uttarakhand electricity regulatory commission dated... · uttarakhand electricity regulatory...
TRANSCRIPT
Page 1 of 8
Before
UTTARAKHAND ELECTRICITY REGULATORY COMMISSION
In the matter of:
Application seeking approval of UERC on the Draft Power Purchase Agreement between
Uttarakhand Power Corporation Ltd. & M/s Sravanthi Energy Pvt. Ltd.
In the matter of:
Uttarakhand Power Corporation Ltd. … Applicant
AND
In the matter of:
M/s Sravanthi Energy Pvt. Ltd. ... Respondent
CORAM
Shri Subhash Kumar Chairman
Shri C.S. Sharma Member
Shri K.P. Singh Member
Date of Hearing: July 30, 2015
Date of Order: July 30, 2015
This Order relates to the Petition filed by Uttarakhand Power Corporation Ltd. (hereinafter
referred to as “UPCL” or “Licensee”) seeking approval of the draft PPA it proposes to execute with
M/s Sravanthi Energy Pvt. Ltd. (hereinafter referred to as “M/s SEPL” or “Generator”) for purchase
of power of 208 MW capacity from generator’s 450 MW gas based power generating station.
The written submissions made by the Petitioner and the Respondent alongwith the
submissions made during the hearing and the Commission’s views & decisions on the same are
discussed in the following paragraphs.
1. Petitioner’s Submissions
1.1 UPCL had filed the Petition dated 13.07.2015 under Section 86(1)(b) of the Electricity Act,
Page 2 of 8
2003 and clauses 5.1, 5.2 & 5.4 of the license conditions of the Distribution and Retail
Supply license dated 20.06.2003 issued by the Commission seeking approval of the draft
PPA it proposes to execute with M/s Sravanthi Energy Pvt. Ltd.
1.2 UPCL submitted that it intends to execute a PPA for procurement of 208 MW power from
the 450 MW gas based power generating plant of M/s SEPL, situated at Kashipur, Distt-
Udham Singh Nagar in the State of Uttarakhand. The validity of PPA is 2 years.
1.3 UPCL had also submitted that Ministry of Power had issued a Scheme for utilization of gas
based power generation capacity both stranded and partially utilised vide its Office
Memorandum No. 4/2/2015-T.H.01 dated 27.03.2015 for partial allocation of gas with
subsidy support to these power projects.
1.4 The Petitioner further submitted that Government of Uttarakhand vide Order no. 456 (2)/
1/2015-04 (03)/160/2010 dated 28.04.2015 had directed it to purchase power from gas
based projects located at Kashipur, Distt-Udham Singh Nagar.
1.5 During the hearing, the Commission asked UPCL whether the Tariff referred to in the PPA
was to be determined under section 62 or adoption of tariff under section 63 of the
Electricity Act, 2003 is proposed. In reply, UPCL submitted that the tariff is to be
determined by the Commission under section 62 of the Act.
1.6 Further, the Commission also enquired from UPCL about the shortfall in availability of
power and also as to whether power was available at a tariff lower than the target price
referred to in the Petition for procurement of power from M/s SEPL. UPCL submitted that
power was available at tariffs lower than that proposed by M/s SEPL. UPCL also informed
that there was a shortage of power by around 300 MW. The Commission also enquired
whether any process was undertaken.
2. Respondent’s Submissions
2.1 The Respondent vide its written submissions and also during the hearing elaborated the
details of the Scheme dated 27.03.2015 issued by MoP.
2.2 M/s SEPL submitted that the tariff under the Petition submitted by UPCL should be
considered under Section 63 of the Electricity Act, 2003.
2.3 The Respondent further submitted that pursuant to the above mentioned Central Govt.
Scheme, 2015 and in accordance with GoU’s Order dated 456(2)/1/2014-04(03)/160/2010
Page 3 of 8
dated 28.04.2015, UPCL was authorized to execute the draft PPA for procuring 208 MW
power from its generating station.
2.4 The Respondent also submitted that GoU’s approval reflects and adopts the Central Govt.
Scheme, 2015 as a matter of policy involving public interest and tantamounts to “directions
in the matters of policy involving public interest” issued by the State Govt. and, in
accordance with Section 108 of Electricity Act, 2003 the Commission “shall be guided by
the same in discharging its functions”.
2.5 M/s SEPL submitted that the above mentioned Scheme of Central Govt. falls within the
parameters of Section 63 of the Act in respect of tariff at which each stranded gas based
power plant would be able to generate and sell electricity as the same is determined
through a transparent process of bidding in accordance with the guidelines issued by the
Central Govt.
3. Commission’s Views & Decisions
3.1 A PPA is a legal document incorporating operational, technical & commercial provisions to
be complied in accordance with the relevant rules & regulations. Section 86(1)(b) of the
Electricity Act, 2003 stipulates that one of the function of the Commission is to regulate
electricity purchase and procurement process of distribution licensees including the price
at which electricity shall be procured from the generating companies or licensees or from
other sources through agreements for purchase of power for distribution and supply
within the State.
3.2 Further, the Distribution and Retail Supply Licence issued by the Commission lays down
certain conditions of license, which amongst others provides the following:
“5.1 The Licensee shall be entitled to:
(a) …
(b) Purchase, import or otherwise acquire electricity from any generating company or
any other person under Power Purchase Agreements or procurement process approved
by the Commission;
…”
(Emphasis added)
3.3 Regulation 39(3) of UERC (Conduct of Business) Regulations, 2014 specifies as under:
“The distribution licensee shall apply to the Commission for approval of the draft Power
Page 4 of 8
Purchase agreement that it proposes to enter into with the supplier. The Commission may pass
orders:
(a) Approving the agreement; or
(b) Approving the agreement with modifications proposed to the terms of the agreement; or
(c) Rejecting the agreement.”
The above mentioned provisions empower the Commission to approve the PPA
proposed by the distribution licensee. However, the Commission is not bound to do so if
the provisions stipulated in PPA are not in accordance with the prevalent laws.
3.4 The Commission observed that the draft PPA submitted by UPCL does not clearly specify
the tariff at which power would be sold from the Respondent’s plant to UPCL. It provided
for both determination of tariff by this Commission in respect of power to be procured by
the licensee from M/s SEPL gas based generating and also for the tariff to be adopted
based on bidding process. Relevant extracts of the PPA are reproduced hereunder:
“2.1 UPCL shall accept and purchase 208 MW power made available to UPCL system from
Generating Company as per the rate to be determined by Hon’ble UERC.”
“2.2 UPCL shall accept and purchase 208 MW power made available to UPCL system from
Generating Company as per the rate to be determined by Hon’ble UERC/appropriate
commission.”
…..
“2.6 In case, Ms/ Sravanthi Energy Pvt. Ltd. is successful in e-bid RLNG organized by
Government of India, the Target Price mandated for the Target PLF shall be applicable to the
UPCL subject to maximum ceiling of Rs. 5.50/kWh. The PSDF support which will be
provided by GoI to UPCL shall be passed on to M/s Sravanthi Energy Pvt. Ltd. to support
the target price.”
3.5 It is apparent that the above mentioned clauses of PPA are ambiguous and also in conflict
with each other. While Clause 2.1 & 2.2 provide for determination of tariff by the
Commission, clause 2.6 stipulates tariff equivalent to the target price mandated for Target
PLF in accordance with the Scheme promulgated by GoI, subject to the ceiling of Rs.
5.50/Unit.
3.6 UPCL’s submission that the tariff is to be determined by the Commission implies that the
tariff Petition has to be filed under Section 62 of the Electricity Act, 2003. As opposed to this
submission made by the Respondent is that the target price be considered under Section 63
Page 5 of 8
of the Act since it was an outcome of the transparent bidding process as required under the
above mentioned Section of the Act. The contention of UPCL as well as the Respondent
have contradiction and does not hold any ground. For determination of Tariff under
Section 62 of the Act, the Commission has to be guided by the Tariff Regulations framed
under the Act, which are for generators selling power to UPCL for long term and not for
short term or medium term procurement of power.
3.7 The following are the objectives of the guidelines for Determination of Tariff by Bidding
Process for Procurement of Power by Distribution Licensees issued by GoI on 19.01.2005
under Section 63 of the Act:
1. Promote competitive procurement of electricity by distribution licensees;
2. Facilitate transparency and fairness in procurement processes;
3. Facilitate reduction of information asymmetries for various bidders;
4. Protect consumer interests by facilitating competitive conditions in procurement of
electricity;
5. Enhance standardization and reduce ambiguity and hence time for materialization of
projects;
6. Provide flexibility to suppliers on internal operations while ensuring certainty on
availability of power and tariffs for buyers.
Thus, the contention of the Respondent that the tariff be adopted under Section 63
of the Act cannot be sustained as no bidding in accordance with the bidding guidelines as
required under Section 63 was carried out by the distribution licensee which was also
affirmed by UPCL. What transpired was a limited reverse bidding amongst similarly
situated plants operating on gas. This by no stretch of imagination can be termed as
competitive bidding for procurement of power.
3.8 The above submissions of Petitioner & Respondent indicates vast gap between their basic
proposals for approval of the PPA to be approved by this Commission. It appears that
representatives of parties in the matter did not discuss the issues in respect of the
provisions made in the draft PPA.
3.9 PPA is an agreement to be executed between the parties following due process of drafting
with mutual consent and comprehensive understanding of the provisions by the parties
involved. The instant PPA submitted by UPCL appears to be not only ambiguous in rate of
Page 6 of 8
supply of power but also as to how this rate is to be determined.
3.10 Further, the licensee submitted that it was filing the Petition in accordance with the
direction issued by GoU and not on its own initiative. However, the letter dated 28.04.2015
issued by Secretary (Energy), GoU to MD, UPCL refers to the proposals dated 23.02.2015
and 11.04.2015 made by the licensee itself for procurement of 428 MW power from the gas
based generating stations situated at Kashipur. The licensee itself is unable to justify the
procurement proposed by it except for the reason that it is having a deficit of about 300
MW. The licensee is expected to understand its own responsibility given under the Act,
Regulations & License Conditions and it should act in accordance with the provisions of
law.
3.11 Furthermore, in Clause 3 of the policy direction dated 29.07.2015 issued by GoU under
Section 108 of the Act to this Commission, it has been mentioned that for the
implementation of the scheme, interventions of the appropriate government, financial
institutions, power developers, gas transporters and regasification terminals to make
power generation affordable from such gas based power plants. In the said policy
direction, the GoU has also directed this Commission under Section 108 of the Act for
taking appropriate action so as to facilitate generation from gas based power plants.
However, the Commission is of the view that it has been bestowed with the
responsibility of regulation of procurement of power by licensee to protect the interest of
the consumer of the State. The Commission allows short/medium term procurement of
power by the licensee provided such procurement is done through a transparent process
and is the least cost option.
The Commission observes that vide its Order dated 03.07.2015 on UPCL’s Petition
seeking approval for purchase of power from a trader on short term basis, the Commission
had approved short term procurement of RTC power of 300 MW during July, 200 MW in
August and 200 MW in September, 2015 by UPCL at a landed price of Rs. 3.37/Unit.
Further, the Commission in its ARR/Tariff Order dated 11.04.2015 has approved the rate of
short term power to be procured during FY 2015-16 as Rs. 3.88/Unit. Moreover, UPCL
during the hearing has also accepted the fact that power is also available at cheaper rates
than the indicative tariff of Rs. 4.70/Unit as proposed in the Petition. The Commission is of
the view that in the interest of public at large in the State of Uttarakhand approving instant
PPA at a rate much higher than the rates prevalent and already approved by the
Page 7 of 8
Commission cannot be considered.
The aforesaid observations are consistent with Regulation 39(2) of UERC (Conduct
of Business) Regulations, 2014 which specifies as under:
“The distribution licensee to establish to the satisfaction of the Commission that the
purchase of power by it is under a transparent power purchase procurement process and
is economical and the power is necessary to meet its service obligation.”
As already discussed above, there is no clarity between the generator and UPCL on
the tariff at which the power would be procured by UPCL. Further, the licensee during the
hearing has admitted that no bidding has been carried out by it for sourcing the power and
also that cheaper power is available in the market at present and therefore any
procurement, as proposed, would be in contravention to the regulation cited above.
3.12 Furthermore, Clause 4.(c.) of the Policy Direction dated 29.07.2015 issued by GoU states as
under:
“The net price of this incremental electricity sold by generating plants regulated by UERC and
purchased by the distribution licensee under this scheme should not exceed the target price
specified in the scheme…”
This provision talks that the net price of the incremental electricity sold by the
generating plants and purchased by the distribution licensee under the scheme would not
exceed the target price specified in the scheme. Hence, it is all the more imperative to arrive
at the net price which has not been covered in the draft PPA submitted by UPCL as has
already been dealt in the preceding Paras.
In this regard, it would also be relevant to refer to Clause 3 of the Policy direction
wherein it has been specified that the Act empowers the UERC to regulate the tariff of the
generating companies owned or controlled by the State Government and to facilitate inter-
state transmission of electricity. The Respondent’s generating plant does not fall under the
category of owned or controlled by the State Government.
Moreover, as stated in Clause 4.(b.)(i.) of the policy, the lead banker has to ensure
that all receipts of money would be utilized only for payments towards the variable cost of
generation, O&M expenses and interest payment as per the regulations, orders and/or
guidelines of UERC, it would be relevant to state that as of now, there is no regulations/
guidelines of the Commission for short/medium term procurement of power. The only
Page 8 of 8
order available on short term procurement of power is the Tariff Order for FY 2015-16,
which lays down the short term rate of Rs. 3.88 per unit.
3.13 Hence, in light of the above discussions, since no process was adopted as required under
the law, to identify this generator for procurement of power on medium term by the
distribution licensee as well as confirmation by the Petitioner, that cheaper power is
available, the Commission does not agree to approve the PPA with or without
modifications as it holds that the basic premises of the PPA, i.e. rate of purchase is not only
ambiguous basis of arriving at has not been established. The Commission decides to
dispose off the petition as dismissed.
3.14 Ordered accordingly.
(K.P. Singh) (C.S. Sharma) (Subhash Kumar) Member Member Chairman