- NEC3 briefing - 1 Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), PhD, MRICS, MCIPS, NEC Consultant - NEC3 briefing - 2 Objectives: Understand the background & philosophy of the contract Understand the key procedures: Early Warnings Programme Compensation Events Develop a practical approach - NEC3 briefing - 3 Problems with Existing Standard Forms Based on disputes and case law Reactive as opposed to pro-active Not focussed on management procedures Little focus on the programme Inflexible Conflict of interest in the role of the Engineer/Architect

Upload: ngonhi

Post on 10-Mar-2018

228 views

Category:

Documents


5 download

TRANSCRIPT

Page 1: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 1

Using the NEC3 contracts effectively

Dr Stuart KingsBSc(Hons), PhD, MRICS, MCIPS, NEC Consultant

- NEC3 briefing - 2

Objectives:

• Understand the background & philosophy of the contract

• Understand the key procedures:Early WarningsProgrammeCompensation Events

• Develop a practical approach

- NEC3 briefing - 3

Problems with Existing Standard Forms

• Based on disputes and case law• Reactive as opposed to pro-active• Not focussed on management procedures• Little focus on the programme• Inflexible• Conflict of interest in the role of the

Engineer/Architect

Page 2: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 4

CORE CLAUSE

10.1 The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of mutual trust and co-operation.

- NEC3 briefing - 5

Recognised Best Practice

National Audit Office Report, Improving Public Services through better construction, published on 14 March 2005.

The NAO recommended the use of contracts that support collaborative working for “the client and the entire integrated team”. The NAO added: “The Engineering and Construction Contract is one example of a contract written in plain English that embeds the principles of good project management in its procedures, and promotes role clarity. It encourages early issue resolution, and contains options as to the choice of procurement route. It is non-adversarial in its tone and spirit, and as such, many clients have adopted it for use in long-term collaborative working arrangements.”

- NEC3 briefing - 6

Project Management procedures now part of the contract!

Traditional contracts: SeparateContract conditions

Project Management procedures

Contractualised Project

ManagementECC:

Combined!

Page 3: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 7

Key benefits of the NEC

1. Flexibility

2. Clarity & simplicity

3. Stimulus to good management

- NEC3 briefing - 8

Flexibility

• Multi-disciplinary

• Design

• Pricing

- NEC3 briefing - 9

Clarity & simplicity

• Plain English

• Present tense

• Simple structure

• Short sentences

• Procedures are not open-ended and conflicting

• No reference to law

• Set of common clauses (irrespective of the main contract chosen)

Page 4: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 10

Stimulus to good management

• Collaborative foresight

• Clear allocation of responsibility

• Early warning procedure

• Detailed procedure for dealing with change

• Programming facility

- NEC3 briefing -

Control mechanisms

- NEC3 briefing - 12

Time, quality, cost triangle:

CE’s/ programme

Mutual trust &

cooperation/ EW’s

Time

Cost

WI/ Defects management

Quality

Page 5: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

Key roles:

Time

Cost

Quality

Project Manager role

Supervisor role

- NEC3 briefing -

Use of the NEC - be prepared for more admin during the project!!

Completion

1-2 monthsNEC

Traditional

EFFORT/

EXPENSE

TIME

- NEC3 briefing -

Structure

Page 6: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 16

NEC structure: Core Clauses(common to ALL main options)1) General2) The Contractor’s main responsibilities3) Time4) Testing & Defects5) Payment6) Compensation events7) Title8) Risks & insurance9) Disputes & termination

Main Options A to F

Secondary Options

- NEC3 briefing - 17

Family of contract documents:

- NEC3 briefing -

MAIN OPTIONS

Page 7: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 19

MAIN OPTIONS

• Option A – Priced Contract With Activity Schedule

• Option B – Priced Contract With Bill of Quantities

• Option C – Target Contract With Activity Schedule

• Option D – Target Contract With Bill of Quantities

• Option E – Cost Reimbursable Contract

• Option F - Management Contract

- NEC3 briefing - 20

MAIN OPTIONS EXPLAINED

• Option A – Plan & Specification

• Option B – Bill of Quantities

• Option C – GMP then open-book

• Option D – Bill of Quantities then open-book

• Option E – Cost Plus

• Option F - Management Contract

- NEC3 briefing - 21

Professional Services Contract:

Consultancy

Page 8: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 22

Term Services Contract:

A contract for a contractor to provide a service (not limited to a professional or construction service) to an Employer from a starting date and throughout a service period.

Not a contract for a project.

- NEC3 briefing - 23

ECC Short Contract:

- Low risk- Low in complexity- Value not relevant- Programme less critical

- NEC3 briefing - 24

ECC Subcontract:

• Complex trades• Medium – high risk• Programme critical

Page 9: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 25

Short subcontract:

• Low risk• Low in complexity• Value not relevant• Programme less critical

- NEC3 briefing - 26

CONTRACT DATA

• Part 1 – Data provided by the Employer

• Part 2 – Data provided by the Contractor

Works  Informa,on  –  General• Brief  descrip,on  of  the  works.• Provision,  content  &  use  of  the  documents.• Management  of  the  works.• Programme.• Comple,on.• Take  over.• Accounts  &  records.• Procurement  procedures.• Subcontractors.• Management  and  staff.• Quality  Assurance.• Security  &  protec,on.• Facili,es  and  services  to  be  provided  by  the  Contractor  for  use  by  the  Employer  and  

Others.• Facili,es  and  services  to  be  provided  by  the  Contractor  for  his  own  use.• Facili,es  and  services  to  be  provided  by  the  Employer  for  use  by  the  Contractor.• Work  by  Others  with  whom  the  Contractor  shares  the  Working  Areas.• Property  in  excavated  materials  of  demolished  buildings.• Marking  Equipment,  Plant  &  Materials.

Source:  Managing  Reality,  Book  2

Page 10: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

“60.1 The following are compensation events. (1) The Project Manager gives an instruction changing the Works Information except

•  a change made in order to accept a Defect

•  a change to the Works Information provided by the Contractor for his design which is made either at his request or to comply with other Works Information provided by the Employer”

Role of the WI: Some key principles:

- NEC3 briefing -

CORE CLAUSES

- NEC3 briefing -

Early Warnings

Page 11: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 31

Early Warning clauses: Clause Description16.1 Both parties give an early warning as soon as they become

aware of any event that could effect:• Time• Quality • Cost• Key Date (NEC3)

- Contractor can raise if his cost may increase (NEC3)- PM enters into a Risk Register (NEC3)

16.2 Either party may instruct the other to attend a ‘risk reduction’ meeting.

Each may instruct other people to attend e.g. subcontractors, client stakeholders.

- NEC3 briefing - 32

Early Warning clauses (continued): Clause Description16.3 At the ‘risk reduction’ (NEC3) meeting those who attend co-operate in:

1. Considering how the matter can be avoided or reduced2. Seeking solutions that will bring advantage to all those effected3. Decide upon actions to take

16.4 The PM records the outcome and gives a record of this to the contractor.

NEC3 requires this record to be in the form of a Risk Register.

Best Practice: The PM maintains a risk register as a formal means of recording

E.W.’s (now mandatory under the NEC3)

- NEC3 briefing -

Programme

Page 12: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 34

Programme clauses: Clause Description

31.2 Each programme (which requires acceptance by the PM) should include:

• starting date, access dates, Key Dates and Completion Date• planned Completion• order & timing of operations (includes statement of how & resource utilised)• planned Completion• provisions for:

•Float•Time risk allowance

• other information which the WI requires

- NEC3 briefing - 35

Programme – practical application

CDPC

SD- starting dateSD

PCCD

- Planned Completion- Completion Date

- Non-critical activity

- Critical activity

Terminal float

Activity 001

Activity 002

Activity 003

Activity 004

Activity 005

Activity 006

Activity 007

Float

Time risk allowance

- NEC3 briefing -

Managing the NEC:

1 = Programme

2 = EW’s

3 = CE’s

Page 13: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing -

Compensation Events

- NEC3 briefing - 38

Compensation Events:

Reasons:

• 60.1 – 60.18 (19 NEC3)

- NEC3 briefing - 39

Summary of Compensation Events60.1(1) Change to the Works Information60.1(2) Access 60.1(3) Employer not providing something60.1(4) Stop or not start any work60.1(5) Employers & Others working time/

conditions60.1(6) Replying to communications60.1(7) Object of value60.1(8) Changing decisions60.1(9) Withholding acceptance60.1(10) Instructions to search

Page 14: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 40

Summary of Compensation Events

60.1(11) Test or inspection causing delay60.1(12) Physical conditions60.1(13) Weather60.1(14) Employer’s risk60.1(15) Take over60.1(16) Employer provides materials, facilities

and samples60.1(17) Correction of an assumption60.1(18) Breach of contract60.1(19) Unforeseen event

- NEC3 briefing - 41

Compensation Events:

4 stage process:

1. Notifying

2. Quoting

3. Assessing

4. Implementing

Clear timescales

CE’s - PM review in principle:

Project Manager Contractor

1 Week (in principle)

In principle

42

Page 15: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

CE’s - Contractor to quantify:

Project Manager Contractor

1 Week (in principle)

Price up

3 Weeks (to quantify)

43

CE’s - PM decide in quantum:

Project Manager Contractor

1 Week (in principle)

Decide in quantum

3 Weeks (to quantify)

2 Weeks (to decide)

44

CE’s - 1st element of time barred rule:

Project Manager ContractorFurther 2 weeks

Contractor notifies (that had no response)

Automatic acceptance in principle

1 Week (in principle)

45

Page 16: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

CE’s - 2nd element of time barred rule:

Project Manager Contractor

1 Week (in principle)

Further 2 weeks

Contractor notifies (that had no response)

Automatic acceptance in quantum!!

3 Weeks (to quantify)

2 Weeks (to decide)

46

- NEC3 briefing - 47

Notifying Compensation Events:

Clause Description61.1 PM notifies the C

61.2 ‘Proposed’ instructions/ change decisions may be requested. These are not ‘put into effect’ until confirmed by the PM.

61.3 C notifies the PM

61.3 If the C does not notify the PM within 8 weeks of becoming aware of the event then he is not entitled to a change in the Prices, Completion Date or Key Date (unless the PM should have notified the event to the C but did not) – NEC3 only.

- NEC3 briefing - 48

Notifying Compensation Events:

Clause Description61.4 ‘Tests’ of the Compensation Event:

• Fault of the contractor?• Not happened or not expected to?• No effect on cost or Completion?• Not a reason stated in the contract?

If PM agrees:- Within 1 week instructs the C to submit a quote, or;- Agrees a longer period to which the C has agreed

Page 17: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 49

Quotations for Compensation Events: Clause Description62.1 PM may instruct the C to submit alternative quotes – different ways

of dealing with the CE. C may also submit further alternatives.

62.2 Revised programme is submitted if remaining work is effected.

62.3 C submits his quote within 3 weeks.

62.3 PM replies within 2 weeks of this. Reply to state:• If a revised quote is required (must state reasons – 62.4),• Acceptance of the quote,• Instruction will not be given, or;• PM to make their own assessment

62.5 Extensions to the timescales may be agreed by both parties prior to the deadlines

- NEC3 briefing -

SECONDARY OPTIONS

- NEC3 briefing - 51

SECONDARY OPTIONS

X1 Price adjustment for inflationX2 Changes in the lawX3 Multiple currenciesX4 Parent company guaranteeX5 Sectional CompletionX6 Bonus for early CompletionX7 Delay damages

Page 18: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

- NEC3 briefing - 52

SECONDARY OPTIONS (continued)

X12 PartneringX13 Performance bondX14 Advanced payment to the ContractorX15 Limitation of the Contractor’s liability

for his design to reasonable skill and care

X16 RetentionX17 Low performance damagesX18 Limitation of liability

- NEC3 briefing - 53

SECONDARY OPTIONS (continued)

X20 Key Performance IndicatorsZ Additional conditions of contract

- NEC3 briefing -

Final thought……managing the NEC:

1 = Programme

2 = EW’s

3 = CE’s

Page 19: Using the NEC3 contracts effectively - CIPS minutes/nec3... · Using the NEC3 contracts effectively Dr Stuart Kings BSc(Hons), ... SD SD - starting date PC CD ... GMP/ Target Price

Example  contract  admin.  monthly  management  report

Early warnings:

Programme:

Compensation events/ cost:

General:

Nr raisedNr resolved

Nr outstanding

Comments:

Comments:

Potential risks:

Key dates:

Latest programme Accepted?

YesNo

Nr raised

Nr resolved

Nr outstanding

£ value

GMP/ Target Price

Forecast cost:______

Forecast FA: ______

Forecast GMP:_____

Trust

PM Contractor

- NEC3 briefing -

‘NEC Contract’:Re-cap:

• Having the right team ethos is key.• Agree as a team how you are going to

communicate/ apply the NEC3.• Ensure the ‘wider’ team appreciate the

key mechanisms.• Constantly review how effectively you are

working as a team.