanism Desired complaints mechanism

    Actual achievements

    Departmental toll free number: 0800687432

    [email protected]

    Short message system

    Not implemented, complaints were dealt with manually e.g. 225 walk ins received & resolved

    2.3 Organisational environment

    In the year under review the Department fully implemented the new organogram and the

    establishment is updated.

    3. STRATEGIC OUTCOME ORIENTED GOALS

    The Department has considered the strategic direction of the Human Settlements, Co-operative

    Governance and Traditional Affairs sectors to align and contribute to national imperatives.

    Furthermore, the strategic intent of the Department was reviewed during 2013/14 in preparation

    for the new electoral cycle which has commenced during the year under review. These goals

    have taken into account the socio-economic environment of the Province.

    Goal Goal Statement Outputs Progress

    1. A professional

    public service

    that is proactive,

    responsive and

    geared towards

    the realisation of

    a developmental

    state

    To ensure continuous

    professional support and

    an enabling environment

    for efficient and effective

    service delivery

    1.1 Implemented

    Performance Management

    Systems in the Department

    annually

    67% (47 of 70) of

    organisational targets

    achieved.

    1 816 employees received

    performance awards

    All queries lodged through

    Departmental, Premier and

    Presidential hotlines have

    been resolved

    1.2 Financial management

    support and advisory

    services for effective

    accountability

    Achieved unqualified audit

    outcome without matters of

    emphasis for 2013/14

    financial year, an

    improvement from 2012/13.

    Voted budget expenditure

    improved from 74% in

    2013/14 to 86% in 2014/15

    All undisputed invoices paid

    within 30 days as per

    standard

    2. Integrated Eradicate informal 2.1 Housing development Multi-Year Housing

  • 24

    Goal Goal Statement Outputs Progress

    human

    settlements with

    socio-economic

    opportunities

    settlements and facilitate

    equitable access to

    adequate housing in an

    integrated and sustainable

    manner.

    properly planned by October

    each year

    Development Plan

    reviewed in accordance

    with the new priorities of the

    MTSF

    10 000 sites identified for

    development

    4 informal settlements in

    mining towns of

    Fetakgomo, Greater

    Tubatse, Lephalale and

    Elias Motsoaledi have been

    identified for formalisation

    to enable implementation of

    various projects of human

    settlements. In addition

    Elias Motsoaledi and

    Greater Tubatse

    municipalities have been

    supported through NUSP

    2.2 Housing backlog

    reduced by 80,000 units

    through implementation of

    different housing

    programmes by 2019

    2 125 houses completed in

    the Province

    10 232 subsidies approved

    for qualifying beneficiaries

    2.3 Security of tenure

    promoted through effecting

    transfer of 3,500 housing

    properties annually to

    qualifying beneficiaries

    497 housing properties

    transferred to beneficiaries

    3 properties devolved to

    municipalities

    3. Sustainable

    Cooperative

    Governance

    system

    • Monitor and play

    oversight role in all

    municipalities in order

    to improve

    performance and good

    governance

    • Co-ordinate and

    provide support to

    Traditional Leadership

    Institutions in order to

    enhance Local

    Governance.

    3.1 Strengthened

    institutional capacity of all

    municipalities by monitoring

    compliance with local

    government legislation

    annually

    Municipal IDP’s assessed

    annually

    Intervened in Ba-

    Phalaborwa municipality to

    ensure compliance with

    legislation

    Monitored and support

    municipalities with MIG

    compliance and

    implementation

    Supported municipalities to

    improve financial

    management and

  • 25

    Goal Goal Statement Outputs Progress

    accountability

    Continued implementation

    of Traditional Affairs

    Framework

  • 26

    4. PERFORMANCE INFORMATION BY PROGRAMME

    4.1 Programme 1: Administration

    Purpose: To provide effective leadership, management and administrative support to core functions of the Department. This is ensured through continuous refinement of corporate policies,

    skills development, efficient and effective financial management, structures and systems in

    compliance with legislation and best practice and championing Batho Pele principles and service

    delivery.

    Sub-programmes

    Administration

    Strategic objectives

    Financial management support and advisory services for effective accountability

    Efficient business processes and back office systems

    Strategic objectives, performance indicators, planned targets and actual achievements

    This programme has managed to achieve most of its planned targets as summarised below: Maintaining Service Excellence: With the aim of providing excellent services as enshrined in our values, the Department was recognized for its performance on vast programmes as indicated below

    Award category Award Institution

    Provincial Government Departments

    doing most to Accelerate Service Delivery

    In Limpopo Province

    Diamond Arrow Award PMR Africa

    Departments that achieved highest score

    on financial reporting ending March 2013

    Annual Public Reporting Awards

    Pyramid shaped glass

    trophy

    SAIGA

    Innovative Enhancement of Internal

    Systems of Government

    1st Runner up for - GITO

    Branch

    Centre for Public

    Service Innovation

    The awards are motivating achievements for the Department to strive for excellence despite its challenges. Human Resources Management:

    The Department filled a total of 69 vacant posts on the organogram

  • 27

    Human resources development has facilitated training programmes aiming to empower and capacitate employees to perform their duties more effectively

    Internship programme has trained a total of 110 graduates and offered learnerships to individuals who require work experience for completion of qualifications.

    There is a reasonable and mutual and harmonious relationship between the employer and employees due to the consistent interaction between the parties in the form of Labour Management Forum as well as bi-lateral meetings with organised labour

    Communication Services: The Department has received positive media coverage as a result of implementation of the reviewed communication plan. A new weekly online newsletter has been launched during the year. Other activities implemented include:

    Successfully hosted and branded fifty six (56) strategic events for the enhancement of CoGHSTA’s image

    During the Back to Basics indaba, CoGHSTA received maximum publicity through eight (8) Community, Local and national Media, and gave access to audience in excess of 4 million with almost 70% of listeners within LSM 5-8, resulting to a lasting footprint for the Department.

    Continuously maintained good relations with Media by hosting Media Networking session

    which brought all strategic partners, politicians and media fraternity under one roof in the

    4th quarter.

    Strategic objectives:

    Programme 1: Administration

    Strategic objectives Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation

    from planned

    target to

    Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    1. Efficient business

    processes and back

    office systems

    99% 100% 100 % None None

    2. Financial management

    support and advisory

    services for effective

    accountability

    100% Process 100%

    of completed

    claims/vouchers

    within 30 days

    100% None None

  • 28

    Performance indicators

    Programme 1: Administration

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target to

    Actual

    Achievement for

    2014/2015

    Comment on

    deviations

    1. Number of posts

    filled

    20 posts filled 30 69 posts filled 39 posts filled Moratorium on

    filling of post was

    lifted

    2. Number of training sessions conducted as per statutory requirement WSP

    1 300 training

    sessions

    conducted

    1 200 1858 658 Additional training conducted for Traditional Affairs Branch

    3. Percentage of

    gender and disability

    representation

    54% Female 46% Male 0.61% people with disability

    50% Gender

    2% people with

    Disability

    55% Women

    0,67% people with disability

    45% Women 1,33% People with disability

    Some of

    applicants with

    disabilities did

    not meet the

    requirements

    4. Percentage of

    targets met

    N/A 100% 67% 33% Programme 2: Human Settlements achieved less than 50% of planned targets

    5. Percentage of

    resolved queries

    logged through the

    Departmental toll free,

    Premier and

    Presidential hotlines

    Resolved 99%

    of queries

    lodged

    100% 100% None None

    6. Percentage of anti-

    fraud and corruption

    cases reported and

    investigated

    85% (40 of 47

    cases)

    100% 100% None None

    7. Percentage of

    undisputed invoices

    paid within 30 days

    100% 100% 100% None None

    8. Type of audit opinion Unqualified

    opinion

    without

    matters of

    emphasis

    Achieve

    unqualified

    opinion without

    matters of

    emphasis

    Achieved

    unqualified

    opinion with

    matters of

    emphasis

    Completeness

    of human

    settlements

    performance

    information

    Improvement

    in monitoring

    of

    performance

    reporting

  • 29

    Programme 1: Administration

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target to

    Actual

    Achievement for

    2014/2015

    Comment on

    deviations

    Performance

    of

    remunerative

    work by

    officials

    without

    permission

    Misstatement

    of balances in

    the AFS

    corrected

    during the

    audit

    More staff

    awareness

    training

    Improve

    monitoring of

    reporting

    9. Percentage of

    allocated budget spent

    74.7% 100% 82% 18% Significant

    underspending

    in Programme 2:

    Human

    Settlements

    Reasons for all deviations

    The lifting of section 100 (1) (b) in the Province has informed the uplifting on the moratorium

    on filling of posts as the Provincial HRM Task Team has been discontinued.

    Delay in procurement processes has impacted on implementation of programmes and

    spending thereof.

    Applicants did not meet requirements specifically people with disabilities

    Additional training programmes implemented at Traditional Affairs Branch for the Admin

    officers and Accounting clerks due to gaps identified.

    Change of management staff impacted negatively on monitoring of performance reporting in

    ISHS

    Uncertainty in accounting treatment of expenditure out of prepaid funds let to misstatement

    Staff ignorance led to remunerative work without permission (RWOPS)

  • 30

    Strategy to overcome areas of under performance

    Posts have been identified to be filled by people with disability and women to ensure that

    equity targets are met

    More vigilance and monitoring should improve financial and non-financial reporting, as well

    as (RWOPS)

    Changes to planned targets

    None

    Sub-programme expenditure

    Sub- Programme Name

    2014/2015 2013/2014

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    R’000 R’000 R’000 R’000 R’000 R’000

    Corporate Services 275,016 272,948 2,068 259,466 255,091 4,375

    Office of the MEC 1,822 1,781 41 1,735 1,667 68

    Total 276,838 274,729 2,109 261,201 256,758 4,443

    Linking performance with budgets

    The programme has successfully implemented planned projects and the budget was fully utilised

    to deliver the outputs below:

    o Recruitment process

    o Maintenance and operations of ICT

    o Communication initiatives

    o Training and development

    o Internal controls measures

  • 31

    4.2 Programme 2: Human Settlements

    The purpose: To ensure provision of housing development, access to adequate accommodation

    in relevant areas, access to social infrastructure and economic opportunities

    To achieve the above mentioned objectives, the programme is divided into three sub-

    programmes:

    Sub-programme Description

    Housing Needs,

    Research and Planning

    This programme focuses on administration, policy

    initiatives and analysis, housing planning as well as

    research for the sector

    Housing Development,

    Implementation,

    Planning and Targets

    This programme focuses on financial, incremental,

    social, rental and rural interventions and

    implementation

    Housing Assets

    Management and

    Property Management

    This programme is geared for sales and transfer of

    properties to households, devolution and maintenance

    of housing properties

    Strategic Objective: To reduce housing backlog through integrated planning and construction,

    with the main aim of promoting economic opportunities through transferring of housing properties

    to beneficiaries.

    Strategic objectives, performance indicators, planned targets and actual achievements

    In the year under review, the Department had significant challenges that hindered recovery from the developments in the 2013/14 financial year. The main delay emanated from the procurement process for Human Settlements Development Grant (HSDG). The Department was part of the pilot project of the Chief Procurement Office from National Treasury. The process of procurement took approximately 7 months to complete. As a result the Department underspent the budget significantly. Subsequently, the HSDG allocation was reduced with an amount of R559 million during February/March 2015. This has impacted on the achievement of targets for the year under review as detailed below, since the procurement process had an effect on all programmes of Human Settlements.

    Human settlements planning were successfully implemented, with the exception of land acquisition during the year. Other programmes including rural housing, disaster/emergency housing, and enhanced people’s housing, rental stock, transferring of housing properties and connection to basic services were affected by the prolonged procurement process during the year. This programme has achieved 21% of its planned targets.

  • 32

    Strategic objectives:

    Programme 2: Integrated Sustainable Human Settlements

    Strategic objectives Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    3. Housing

    development properly

    planned by October

    each year

    Not achieved Formalise 4

    settlements

    Not achieved None None

    4. Reduced housing

    backlog by 80 000 by

    2019

    2 877 10 500 2 065 8 435 The pilot procurement project delayed the process of appointment of contractors

    5. Transferred 50 000

    housing properties to

    beneficiaries by 2019

    767 3 150 497 2 653 The pilot procurement project delayed the process of appointment of contractors

    Performance indicators

    1

    2

    Programme 2: Integrated Sustainable Human Settlements

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    1. A Multi-Year

    Housing Development

    Plan/APP developed by

    October

    Multi-Year Housing Development Plan reviewed

    Reviewed Multi–year Human Settlement development plan

    Multi-Year

    Housing

    Development

    Plan reviewed

    None None

    2. Number of informal

    settlements formalised

    through township

    establishment

    Not achieved

    4 settlements formalised

    0 4 The three service providers appointed in March 2015 for a period of 2 years.

    1 Customised Indicators

    2 Provincial Specific Indicators

  • 33

    Programme 2: Integrated Sustainable Human Settlements

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    3. Number of Hectares

    of land acquired

    0 50ha 0 50ha Identified land

    was overpriced

    4. Number of planned

    human settlement

    (housing) development

    based on IDP’s,

    National and Provincial

    priorities approved

    (Number of

    development sites

    identified)

    N/A 10 000 10 000 None None

    5. Number of

    municipalities

    accredited on housing

    provision

    Prepared one

    municipality for

    level two

    Accreditation

    Confirm one municipality for level 2 Accreditation

    0 1 Municipality Municipality has not improved the audit outcomes

    6. Number of capacity

    building workshops

    conducted

    35 35 38 3 The additional

    three workshops

    were requested

    by Presidency in

    Muyexe

    7. Number of

    municipalities

    capacitated and

    supported with regard

    to human settlement

    (housing) development

    planning

    2 (Elias

    Motsoaledi &

    Tubatse

    supported)

    2 Municipality

    supported

    through NUSP

    2 None None

    8. Number of Acts

    passed and/or policy

    guidelines approved

    Draft provincial

    housing

    allocation policy

    available

    Informal

    settlement Bill still

    with the

    Provincial

    Legislature for

    gazetting

    Pass1 Policy/

    Act

    0 1 Draft policy on

    Provincial

    Housing

    Allocation

    available

  • 34

    Programme 2: Integrated Sustainable Human Settlements

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    9. Number of research

    papers completed

    None 1 0 1 Research paper

    on Housing

    Cooperatives still

    at Draft stage

    10. Number of new

    housing units

    completed in the

    Province across all

    housing programmes

    being utilized by the

    Province

    2 877 10 500 2 065 8 435 The pilot procurement project delayed the process of appointment of contractors

    11. Number of Housing

    stock/RDP rectified

    95

    700 60 640 The pilot procurement project delayed the process of appointment of contractors

    12. Number of

    households connected

    to basic services as

    part of the informal

    Settlement Upgrading

    Programme

    N/A 3 000 0 3 000 The pilot procurement project delayed the process of appointment of contractors

    13. Number of rental

    units built (CRU) and

    (SH)

    N/A 250 0 250 The pilot procurement project delayed the process of appointment of contractors

    14. Number of new

    sites connected to

    basic water and

    sanitation services as

    part of the Integrated

    Residential

    Development

    Programme

    N/A 500 0 500 Polokwane Ext.

    121 and 86 –

    service provider

    was delayed due

    to outstanding

    power of attorney

    from DPW.

    15. Number of

    Enhanced Peoples

    Housing Process units

    N/A 150 0 150 The pilot procurement project delayed the process of appointment of

  • 35

    Programme 2: Integrated Sustainable Human Settlements

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    completed contractors

    16. Number of units

    transferred through the

    Enhanced Extended

    Discount Benefit

    Scheme

    135 150 188 38 Carryover

    projects from

    2013/14

    17. Number of rental

    units sold to

    beneficiaries

    N/A N/A N/A N/A N/A

    18. Number of rental

    units transferred

    N/A N/A N/A N/A N/A

    19. Number of units

    registered and

    endorsed

    767 3 000 309 2 691 The pilot procurement project delayed the process of appointment of contractors

    20. Number of debtors

    reduced per financial

    year

    N/A N/A N/A N/A N/A

    21. Number of rental

    units devolved to

    municipalities in terms

    of section 15 of the

    housing Act, 97

    None 3 3 None None

    22. Number of projects

    approved

    80 80 32 48 Outcome of SCM

    yielded fewer

    contractors than

    expected.

    23. Number of job

    opportunities created

    466 5 500 392 5 108 The pilot procurement project delayed the process of appointment of contractors

    24. Number of

    beneficiaries/ subsidies

    approved on HSS

    N/A 10 500 10 171 329 Some applicants

    for subsidies did

    not qualify in

    identified areas

  • 36

    Programme 2: Integrated Sustainable Human Settlements

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    25. Percentage of

    disputes/cases

    resolved

    89% (189 of

    213)

    100% 91% (273 of

    301)

    9% Non-availability of

    parties

    26. Number of Reports

    submitted (MEC

    advisory panel)

    1 1 0 1 New advisory

    panel was

    constituted in the

    4th quarter.

    27. Number of Finance-

    Linked Individual

    Subsidy Programme

    (FLISP) units

    completed

    N/A 300 60 240 Applicants failing National Credit Act requirements.

    Note: Performance Indicator 11 has been funded under blocked projects

    Reasons for all deviations

    The National Treasury pilot on procurement for Human Settlements delayed appointment of

    service providers to implement Housing projects for the year

    Beneficiaries for rural housing programme saturated in Lephalale and others failing searches

    In accordance with FLISP criteria, applicants did not fulfil all requirements

    Affected parties to disputes not adhering to the procedure of case management therefore delaying

    conclusion.

    Strategy to overcome areas of under performance

    Extension of contract period granted for contractors appointed in 2014/15 financial year.

  • 37

    Sub-programme expenditure

    2014/2015 2013/2014

    Sub- Programme Name Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    R’000 R’000 R’000 R’000 R’000 R’000

    Housing needs, research

    and planning

    16,875

    14,898

    1,977

    22,432

    22,384

    48

    Housing development ,

    implementation ,

    planning and targets

    874,201

    629 462

    244 739

    716,363

    338,014

    378,349

    Housing asset

    management and

    property management

    32,753

    32,572

    181

    37,900

    34,297

    3,603

    Total 923,829 676 932 246 897 776,695 394,695 382,000

    Linking performance with budgets

    Significant underspending in programme 2 is from transfers and subsidies, which funds the

    implementation of human settlements development. Expenditure and performance recorded is

    lower than planned. This is attributed mainly to delayed appointment of contractors.

    file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!V331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!V331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AK331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AK331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AK331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AZ331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AZ331file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/11966CCA.xlsm%23RANGE!AZ331

  • 38

    4.3 Programme 3: Cooperative Governance

    The purpose: The programme aims at capacitating municipalities to implement their legal

    mandates through the following sub-programme:

    List of the sub-programmes

    Sub-programme Description

    Local Government

    Support

    To support municipalities with administration

    requirements and compliance, financial management

    and accountability, public participation, capacity

    development as well as perform monitoring and

    evaluation

    Development Planning To support and monitor municipalities on spatial

    planning, disaster management, land use

    management, municipalities infrastructure delivery,

    local economic development and IDP coordination

    Strategic Objective: The objective of this programme focuses on capacity development in municipalities. Municipalities require constant monitoring and evaluation with the purpose of implementation on corrective actions to ensure service delivery. Governance in municipalities has improved in the past five years. This is evident in the:

    Professionalisation of the recruitment of senior managers in municipalities

    Development and implementation of valuation rolls in all 25 local municipalities

    Compliance with the Municipal Systems Act by installing controls to ensure proper and effective governance systems

    Development and implementation of credible IDP’s

    Strategic oversight on financial management programme

    Strategic objectives, performance indicators, planned targets and actual achievements

    The Sub-Department has monitored the performance of municipalities in compliance with relevant legislation. Concurrently, provided support to municipalities to ensure continued service delivery. This is done to ensure that municipalities are functional and able to perform their constitutional mandate of providing services to citizens timeously. Financial management in municipalities The improvement of financial management in municipalities has been a cornerstone of our intervention for immediate impact and preservation of long term goals to enhance municipal efficiency and viability. Through targeted and focused intervention there has been a remarkable progress on the audit outcomes of 2013/14 as depicted on the table below:

    Municipal Audit Outcomes

    Audit opinion 2012/13 2013/14

    Unqualified 0 12

    Qualified 18 11

  • 39

    Audit opinion 2012/13 2013/14

    Adverse 3 1

    Disclaimers 9 6

    It is imperative that systems have to be established and maintained to ensure effective, efficient and economic use of resources and to prevent fruitless and wasteful expenditure by this important sphere of government.

    The system of local government is maturing in the Province. The Provincial Executive Council (EXCO) has evoked section 139(4)(b) in Ba-Phalaborwa in order to assist in compliance with Municipal Property Rates Act and to ensure that maximum revenue is collected for the interest of both government and community. Implementation of the Operation Clean Audit Plan

    Twenty seven (27) municipalities have developed and submitted the audit remedial action plans to address issues raised by the Auditor General in respect of the 2013/14 municipal audit. The following three (3) municipalities have not yet submitted the audit remedial action plans in respect of the 2013/14 municipal audit namely: Aganang, Mogalakwena, and Ba-Phalaborwa.

    The reasons for non-compliance are that Ba-Phalaborwa municipality is disputing the audit outcomes, and Aganang municipality submitted the Annual Financial Statements late and received the audit opinion late in February 2015. Several engagements were done at Mogalakwena municipality to be assisted to develop remedial plans. However, to date, the municipality has neither provided an action plan nor availed themselves to be assisted by the Department. The Department has assessed twenty one (21) audit remedial action plans and provided written feedback.

    SPLUMA implementation

    The Spatial Planning and Land Use Management Act, (SPLUMA) was enacted during 2013. The Province has finalised Regulations to the Act implementation is 1 July 2015. The Action plan with key tasks to be undertaken by the Municipalities has been developed and coupled with the generic Modalities on Agreements for the Joint District Municipal Tribunal format. The Department of Rural Development and Land Reform has also appointed a Service Provider to assist municipalities in the development of modalities regarding, by-laws, delegations, tariffs and the drafting of the Memorandum of Understanding in preparation for the implementation of the Act.

    Strategic objectives

    Programme 3 : Co-operative Governance

    Strategic objectives Actual

    Achievement

    2013/2014

    Planned

    Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    6. Improved support

    and oversight in all

    municipalities by

    2015

    4 Reports on

    implementation

    of municipal

    capacity

    development

    plan

    4 None None

  • 40

    Performance indicators

    3

    4

    Programme 3 : Co-operative Governance

    Performance Indicator Actual Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual Achievement

    2014/2015

    Deviation from planned target

    to Actual Achievement

    2014/2015

    Comment on deviations

    1. Number of municipal performance reports compiled as per the requirements of Section 47 of the MSA

    N/A 1 1 None None

    2. Number of municipalities supported to improve audit outcomes

    5 30 30 None None

    3. Number of

    municipalities with

    functional performance

    audit committees

    30 30 30 None None

    4. Number of

    municipalities with

    functional Performance

    Management System

    (PMS)

    N/A 30 30 None None

    5. Number of

    municipalities supported

    with fraud and anti-

    corruption strategy

    N/A 30 8 22 Capacity challenges

    6. Number of reports on

    the filing of municipal

    managers and section 56

    4 4 4 None None

    7. Number of

    municipalities with HR

    policies norms and

    standards

    30 30 30 None None

    8. Number of

    municipalities supported to

    fill top six positions filled by

    30 30 30 None None

    3 Customised Indicators

    4 Provincial Specific Indicators

  • 41

    Programme 3 : Co-operative Governance

    Performance Indicator Actual Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual Achievement

    2014/2015

    Deviation from planned target

    to Actual Achievement

    2014/2015

    Comment on deviations

    competent staff

    9. Number of

    municipalities capacitated

    to implement individual

    PMS with respect to sec

    56 & 57 managers

    30 30 30 None None

    10. Number of

    municipalities supported in

    MPRA implementation

    24 25

    25 None None

    11. Number of

    municipalities with MPAC

    30 30 30 None None

    12. Number of reports on

    government debts

    reduction

    4 4 4 None None

    13. Number of reports on

    the implementation of

    clean audit plan

    4 4 4 None None

    14. Number of

    municipalities supported to

    establish audit committees

    30 30 30 None None

    15. Number of reports on

    implementation of

    Municipal capacity

    development plan

    4 4 4 None None

    16. Number of

    municipalities supported to

    spend MIG

    29 29 29 None None

    17. Number of report

    produced on households

    with access to basic

    services i.e. (water,

    sanitation, electricity,

    refuse removal) from

    municipalities

    1 1 1 None None

  • 42

    Programme 3 : Co-operative Governance

    Performance Indicator Actual Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual Achievement

    2014/2015

    Deviation from planned target

    to Actual Achievement

    2014/2015

    Comment on deviations

    18. Number of

    Municipalities with

    functional ward

    committees

    25 25 23 2 Non-submission of

    reports by

    Mogalakwena and

    Greater Tubatse

    19. Number of

    municipalities with

    functional IGR structures

    5 5 5 None None

    20. Number of Izimbizo

    held by MEC, Mayors &

    Councillors

    4 4 4 None None

    21. Number of awareness

    campaign conducted for

    elections

    4 2 2 None None

    22. Number of

    municipalities where full

    CDW programmes are

    implemented

    25 25 25 None None

    23. Number of district

    municipalities with disaster

    management centres

    supported

    5 5 5 None None

    24. Number of meetings of

    the Intergovernmental

    Disaster Management

    forum

    4 4 4 None None

    25. Number of provincial

    fire preparedness reports

    compiled

    1 1 1 None None

    26. Number of municipalities supported to implement SDFs in term of guidelines

    30 30 30 None None

    27. Number of

    municipalities

    implementing LUMS

    12 12 12 None None

  • 43

    Programme 3 : Co-operative Governance

    Performance Indicator Actual Achievement

    2013/2014

    Planned Target

    2014/2015

    Actual Achievement

    2014/2015

    Deviation from planned target

    to Actual Achievement

    2014/2015

    Comment on deviations

    28. Number of reports on

    the Statutory Board

    (Townships Board)

    4 5 5 None None

    29. Number of

    municipalities supported

    with spatial and land use

    management

    N/A 30 30 None None

    30. Number of demarcated

    sites available for Human

    Settlements

    5450 5000 5130 130 Additional sites

    emanates from

    public parcels and

    other communities

    that were not

    engaged during the

    planning phase

    31. Number of municipalities supported with the development of legally compliant IDP

    30 30 30 None None

    32. Number of municipalities with LED strategies assessed

    N/A 30 30 None None

    33. Number of District LED fora established

    5 5 5 None None

    34. Number of work opportunities created through the community work programme

    23 969 17 000 21 496 4496 CoGTA provided

    more allocation to

    expand to additional

    4 municipalities

    Reasons for all deviations

    The Sub-Department has achieved 97% of its targets and the reasons are as follows:

    Additional work opportunities: Greater Tzaneen, Greater Tubatse and Greater Giyani

    increased by a combined total of 2496 participants. The program expanded by 2000

    participants to 4 municipalities being Musina, Greater Letaba, Elias Motsoaledi and

    Polokwane municipality. Each municipality has 500 participants

    Mogalakwena and Greater Tubatse municipalities are not complying with the IGR Act

  • 44

    Strategy to overcome areas of under performance

    Accounting Officers of municipalities have been engaged

    Sub-programme expenditure

    2014/2015 2013/2014

    Sub- Programme Name

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    R’000 R’000 R’000 R’000 R’000 R’000

    Local Governance 174,796 174,443 354 173,235 173,011 224

    Development

    Planning 58,009 57,870 138 66,335 60,870 5,465

    Total

    232,805 232,313 492 239,571 233,881 5,690

    Linking performance with budgets

    The programme has achieved 97% of its planned targets during the year in accordance

    with allocated budget.

    4.4 Programme 4: Traditional Affairs

    The purpose: Aims to support the institution of Traditional Leadership to operate within the

    context of co-operative governance

    List of the sub-programmes

    Sub-programme Description

    Traditional Institutional

    Admin

    To support Traditional Institutions with administration,

    resource administration, land administration and

    facilitation of rural development

    Administration of

    Houses of Traditional

    Leaders

    To support Houses of Traditional leadership with

    administration of its committees and Local Houses

    Strategic Objective: Ensure that provisions of Traditional Leadership legislation and policies are

    implemented

    Strategic objectives, performance indicators, planned targets and actual achievements

    The Provincial Commission on Traditional Leadership, Disputes and Claims has

    received 507 applications and 175 cases have been completed to date.

    The President of the Republic has on 09 February 2014 approved salary increases

    for all categories of Traditional Leaders. This has been done per Proclamation No.9

    of 2014, published in Government Gazette No. 37352 dated 18 February 2014. The

    file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V481file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK481file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK481

  • 45

    Department has paid salary adjustments for 2014/15 and arrears on Persal System

    for active Traditional Leaders. The payment was made during June 2014.

    In line with Framework for the Provision of Enabling Resources to Qualifying

    Traditional Leaders and members of Houses of Traditional Leaders the Department

    is still mobilising resources to implement some of the tools of trade such as: motor

    vehicles, provisions for Kings and construction of traditional councils' offices.

    Furthermore, 29 previously recognised Traditional Leaders were paid allowances

    including arrears

    Strategic objective

    Programme 4: Traditional Institutional Development

    Strategic objectives Actual

    Achievement

    2012/2013

    Planned

    Target

    2013/2014

    Actual

    Achievement

    2013/2014

    Deviation from

    planned target to

    Actual

    Achievement for

    2013/2014

    Comment on

    deviations

    7. Supported all

    established

    institutions of

    Traditional Leaders

    by 2019

    12 12 12 None None

    Performance indicators

    Programme 4: Traditional Institutional Development

    Performance

    Indicator

    Actual

    Achievement

    2013/2014

    Planned

    Target

    2014/2015

    Actual

    Achievement

    2014/2015

    Deviation from

    planned target

    to Actual

    Achievement

    for 2014/2015

    Comment on

    deviations

    1. Number of sittings by the Provincial House of Traditional Leaders

    2 2 2 None None

    2. Number of sittings by the local house of traditional leaders

    10 10 10 None None

    3. Number of Traditional Councils supported

    184 185 185 None None

  • 46

    Sub-programme expenditure

    2014/2015 2013/2014

    Sub- Programme Name

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    Final Appropriation

    Actual Expenditure

    (Over)/Under Expenditure

    R’000 R’000 R’000 R’000 R’000 R’000

    Traditional Institutional Administration

    335,056

    334,654

    402

    304,530

    294,614

    9,916

    Administration of Houses of Traditional Leaders

    6,988

    6,844

    144

    6,925

    6,692

    233

    Total 342,044 341,498 545 311,455 301,306 10,149

    Linking performance with budgets

    The funds in this programme have been utilised towards compensation of Traditional Leaders and supporting of the functioning of Traditional Leadership institutions.

    file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!V631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK631file:///C:/Users/19279931/AppData/Local/Microsoft/19279931/My%20Documents/81593643/AppData/Local/Microsoft/Windows/Temporary%20Internet%20Files/Content.MSO/AF624151.xlsm%23RANGE!AK631

  • 47

    5. TRANSFER PAYMENTS

    5.1. Transfer payments to public entities

    No transfer payments were made to any public entity

    5.2. Transfer payments to all organisations other than public entities

    No transfer payments were made to any organisations

    6. CONDITIONAL GRANTS

    6.1. Conditional grants and earmarked funds paid

    Not Applicable to the Department

    6.2. Conditional grants and earmarked funds received

    The table below details the conditional grants and earmarked funds received for the period 1 April

    2014 to 31 March 2015.

    Conditional Grant Human Settlement Development Grant:

    Department who transferred the grant

    Human Settlements

    Purpose of the grant To provide funding for the creation of

    Sustainable human settlements.

    Expected outputs of the grant

    Accelerated delivery of housing

    opportunities

    Efficient utilisation of land for Human

    Settlements development

    Improved property market

    Rectification

    Actual outputs achieved 2065 housing units completed

    497 properties transferred to beneficiaries

    Amount per amended DORA (R’000)

    R 825,603

    Amount received (R’000) R 825,603

  • 48

    Reasons if amount as per DORA was not received

    None

    Amount spent by the Department (R’000)

    R583,021

    Reasons for the funds unspent by the entity

    The pilot procurement project delayed the process of appointment of contractors

    Reasons for deviations on performance

    The pilot procurement project delayed the process of appointment of contractors

    Measures taken to improve performance

    Extension of contract period granted for contractors appointed in 2014/15 financial year.

    Monitoring mechanism by the receiving Department

    Inspections carried out during construction

    process

    Enhanced project management through

    decentralisation in local municipal areas

    Technical support through deployment of

    Cuban Technical Advisors

    7. DONOR FUNDS

    7.1. Donor Funds Received

    No donor funds were received during the year under review

    8. CAPITAL INVESTMENT

    8.1. Capital investment, maintenance and asset management plan

    Infrastructure

    projects

    2014/2015 2013/2014

    Final Appropriation

    R’000

    Actual Expenditure

    R’000

    (Over)/Under Expenditure

    R’000

    Final Appropriation

    R’000

    Actual Expenditure

    R’000

    (Over)/Under Expenditure

    R’000

    New and replacement assets

    825,603

    583 021 242 582 682,110 303,449 378,661

    Total 825,603 583 021 242 582 682,110

    303,449 378,661

  • 49

    PART C: GOVERNANCE

  • 50

    1. RISK MANAGEMENT

    1.2 Risk management policy and strategy.

    The Department has a Risk Management Strategy and policy and they are reviewed

    annually and approved by the Accounting officer.

    1.2 Regular risk assessments

    Risk Assessment is conducted on an annual basis to identify risks that have a

    potential to adversely affect achievements of Departmental Objectives and overall

    efficiency and effectiveness of business processes.

    1.3 Risk Management Committee

    The Risk Management Committee exists in terms of the Risk Committee Charter

    reviewed on an annual basis. The Risk Committee reviews the Departments system

    of Risk Management and oversees implementation of recommendations relating to

    risk management

    1.4 Audit Committee

    The Audit Committee considers the Department’s risk management report on a quarterly

    basis and advises the Department on improvements of risk management.

    Progress in the management of risks, whether this has transmitted into improvements in

    the Department’s performance, and if not, what it plans on doing to address this problem

    In the year under review, the Department mitigated 40% of the prioritized risks. Risks for

    which target could not be achieved continue to be significant to the achievement of

    Departmental objectives and as a result have been targeted during the 2015/16 financial

    year.

    For the financial year under review, a risk assessment was conducted and the following

    are prioritized risks:

    Risk Progress

    Inability to meet equity targets Two people with disability were appointed

    Theft and insecurity CCTV to be procured during 2015/16 FY.

    Adverse reputation of the Department Assessment report on all social media platforms made, of which

    outcome was presented to management

    Loss of records at traditional councils Monitored compliance with the record management policy and

    the file plan at Sekhukhune District Municipality

  • 51

    Risk Progress

    Poor financial management in

    municipalities and ineffective

    implementation of Audit action plans

    Assessments were conducted through Back to Basics approach

    Limitations to acquire well located land Land identified in Tzaneen and Burgersfort

    Inadequate bulk infrastructure Business plan finalized.

    Capacity constraints in project

    management and engineering skills

    Continued monitoring of projects and joint inspection between

    stakeholders conducted

    Inaccessibility of credit to

    beneficiaries(gap market)

    FLISP project launched (Bendor Ext. 100)

    Fraud and corruption Received 56 cases and 48 have been finalized.

    Prolonged operational stoppages Service provider to develop BCP appointed on the

    12/02/2015.BCP will be finalized December 2015

    2. FRAUD AND CORRUPTION

    Fraud prevention initiatives

    Fraud Prevention Plan developed and has been implemented through developing of Anti-

    Fraud &Corruption Strategy, awareness workshops and conducting investigation on

    cases reported.

    Mechanisms in place to report fraud and corruption

    Procedure manual developed and all cases received are sanctioned by Head of Department before official investigation is conducted. Whistle blowing policy in place to guide officials on the process and management.

    Procedure on handling reported cases

    Cases are reported to the Head of Department office and upon findings emanating from the investigation, recommendation are forwarded to Head of Department for his/her consideration. Those which requires further referral to other units and or agencies, such referrals are done for their further handling

    3. MINIMISING CONFLICT OF INTEREST

    All employees are required to apply to the Executive Authority for permission to conduct

    remunerative work outside the public service in terms of Section 30 of the Public Service

    act. The Department has entered into an agreement with Companies and Intellectual

    Property Commission (CIPC) in terms of which access has been provided for the

    purposes of viewing on the CIPC database. Before an award is made to the prospective

    bidder a search is performed to determine if either of the directors/members is a

    governmental employee.

  • 52

    Where a conflict of interest is identified, disciplinary proceedings are instituted against the

    affected employee.

    4. CODE OF CONDUCT

    Ethical practices in the Department are in line with the Code of Conduct for the Public

    Service. There is a reasonable mutual and harmonious relationship between employer

    and employee in the Department due to consistent interaction between the parties in the

    form of Labour Management Forum as well as bilateral meetings with organised labour.

    The Department regularly conducts workshops, briefing sessions, inductions and training

    sessions in relation to both PSCBC Resolution 1 of 2003 and PSCBC Resolution 14 of

    2002. Disciplinary Code and Procedures Policy has been approved by the Executive

    Authority and is in force.

    In case of breach of Code of Conduct, disciplinary proceedings will be instituted against

    the affected employee.

    5. HEALTH SAFETY AND ENVIRONMENTAL ISSUES

    The Department has a functioning Employee Wellness Unit which addresses all the

    Health Safety and Environmental issues.

    The Department has a Committee that deals with Health Safety and Environment.

    Audits are done on continuous basis to address issues that might pose risk to Healt