varun plastics - an operations case study

Upload: sailesh-nallapothu

Post on 10-Apr-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 Varun Plastics - An Operations Case Study

    1/20

    Prepared By

    Group I2

  • 8/8/2019 Varun Plastics - An Operations Case Study

    2/20

  • 8/8/2019 Varun Plastics - An Operations Case Study

    3/20

  • 8/8/2019 Varun Plastics - An Operations Case Study

    4/20

    # Varun plastics make PVC pipes of nine different sizes by

    following same manufacturing process and facility.

    # But the pipes which have most demand and hence

    produced more are pipes having diameter 1 inch, 2 inchand 2.5 inches.

    # Same machinery, facility and input is used for

    manufacturing pipes of different sizes, they only change

    the die size for pipes of different diameters.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    5/20

    ) The plant covers an area of 120 ft by 45 ft and is divided into many

    sections. About one third of the space is meant for machines and two

    third is meant for storage and other purposes.5

  • 8/8/2019 Varun Plastics - An Operations Case Study

    6/20

  • 8/8/2019 Varun Plastics - An Operations Case Study

    7/20

    ) Administrative Office :

    Forecasting, scheduling of machines, ordering and procurement of rawmaterials and delivery to the customers.

    ) Stabilizer Unit :

    Its basically a huge mixing

    machine.

    Raw materials (PVC rasin andstablizer) in the form ofpowder are poured ration of4:1.

    They are mixed for 10-15minutes and the resultantmaterial is used as the rawmaterial for the extrusionprocess.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    8/20

    ) Pipe Extrusion Machine :

    The mixture is grounded into the

    extrusion machine and resultant pasteis molded into pipes under very high

    temperature.

    The hot pipes are then passed throughthe two coolers to reduce itstemperature in stages, so that it gets

    hardened and set.

    When the hard pipes touch the end part

    of the machine, it gets diced offautomatically (using a switch and saw)

    thus regulating the length of all the

    pipes at a uniform level.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    9/20

    ) Coupling Section :

    The finished pipes are heated at the openings to make it soft and then are forced

    on the die to make the edges bell shaped.

    This is in accordance with the requirements of the dealers and customers, for

    the various usage purposes.

    ) Weighing Machine : Each pipe is weighed to ensure the quality and meet the specifications of

    customer.

    ) Cutting area :

    Used to cut some of the pipes into smaller pieces to be used as hinges and

    joints.

    ) Finished Goods Stock :

    Area within and outside the manufacturing factory. No fear of rusting.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    10/20

    Molding Cooling

  • 8/8/2019 Varun Plastics - An Operations Case Study

    11/20

    ) Generator Unit : kept in an isolated sound proof room so that the noise generated doesnt

    affect the regular production process.

    A 125 kw diesel generator is used for alternate power supply in the plant.

    Using power from generator costs 1.5 times the normal electricity chargesand is usually used for 150-250 hrs per month.

    ) Quality testing lab :

    Quality testing lab consists of various equipments for testing the pipes ondifferent parameters.

    One pipe from each lot (once in an hour) is selected randomly to test onall the parameters specified under government standards.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    12/20

    Quality Testing Lab Finished Good inventory

  • 8/8/2019 Varun Plastics - An Operations Case Study

    13/20

    X The high quality product at competitive price and good relationship

    with suppliers are the reason of success of Varun plastic in this highlyfragmented and fiercely competitive market.

    X According to the owner of Varun plastics the total market size of PVCpipes in Karnataka is 5000 tons per week.

    X This is highly fragmented market dominated by many players. Earlier

    there were 12 competitors but now only eight have remained.

    X The sales of Varun plastic per year hover around 500-550 metric ton.

    The break even production is around 400 metric ton.

    X Sales are around 3 crores and profit margin around 2-3 % each yeargiving PAT approximately 9 lakhs.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    14/20

    Forecasting :

    The sales data from the past year is used to do the sales forecasting.

    They have maintained the data for sales of last ten years.

    Also based on the past sales data, demand from the suppliers and some

    personal experience is used to determine which kind of pipes will be in

    more demand in coming year.

    Those kinds of pipe are produced in abundance. The demand is not uniform throughout the year.

    The 70 % of the demand comes in four months from December to Marcheach year.

    They use the lean period to manufacture and stock the products so asto meet the demand of peak period.

    During peak season they work for 7 days a week , but in lean season

    work 6 days a week.

    Since PVC pipes are rust free, they are stored in open area throughout

    the year.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    15/20

  • 8/8/2019 Varun Plastics - An Operations Case Study

    16/20

    Highly quality conscious : ISO 9001:2000 certification.

    Lab test within the plant :Cost of quality .

    The total cost of the lab is around 3.5 lakhs.

    Quality check within half an hour whenever new production starts.

    Regular check every one hour.

    If any product fails the quality test, the entire batch of that productis discarded.

    On an average 5-6 % of total production is discarded each year. Thisdiscarded material is not reused but sold to others on 15-16% oforiginal rate.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    17/20

    Maintenance :

    Every year during month, of July plant is closed for three weeks formaintainace work.

    All equipments are dismantled and each part is looked for any wearand tear and then appropriately repaired or replaced. This is done to

    avoid any breakdown during production periods.

    All electric wiring and other building infrastructure is also checked

    thoroughly.

    All repair work is done by in-house workers.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    18/20

  • 8/8/2019 Varun Plastics - An Operations Case Study

    19/20

    The problem area is the stabilizer.

    Reason for problems is the exact composition of stabilizer is notfixed.

    It depends upon manufacturer to manufacture.

    Earlier Varun Plastics used to manufacture in house stabilizer by

    purchasing the different components of stabilizer and then

    mixing them.

    But now they have buy is from outside vendor.

    This has improved the quality and decreased the failure rate but

    the products still fail quality tests.

  • 8/8/2019 Varun Plastics - An Operations Case Study

    20/20

    THANK YOU