vishal structurals wllvishaltanks.com/wp-content/uploads/2020/10/vishal... · 2020. 10. 24. · 42...
TRANSCRIPT
42 YEARS EPC IN OIL AND GAS IFRASTRUCTURE PROJECT
VISHAL STRUCTURALS WLL
INTRODUCTION
• VSWLL is a contractor for engineering, procurement, construction of tankage, pipelines, infrastructure,
heavy structurals, firefighting systems, mechanical projects, electrical & instrumentation, revamping and
re-furbishing projects etc. And manufacture and supply of shop fabricated process equipment on EPC
basis.
• We are an ISO 9001:2015,ISO14001:2015 & ISO 45001:2018 certified engineering company
constructing major tankage, LPG storage spheres, pipelines (cross country & unit) and structural projects,
infrastructure, revamping and refurbishing projects etc. On turn-key basis. We are also supplying shop
fabricated process equipment’s such as pressure vessels, process drums, towers, stacks and columns etc.
For petrochemical industries.
• We are in the EPC business for the past 43 years and have constructed more than 1000 nos. Large
diameter petroleum storage tanks. Pipelines for petroleum / gas and several other
• We have successfully completed 03 nos of fuel storage terminals in Malawi.
• Recently we are doing 8 nos of storage tank at BAPCO.
• Front – end Engineering & Design (feed) and detailed design.
• Full multi- disciplined EPC utility and offsite plants.
• Construction management support services to International project management companies on large
to mega projects.
• Direct construction for utility and offsite plants.
• Integration of Utility and offsite system as well as precommissiong, commissioning and start up
supervision and execution.
• Maintenance and operation s support for facility owners.
• With a dedicated multi- disciplined engineering and design team, we can provide the necessary
expertise to deliver turnkey utilities and offsite facilities from beginning to end.
• Our engineering and design services cover all the disciplines including process, civil, architectural ,
structurals, mechanical, piping , electrical , instrumentation, control system and HVAC.
SERVICES OFFERED
COMMERCIAL REGISTRATION CERTIFICATE AT BAHRAIN
INTEGRATED MANAGEMENT SYSTEM - ISO 9001 : 2015 ISO 14001 ISO 18001
SAFETY IS OUR FIRST PRIORITY: HSE POLICY
ORGANISATION STRUCTURE (PROJECT MANAGEMENT)
GENERAL MANAGER ENGINEERING
GENERAL MANAGER FINANCE
GENERAL MANAGER PROCUREMENT
GENERAL MANAGER PROJECTS
DGM PROJECTS
SR MANAGERS(PROJECTS
MANAGER(Q.A. / Q.C.)
RESIDENT CONSTRUCTION
MANAGERS
INSPECTIONENGINEERS
SITE INCHAGESASSISTANTS
SITEENGINEERS
PLANNING ENGINEERS
SAFETY OFFICERS
SUPERVISORSTECHNICIANS
MANAGERSs(PROCUREMENT)
PURCHASEOFFICER
ASSISTANTS
MANAGERSs(PROCUREMENT)
PURCHASEOFFICER
ASSISTANTS
MANAGING DIRECTOR
DIRECTOR
EXECUTIVE DIRECTOR
VICE PRESIDENT PROJECTS
PROJECT HEAD SERVICES
MANAGER ACCOUNTS
ACCOUNTS TEAM
• M/S MOTT MACDONALD CONSULTANT (I) PVT LTD
• M/S TOYO ENGINEERING INDIA PVT LTD
• M/S UOP
• M/S ENGINEERS INDIA LTD
• M/S JACOBS ENGINEERING (I) PVT LTD
• M/S MECON INDIA LTD
• M/S TRIUNE ENERGY SERVICE PVT LTD
• M/S PROJECT & DEVELOPMENT INDIA LTD
• M/S WORLEY PARSONS INDIA
• M/S BECHTEL
• M/S TATA CONSULTANCY
• M/S SGS
• M/S INDIAN REGISTRAR OF SHIPPING
• M/S BUREAU VERITAS
• M/S LLOYD’S REGISTER
• M/S DET NORSKE VERITAS
SEVERAL PROJECTS CARRIED OUT UNDER THE DESIGN
AND INSPECTION OF RENOWED COMPANY
• M/S INDIAN OIL CORPORATION LTD.
• M/S HINDUSTAN PETROLEUM CORPORATION LTD.
• M/S BHARAT PETROLEUM CORPORATION LTD
• M/S OIL AND NATURAL GAS CORPORATION LTD.
• M/S ONGC – MRPL
• M/S CAIRN ENERGY INDIA PTY LTD.
• M/S RELIANCE INDUSTRIES LTD.
• M/S ESSAR OIL LTD
• M/S PRAXAIR INDIA LTD
• M/S AIR LIQUIDE INDIA LTD.
• M/S KELLOGS INDIA LTD
• M/S ADANI PORT LTD
• M/S IMC LTD
• M/S KESAR ENTERPRISES LTD
• M/S MUMBAI PORT TRUST
• M/S NALCO LTD.
• M/S NATIONAL OIL COMPANY OF MALAWI LTD
➢VSPL TO EXECUTE THE PROJECT.
❑ RESPONSIBLE OFFICES FOR VARIOUS ACTIVITIES
➢ TECHNICAL MATTERS - VSWLL/VSPL ENGINEERING AT BAHRAIN/ INDIA
➢ COMMERCIAL MATTERS - VSWLL/VSPL ENGINEERING AT BAHRAIN/ INDIA
➢ DETAILED ENGINEERING DRAWINGS - VSWLL/VSPL ENGINEERING AT BAHRAIN/ INDIA
➢ PROCUREMENT - VSWLL/VSPL ENGINEERING AT BAHRAIN/ INDIA
➢ EXPEDITION / INSPECTION CORDINATION - VSWLL/ VSPL PROJECT OFFICE
➢ INSPECTION - VSWLL/ VSPL PROJECT OFFICE
➢ PROJECT MANAGEMENT - VSWLL/VSPL ENGINEERING AT BAHRAIN/ INDIA
➢ CONSTRUCTION, PRE- COMM. ETC - VSWLL/VSPL SITE OFFICE
➢ HSE ACTIVITIES - VSWLL/VSPL SITE OFFICE
➢ QUALITY CONTROL - VSWLL/VSPL SITE OFFICE
➢ STATUTORY APPROVAL - VSWLL/VSPL SITE OFFICE
➢ FINANCE CONTROL - VSWLL/VSPL FINANCE DEPT. AT BAHRAIN/ INDIA
➢ DOCUMENT CONTROL - VSWLL/VSPL ENGINEERING AT BAHRAIN/ INDIA
PROJECT MONITORING METHODOLOGY
➢PROJECT MGMT. WITH PRIMAVERA & MICROSOFT
PROJECT IN HOUSE.
➢ SOIL SURVEY AND SOIL INVESTIGATION-
OUTSOURCED
➢ DESIGN OF CIVIL IN HOUSE
➢ DESIGN OF MECHANICAL IN HOUSE
➢ DESIGN OF ELECTRICAL IN HOUSE
➢ DESIGN OF INSTRUMENTATION IN HOUSE
➢ SOFTWARE INVOLVED IN DESIGN :-
▪ DESIGN DONE AS PER ASME, DIN , BS, API , IS
STANDARDS USING, STAAD PRO , PIPENET, SPIDER
AND AUTO -CADD TO MAKE THE DRAWINGS
➢ HAVING MANPOWER RESOURCE:-
▪ CIVIL DESIGN ENGINEERS- 03 NOS
▪ MECHANICAL DESIGN ENGINEERS (PIPELINE)- 12
NOS
▪ MECHANICAL DESIGN ENGINEERS (TANK)- 08 NOS
▪ DESIGN ENGINEERS (ELECTRICAL) – 04 NOS
▪ DESIGN ENGINEERS (INSTRUMENTATION) – 03 NOS
IN HOUSE FACILITIES OF DESIGN AND DRAWING
➢ALL DESIGN VETTED THROUGH:-
▪ IACS –TUV, BV, LRS, ABS, SGS, DNV , GLI,BV, IRS
▪ INSTITUTES- IIT , VJTI, REC OF INDIA
➢ OUR DESIGN CONSULTANT:-
▪ TEBODINE , BAHRAIN
▪ TATA ENGINEERING CONSULTANCY
▪ PE-MECH CONSULTANT PVT. LTD.- NAVI MUMBAI
▪ PROGRESSIVE ENGINEERING- NAVI MUMBAI
WE HAVE A TIEUP WITH NASS INDUSTRIAL SERVICES FULL FLEDGED FABRICATION UNIT AT HIDD , BAHRAIN
EQUIPPED WITH MODERN MACHINERIES INCLUDING HEAVY DUTY PLATE BENDING MACHINES, TIG WELDING
MACHINES, PROFILE CUTTING MACHINE, PLASMA CUTTING MACHINES, E.O.T CRANE ETC. OUR FACTORY ARE
APPROVED BY MOST OF THE LEADING THIRD PARTY INSPECTION AGENCIES INCLUDING M/S LLOYDS REGISTER , M/S
TUV AND M/S BUREAU VERITAS. WE ARE REGULAR SUPPLYING FABRICATED EQUIPMENTS SUCH AS PRESSURE
VESSELS, HEAT EXCHANGERS, STORAGE TANKS, STACKS, COLUMNS, TOWERS, PROCESS DRUMS, ETC. IN STAINLESS
STEEL AND CARBON STEEL MATERIALS FROM OUR SHOP AS PER THE REQUIREMENT OF INTERNATIONAL DESIGN
CODES.
SHOP FACILITIES
➢ NOW A DAYS WE HAVE STARTED AUTOMATIC AGW/SAW WELDING FOR TANK CONSTRUCTION.
➢ HORIZONTAL JOINTS ARE BEING WELD WITH AUTOMATIC GIRTH WELDING PROCESS IS AGW/SAW. BY THIS WE
ARE COMPLETING ALL HORIZONTAL JOINTS IN 50% FASTER THEN MANUAL WELDING AND ALSO WITH 50%
MANPOWER.
➢ SAME PROCESS WE ARE FOLLOWING IN BOTTOM WELDING & ROOF WELDING WITH VERTICAL AUTOMATIC SAW
WELDING MACHINE IN ROTAR BASE.
SITE FACILITIES – DOUBLE SIDED FULLY AUTOMATIC
WELDING MACHINE
AUTOMIZED WELDING OF SEAMS
ONGOING PROJECTS AT A GLANCE
IN KINGDOM OF BAHRAIN
Description Tanks size (OD x Ht)Type of
RoofQTY
Tank WT(in MT)
A/B Crude Oil Tanks TANK 55.770 M x 16.46 M EFR 02 1866.00
1 RHCU Feed Tank 67.36 M x 16.46 M DR 02 2816.00
FED Storage Tank 54.00 M x 17.70 M CR 01 918.00
Description Tanks size (OD x Ht)Type of
RoofQTY
Tank WT(in MT)
CFPP Additive Tank 4.712 M x 7.62 M CR 01 12.00
Sweet Water Jockey Storage Tank
12.90 M x 12.90 M CR 01 54.00
Naphtha/Kero Tank 76.20 M x 19.507 M EFR 01 1730.00
BAPCO –BMP-TTSJV PROJECT FROM NIS
BAPCO – BMP PROJECT , BAHRAIN (STORAGE TANK)
• UNIT-372 -TK2 –TANK NO-372D0279
• 54 MTR DIA X 15.22 MTR HEIGHT
• COLUMN SUPPOTTED FIXED CONE ROOF
• FED STORAGE TANK EMPTY WEIGHT – 912.126 MT
ONGOING PROJECTS AT A GLANCE
IN KINGDOM OF BAHRAIN
ONGOING PROJECTS AT A GLANCE
IN KINGDOM OF BAHRAIN
BAPCO – BMP PROJECT , BAHRAIN
(STORAGE TANK) - COLUMN SUPPORTED CR TANK
• Birdcage and top platform Scaffolding
BAPCO – BMP PROJECT , BAHRAIN
(STORAGE TANK) – DOUBLE DECK EFR TANK
• UNIT-050 –TK 1 –TANK NO-050D1001- 952.252MT
• 55.77 MTR DIA X 17 MTR HEIGHT
ONGOING PROJECTS AT A GLANCE
IN KINGDOM OF BAHRAIN
BAPCO – BMP PROJECT , BAHRAIN
(STORAGE TANK) - CONSTUCTION OF DOUBLE DECK
ONGOING PROJECTS AT A GLANCE
IN KINGDOM OF BAHRAIN
Tank Repair and Revamp in KSA Khafji Project
ONGOING PROJECTS AT A GLANCE
IN KINGDOM OF SAUDI ARABIA
From: Workflow Mailer - EBSPRD <[email protected]>To: Kishore Krishnamoorthy <[email protected]>Sent: Thursday, February 27, 2020, 05:51:34 PM GMT+5:30
Subject: FYI: BAPCO Supplier Collaboration Network: Registration Submitted
To Kishore
KrishnamoorthySent 27-FEB-20
12:19:57ID 7564158
Thank you for submitting your company details and expressing interest in developing a business
relationship with Bapco.
Your company is now included on potential bidders list and will be subject to a full Qualification audit
before any potential future contract could be issued.
Please be advised that Bapco requirements for goods and services are advertised periodically
through Public Prequalifications and/or Public Tenders which are published on the Bahrain Tender
Board website at http://www.tenderboard.gov.bh/.
Non-approved vendors are welcome to participate in these public advertisements. Vendors that
successfully meet all the Public Prequalification requirements and/or is the successful bidder of a
Public Tender will be included in Bapco's Approved Vendor List.
BAPCO VENDOR REGISTRATIONIN KINGDOM OF BAHRAIN
BAPC VENDOR REGISTRATION IN KUWAIT
KUWAIT OIL COMPANY
PROJECT EXECUTION EXCELLENCE
ACHIEVING BEST CONTRACTOR AWARD – RSPL LTD
PROJECT EXECUTION EXCELLENCE
SAFETY ACHIEVEMENTS- SAFE MAN HOURS
PROJECT EXECUTION EXCELLENCE
SAFETY ACHIEVEMENTS FOR CONSTRUCTION
PROJECT EXECUTION EXCELLENCE
SAFETY APPRECIATION
PROJECT EXECUTION EXCELLENCE
SAFETY INSTRUCTIONS GIVEN PRIOR TO START OF
PERFORMING JOB.
PROJECT EXECUTION EXCELLENCE
Note- Safety induction done by safety managers
SAFETY AWARD AT BAPCO PROJECT
PROJECT EXECUTION EXCELLENCE
➢ RESPONSIBILITIES OF STAFF AND LABOUR AT CONSTRUCTIONS SITE.
➢ THE HSE ACTIVITIES ARE EXECUTED BY A DEDICATED HSE TEAM CONSISTING OF HSE MANAGER AND
SUPERVISORS UNDER THE GUIDANCE OF PROJECT MANAGER.
➢ FOR EACH ACTIVITY, THERE WILL BE A WRITTEN PROCEDURE.
➢ THE HSE TEAM SHALL FOLLOW THE WRITTEN HSE PROCEDURES, REPORTING SYSTEM ETC.
➢ THE HSE TEAM SHALL CONDUCT REGULAR TOOL BOX MEETINGS, SAFETY DRILL, SAFETY AWARENESS
PROGRAMME ETC.
➢ NO WORK SHALL BE ALLOWED TO BE CARRIED OUT WITHOUT PROPER PERMIT.
➢ HSE TEAM WILL ENSURE THAT THE WORKERS, STAFF ETC WEARING PROPER P.P.E AND OTHER SAFETY
HARNESS (AS REQUIRED) AT THE WORK SITE.
➢ HSE TEAM WILL ENSURE THAT FIRST- AID KITS AND OTHER MEDICAL AIDS ARE ALWAYS AVAILABLE AT SITE.
➢ HSE TEAM SHALL ENSURE THAT ALL THE EQUIPMENT’S, MACHINERIES, LIFTING TOOLS AND TACKLES ETC
ARE HAVING PROPER CERTIFICATES AND COLOUR CODES AS REQUIRED.
➢ HOUSEKEEPING FOR SITE .
➢ WHAT INJURIES AND ILLNESS MUST BE REPORTED.
➢ ORGANISING THE SAFE USE OF DANGEROUS GOODS AND HAZARDOUS CHEMICALS.
➢ CONTROLLING HAZARDS SUCH AS DUST, NOISE AND FUMES.
➢ PROVIDING HYGIENE FACILITIES SUCH AS TOILETS AND CHANGE ROOMS.
➢ HYGIENIC WORK PRACTICES.
➢ FIRE FRIGHTENING EQUIPMENT AT SITE FOR FIRE SAFETY.
➢ PROVIDING INSTRUCTION, TRAINING AND SUPERVISION TO SUPPORTED EMPLOYEES.
➢ MONITORING YOUR WORK AREA AND EMPLOYEE HEALTH.
SAFETY PARAMETER FOR CONSTRUCTION SITE
PROJECT EXECUTION EXCELLENCE
➢ MAINTAINING INFORMATION AND RECORDS ON HEALTH AND SAFETY.
➢ SUPPORTING AN INJURED SUPPORTED EMPLOYEE’S RETURN TO WORK.
➢ DEMONSTRATING SAFE WORK PRACTICES.
➢ HAZARD IDENTIFICATION AND EMERGENCIES.
➢ EMERGENCY ROOM FACILITIES/CLINICS.
➢ EMERGENCY PREPAREDNESS TRAINING.
➢ HEALTH CARE FACILITY POLICY AND PROCEDURES.
➢ CONSTRUCTION SAFETY AGREEMENT.
➢ HEAT ILLNESS PREVENTION FOR EG. PROVISION OF WATER, ACCESS TO SHADE, WRITTEN PROCEDURES ETC.
➢ GOOD QUALITY DB WITH ELCB WILL BE USED.
➢ HSE TEAM WILL ENSURE THAT FIRST- AID KITS AND OTHER MEDICAL AIDS ARE ALWAYS AVAILABLE AT SITE.
➢ ISSUE ENVIRONMENTAL GUIDELINES FOR CONSTRUCTION SITES
➢ LAND DISTURBANCE
➢ NOISE AND VIBRATION
➢ WASTE MINIMISATION
➢ CONTAMINATED MATERIAL AND WASTES
➢ INSPECTIONS, MONITORING AND AUDITS
SAFETY PARAMETER FOR CONSTRUCTION SITE
PROJECT EXECUTION EXCELLENCE
SAFETY EQUIPMENTS
1. SAFETY HELMETS
2. SAFETY SHOES
3. SAFETY GOGGLES
4. SAFETY BELTS
5. SAFETY GLOVES
6. SAFETY JACKETS
7. BOILER SUITS
8. SAFETY BARRICADING TAP
9. SAFETY MASS
10. SAFETY EAR PLUG
11. PERSONAL GAS MONITORING DEVICE
SAFETY EQUIPMENTS DURING SITE WORK
PROJECT EXECUTION EXCELLENCE
SAFETY PROCEDURES
1. SAFETY SIGN AND SYMBOLS.
2. SAFETY POSTERS TO PREVENT FROM ACCIDENT.
3. SAFETY INDUCTION TRAININGS.
4. SAFETY SLOGANS .
5. REGULAR MEDICAL CHECKUP OF STAFF AND LABOURS
6. HEIGHT PASS DURING WORKING AT HEIGHT.
7. FIIRE FIGHTING EQUIPMENT
8. PROPER HOUSEKEEPING AT SITE
SAFETY PRECAUTION FOLLOWED AT SITE
PROJECT EXECUTION EXCELLENCE
QUALITY CONTROL
QUALITY ASSURANCE OF MATERIAL
➢ ONLY APPROVED AND REPUTED VENDORS WILL BE SELECTED BY CLIENT.
➢ ALL MATERIAL TO BE USED IN THE PROJECT AS PER STANDARD OR EQUIVALENT STANDARDS.
➢ FOLLOWING DOCUMENTS WILL BE SUBMITTED.
• TC (TEST CERTIFICATE)
• FIELD QUALITY PLAN (FQP)
MATERIAL QUALITY PLAN WILL BE SUBMITTED FOR BROUGHT OUT ITEMS FOR APPROVALS AND
ALL THE MATERIALS WILL BE SUPPLIED AS PER THE SAME.
QUALITY ASSURANCE INSTALLATION-GENERAL
➢ QUALITY BEGINS AT SITE WITH DAY ONE WHILE MATERIALS ARE START RECEIVING AT SITE .
➢ AFTER RECEIPT OF MATERIAL, OUR MECHANICAL ENGINEER /QA/QC ENGINEER PHYSICALLY
CHECKED THE MATERIAL BEFORE STACKING THE SAME AT STORE YARD/STORE ROOM.
➢ IF ANY DEFECTS FOUND THEY INSTANTLY REPORT TO HO AND WRITE A NOTE ON LR COPY.
➢ OUR QA/QC ENGINEER ALSO ENSURE THE PROPER STACKING OF OUTDOOR/INDOOR STORED
MATERIAL TO AVOID THE SURFACE DEFORMATION DUE TO CORROSION, DAMAGE DUE TO PUTTING
WEIGHT IMPROPERLY ETC.
PROJECT EXECUTION EXCELLENCE
QUALITY CONTROL
➢ ONCE OUR ENGINEER SATISFIED WITH QUALITY OF MATERIAL RECEIVED AT SITE
THEREAFTER THEY CALL CUSTOMER ENGINEER AND MAKE THE INWARD INSPECTION
MATERIAL REPORT FOR FURTHER RECORD.
➢ BEFORE STARTS THE WORK SURFACE OF PIPES AND OTHER MATERIAL IS CLEAN PROPERLY
➢ MATERIAL CHECKED CONSTANTLY BY QA/QC BEFORE COMMENCE THE WELDING.
➢ WHEN GROOVE FOUND PROPERLY THEN THEY ALLOW TO WELDING TO ONLY QUALIFIED
WELDER.
➢ WELDER QUALIFICATION WILL BE DONE AS PER APPROVED WPS/PQR.
➢ THEY ALSO DO THE 10% RADIOGRAPHY RANDOMLY TO ENSURE PROPER WELDING QUALITY
BY WELDER.
➢ AFTER WELDING, JOINT WILL BE PROPERLY CLEANED FOR VISUAL CHECKING OF CLIENT
AND NDT TEST.
➢ AFTER RECEIPT OF QUALITY CLEARANCE FROM CUSTOMER, MATERIAL WILL BE TESTED.
➢ THE ABOVE PROCEDURE IS ALSO DOCUMENTED BY OUR QA/QC ENGINEER FOR FUTURE
REFERENCE
PROJECT EXECUTION EXCELLENCE
SEVERAL HEAVY EQUIPMENT ERECTION
COLUMN ERECTION & COMMISSIONING
PROJECT EXECUTION EXCELLENCE
LAND ACQUISITION AND SITE SURVEY FOR THE PROJECT
PROJECT EXECUTION EXCELLENCE
SOIL INVESTIGATION
SOIL TESTING DONE AT NABL APPROVED LABORATORY
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF SITE OFFICE AND TCF
SITE OFFICE CUM STORE
FABRICATION YARD
ROAD
SECURITY AND REST ROOM
PROJECT EXECUTION EXCELLENCE
PROJECT CIVIL WORK CONSTRUCTION
BOUNDARY WALL
ADMIN BUILDING
PIPE RACK
TANK
FOUNDATION RING WALL
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF CIVIL BLDG. AND SHEDS
CONTROL ROOM
DG SHED ROOM
MAIN PUMP HOUSE
TLF SHED
PROJECT EXECUTION EXCELLENCE
COMPLETION OF CIVIL BLDG. AND SHEDS
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF ROAD WORKS & BOUNDARY WALL
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF MECHANICAL WORKS
TANK ERECTION
WORK
PIPELINE
WORK
STRUCTURAL
WORK
PLANT PIPING
WORK
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF VARIOUS TANK FOUNDATIONS
RCC RING WALL
FOUNDATIONS
PILE
FOUNDATIONS
APRON TYPE
FOUNDATIONS
DOUBLE WALL TANK
FOUNDATION
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF TANK – BOTTOM PLATE LAYING
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF TANKAGE BY -
(JACKING AND CONVENTIONAL METHOD)
JACKING
METHOD
JACKING
METHOD
CONVENTIONAL
METHOD
CONSTRUCTION OF CRYOGENIC TANK
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF PIPING WORKS
PROJECT EXECUTION EXCELLENCE
CONSTRUCTION OF CROSS COUNTRY PIPELINE & JETTY
LOADING AND UNLOADING FACILITIES
PROJECT EXECUTION EXCELLENCE
ERECTION OF EQUIPMENTS AND PIPES SPOOL
PROJECT EXECUTION EXCELLENCE
INSTALLATION OF ELECTRICAL FACILITIES
PROJECT EXECUTION EXCELLENCE
INSTALLATION OF INSTRUMENTATION FACILITIES
PUMP HOUSETANK
AREA
CONTROL
ROOMPIPELINE
PROJECT EXECUTION EXCELLENCE
TANKS AND PIPELINE REPAIRING AND MODIFICATION
TANK ANNULAR
PLATE
TANK SHELL
PLATE
REPLACING EXISTING
PIPELINE
REPARING OF
PIPELINE
PROJECT EXECUTION EXCELLENCE
TANK CALIBRATION
PROJECT EXECUTION EXCELLENCETANK CALIBRATION
COMMISSIONING OF PLANT
PROJECT EXECUTION EXCELLENCE
ONGOING PROJECTS AT A GLANCE AT INDIA
HPCL CALICO- MAHUL (PIPING WORKS)
PROJECT EXECUTION EXCELLENCE
STORAGE TANK FOUNDATION WORK AT HPCL HISSAR
HSD TANK-
1
HSD TANK-3
HSD TANK-2
U/G
TANK
PROJECT EXECUTION EXCELLENCE
TANK FOUNDATION & FABICATION WORK AT IOCL DUMAD
PROJECT EXECUTION EXCELLENCE
REPAIRS/ REPLACEMENT OF DOLPHIN GRAVITY FENDER LINKAGE
ASSEMBLIES OF DOLPHIN NO. 01 & 2 AT JETTY NO.1 MARINE OIL
TERMINAL, JAWAHAR DWEEP
PROJECT EXECUTION EXCELLENCEMUMBAI PORT TRUST
RSPL LTD. – DWARKA, GUJARAT
FIELD ERECTED TANKS AND VESSEL PACKAGE
TANK FOUNDATION, TANK AND SILO, BUNKER , HOPPER
TANKS AND BLDG. WORK
PROJECT EXECUTION EXCELLENCE
RSPL –DWARKA
PROJECT EXECUTION EXCELLENCE
STORAGE TANKS , SILO & BUNKER
RSPL –DWARKA
(STORAGE TANKS , SILO & BUNKER)
PROJECT EXECUTION EXCELLENCE
Bahrain Office & Workshop:
13G, Rd:401, Block 604,Sitra Industrial Area,Kingdom of Bahrain
M. +973-36183156Tel +973-77082839Whatsup +91-9769651307
India Group-Headquarter
703, Krishna-Govinda Towers,Plot No: 22-26, Sector: 24, Vashi,(Opp. Sanpada Railway Station)Navi Mumbai – 400705, India.
Ph: +9122-27842244+9122 2784 2245+912227842246
Fax: +9122-27845566www.vishaltanks.comwww.vishalstructurals.ininfo@vishalstructurals.in
CONTACT US