volume no. 2 division 21- 33 construction ......12. astm f438: standard specification for...

864
VOLUME NO. 2 DIVISION 21- 33 CONSTRUCTION DOCUMENT SPECIFICATIONS FOR THE HAGERSTOWN COMMUNITY COLLEGE CENTER FOR BUSINESS & ENTREPRENEURIAL HAGERSTOWN, MARYLAND PROJECT NO. HCC20-002 BFM PROJECT NO. 18044 DGS PROJECT NO. CC-02-461 HAGERSTOWN COMMUNITY COLLEGE BOARD OF TRUSTEES DR. JAMES S. KLAUBER PRESIDENT December 6, 2019 Prepared by: BUSHEY FEIGHT MORIN ARCHITECTS INC. 473 North Potomac Street Hagerstown, Maryland 21740 (301) 733-5600

Upload: others

Post on 18-Feb-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

  • VOLUME NO. 2

    DIVISION 21- 33

    CONSTRUCTION DOCUMENT

    SPECIFICATIONS

    FOR THE

    HAGERSTOWN COMMUNITY COLLEGE

    CENTER FOR BUSINESS & ENTREPRENEURIAL

    HAGERSTOWN, MARYLAND

    PROJECT NO. HCC20-002

    BFM PROJECT NO. 18044

    DGS PROJECT NO. CC-02-461

    HAGERSTOWN COMMUNITY COLLEGE

    BOARD OF TRUSTEES

    DR. JAMES S. KLAUBER

    PRESIDENT

    December 6, 2019

    Prepared by:

    BUSHEY FEIGHT MORIN ARCHITECTS INC. 473 North Potomac Street

    Hagerstown, Maryland 21740

    (301) 733-5600

    WILLIJI12-18

  • DIVISION 21

    FIRE SUPPRESSION

    BUSHEY FEIGHT MORIN ARCHITECTS INC.

    473 NORTH POTOMAC STREET

    HAGERSTOWN, MARYLAND 21740

    301-733-5600 FAX: 301-733-5612

  • SECTION 21 05 00 - COMMON WORK RESULTS FOR FIRE SUPPRESSION

    HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 1

    PART 1 GENERAL

    1.1 SUMMARY

    A. Section includes:

    1. Above Ground Piping2. Pipe Hangers and Supports3. Piping Specialties4. Valves5. Alarm Check Valve (Riser Check Valves)6. Water Alarm Bell7. Detector Check Valves8. Signs9. Plastic Pipe Markers10. Firestopping11. Firestopping Accessories

    B. Related Sections: The following sections contain requirements that relate to this section:

    1. Division 07 Section: “Firestopping”: Product requirements for firestopping specified for placement by this section.

    2. Division 09 Section: “Painting and Coating” Execution requirements for piping painting specified by this section.

    3. Division 21 Section: “Common Motor Requirements for Fire Suppression Equipment.”

    4. Division 21 Section: “Fire Suppression Sprinkler System” for wet or dry type sprinkler system heads and accessories.

    5. Division 21 Section: “Dry Pipe Fire Suppression Sprinkler System” for components specific to dry pipe sprinkler systems.

    6. Division 28 Section: “Fire Detection and Alarm” for interface of fire suppression system with fire alarm.

    1.2 REFERENCES (Unless otherwise noted, references apply to “latest editions.”)

    A. ASME (American Society of Mechanical Engineers):

    1. ASME B16.1 - Gray Iron Pipe Flanges and Flanged Fittings2. ASME B16.11 - Forged Fittings, Socket-Welding and Threaded.3. ASME B16.18 - Cast Copper Alloy Solder Joint Pressure Fittings.4. ASME B16.22 - Wrought Copper and Copper Alloy Solder Joint Pressure

    Fittings.5. ASME B16.25 - Buttwelding Ends.6. ASME B16.3 - Malleable Iron Threaded Fittings.7. ASME B16.4 - Gray Iron Threaded Fittings.8. ASME B16.5 - Pipe Flanges and Flanged Fittings.9. ASME B16.9 - Factory-Made Wrought Buttwelding Fittings.10. ASME B36.10M - Welded and Seamless Wrought Steel Pipe.

  • 21 05 00 - 2 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    11. ASME B31.9 – Building Services Piping.12. ASME Sectin IX – Boiler and Pressure Vessel Code – Welding and Brazing

    Qualifications.

    B. ASTM (American Society for Testing and Materials International):

    1. ASTM A53/A53M: Standard Specification for Pipe, Steel, Black and Hot-Dipped, Zinc-Coated, Welded and Seamless.

    2. ASTM A135/135M: Standard Specification for Electric-Resistance-Welded Steel Pipe.

    3. ASTM A234/A234M: Standard Specification for Piping Fittings of Wrought Carbon Steel and Alloy Steel for Moderate and High Temperature Service.

    4. WSTM A795/A795M: Standard specifications for Black and Hot-Dipped Zinc-Coated (Galvanized) Welded and Seamless Steel Pipe for Fire Protection Use.

    5. ASTM A536/A536M: Standard Specification for Ductile Iron Castings.6. ASTM B247/B247M: Standard Specification for Aluminum and Aluminum-

    Alloy Die Forgings, Hand Forgings, and Rolled Ring Forgings.7. ASTM B32: Standard Specification for Solder Metal.8. ASTM B75/B75M: Standard Specification for Seamless Copper Tube.9. ASTM B88/B88M: Standard Specification for Seamless Copper Water Tube.10. ASTM B251/B251M: Standard Specification for General Requirements for

    Wrought Seamless Copper and Copper-Alloy Tube.11. ASTM D3309: Standard Specification for Polybutylene (PB) Plastic Hot- and

    Cold-Water Distribution Systems.12. ASTM F438: Standard Specification for Socket-Type Chlorinated Poly (Vinyl

    Chloride) (CPVC) Plastic Pipe Fittings, Schedule 40.13. ASTM F439: Standard Specification for Socket-Type Chlorinated Poly (Vinyl

    Chloride) (CPVC) Plastic Pipe Fittings, Schedule 80.14. ASTM F442/F442M: Standard Specification for Chlorinated Poly (Vinyl

    Chloride) (CPVC) Plastic Pipe (SDR-PR).15. ASTM F493: Standard Specification for Solvent Cements for Chlorinated Poly

    (Vinyl Chloride) (CPVC) Plastic Pipe and Fittings.

    C. AWS (American Welding Society):

    1. AWS A5.8/A5.8M: Specification for Filler Metals for Brazing and Braze Welding.

    2. AWS D1.1/D1.1M: Structural Welding Code - Steel.

    D. AWWA (American Water Works Association):

    1. AWWA C110 - American National Standard for Ductile-Iron and Grey-Iron Fittings, 3 in. through 48 in., for Water and Other Liquids.

    2. AWWA C111 - American National Standard for Rubber-Gasket Joints for Ductile-Iron Pressure Pipe and Fittings.

    3. AWWA C151 - American National Standard for Ductile-Iron Pipe, Centrifugally Cast, for Water.

    4. AWWA C606 – American National Standard for Grooved and Shouldered Joints .

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 3

    E. NFPA (National Fire Protection Association):

    1. NFPA 3 – Standard for Commissioning of Fire Protection and Life Safety Systems

    2. NFPA 13 - Installation of Sprinkler Systems.3. NFPA 14 - Standard for the Installation of Standpipe, Private Hydrants and Hose

    Systems.4. NFPA 15 – Standard for Water Spray Fixed Systems for Fire Protection.5. NFPA 24 - Installation of Private Fire Service Mains and Their Appurtenances.

    F. UL (UL Fire Protection Equipment Directory)

    1. UL 1887 - Fire Tests of Plastic Sprinkler Pipe for Visible Flame and Smoke Characteristics.

    G. FM Global:

    1. FM – Approval Guide, A Guide to Equipment, Materials and Services Approved by Factory Mutual Research for Property Conservation.

    1.3 DEFINITIONS

    A. Working plans and sprinkler system shop drawings as used in this Section refer to documents (including drawings and calculations) prepared pursuant to requirements in NFPA 13, “Standard for the Installation of Sprinkler Systems,” latest edition for obtaining approval of authority having jurisdiction.

    B. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term product includes the terms material, equipment, system, and terms of similar intent.

    1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

    2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

    3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

    C. Substitutions: Changes proposed by Contractor in products, materials, equipment, and methods of construction required by the Contract Documents.

    D. Basis-of-Design Product Specification: Where a specific manufacturer's product is named, or a product is accompanied by the words "basis of design," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in service performance, physical properties, appearance, and other

  • 21 05 00 - 4 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    characteristics for purposes of evaluating comparable products of other named manufacturers.

    E. Firestopping (Through-Penetration Protection System): Sealing or stuffing material or assembly placed in spaces between and penetrations through building materials to arrest movement of fire, smoke, heat, and hot gases through fire rated construction.

    F. Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

    G. Extended Warranty: Written warranty required by or incorporated into the Contract Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Owner.

    H. Other definitions for fire protection systems are included in referenced NFPA standards.

    1.4 SYSTEM DESCRIPTION

    A. Layout sprinkler system piping and heads and all fire protection piping in accordance with requirements of the National Fire Protection Association and Washington County Fire Marshal. Areas requiring sprinklers shall be designed for occupancy as required by applicable codes. Conceal fire protection piping in finished spaces unless indicated otherwise. System drains and inspector's test shall not be located in finished spaces.

    B. Sprinkler equipment and work shall conform to requirements of NFPA 13, “Standard for the Installation of Sprinkler Systems,”. In addition, all work shall conform to requirements of all codes and regulations of authorities having jurisdiction over this work, including, but not limited to International Fire Code. Layout and size all piping based on hydraulic calculations.

    1. Provide structural work and equipment required for expansion and contraction of piping. Verify anchors, guides and expansion joints provide an adequately protected system.

    C. Detailed, dimensional layout and Working Plans, together with descriptive specifications, hydraulic calculations and engineering data sheets for all manufactured material and equipment, shall be furnished for review. Prior to submission of these Working Plans to Engineer, submit drawings and data to the local authorities for review and approval. Provide local authority’s approval letter in the data provided to the Engineer. No material will be reviewed by Engineer until these prior approvals have been obtained. No materials shall be ordered or installed until these prior approvals have been obtained. Provide hydraulic calculations. All costs related to changes required by the Fire Marshal, Underwriters, local authorities and other reviewing authorities shall be the Contractor's responsibility.

    D. Final design of the system shall be coordinated with field conditions and available water supply. All fire protection piping and equipment shown on the Contract Drawings are for suggestive purposes only. Field verify all conditions. All items of equipment shall be installed by on the job measurements and coordinated with all other trades. Under no circumstances shall the Contract Drawings be scaled.

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 5

    E. Provide all necessary parts and accessories to build a complete and operable system, even though such parts and accessories may not be shown or mentioned herein.

    F. Obtain accurate water flow test data before completing design of sprinkler/standpipe systems. If necessary, perform a fire flow test at the nearest fire hydrants. In certain localities the local water department will perform this test. In those locations, pay the local authority fee for the test.

    G. Firestop interruptions to fire rated assemblies, materials, and components.

    1.5 SUBMITTALS

    A. Division 01 Section: “Submittal”: Submittal Procedures.

    B. Shop Drawings: Indicate pipe materials used, jointing methods, supports, floor and wall penetration seals. Indicate installation, layout, weights, mounting and support details, and piping connections.

    C. Shop Drawings and Product Data:

    1. Clearly identify all submittals: a. Indicate intended application, location, etc.b. Each submittal shall indicate the associated specification section, and

    paragraphs. Do not combine product data and shop drawing submittals from different spec sections into a single submittal package, even though they may be the same distributor, vendor or part of a single material order.

    c. Clearly indicate the exact type, model number, size and special features of the proposed item.

    d. Include catalog spec sheets to completely describe proposed equipment.e. Factory order forms only showing the required capacities are not

    acceptable.f. Identify all options furnished to meet specifications.g. The Architect shall not select equipment ratings and/or options.

    Submittals not properly marked shall be returned without review.

    D. Comparable Products Submission:

    1. Document each request for a proposed comparable product with supporting data substantiating compliance of proposed product with Basis-of-Design product.

    2. Use the attached “Comparable Product Submittal Form” in addition to the requirements specified herein.

    3. Comparable products will not be reviewed without completion of the attached form.

    E. Coordination Drawings:

    1. Building Information Model (BIM):

    a. Coordination drawings shall be created from 3D BIM model of all Mechanical, Electrical, Fire Protection, and Plumbing systems. Assign

  • 21 05 00 - 6 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    an individual to serve as the main point of contact for the BIM related issues. This individual shall have sufficient BIM experience required for the size and complexity of the project and shall have relevant proficiency in the BIM process.

    b. Coordinate construction sequencing and scheduling activities and assure they are integrated with the BIM documents.

    c. All design modifications in the field, RFI Responses, Submittals, and Owner requested changes shall be documented and updated in the BIM documents in a timely manner.

    d. All coordination efforts and BIM updates shall be provided without changes to the contract cost and/or schedule.

    2. Prepare coordination drawings to a scale of ¼”=1’0” or larger, detailing major elements, components, and systems of mechanical equipment and materials in relationship with other systems, installations, and building components.

    3. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are of importance to the efficient flow of the work, including (but not necessarily limited to) the following:

    a. The proposed locations of piping, valving, ductwork, equipment, and materials.

    b. Planned piping layout, including valve and specialty locations and valve stem movement.

    c. Planned duct systems layout, including elbow radii and duct accessories.d. Clearances for installing and maintaining insulation.e. Clearances for serving and maintaining equipment, including tube

    removal, filter removal, and space for equipment disassembly required for periodic maintenance.

    f. Equipment connections and support details.g. Exterior wall and foundation penetrations.h. Fire-rated wall and floor penetrations.i. Sizes and location of required concrete pads and bases.j. Duct fire dampers.k. Access doors.l. Clearances at electrical components in accordance with the National

    Electrical Code.m. Indicate scheduling, sequencing, movement, and positioning of large

    equipment into the building during construction.n. Prepare floor plans, elevations, and details to indicate penetrations in

    floors, walls, and ceilings and their relationship to other penetrations and installations. Show all wall mounted access doors for devices in ductwork or piping.

    o. Prepare reflected ceiling plans to coordinate and integrate installations, air outlets and inlets light fixtures, communication systems components, cable trays, sprinklers, access doors and other ceiling mounted items.

    F. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

    G. Sprinkler system drawings identified as “working plans,” prepared according to NFPA 13. Submit required number of sets to authority having jurisdiction for review, comment,

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 7

    and approval. Include system hydraulic calculations where applicable. After obtaining approval, submit to the Engineer for review.

    1. Sprinklers shall be referred to on drawings and shall be specifically identified by the listed manufacturer’s style or series designation. Trade names and abbreviations are not permitted.

    H. Licensed engineer’s sprinkler system drawings specified in “Quality Assurance” article to authority having jurisdiction. Include system hydraulic calculations where applicable.

    I. Test reports and certificates as described in NFPA 13. Include “Contractor’s Material & Test Certificate for Aboveground Piping” and “Contractor’s Material & Test Certificate for Underground Piping.”

    J. Record Drawings: Prepare record documents in accordance with the requirements in Division 01 Section: "Execution Requirements." In addition to the requirements specified in Division 01, indicate the following installed conditions:

    1. Mains and branches of piping systems, with valves and control devices located and numbered, concealed unions located, and with items requiring maintenance located (i.e., valves, tamper switches, flow switches indicating valves, etc., strainers, tanks, etc.). Valve location diagrams, complete with valve tag chart. Refer to Section “Identification for Plumbing Piping and Equipment." Indicate actual inverts and horizontal locations of underground piping.

    2. Equipment locations (exposed and concealed), dimensioned from prominent building lines.

    3. Approved substitutions, Contract Modifications, Responses to Contractor’s Request for Information, and actual equipment and materials installed.

    4. Record the locations and invert elevations of underground installations.

    1.6 CLOSEOUT SUBMITTALS

    A. Division 01 Section: “Execution Requirements”: Closeout procedures.

    B. Project Record Documents: Record actual locations of components and tag numbering.

    C. Operation and Maintenance Data: Submit spare parts lists.

  • 21 05 00 - 8 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    1.7 QUALITY ASSURANCE

    A. Manufacturer Qualifications:

    1. Firms whose equipment, specialties, and accessories are listed by product name and manufacturer in UL Fire Protection Equipment Directory and FM Approval Guide and that conform to other requirements indicated.

    B. Listing/Approval Stamp, Label, or Other Marking:

    1. On equipment, specialties, and accessories made to specified standards.

    C. Listing and Labeling:

    1. Equipment, specialties, and accessories that are listed and labeled. The Terms “Listed” and “Labeled”: as defined in “National Electrical Code”, Article 100.

    D. Comply with requirements of authority having jurisdiction for submittals, approvals, materials, hose threads, installation, inspections, and testing.

    E. Comply with requirements of Owner’s insurance underwriter for submittals, approvals, materials, installation, inspections, and testing.

    F. Licensed Engineer: Submit design drawings, design calculation, and installation inspection reports. Include seal and signature of registered engineer licensed in jurisdiction where Project is located, certifying compliance with specifications.

    G. Installer’s Qualifications: Firms qualified to install and alter fire protection piping, equipment, specialties, and accessories, and repair and service equipment. A qualified firm is one that is experienced (minimum of 5 previous projects similar in size and scope to this Project) in such work, familiar with precautions required, and in compliance with the requirements of the authority having jurisdiction. Submit evidence of qualifications to the Engineer upon request. Refer to Division 01 Section: “Quality Requirements” for definition of “Installer”.

    H. To assure uniformity and compatibility of piping components in grooved piping systems, all grooved products utilized shall be supplied by a single manufacturer. Grooving tools shall be supplied from the same manufacturer as the grooved components.

    1. All castings used for coupling housings, fittings, valve bodies, etc., shall be date stamped for quality assurance and traceability.

    1.8 PROJECT / SITE CONDITIONS

    A. Existing Conditions:

    1. For existing building retrofits and renovations where existing piping mains, brackets, etc. are being re-used to any extent, field survey existing system and existing sprinkler head types. Design new work taking into consideration the existing systems and equipment that may affect performance of new work and

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 9

    the new design.

    1.9 PRE-INSTALLATION MEETINGS

    A. Division 01 Section: “Administrative Requirements”: Pre-installation meeting.

    B. Convene minimum two weeks prior to commencing work of this section.

    1.10 DELIVERY, STORAGE, AND HANDLING

    A. Division 01 Section: “Product Requirements”: Product storage and handling requirements.

    B. Deliver and store valves in shipping containers with labeling in place.

    C. Furnish cast iron and steel valves with temporary protective coating.

    D. Furnish temporary end caps and closures on piping and fittings. Maintain in place until installation.

    E. Maintain sprinkler protective caps and bulb protectors until system is ready to be placed in service.

    1.11 WARRANTY

    A. Division 01 Section: “Execution Requirements”: Project warranties and product bonds.

    1.12 SPECIAL TOOLS & OPERATING ACCESSORIES

    A. Wherever any products provided under this Division have tamperproof, special or restrictive hardware, as specified or where provided from the manufacturer as standard or optional construction, provide a minimum of two (2) matching tools, bits, sockets, etc. needed for operation and/or access to such items. This shall include, but is not limited to:

    1. Tamperproof screws, bolts, etc. on devices, enclosures, covers, etc.2. Penta-head bolts used on handhole and/or manhole lids.3. Penta-head bolts used on switchgear, transformers, etc.4. Any other special tools which are unique to that product.

  • 21 05 00 - 10 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    PART 2 PRODUCTS

    2.1 ABOVE GROUND PIPING

    A. Steel Pipe: ANSI/ASTM A53 schedule 40 black steel or ASME A135 and ASTM A795 Schedule 10 black or galvanized.

    1. Mechanical Grooved Couplings: Ductile iron housing clamps to engage and lock, "C" shaped, “installation ready” or “Flushseal” elastomeric sealing gasket, steel bolts, nuts, and washers; galvanized for galvanized pipe.a. Rigid Type: Housings shall be cast with offsetting, angle-pattern bolt

    pads to provide system rigidity and support and hanging in accordance with NFPA 13. Tongue and recess rigid type couplings shall only be used if the contractor uses a torque wrench for installation and provides a report to the engineer validating torque ratings were followed after installation. Required toque shall be in accordance with the manufacturer’s latest recommendation.1) 1-1/4” through 12”: Installation Ready” stab-on design, for

    direct ‘stab’ installation onto grooved end pipe without prior field disassembly and no loose parts. Viking V-Z05 V-7705, Victaulic Firelock® EZStyle 009H (1-1/4”-4”) or Victaulic Style 107N QuickVic™ (2”-12”).

    2) 2” and Larger: Standard rigid coupling design. Viking V-Zo5 or Victaulic Style 07.

    b. Flexible Type: Use in seismic areas and where required by NFPA 13.1) 2” through 8”: “Installation Ready” stab-on design, for direct

    ‘stab’ installation onto grooved end pipe without prior field disassembly and no loose parts. Viking: V-Z05, V-7705 or Victaulic 177 QuickVic™ or Grinnell G-Fire Figure 705.

    2) 2” and Larger: Standard flexible coupling design. Victaulic Style 75 or 77, Grinnell G-Fire Figure 705.

    c. Coupling gaskets shall be supplied for use as follows:

    Fire Protection Service Temperature Range Gasket RecommendationDry Systems Ambient FlushSeal®, EZ Style 009H or

    QuickVic™ design, Grade EPDM, Type A, Grinnell G-FIRE Figure 577, Tri-Seal Grade E “EPDM” gasket.

    Freezer Applications -30°F to 0°F(-34°C to -17°C)

    FlushSeal®, Grade L, Silicone, Grinnell G-FIRE Figure 577, Tri-Seal Grade E “EPDM” gasket – Petroleum-free silicone-based lubricant.

    Water/Wet Systems Ambient C-Shape, EZ Style 009H, or QuickVic ™ design or Grinnell G-FIRE, Grade EPDM, Type A, Pre-Lubricated

    2. Grooved End Fittings: ASTM A536 ductile iron, short radius, full flow FireLock® fittings, or standard ASTM A536 ductile iron, ASTM A234 forged

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 11

    steel, or ASTM A53 factory fabricated carbon steel fittings with factory grooved ends designed to accept Viking, Victaulic, or Grinnell G-FIRE.couplings.

    3. Installation-Ready™ fittings for Schedule [40][10] grooved end steel piping in fire protection applications sizes NPS 1- 1/4 thru 2 ½ . Fittings shall consist of a ductile iron housing conforming to ASTM A-536, Grade 65-45-12, with Installation-Ready™ ends. Fittings complete with pre-lubricated Grade “E” EPDM Type ‘A’ gasket; and ASTM A449 electroplated steel bolts and nuts. System shall be UL listed for a working pressure of 300 psi and FM approved for working pressure 65 psi.

    4. Mechanical Formed Fittings: Stainless steel pipe, ASTM A312, Schedule 10S, Type 304/304L stainless steel with plain ends. Stainless steel housing with integral pipe stop and O-ring pocket and O-ring uniformly compressed into permanent mechanical engagement onto pipe.

    D. All piping installed outside or otherwise exposed to freezing weather, shall be externally galvanized. Antifreeze loops are not permitted. Piping shall be painted red and the galvanized surface shall be properly prepped prior to painting to insure bonding.

    2.2 PIPE HANGERS AND SUPPORTS

    A. Conform to NFPA 13 for wet and dry pipe sprinkler systems and NFPA 14 for stand pipe systems.

    B. Hangers for Pipe Sizes 1/2 to 1-1/2 inch: cadmium plated, adjustable swivel, split ring.

    C. Hangers for Pipe Sizes 2 inch and Over: cadmium plated, swivel split rings.

    D. Multiple or Trapeze Hangers: Steel channels angle iron and steel schedule 40 pipe with welded spacers and hanger rods.

    E. Wall Support for Pipe Sizes to 3 inches: Cast iron hook.

    F. Wall Support for Pipe Sizes 4 inches and Over: Welded steel bracket and wrought steel clamp.

    G. Vertical Support: Steel riser clamp.

    H. Floor Support: Cast iron adjustable pipe saddle, lock nut, nipple, floor flange, and concrete pier or steel support.

    I. Copper Pipe Support: Carbon steel ring, adjustable, copper plated.

    J. Victualic Style 009H, 005, 107H and 07 rigid couplings may be used with IPS steel piping systems, which meet the support and hanging requirements of NFPA 13. An adequate number of Victaulic Style 177, 75 and 77 flexible couplings shall also be used to compensate for thermal expansion/contraction of the pipe.

    2.3 PLASTIC PIPE MARKERS:

    A. Provide pipe markers with the following background colors and designations:

  • 21 05 00 - 12 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    SERVICESTENCIL DESIGNATION

    LETTER COLOR BACKGROUND COLOR

    JACKET

    Fire Protection Fire Sprinkler Water White Safety Red Red

    B. Snap On Type: Provide manufacturer's standard pre printed, semi rigid snap on, color coded pipe markers, complying with ANSI A13.1

    C. Small Pipes: For external diameters less than 6", provide full band pipe markers, extending 360 degrees around pipe at each location, fastened by one of the following methods:

    1. Snap on application of pre tensioned semi rigid plastic pipe marker.2. Adhesive lap joint in pipe marker overlap.3. Taped to pipe (or insulation) with color coded plastic adhesive tape, not less than

    3/4" wide; full circle at both ends of pipe marker, tape lapped 1 1/2".

    2.4 FIRESTOPPING

    A. Furnish materials in accordance with requirements of the National Fire Protection Association and Washington County Fire Marshal standards.

    B. Product Description: Different types of products by multiple manufacturers are acceptable as required to meet specified system description and performance requirements; provide only one type for each similar application.

    1. Silicone Firestopping Elastomeric Firestopping: Single component silicone elastomeric compound and compatible silicone sealant.

    2. Foam Firestopping Compounds: Single component foam compound.3. Formulated Firestopping Compound of Incombustible Fibers: Formulated compound

    mixed with incombustible non-asbestos fibers.4. Fiber Stuffing and Sealant Firestopping: Composite of ceramic fiber stuffing insulation

    with silicone elastomer for smoke stopping.5. Mechanical Firestopping Device with Fillers: Mechanical device with incombustible

    fillers and silicone elastomer, covered with sheet stainless steel jacket, joined with collars, penetration sealed with flanged stops.

    6. Intumescent Firestopping: Intumescent putty compound which expands on exposure to surface heat gain.

    7. Firestop Pillows: Formed mineral fiber pillows.

    C. Color: As selected from manufacturer’s full range of colors.

    2.5 FIRESTOPPING ACCESSORIES

    A. Primer: Type recommended by firestopping manufacturer for specific substrate surfaces and suitable for required fire ratings.

    B. Dam Material: Permanent:1. Mineral fiberboard.2. Mineral fiber matting.3. Sheet metal.

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 13

    4. Plywood or particle board.5. Alumina silicate fire board.

    C. Installation Accessories: Provide clips, collars, fasteners, temporary stops or dams, and other devices required to position and retain materials in place.

    D. General:1. Furnish UL listed products.2. Select products with rating not less than rating of wall or floor being penetrated.

    E. Non-Rated Surfaces:1. Stamped steel, chrome plated, hinged, split ring escutcheons or floor plates or ceiling

    plates for covering openings in occupied areas where piping is exposed.

    2. For exterior wall openings below grade, furnish mechanical sealing device to continuously fill annular space between piping and cored opening or water-stop type wall sleeve.

    PART 3 EXECUTION

    3.1 EXAMINATION

    A. Verify openings are ready to receive sleeves.

    B. Verify openings are ready to receive firestopping.

    3.2 PREPARATION

    A. Ream pipe and tube ends. Remove burrs.

    B. Remove scale and foreign material, from inside and outside, before assembly.

    C. Prepare piping connections to equipment with flanges or unions.

    D. Unions and flanges for servicing and disconnect are not required in installations using grooved mechanical joint couplings. (The couplings shall serve as disconnect points, if required.)

    E. Do not drill or cut structural members.

    F. Clean substrate surfaces of dirt, dust, grease, oil, loose material, or other matter affecting bond of firestopping material.

    G. Remove incompatible materials affecting bond.

    H. Install damming materials to arrest liquid material leakage.

    3.3 LAYOUT

    A. Coordinate layout and installation of fire protection system with all other buildings, structural, mechanical and electrical work. Locate sprinkler heads symmetrically with respect to ceiling tiles, lighting fixtures, registers, grilles, diffusers, etc. Installer is cautioned that sprinkler mains must be located to prevent conflicts with other work and in

  • 21 05 00 - 14 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    any case, sprinkler Installer shall be responsible for coordination of his work with work of other trades.

    B. System shall include, but not be limited to, hydraulic calculations, resizing and providing all equipment and piping as necessary to meet all requirements of NFPA 13 and 14 and all codes and regulations of authorities having jurisdiction over this work.

    C. Installer shall obtain all flow tests required for system calculations and design.

    D. Provide metal boxes spare sprinkler heads of all types and special sprinkler wrenches as required by NFPA.

    E. Install piping in accordance with NFPA 13 for sprinkler systems.

    F. Install pipe sleeve at piping penetrations through walls and floors. Seal pipe sleeve penetrations to maintain fire resistance equivalent to fire separation.

    G. Slope piping and arrange systems to drain at low points.

    3.4 INSTALLATION

    A. Install piping in accordance with requirements of the National Fire Protection Association and Washington County Fire Marshal standards.

    B. Route piping in orderly manner, plumb and parallel to building structure. Maintain gradient.

    C. Install piping to conserve building space, to not interfere with use of space and other work.

    D. Group piping whenever practical at common elevations.

    E. Install pipe sleeve at piping penetrations through footings, partitions, walls, and floors. Seal pipe and sleeve penetrations to maintain fire resistance equivalent to fire separation.

    F. Install piping to allow for expansion and contraction without stressing pipe, joints, or connected equipment.

    G. General Sprinkler System

    1. Provide a wet pipe sprinkler system as required by local authorities. System components shall include alarm check valve, water gong, siamese connection, shut-off valves, zone valves, main piping, branch piping, fire hose stations, inspector's test, drains, sprinkler heads and all other incidental appurtenances as required.

    2. All areas of the entire building shall be protected by the sprinkler system. A dry pipe sprinkler system and/or dry type heads shall be provided where system may be exposed to potential freezing.

    3. Provide dry pipe sprinkler system for all areas of the building where freezing conditions may occur and as indicated on the contract drawings. Provide hydraulically designed system to NFPA 13 occupancy requirements.

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 15

    H. Pipes and Fittings:

    1. Comply with requirements of NFPA 13 for installation of fire protection piping and valving materials. Install piping products where indicated, in accordance with manufacturer's written instructions and in accordance with recognized industry practices to ensure that piping systems comply with requirements and serve intended purposes.

    2. Install flexible pipe connectors or grooved system manufacturer’s flexible couplings on pipes connected to equipment supported by vibration isolation. Provide line size flexible connectors.

    3. Install flexible connectors or Victaulic, Grinnell flexible couplings at right angles to displacement. Install one end immediately adjacent to isolated equipment and anchor other end. Install in horizontal plane unless indicated otherwise.

    4. Rigidly anchor pipe to building structure. Provide pipe guides to direct movement only along axis of pipe. Erect piping so strain and weight is not on cast connections or apparatus.

    5. Provide support and anchors for controlling expansion and contraction of piping. Provide loops, pipe offsets, and swing joints, or expansion joins where applicable.

    6. Listed corrosion – resistant sprinklers shall be installed in locations where chemicals, moisture, or other corrosive vapors sufficient to cause corrosion of such devices.

    7. Grooved joint piping systems shall be installed in accordance with the manufacturer’s guidelines and recommendations. All grooved couplings, fittings, valves, and specialties shall be the products of a single manufacturer. Grooving tools shall be of the same manufacturer as the grooved components. The gasket style and elastomeric material (grade) shall be verified as suitable for the intended service as specified. Gaskets shall be molded and produced by the grooved system manufacturer. Grooved end shall be clean and free from indentations, projections, and roll marks in the area from pipe end to groove for proper gasket sealing. A factory-trained field representative shall provide on-site training for contractor’s field personnel in the proper use of grooving tools and installation of grooved piping products. Factory-trained representative shall periodically review the product installation. Contractor shall remove and replace any improperly installed products.

    I. Pipe Hangers and Supports:

    1. Install in accordance with NFPA 13.

    2. Install hangers to with minimum 1/2 inch space between finished covering and adjacent work.

    3. Place hangers within 12 inches of each horizontal elbow.

  • 21 05 00 - 16 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    4. Use hangers with 1-1/2 inch minimum vertical adjustment. Design hangers for pipe movement without disengagement of supported pipe.

    5. Support vertical piping at every other floor. Support riser piping independently of connected horizontal piping.

    6. Where installing several pipes in parallel and at same elevation, provide multiple or trapeze hangers.

    7. Install copper plated hangers and supports for copper piping.

    8. Prime coat exposed steel hangers and supports. Hangers and supports located in crawl spaces, pipe shafts, and suspended ceiling spaces are not considered exposed.

    J. Slope piping and arrange systems to drain at low points. Install eccentric reducers to maintain top of pipe level.

    K. Prepare pipe, fittings, supports, and accessories for finish painting. Where pipe support members are welded to structural building framing, scrape, brush clean, and apply one coat of zinc rich primer to welding.

    L. Do not penetrate building structural members unless indicated.

    M. Where more than one piping system material is specified, install compatible system components and joints. Install flanges, union, and couplings at locations requiring servicing.

    N. Die cut threaded joints with full cut standard taper pipe threads with red lead and linseed oil or other non-toxic joint compound applied to male threads only.

    O. Install drain valves at main shut-off valves, low points of piping and apparatus.

    P. Where inserts are omitted, drill through concrete slab from below and install through-bolt with recessed square steel plate and nut recessed into and grouted flush with slab.

    3.5 INSTALLATION - FIRESTOPPING

    A. Install material at fire rated construction perimeters and openings containing penetrating sleeves, piping, ductwork, and other items, requiring firestopping.

    B. Apply primer where recommended by manufacturer for type of firestopping material and substrate involved, and as required for compliance with required fire ratings.

    C. Apply firestopping material in sufficient thickness to achieve required fire and smoke rating,to uniform density and texture.

    D. Place foamed material in layers to ensure homogenous density, filling cavities and spaces. Place sealant to completely seal junctions with adjacent dissimilar materials.

    E. Fire Rated Surface:1. Seal opening at floor, wall, partition, ceiling, and roof as follows:

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 17

    a. Install sleeve through opening and extending beyond minimum of 1 inch on both sides of building element.

    b. Size sleeve allowing minimum of 1 inch void between sleeve and building element.c. Pack void with backing material.d. Seal ends of sleeve with UL listed fire resistive silicone compound to meet fire

    rating of structure penetrated.2. Where cable tray, bus, cable bus, conduit, wireway, or trough, penetrates fire rated

    surface, install firestopping product in accordance with manufacturer's instructions.

    F. Non-Rated Surfaces:1. Seal opening through non-fire rated wall, partition floor, ceiling, and roof opening as

    follows:a. Install sleeve through opening and extending beyond minimum of 1 inch (25 mm)

    on both sides of building element.b. Size sleeve allowing minimum of 1 inch void between sleeve and building element.c. Install type of firestopping material recommended by manufacturer.

    2. Install escutcheons, floor plates, or ceiling plates where conduit, penetrates non-fire rated surfaces in occupied spaces. Occupied spaces include rooms with finished ceilings and where penetration occurs below finished ceiling.

    3. Exterior wall openings below grade: Assemble rubber links of mechanical sealing device to size of piping and tighten in place, in accordance with manufacturer's instructions.

    4. Interior partitions: Seal pipe penetrations at clean rooms, laboratories, hospital spaces, computer rooms, telecommunication rooms, and data rooms. Apply sealant to both sides of penetration to completely fill annular space between sleeve and conduit.

    3.6 TESTS

    A. The sprinkler systems installation shall be hydrostatically tested, inspected and approved, in accordance with NFPA 13 and 14. Test certificate shall be forwarded to Architect as proof of compliance.

    B. Tests shall be performed in accordance with the requirements of local authorities and shall prove the systems to be adequate and satisfactory in every respect. All tests shall be performed in the presence of the local authorities or his representative. Provide written notice to the local authorities 5 working days prior to all testing.

    C. Any deficiencies revealed by these tests shall be corrected and the systems shall be retested until acceptable results are obtained.

    D. Use the NFPA 13, “Standard Contractor’s Material and Test Certificate for Aboveground Piping” and/or the “Standard Contractor’s Material and Test Certificate for Belowground Piping”, which ever is appropriate to this project.

    3.7 BUILDING INFORAMTION MODEL (BIM) COORDINATION DRAWINGS

    A. The contract drawings are diagrammatic and do not indicate every component and duct/piping offset fittings required for a complete installation. Incorporate all necessary and required components and routing modifications to ensure that all systems are coordinated and in compliance with specified ceiling heights wall thinness, building structure, etc.

  • 21 05 00 - 18 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    B. It is the contractor’s responsibility to conduct and manage an adequate and thorough BIM and conduct a clash detection process so that all major interferences between building components have been detected and resolved before fabrication and installation of systems. The contractor shall assemble a composite BIM for each subcontractor’s BIM. Vertical shafts shall also be reviewed to ensure that adequate space has been allocated for all of the vertical mechanical systems and that all of the shafts lie up floor to floor.

    C. All coordination efforts and BIM updates shall be provided without changes to the contract cost and/or schedule. The accuracy of the BIM shall be verified by the contractor and approved, prior to submittal to the Architect for review.

    D. Update BIM based on submittals, RFIs, or Owner directed changes and maintain the BIM based on construction activities. BIMs will be revised throughout construction, based on owner directives, revised contract documents, and As-Built conditions.

    3.8 AS-BUILT DRAWINGS

    A. Provide separate as-built drawings and record documents of all fire protection systems as required hereinbefore in this section.

    3.9 INSTALLATION OF BASIC IDENTIFICATION

    A. Provide identification on all piping mains and branches greater then fifteen feet in length (15’).

    B. Provide fire protection signs on piping in accordance with NFPA 13 and 14 requirements.

    3.10 FIELD QUALITY CONTROL

    A. Division 01 Section: “Quality Requirements”: Requirements for inspecting and testing.

    B. Sprinkler Piping Flushing: Prior to connecting sprinkler risers for flushing, flush water feed mains, lead in connections and control portions of sprinkler piping. After fire sprinkler piping installation has been complete and before piping is placed in service, flush entire sprinkler system, as required to remove foreign substances, under pressure as specified in NFPA 13 and 14. Continue flushing until water is clear and check to ensure that debris has not clogged sprinklers.

    3.11 DOCUMENTATION

    A. The following materials shall be furnished by the contractor at the conclusion of the final acceptance test:

    1. Operating and maintenance instructions of controllers, alarm valves, etc. as required by NFPA 13.

    2. The spare sprinkler heads hereinbefore specified and wrench(s).3. A copy of NFPA 25, “Water-Based Fire Protection Systems.”

  • HCC: CBES COMMON WORK RESULTS FOR FIRE SUPPRESSION 21 05 00 - 19

    3.12 DEMONSTRATION OF FIRE PROTECTION SYSTEMS

    A. Demonstrate equipment, specialties, and accessories. Review operating and maintenance information.

    B. Schedule demonstration with at least seven (7) days’ advance notice.

    3.13 START-UP AND TESTING - FIRE PROTECTION SYSTEMS

    A. Starting Procedures: Follow manufacturer’s written procedures. If no procedures are prescribe manufacturer, proceed as follows:

    1. Verify that specialty valves, trim, fittings, controls, and accessories have been installed correctly operate correctly.

    2. Verify that excess pressure pumps and accessories have been installed correctly and operate correctly.

    3. Verify that air compressors and their accessories have been installed correctly and operate correctly.

    4. Verify that specified tests of piping are complete.5. Check that damaged sprinklers and sprinklers with paint or coating not specified

    have been replaced with new, correct type of sprinklers.6. Check that sprinklers are correct type, have correct finish and temperature

    ratings, and have guards where required for applications.7. Check that potable water supplies have correct type of backflow preventer.8. Drain dry-pipe sprinkler systems. 9. Pressurize and check dry-pipe sprinkler systems air pressure maintenance

    devices, and air compressors. 10. Check that hose valves and fire department connections have threads compatible

    with local fire department equipment and have correct pressure rating.11. Fill wet-pipe sprinkler systems with water.12. Fill wet standpipe systems with water.13. Check for correct type and size hose valves. Check for correct type and size hose

    valves, racks, hoses and nozzles.14. Energize circuits to electrical equipment and devices.15. Start and run air compressors. 16. Adjust operating controls and pressure settings.

    B. Coordinate with fire alarm system tests. Operate systems as required.

    C. Coordinate with fire pump tests. Operate systems as required.

    3.14 CLEANING

    A. Division 01 Section: “Execution and Closeout Requirements”: Final cleaning.

    B. Clean entire system after other construction is complete.

    C. Clean adjacent surfaces of firestopping materials.COMPARABLE PRODUCT SUBMITTAL FORM

  • 21 05 00 - 20 COMMON WORK RESULTS FOR FIRE SUPPRESSION HCC: CBES

    Table of Compliance (Sample)Shop Drawing and Product Data Submittal

    The Contractor shall prepare a Table of Compliance Form similar in format to the sample shown below to facilitate and expedite the Shop Drawing and Product Data Review. Failure to comply with this requirement will be basis for rejecting the Submittal.

    The Table of Compliance Form will list and compare the performance parameters as the submitted equipment to that listed on equipment schedule and specifications as basis of design. All non-compliance items (differences) must be explained in full, indicating their impact, if any, on maintainability, durability, energy use, operating costs, code compliance and environmental considerations.

    (Sample)TABLE OF COMPLIANCE

    EQUIPMENT: _______________________ SPEC. SECTION: _______________________

    BASIS OF DESIGNSAMPLE ITEMS

    DRAWINGS SUBMITTED EXPLANATION

    Flow (Cfm Or Gpm)Ext. Static Press.Head (Ft.)Electrical RequirementsCooling CapacityHeating CapacityDischarge Air Temp.Filter Type & Eff.Equipment Eff. (Eer)Sound DataWeightsEtc.

    Specifications:

    A. Quality assurance compliance (ARI)

    (ASHRAE)(AMCA)(UL)

    B. Specifications: List each and every specification paragraph

    C. Etc.Other:

    END OF SECTION

  • SECTION 21 05 13 - COMMON MOTOR REQUIREMENTS FOR FIRE-SUPPRESSION EQUIPMENT

    HCC:CBES COMMON MOTOR REQUIREMENTS FOR 21 05 13 - 1

    FIRE-SUPPRESSION EQUIPMENT

    PART 1 GENERAL

    1.1 SUMMARY

    A. Section includes:

    1. Single Phase Motors2. Source Quality Control3. Bearing Protection Ring

    B. Related Sections: The following sections contain requirements that relate to this section:

    1. Division 26 Section: “Common Work Results for Electrical”.2. Division 26 Section: “Grounding and Bonding for Electrical Systems”.

    1.2 REFERENCES(Unless otherwise noted, references apply to “latest editions.”)

    A. American Bearing Manufacturers Association:

    1. ABMA 9 - Load Ratings and Fatigue Life for Ball Bearings.

    B. National Electrical Manufacturers Association:

    1. NEMA MG 1 - Motors and Generators.

    C. International Electrical Testing Association:

    1. NETA ATS - Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems.

    1.3 SUBMITTALS

    A. Division 01 Section: “Submittals”: Submittal Procedures.

    B. Product Data: Submit catalog data for each motor furnished loose. Indicate nameplate data, standard compliance, electrical ratings and characteristics, and physical dimensions, weights, mechanical performance data, and support points.

    C. Test Reports: Indicate procedures and results for specified factory and field testing and inspection.

    1.4 QUALIFICATIONS

    A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

    B. Testing Agency: Company member of International Electrical Testing Association and specializing in testing products specified in this section with minimum five (5) years documented experience.

  • 21 05 13 - 2 COMMON MOTOR REQUIREMENTS FOR HCC:CBES FIRE-SUPPRESSION EQUIPMENT

    1.5 DELIVERY, STORAGE, AND HANDLING

    A. Division 01 Section: “Product Requirements”: Product storage and handling requirements.

    B. Lift only with lugs provided. Handle carefully to avoid damage to components, enclosure, and finish.

    C. Protect products from weather and moisture by covering with plastic or canvas and by maintaining heating within enclosure.

    D. For extended outdoor storage, remove motors from equipment and store separately.

    PART 2 PRODUCTS

    2.1 PRODUCT REQUIREMENTS FOR MOTORS FURNISHED WITH EQUIPMENT

    A. Motors 3/4 hp and Larger: Three-phase motor as specified below.

    B. Motors that operate with Variable Frequency Drives to meet the MG 1 Part 31 specifications with insulation that can withstand 1600 V peak voltage and a 1 msec rise time and improved baring lubrication for higher temperature operation

    C. Motors Smaller Than 3/4 hp: Single-phase motor as specified below, except motors less than 250 watts or 1/4 hp may be equipment manufacturer’s standard.

    D. Single Phase Motors:

    1. Permanent split-capacitor type where available, otherwise use split-phase start/capacitor run or capacitor start/capacitor run motor.

    2. Voltage: 115/230 volts, single phase, 60 Hz.

    E. Wiring Terminations: Furnish terminal lugs to match branch circuit conductor quantities, sizes, and materials indicated.

    2.2 SOURCE QUALITY CONTROL

    A. Test motors in accordance with NEMA MG 1, including winding resistance, no-load speed and current, locked rotor current, insulation high-potential test, and mechanical alignment tests.

    2.3 BEARING PROTECTION RING

    A. All motors driving by a variable frequency PWM drive shall include a maintenance free, circumferential, conductive micro fiber shaft grounding ring to discharge shaft currents to ground.

    B. Provide AEGIS SGR Bearing Protection Ring as manufactured by Electro Statis Technology or an acceptable comparable product.

  • HCC:CBES COMMON MOTOR REQUIREMENTS FOR 21 05 13 - 3

    FIRE-SUPPRESSION EQUIPMENT

    PART 3 EXECUTION

    3.1 EXISTING WORK

    A. Disconnect and remove abandoned motors.

    B. Maintain access to existing motors and other installations remaining active and requiring access. Modify installation or provide access panel.

    C. Clean and repair existing motors to remain or are to be reinstalled.

    3.2 INSTALLATION

    A. Install securely on firm foundation. Mount ball bearing motors with shaft in any position.

    B. Install engraved plastic nameplates in accordance with Division 23 Identification.

    C. Ground and bond motors in accordance with Division 26 requirements.

    3.3 FIELD QUALITY CONTROL

    A. Division 01 Section: “Quality Requirements”: Field inspection, testing, adjusting, and balancing.

    B. Inspect and test in accordance with NETA ATS, except Section 4.

    C. Perform inspections and tests listed in NETA ATS, Section 7.15.

    END OF SECTION

  • SECTION 21 13 12 - FIRE SUPPRESSION SPRINKLER SYSTEMS

    HCC: CBES FIRE SUPPRESSION SPRINKLER SYSTEMS 21 13 12 - 1

    PART 1 GENERAL

    1.1 SUMMARY

    A. Section includes:1. Wet Pipe Sprinkler System2. Sprinkler Heads3. System Design, Installation, and Certification4. Sprinkler System Piping Specialties

    B. Related Sections: The following sections contain requirements that relate to this section:1. Division 21 Section: “Common Work Results for Fire Suppression” for Pipe

    materials, fittings, valves and equipment for fire suppression systems.2. Division 21 Section: “Common Motor Requirements for Fire Suppression

    Equipment” for motors and their accessories, normally supplied as part of equipment assemblies.

    3. Division 26 Section: “Common Work Results for Electrical” for requirements of electric connections to equipment specified by this section.

    4. Division 26 Section : Equipment Wiring Connections: Execution requirements for electric connections to equipment specified by this section.

    5. Division 28 Section: “Fire Detection and Alarm” for interface of fire suppression system with fire alarm.

    1.2 REFERENCES(Unless otherwise noted, references included throughout this specification section apply to “latest editions”.)

    A. National Fire Protection Association:1. NFPA 13 - Installation of Sprinkler Systems, current edition.

    1.3 SYSTEM DESCRIPTION

    A. System to provide coverage for entire building.

    B. Provide hydraulically designed fire suppression system to NFPA 13 occupancy requirements.

    C. Interface system with building fire and smoke alarm system.

    D. Provide fire department connections as indicated on drawings.

    1.4 SUBMITTALS

    A. Division 01 Section: “Submittals”: Submittal Procedures.

    B. Shop Drawings: Indicate layout of unfinished and finished ceiling areas indicating sprinkler locations coordinated with ceiling installation. Indicate detailed pipe layout, hangers and supports, sprinklers, components and accessories. Indicate system controls.

  • 21 13 12 - 2 FIRE SUPPRESSION SPRINKLER SYSTEMS HCC: CBES

    C. Product Data: Submit data on sprinklers, valves, and specialties, including manufacturers catalog information. Submit performance ratings, rough-in details, weights, support requirements, and piping connections.

    1. Sprinklers shall be referred to on drawings and shall be specifically identified by the listed manufacturers’ style or series designation. Trade names and abbreviations are not permitted.

    D. Design Data: Submit design calculations; signed and sealed by professional engineer or NICET Level III certified professional, upon written proof of acceptance of NICET Certification by local Authority Having Jurisdiction (AHJ).

    E. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

    1.5 CLOSEOUT SUBMITTALS

    A. Division 01 Section: “Execution Requirements”.

    B. Project Record Documents: Record actual locations of sprinklers and deviations of piping from drawings. Indicate drain and test locations.

    C. Operation and Maintenance Data: Submit components of system, servicing requirements, record drawings, inspection data, replacement part numbers and availability, and location and numbers of service depot.

    1.6 QUALITY ASSURANCE

    A. Perform Work in accordance with requirements of the National Fire Protection Association and Hagerstown County Fire Marshal.

    B. Maintain one copy of each document on site.

    1.7 QUALIFICATIONS

    A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

    B. Installer: Company specializing in performing Work of this section with minimum three years documented experience.

    C. Design system under direct supervision of Professional Engineer or NICET Level III certified professional, upon written proof of acceptance of NICET Certification by local AHJ experienced in design of this Work and licensed at Project location.

    1.8 EXTRA MATERIALS

    A. Division 01 Section: “Execution Requirements”: Spare parts and maintenance products.

    B. Furnish extra sprinklers under provisions of NFPA 13.

    C. Furnish suitable wrenches for each sprinkler type.

  • HCC: CBES FIRE SUPPRESSION SPRINKLER SYSTEMS 21 13 12 - 3

    D. Furnish metal storage cabinet located adjacent to alarm valve.

    PART 2 PRODUCTS

    2.1 SPRINKLER HEADS

    A. Sprinklers shall be glass bulb type, with hex shaped wrench boss integrally cast into the sprinkler body to reduce the risk of damage during installation. (Wrenches shall be provided by the sprinkler manufacturer that directly engage the cast wrench boss.)Basis of Design: Victaulic or TYCO.

    B. Except as noted below, sprinkler heads shall be1/ 2" orifice as manufactured by Victaulic or an approved comparable product by Viking or TYCO. The sprinklers shall be:

    1. Ceiling Mounted: Recessed type Victaulic Model V27, Viking Model M or TYCO Series TY-FRB with white polyester finish or concealed. Provide quick response heads.

    2. Wall Mounted: Victaulic Model V27, Viking Model M or TYCO Series TY-FRB with white polyester finish or concealed. Provide quick response heads.

    3. Unfinished Areas: Victaulic Model V27, Viking Model M or TYCO Series TY-FRB with bronze finish, Standard Upright or Pendent, quick response.

    4. Dry Type Sidewall and Pendent Heads: Victaulic V36 or Tyco Series DS-3, DS-1, DS-C, DS-2 dry type where provided to serve areas of potential freezing.

    C. The temperature rating of the sprinklers shall be 155°F except where varying temperature ratings are required by code or the approving authorities (such as in the Boiler Room).

    D. Provide extended escutcheons in rooms with surface mounted lighting fixtures.

    E. Additional sprinklers shall be furnished as required by NFPA 13. The sprinklers shall be in a spare sprinkler cabinet and include one sprinkler head wrench for each type of sprinkler. A minimum of 1 cabinet shall be provided per floor, at a location to be determined in the field during construction.

    F. Sprinkler guards shall be provided in all rooms where no suspended ceiling is being provided. Sprinkler guards must be listed with the sprinkler to which they are attached.

    G. Flexible Stainless Steel Sprinkler Drop Systems may be used to locate sprinklers as required by final finished ceiling tiles and walls. The drop shall include a UL approved Series AH2 braided hose with a bend radius to 2” to allow for proper installation in confined spaces. Union joints shall be provided for ease of installation. The flexible drop shall attach to the ceiling grid using a one-piece open gate Series AB1 or AB2 bracket. The bracket shall allow installation before the ceiling tile is in place. The braided drop system shall be UL listed and FM Approved for sprinkler services to 175 psi. Basis of Design: Victaulic Vic-Flex or TYCO FASTFLEX Model FB Flexible Braided Hose.

  • 21 13 12 - 4 FIRE SUPPRESSION SPRINKLER SYSTEMS HCC: CBES

    PART 3 EXECUTION

    3.1 INSTALLATION

    A. Install in accordance with NFPA 13, and in accordance with all applicable Codes, Standards and the Authority having jurisdiction requirements.

    B. Locate outside alarm-gong on building wall per NFPA 13, requirements.

    C. Place pipe runs to minimize obstruction to other work.

    D. Install piping in concealed spaces above finished ceilings.

    E. Center sprinklers in two directions in ceiling tile and install piping offsets.

    F. Do not install sprinklers that have been dropped, damaged, or show a visible loss of fluid. Never install sprinklers with cracked bulbs.

    G. Sprinkler bulb protector shall be removed by hand after installation and prior to the system being placed in service. Do not use tools or any other device(s) to remove the protector that could damage the bulb in any way.

    H. Install guards on sprinklers in exposed area installations.

    I. Hydrostatically test entire system.

    J. Require test be witnessed by Fire Marshal, authority having jurisdiction, and Owner's insurance underwriter.

    3.2 INTERFACE WITH OTHER PRODUCTS

    A. Verify signal devices are installed and connected to fire alarm system.

    B. Piping specialties: Contractor shall coordinate with fire alarm system vender for system requirements.

    3.3 CLEANING

    A. Division 01 Section: “Execution Requirements”: Final cleaning.

    B. Flush entire piping system of foreign matter.

    3.4 PROTECTION OF INSTALLED CONSTRUCTION

    A. Division 01 Section: “Execution Requirements”: Protecting installed construction.

    B. Apply masking tape or paper cover to protect concealed sprinklers, cover plates, and sprinkler escutcheons not receiving field paint finish. Remove after painting. Replace painted sprinklers with new.

    END OF SECTION

  • SECTION 21 13 16 - DRY-PIPE SPRINKLER SYSTEMS

    HCC: CBES DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 1

    PART 1 GENERAL

    1.1 SUMMARY

    A. Section includes:

    1. Dry Pipe Sprinkler System Design2. Dry Pipe Valves and Accessories3. Dry Pipe System Air Compressor4. Dry Pipe System Air Receiver5. Dry Pipe System Controls and Installation6. Dry Pipe Certification.

    B. Related Sections: The following sections contain requirements that relate to this section:

    1. Division 21 Section: “Common Work Results for Fire Suppression,” for pipe materials, fittings, valves and equipment for fire suppression systems.

    2. Division 21 Section: “Common Motor Requirements for Fire Suppression Equipment” for motors and their accessories normally supplied as part of equipment assemblies.

    3. Division 21 Section: “Fire Suppression Sprinkler System” for wet and dry type sprinkler system heads and accessories.

    4. Division 21 Section: “Vibration and Seismic Controls for Fire-Suppression Piping and Equipment” Product requirements for vibration isolators for placement by this section.

    5. Division 26 Section: “Equipment Wiring Connections” Execution requirements for electric connections to equipment specified by this section

    6. Division 28 Section: “Fire Detection and Alarm” for interface of fire suppression system with fire alarm.

    1.2 REFERENCES(Unless otherwise noted, references included throughout this specification section apply to “latest editions.”)

    A. National Fire Protection Association:1. NFPA 13 - Installation of Sprinkler Systems.2. NFPA 25 – Standard for the Inspection, Testing and Maintenance of Water-Based Fire

    Protection System.

    1.3 SYSTEM DESCRIPTION

    A. System to provide coverage for building areas noted on drawings.

    B. Provide hydraulically designed system to NFPA 13 occupancy requirements.

    C. Interface system with building fire and smoke alarm system.

    D. Provide fire department connections as indicated on drawings.

  • 21 13 16 - 2 DRY-PIPE SPRINKLER SYSTEMS HCC: CBES

    1.4 SUBMITTALS

    A. Division 01 Section: “Submittal Procedures”: Submittal Procedures.

    B. Shop Drawings: Indicate layout of finished ceiling areas indicating sprinkler locations coordinated with ceiling installation. Indicate detailed pipe layout, hangers and supports, sprinklers, components and accessories. Indicate system controls.

    C. Product Data: Submit data on sprinklers, valves, pumps, compressors and specialties, including manufacturers catalog information. Submit performance ratings, rough-in details, weights, support requirements, and piping connections.

    1. Sprinklers shall be referred to on drawings and shall be specifically identified by the listed manufacturers’ style or series designation. Trade names and abbreviations are not permitted.

    D. Design Data: Submit design calculations.

    E. Manufacturer's Certificate: Certify products meet or exceed specified requirements.

    F. Shop drawings and calculations shall be reviewed by NICET IV.

    1.5 CLOSEOUT SUBMITTALS

    A. Division 01 Section: “Execution Requirements”.

    B. Project Record Documents: Record actual locations of sprinklers and deviations of piping from drawings. Indicate drain and test locations.

    C. Operation and Maintenance Data: Submit components of system, servicing requirements, record drawings, inspection data, replacement part numbers and availability, and location and numbers of service depot.

    1.6 QUALITY ASSURANCE

    A. Perform Work in accordance with NFPA 13 and all applicable Codes, Standards and the Authority having jurisdiction requirements.

    B. Maintain one copy of each document on site.

    1.7 QUALIFICATIONS

    A. Manufacturer: Company specializing in manufacturing products specified in this section with minimum three years documented experience.

    B. Installer: Company specializing in performing Work of this section with minimum three years documented experience.

    C. Design system under direct supervision of Professional Engineer or NICET Level IV certified professional, upon written proof of acceptance of NICET Certification by local AHJ experienced in design of this Work and licensed at Project location.

  • HCC: CBES DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 3

    1.8 EXTRA MATERIALS

    A. Division 01 Section: “Execution Requirements”: Spare parts and maintenance products.

    B. Furnish extra sprinklers under provisions of NFPA 13.

    C. Furnish suitable wrenches for each sprinkler type.

    D. Furnish metal storage cabinet located adjacent to alarm valve.

    E. Furnish install and equip spare sprinkler cabinent in accordance with NFPA 13, and located next to sprinkler system riser. Applicable to pararaphs 1.8: B, C, & D.

    PART 2 PRODUCTS

    2.1 GENERAL

    A. Auxiliary drains shall consist of a 1/2 inch valve with nipple and cap for under 5 gallons capacity of trapped and two 1 inch valves with 2 inch by 12 inch nipple or equivalent for over 5 gallons. Drum Drips Assemblies shall be those manufactured by AGF and sold by Viking supply net model 5200A or as manufactured by Wiliag and sold by Tyco – Model DD-1, or an acceptable comparable product. Tie in drains shall be minimum 1-inch.

    B. Installation, location, and protection of dry pipe sprinkler systems shall be in accordance with NFPA 13. The required continuous air compressor and heater(s) shall be connected to an emergency electrical power source.

    C. Sufficient gate valves and check valves shall be provided so that either pump can be isolated for inspection and service.

    D. An approved dry pipe valve with all the trimmings shall be installed on the system side of the main water valve. Dry pipe valve shall be manufactured by Victaulic Series 768N, Tyco Model DPV-1, Viking G series, or an acceptable comparable product. The valve shall be externally resettable, and all internal components shall be replaceable with valve in the installed position. Required air pressure shall be per the incoming water supply. All equipment shall be located and installed so that it is accessible for inspection, removal and repair and shall be substantially supported.

    E. Quick Opening Devices:

    1. Viking model D2, Tyco Model QRS/ACC-1, Victaulic Series 746-LPA, or VIZOR, Electronic Dry Pipe Valve Accelerator: a. Where rapid valve activation is required due to system volume or water

    transit time to a remote test connection, a quick opening device specifically investigated for use with the dry pipe valve shall be utilized.

    b. This quick opening device shall automatically adjust to both small and slow changes in system pressure but shall trip when there is a rapid and steady drop in pressure.

    c. Upon tripping, the quick opening device shall introduce system air pressure into the intermediate chamber of the dry pipe valve. This

  • 21 13 16 - 4 DRY-PIPE SPRINKLER SYSTEMS HCC: CBES

    pressure shall neutralize the differential pressure holding the dry pipe valve closed and permits it to open.

    d. The quick opening device shall have an internal anti-flood device and a ball float that shall combine to prevent water and water borne debris from entering the more sensitive operating areas of the quick opening device.

    e. The quick opening device shall be UL listed and FM approved.

    F. Air Maintenance Devices:

    1. Viking model D-2, Tyco model AMD-1 Air Maintenance Device Pressure Reducing Type:

    a. Where a dry pipe system is supplied by an automatic air compressor or plant air system, a device used for automatic maintenance of air pressure shall be provided and shall be specifically listed for such service.

    b. Where automatic air is supplied to more than one dry pipe system, each system shall have its own air maintenance device.

    c. In applications where there is a compressed air source, which is controlled at a higher pressure than the desired system pressure, an air maintenance device that is field adjustable shall be utilized.

    d. Air maintenance devices shall be UL listed or FM approved.

    G. Anti-Column

    1. The device will incorporate an internal float that will allow venting of the riser when an accumulation of water is present and automatically seat and close the drain once the water is vented. The device shall be capable of operation with air pressure as low as 7 PSI and listed for water pressure up to 250 PSI. Anti-column device to be Viking model LD-1.

    2.2 DRY PIPE COMPRESSOR SYSTEM

    A. Compressor

    1. Provide an air supply capable of restoring system pressure within 30 minutes. Acceptable air supply arrangement is a tank mounted air compressor with an air maintenance device between the air compressor and the air supply inlet on the system riser. System compressed air supply shall be clean, dry, and oil free. Compressor shall be manufactured by general air products.

    2. Provide air cooled, single-state compressor with heavy balanced cast iron flywheel.

    3. Pressure shall be up to 100 P.S.I.G. intermittent.4. Lubrication shall be splash lubricated from dippers on connecting rods.5. Air filters: pad type shall be built internally into cylinder head and are easily

    removed for cleaning or replacement.6. Bearings shall be heavy-duty bronze journal bearings, extra large for long life.7. Crank shafts shall be heavy-duty, machined and ground with integral

    counterweights.8. Connecting Rods shall be aluminum alloy with extra large bearings.

  • HCC: CBES DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 5

    9. Crankcases shall be cast iron with integral cast mounting feet. There is no gasket joint below oil level line. Units are equipped with duct tight breather valves.

    10. Cylinders shall be iron alloy, precision bored and honed. Castings shall have deep cooling fins and shall be separate from crankcase to permit replacement.

    11. Pistons shall be automotive type with two (2) compression and one (1) oil control ring. Hardened and ground piston pins.

    12. Cylinder heads shall be cast iron with deep cooling fins.13. Valves shall be replaceable disc type with hardened guides on single cylinder and

    high efficiency reed type (three (3) intake and three (3) discharge reeds per cylinder) on 2 & 4 cylinder units.

    14. Oil level dipstick on 2 & 4 cylinder units. Visual on single cylinder unit.Electric Motors.

    15. Provide NEMA type motors rated for continuous duty. Open, drip-proof motors with 1.25 service factor on fractional horsepower and 1.15 service factor on integral horsepower. Motors shall be dual voltage rated.

    2.3 AIR RECEIVERS

    A. Tank mounted unit shall be built to ASME specifications and National Board certified. Equipped with pressure gauge and ASME safety valve.

  • 21 13 16 - 6 DRY-PIPE SPRINKLER SYSTEMS HCC: CBES

    2.4 BASES

    A. Base mounted unit shall be heavy-duty welded steel construction with necessary bolt holes for mounting.

    2.5 BELT GUARD

    A. Provide totally enclosed steel belt guard providing maximum operating safety. Louvered to allow flow of cooling air over compressor pump. Easily unbolted front cover for belt replacement.

    2.6 DRIVE

    A. V-belt drive shall be designed for high load factor. Properly aligned for quiet continuous and efficient service.

    2.7 CHECK VALVE

    A. Units shall be equipped with quiet operating check valve.

    2.8 AFTERCOOLER

    A. Units shall have large diameter copper discharge line to deliver cooler air to air receiver.

    2.9 AIR PRESSURE SWITCH

    A. Units shall be equipped with heavy-duty NEMA 1 adjustable pressure switch. Pressure switch shall be equipped with unloader valve to allow for a loadless start.

    PART 3 EXECUTION

    3.1 INSTALLATION

    A. Install in accordance with NFPA 13, and in accordance with all applicable Codes, Standards and the Authority having jurisdiction requirements.

    B. Install air compressor on vibration isolators.

    C. Install buried shut-off valves in valve box. Install with post indicator.

    3.2 INTERFACE WITH OTHER PRODUCTS

    A. Verify devices are installed and connected to fire alarm system.

    3.3 CLEANING

    A. Division 01 Section: “Execution Requirements”.

    B. Flush entire piping system of foreign matter.

  • HCC: CBES DRY-PIPE SPRINKLER SYSTEMS 21 13 16 - 7

    3.4 PROTECTION OF INSTALLED CONSTRUCTION

    A. Division 01 Section: “Execution Requirements”: Protecting installed construction.

    B. Apply masking tape or paper cover to sprinklers, cover plates, and sprinkler escutcheons not receiving field painted finish. Remove after painting. Replace any painted sprinklers with new sprinklers.

    3.5 SUPERVISION AND TRAINING

    A. A Consulting Services Package for Commissioning the nitrogen generator shall be provided by Nitrogen System Manufacturer. Contact Nitrogen system Manufacturer to schedule commissioning at least 3 weeks in advance. The fire sprinkler contractor shall have Nitrogen System Manufacturer assist in final system commissioning. The fire sprinkler contractor shall confirm that all Nitrogen Generator System connections have been made as specified and as indicated in the manufacturer’s installation instructions.

    END OF SECTION

  • DIVISION 22

    PLUMBING

    BUSHEY FEIGHT MORIN ARCHITECTS INC.

    473 NORTH POTOMAC STREET

    HAGERSTOWN, MARYLAND 21740

    301-733-5600 FAX: 301-733-5612

  • SECTION 22 05 00 - COMMON WORK RESULTS FOR PLUMBING

    HCC:CBES COMMON WORK RESULTS FOR PLUMBING 22 05 00 -1

    PART 1 GENERAL

    1.1 RELATED DOCUMENTS

    A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this and the other sections of Division 22.

    B. Motors shall comply with Division 23 Section - “Common Motor Requirements”.

    C. Variable Frequency Drives shall comply with Division 23 Section - “Variable Frequency Drives”.

    1.2 SUMMARY

    A. Section includes:

    1. General administrative and procedural requirements, as well as the following basic plumbing materials and methods.

    2. Submittals.3. Coordination drawings.4. Record documents.5. Operation and Maintenance manuals.6. Rough-ins.7. Plumbing installations.8. Cutting and patching.9. Concrete equipment base construction requirements.10. Equipment nameplate data requirement.11. Labeling and identifying mechanical systems and equipment is specified in

    Division 22 Section “Identification for Plumbing Piping and Equipment.”12. Non-shrink grout for equipment installations.13. Field-fabricated metal and wood equipment supports.14. Installation requirements common to equipment specification Sections.15. Plumbing demolition.16. Touchup painting and finishing.

    1.3 ACRONYMS

    A. The following list of abbreviations are utilized within the specifications and are provided as a reference:

    ADA - American Disability ActAGA - American Gas AssociationANSI - American National Standards InstituteASHRAE - American Society of Heating, Refrigerating and Air Conditioning

    EngineersASME - American Society of Mechanical EngineersASTM - American Society for Testing and MaterialsAWS - American Welding SocietyAWWA - American Water Works Association

  • 22 05 00 -2 COMMON WORK RESULTS FOR PLUMBING HCC:CBES

    IBC - International Building CodeCS - Commercial StandardCSA - Canadian Standards AssociationIBR - Institute of Boiler and Radiator ManufacturersIEEE - Institute of Electrical and Electronics EngineersIMC - International Mechanical CodeIPC - International Plumbing CodeMOSHA - Maryland Occupational Safety and Health AdministrationMSSP - Manufacturers Standards Society of the Valve and Fittings IndustryNEC - National Electrical CodeNEMA - National Electrical Manufacturers AssociationNFPA - National Fire Protection AssociationOSHA - Occupational Safety and Health AdministrationSMACNA - Sheet Metal and Air Conditioning Contractors National AssociationTEMA - Tubular Exchanger Manufacturers AssociationUL - Underwriters' Laboratories

    1.4 DEFINITIONS

    A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term product includes the terms material, equipment, system, and terms of similar intent.

    1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

    2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

    3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

    B. Substitutions: Changes proposed by Contractor in products, materials, equipment, and methods of construction required by the Contract Documents.

    C. Basis-of-Design Product Specification: Where a specific manufacturer's product is

    named, or a product is accompanied by the words "basis of design," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers.

    D. Manufacturer's Warranty: Preprinted written warranty published by individual manufacturer for a particular product and specifically endorsed by manufacturer to Owner.

    E. Extended Warranty: Written warranty required by or incorporated into the Contract

  • HCC:CBES COMMON WORK RESULTS FOR PLUMBING 22 05 00 -3

    Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Owner.

    1.5 SYSTEM DESCRIPTION

    A. Design Requirements: Contract drawings are generally diagrammatic and do not indicate all offsets, fittings, transitions, access panels and other specialties required.

    1. Furnish and install all items as may be required at no additional cost to fit the work to the conditions encountered.

    2. Arrange piping, equipment and other work generally as shown on the contract drawings, providing proper clearances and access.

    3. Where departures are proposed because of field conditions or other causes, prepare and submit detailed shop drawing submittal for approval in accordance with Submittals specified below.

    4. Subject to the provisions of Division 01, Architect may make reasonable changes in location of equipment piping and ductwork up to the time of rough-in or fabrication.

    1.6 SUBMITTALS

    A. Division 01 Section: “Submittals”: Submittal Procedures.

    B. Shop Drawings and Product Data:

    1. Clearly identify all submittals: a. Indicate intended application, location, etc.b. Each submittal shall indicate the associated specification section, and

    paragraphs. Do not combine product data and shop drawing submittals from different spec sections into a single submittal package, even though they may be the same distributor, vendor or part of a single material order.

    c. Clearly indicate the exact type, model number, size and special features of the proposed item.

    d. Include catalog spec sheets to completely describe proposed equipment.e. Factory order forms only showing the required capacities are not

    acceptable.f. Identify all options furnished to meet specifications.g. If product is within system supplying fixture intended to dispense

    potable water for human consumption, including drinking and cooling, submittals shall indicate that product is “lead free”, containing not more than a weighted average of 0.25% lead with respect to the wetted surfaces.

    h. Solder and flux for soldered joints in potable water piping shall be “lead free”, containing not more than 0.2% lead.

    i. The Architect shall not select equipment ratings and/or options. Submittals not properly marked shall be returned without review.

    C. Product Substitutions: Comply with requirements of Division 01.

  • 22 05 00 -4 COMMON WORK RESULTS FOR PLUMBING HCC:CBES

    D. Comparable Products Submission:

    1. Document each request for a proposed comparable product with supporting data substantiating compliance of proposed product with Basis-of-Design product.

    2. Use the attached “Comparable Product Submittal Form” in addition to the requirements specified herein.

    3. Comparable products will not be reviewed without completion of the attached form.

    E. Coordination Drawings:

    1. Building Information Model (BIM):

    a. Coordination drawings shall be created from 3D BIM model of all Mechanical, Electrical, Fire Protection, and Plumbing systems. Assign an individual to serve as the main point of contact for the BIM related issues. This individual shall have sufficient BIM experience required for the size and complexity of the project and shall have relevant proficiency in the BIM process.

    b. Coordinate construction sequencing and scheduling activities and assure they are integrated with the BIM documents.

    c. All design modifications in the field, RFI Responses, Submittals, and Owner requested changes shall be documented and updated in the BIM documents in a timely manner.

    d. All coordination efforts and BIM updates shall be provided without changes to the contract cost and/or schedule.

    2. Prepare coordination drawings to a scale of ¼”=1’0” or larger, detailing major elements, components, and systems of mechanical equipment and materials in relationship with other systems, installations, and building components.

    3. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are of importance to the efficient flow of the work, including (but not necessarily limited to) the following:

    a. The proposed locations of piping, valving, ductwork, equipment, and materials.

    b. Planned piping layout, including valve and specialty locations and valve stem movement.

    c. Planned duct systems layout, including elbow radii and duct accessories.d. Clearances for installing and maintaining insulation.e. Clearances for serv