nec3 ecc introductory training - scalar homescalar.uk.com/nec3 ecc introduction training 2.pdf ·...
TRANSCRIPT
1
NEC3 ECCIntroductory Training
John Rayner
House Keeping and Safety
• Fire Alarm• Toilets• Mobile phones
Please remember to switch all mobile phones to silent
2
Introductions
John Rayner
Name:NEC3 Knowledge:
Content
• General Overview & principles
• Payment
• Early warnings and compensation events
• Roles and responsibilities, Defects and the programme
3
Perceptions….
“Contractual”negative, aggressive, claim conscious
contractual = transparent = less disputes = more satisfactory result
“transparent”positive, collaborative, pro-active
Objectives of the NEC
Clarity
Flexibility
Stimulus to good
management
4
Objectives of the NEC
Clarity
Flexibility
Stimulus to good
management
Clarity
• written in straight forward plain language -avoids legal phrases and as far as possible subjective terms
• no long sentences – uses bullet points
• no cross referencing between the clauses
• process driven, with flow charts available to demonstrate the process and ensure that there are no open ends
• series of defined terms identified within the contract
• contract specific items kept separate in Contract Data
Objectives of the NEC
Clarity
Flexibility
Stimulus to good
management
Flexibility
• used across the whole of the construction industry
• flexible design allocation responsibility
• used across a range of contract strategies
• allows a series of “bolt on” optional clauses to allow the contract to be tailored to meet the requirements of a specific project
• used internationally as well as domestically
5
Objectives of the NEC
Clarity
Flexibility
Stimulus to good
management
Stimulus to good
management
• clauses/processes intended to help the management of the project, not hinder
• obligates actions, and within period stated or within period of reply
• identifies risk early when effects can be best managed
• assessments of compensation events based on predicted not retrospective effect.
• programme revised and accepted forms integral part of the contract
Overview of the NEC3 - Principles
Clause 10.1
The Employer, the Contractor, the Project Manager and the Supervisor shall act as stated in this contract and in a spirit of
mutual trust and co-operation.
6
Overview of the NEC3 – The Suite
• Engineering and Construction Contract
• Engineering and Construction Sub-contract
• Engineering and Construction Short Contract
• Engineering and Construction Short Sub-Contract
• Professional Services Contract
• Professional Services Short Contract
• Adjudicator’s Contract
• Term Service Contract
• Term Service Short Contract
• Framework Contract
• Supply Contract
• Short Supply Contract
ECC General Structure and Form
• The Core Clauses
• Main Option Clauses
• Secondary Option Clauses
• Contract Data Parts 1 & 2
• Schedule of Cost Components
• Works Information
• Site Information
7
Contract Format
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Core Clauses
Core Clauses
• Arranged in a structure that helps gain familiarity
• Clearly defined sections
• Limited cross referencing
• Written in ordinary language
• Flow chart basis led to simplified structure
• Are not altered by the Options, merely added to with unique numbering
8
Core Clauses
Core Clauses
• 1 – General
• 2 – The Contractor’s main responsibilities
• 3 – Time
• 4 – Testing and Defects
• 5 – Payment
• 6 – Compensation Events
• 7 – Title
• 8 – Risks and Insurance
• 9 – Termination
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Main Option Clauses
Main Option Clauses
• Option A: Priced contract with Activity Schedule
• Option B: Priced contract with Bill of Quantities
• Option C: Target contract with Activity Schedule
• Option D: Target contract with Bill of Quantities
• Option E: Cost reimbursable contract
• Option F: Management contract
• Option W1 or W2 Dispute Resolution
9
Main Option Risk Balance
A
F
B
D
C
E
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
Bill of Quantities
Target Price with Activity Schedule
Target Price with Bill of Quantities
Cost reimbursable
Management contract
Secondary Option Clauses
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Secondary Option Clauses
• X1 – Price adjustment for inflation
• X2 – Changes in Law
• X3 – Multiple currencies
• X4 – Parent Company Guarantee
• X5 – Sectional Completion
• X6 – Bonus for early completion
• X7 – Delay damages
10
Secondary Option Clauses
Secondary Option Clauses
• X12 – Partnering
• X13 – Performance bond
• X14 – Advanced payment to the Contractor
• X15 – Limitation of the contractor’s liability for his design to reasonable skill and care
Secondary Option Clauses
Secondary Option Clauses
• X16 – Retention
• X17 – Low performance damages
• X18 – Limitation of liability
• X20 – Key Performance Indicators (not used with X12)
• Option Z – additional conditions of contract
11
Option Y(UK) Clauses
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Y(UK) Option Clauses
• Y(UK)1 – Project bank account
• Y(UK)2 – Housing Grants, Construction and Regeneration Act 1996 / Local Democracy, Economic Development and Construction Act 2009
• Y(UK)3 – The Contracts (Rights of Third Parties)
Act 1999
Contract Data Part 1
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Contract Data Part 1
• Employer’s Information
• Key roles (E, PM, S)
• Boundaries of the site
• Period for reply
• Time scales, Defects, payment
• Compensation Events and risk
• Option clause requirements• Key date
• Sectional completion
• Contractor’s share
• Retention percentage
• Option Z
12
Contract Data Part 2
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Contract Data Part 2
• Contractor’s Information
• Key people
• Matters to be included in the risk register
• WI for Contractor’s design
• First programme
• Data for the Main Option
• Data for the schedule of cost components
• Equipment rates
• Working Area Overheads
• Defined Cost rates and percentages for design and manufacture and fabrication
• People percentage
• Published list of Equipment and percentage adjustment
Schedule of Cost Components
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Schedule of Cost
Components
• People
• Equipment
• Plant and materials
• Charges
• Manufacture and fabrication
• Design
• Insurance
13
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Works Information
Works Information
• Specifies and describes the works
• States any constraints on how the Contractor Provides the Works
• Documents are referenced in the Contract Data
• Given in an instruction
Site Information
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Schedule of Cost
Components
• Describes the Site and its surroundings
• Referenced in the Contract Data
– SI reports and test results
– Physical condition reports
– References to available information
– Statutory undertakers
– H&S Files
• Contains only factual information
14
Exercise
• The NEC3 uses the Contract Data to define the full terms and conditions. The pro-foma entry is:
• Write out the definition of the conditions of contract selecting the right options to ensure that the commercial requirements are met.
The conditions of contract are the core clauses and the clauses for main Option . . . . , dispute resolution Option . . . and secondary Options . . . of the NEC3 Engineering and Construction Contract April 2013.
Break
15
Payment Options (Main Options A – F)
• Payment provisions are stated in main options A to F
• Each options varies the financial risk
• Payment depends on the definition of Price for Work Done to Date
Option A
A
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
16
Main Option A
• Priced Contract with Activity Schedule
• Activity Schedule does not have to describe all the work
• Paid only on Completing each activity
• Shorter Schedule of Cost Components – or agreed rates and prices
• No recovery for the costs of preparing compensation events
Option B
A
B
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
Bill of Quantities
17
Main Option B
• Priced contract with bill of quantities
• Use chosen method of measurement
• BoQ corrected and new rates used/agreed
• Payment on a remeasure basis
• Final BoQ a complete description of the works
• No recovery for the costs of preparing compensation events
Options C & D
A
B
D
C
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
Bill of Quantities
Target Price with Bill of Quantities
Target Price with Activity Schedule
18
Main Options C & D
• Target Contract with Activity Schedule (C) or Bill of Quantities (B)
• Activity Schedule or Bill of Quantities is not a payment document
• Contractor paid on a Defined Cost plus Fee basis• Pain/Gain share on Completion and final account• Risk in the target similar to Option A• Contractor recovers the costs of preparing
compensation events
Option C&D Pain/Gain
Pric
es (ta
rget)
at a
ward
Pric
es (ta
rget) w
ith
CE
’s a
t Com
ple
tion
PW
DD
PW
DD
Contractor’s share (% set at tender stage)
Emp
loyer p
ays
19
Option E
A
B
D
C
E
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
Bill of Quantities
Target Price with Activity Schedule
Target Price with Bill of Quantities
Cost reimbursable
Main Option E
• Cost reimbursable contract
• Contractor paid Defined Cost plus the Fee
• Compensation events require the Contractor to re-forecast
20
Option F
A
F
B
D
C
E
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
Bill of Quantities
Target Price with Activity Schedule
Target Price with Bill of Quantities
Cost reimbursable
Management contract
Main Option F
• Management contract
• Contractor does no or little work
• Contractor lets work packages
• Contractor is paid a tendered fee for the work undertaken
21
Option A
A
Contractor – increasing financial risk
Emp
loye
r –
incr
easi
ng
fin
anci
al r
isk
Activity Schedule
Activity Schedule - Definitions
• 11.2 (20) The Activity Schedule is the activity schedule unless later changed in accordance with this contract.
• 11.2 (27) The Price for Work Done to Date is the total of the Prices for• each group of completed activities and• each completed activity which is not in a group.• A completed activity is one which is without Defects
which would either delay or be covered by immediately following work.
• 11.2 (30) The Prices are the lump sum prices for each of the activities on the Activity Schedule unless later changed in accordance with this contract.
22
The Activity Schedule - Programme
• 31.4 The Contractor provides information which shows how each activity on the Activity Schedule relates to the operations on each programme which he submits for acceptance.
The Activity Schedule - Payment
• 54.1 Information in the Activity Schedule is not Works Information or Site Information.
• 54.2 If the Contractor changes a planned method of working at his discretion so that the activities on the Activity Schedule do not relate to the operations on the Accepted Programme, he submits a revision of the Activity Schedule to the Project Manager for acceptance.
• 54.3 A reason for not accepting a revision of the Activity Schedule is that it does not comply with the Accepted Programme, any changed Prices are not reasonably distributed between the activities or the total of the Prices is changed.
23
Activity Schedule - CE’s
• 63.12 Assessments for changed Prices for compensation events are in the form of changes to the Activity Schedule.
The Activity Schedule
• Effectively they are a bar on a bar chart, which the Contractor has priced
• An activity can include fixed overheads, time related charges, temporary works, materials on site as well as the permanent works.
• The activity schedule is drawn from the programme, but is a separate document
Under Option A, Priced Contract• Contractor is paid price for activity if completed by
next assessment date• Determines cash flow & the Prices
24
Lunch
Early warnings
• The NEC
… is based on the principle that foresight applied collaboratively mitigates problems
and shrinks risk
25
Early warnings
• Clause 16
• What is it’s aim
• Note early warnings do not give entitlement to additional money or time – only compensation events will do that.
• Both parties are obligated to give early warnings (10.1)
Early warnings
16.1 The Contractor and the Project Manager give an early warning by notifying the other as soon as either becomes aware of any matter which could• increase the total of the Prices,
• delay Completion,
• delay meeting a Key Date, or
• impair the performance of the works in use
In the notification the Contractor and the Project Manager state whether the early warning must be dealt with immediately.
26
Two extremes of understanding:
• Project Manager stated that he “does not want any early warnings on this project”
two extremes of understanding:
• Project Manager stated that he “does not want any early warnings on this project”
• Project Manager says “Give me as many early warnings as you can”
27
Absence of an early warning
If the Project Manager decides that the Contractor did not give an early warning of the event which an experienced contractor could have given, he notifies this decision to the Contractor when he instructs him to submit a quotation for a compensation event (61.5)
The Project Manager is able to review and incorporate in his assessment the consequences of a lost opportunity to mitigate the event (63.5)
Disallowed Cost if the cost was incurred because the Contractordid not give an early warning the contract requires him to give
Early warnings
• The early warning process is the contractual communication tool to– identify potential problems
– consider proposals to avoid or mitigate their effect
– seek mutually acceptable solutions
• Early warnings should be encouraged as a positive process
• They should not be seen as a precursor to a compensation event claim
28
Early warnings exercise
• Sketch out the flow chart for the early warning process
• Consider the interaction of the Project Managerand the Contractor
Early warnings exercise
29
Compensation events
• Compensation events are the NEC3 ECC’s mechanism to reimburse the Contractor for:
– Risk events
– Additional works
– Additional attendances
– Breaches of contract by the Employer, Project Manager and the Supervisor
The compensation event processNotification by PM or C
8 week time bar for certain CE’s (61.3.)
PM’s decision
Instruct a quote
C submits quote
PM response(accept / not accept / self
assess)
PM assessment (if required)
Implementation
< 2 weeksDeemed acceptance 2 weeks after reminder
Should an EW been given?
< 3 weeks
< 2 weeks
< 3 weeks
PM to state any assumptions
May be instructed to submit proposed or alternative quotes
Deemed acceptance 2 weeks after reminder
Only changes if PM’s assumptions are incorrect
30
Compensation event exercise
• Identify those events for which the time bar in clause 61.3 does not apply.
• Determine which of the scenarios are, or are not, compensation events.
Evaluating Compensation Events
63.1 The changes to the Prices are assessed as the effect of the compensation event upon
• the actual Defined Cost of the work already done,
• the forecast Defined Cost of the work not yet done and
• the resulting Fee.
31
Defined Cost
11.2 (22) Defined Cost is the cost of the components in the Shorter Schedule of Cost Components whether work is subcontracted or not excluding the cost of preparing quotations for compensation events.
Fee
11.2 (8) The Fee is the sum of the amounts calculated by applying the subcontracted fee percentage to the Defined Cost of subcontracted work and the direct fee percentage to the Defined Cost of other work.
32
Schedule of Cost Components
Core Clauses
Main Option Clauses
Secondary Option Clauses
Y (UK) Option Clauses
Contract Data Part 1
Contract Data Part 2
Schedule of Cost
Components
Works Information
Site Information
Schedule of Cost
Components
• People
• Equipment
• Plant and materials
• Charges
• Manufacture and fabrication
• Design
• Insurance
SSCC Pigeon Holes
Equipment
OHD’s
In WA
Agency
Visiting
Site based
Purchased
CT Data
In the List
Used in WA
Credits
Testing
Packaging
Delivery
Purchasing
Specials
PM & S
Authorities
Cancelled
PFPO
Rates in CD
Employees
Paid
Off Site
CHargesP&MPeople
Expenses
DesignM&F
33
What’s in the Fee
• Everything that can’t be pigeon holed!
– Insurance
– Bonds and warranties
– Costs incurred for overheads outside the Working Areas
– Costs incurred by people outside the Working Areas
– The cost of preparing quotations for compensation events
– Profit & risk (corporate rather than operational)
Break
34
THE ROLE OF THE PROJECT MANAGER AND SUPERVISOR
Role of the Project Manager
Principal Obligations
• To act in accordance with the Contract
• To act as an agent of the Employer
• To act impartially on certain matters
• To act in spirit of mutual trust and co-operation
35
Role of the Project Manager
Employer
Project Manager
Subcontractor
Designer
Supplier
Subcontractor
Subcontractor
Comm Mgt
Contract Admin
Project Control
Planning
Communications
Stakeholder Mgt
Doc Control
H&S
Design
Adjudicator
tribunal
Contractor
Key responsibilities of the PM
• To communicate in a form which can be read, copied and recorded
• To reply to a communication within the period of reply
• To issue certificates to the Employer and the Contractor
• To notify the Contractor before delegating any actions
• May give an instruction which changes the Works Information
• To give early warning of matters (delay, cost or performance)
• To enter early warning matters in the Risk Register
• To record decisions made by revising the Risk Register
• To accept particulars of the Contractor’s design
• To accept replacement persons proposed by the Contractor
36
Role of the Supervisor
Employer
Project Manager
Subcontractor
Designer
Supplier
Subcontractor
Subcontractor
Supervisor
Comm Mgt
Contract Admin
Project Control
Planning
Communications
Stakeholder Mgt
Doc Control
H&S
Design
Adjudicator
tribunal
Quality Control
Contractor
Role of Supervisor
• Ensure on behalf of the Employer, that the works are provided to the standard and performance required in the Works Information;
• Witness and/or carry out tests and inspections;
• Notification of Defects;
• Issuance of the Defects Certificate.
37
Defects
• What is a Defect?
• Who’s responsibility
• Correcting Defects
• Uncorrected Defects
Defects
Clause 11.2 (5)
A Defect is
• a part of the works which is not in accordance with the Works Information or,
• a part of the works designed by the Contractorwhich is not in accordance with this contract or Applicable Law or the Contractor’s design which the Project Manager has accepted.
38
Defect terminology
• Defect – see 11.2(5)• defect correction period
– The period of time the Contractor has to correct a Defect
• defect date– the period of time after Completion that the Contractor
is entitled to return to correct any Defects in the works
• Defects Certificate– A certificate issued after the defects date stating what
Defects remain uncorrected or a statement that there are none.
Notifying Defects
Clause 42.1• Until the defects date, the Supervisor may instruct the
Contractor to search for a Defect.Clause 60.1 (10)• If no Defect is found the matter is a compensation event
unless the search was needed only because the Contractorgave insufficient notice of doing work obstructing a required test or inspection.
Clause 42.2 • Until the defects date, the Supervisor notifies the Contractor
of each Defect as soon as he finds it and the Contractornotifies the Supervisor of each Defect as soon as he finds it.
39
Choices on defective work
Correction by the Contractor
• Pre-Completion (43.1)
• Post-Completion (43.2)– defects correction period / defects date / access availability
Correction by Others
• When access is provided – Cost to Employer (45.1)
• When access is not provided – Cost to Contractor (45.2)
Accepting non-correction of a Defect
• Submission of a Quotation (44.2)
Other commercial implications
Clause 11.2 (25)
Disallowed Cost
• Correcting Defects after Completion;
• correcting Defects caused by the Contractor not complying with a constraint on how he is to Provide the Works stated in the Works Information
40
Exercise
• Sketch (not to scale) a contract time line showing;– starting date
– Completion
– the defects date (assume 12 months)
– defects correction periods• 1) before Completion, and
• 2) after Completion
– Issue of the Defect Certificate
Defect Correction
Completion
Period between Completion and the defects date
(typically 12 months)
defects date
Defect
notified
defect correction
period
Defect
notified
defect correction
period
Defects Certificate
issued at this point
or at the defects
date if the defect
correction period
for the last notified
Defect ends before
the defects date
Completion Certificate issued
within 1 week of the Project
Manager deciding Completion
has been achieved
Defect
notified
Defect
notified
defect correction
period for Defects
notified before
Completion
Defect
notified
defect correction
period
41
Programme Objectives
• Understand the programming requirements of an NEC contract
• Understand the commercial and operational implications of the NEC programming mechanisms
The Accepted Programme
• Reflection of the work done and to be done• Not Site information or Works Information• Belongs to the Contractor• Each new programme when accepted supersedes
the previous one• Used to assess time in a compensation event• Fundamental to the management of a project• Requires considerable effort to maintain – for good
reason
42
The Accepted Programme
• Planned Completion, fluctuates with risk occurrences• Terminal float, maintains Contractor’s effectiveness• Key Dates: Employer requirements – clear and
unambiguous• Acceptances – especially Contractor design• Plant and Materials the Employer is to provide e.g.
specialist materials or standard plant• Order and timing of the work – documents must be
compatible• Resource statements – be careful when calling for
information
84
43
Float
• Free float: the amount of time a task can be delayed before affecting any other task
• Total float: the amount of time a task can be delayed without affecting planned Completion
• Terminal float: the float between planned Completion and the Completion Date – belongs to the Contractor
• Free float and total float are available to accommodate the time effects of compensation events and therefore in essence belong to the project
Float
Activity 1
Activity 5
Activity 4
Activity 2
Start Completion Date
Planned Completion
TRA
TRA
TRA
TRATerminal Float
Total Float
Activity 3
Free Float
44
Float
Activity 1
Activity 5
Activity 4
Activity 2
Start Completion Date
Planned Completion
TRA
TRA
TRA
TRATerminal Float
Activity 3
Free Float
Time Risk Allowance
Activity TRA -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Start 0w
Activity A 1w
Activity B 1d
Activity C 1d
Activity D 0d
Activity E 2d
Activity F 1d
Planned Completion 0d
Completion Date 0d
3 weeks
4 weeks
4 weeks
4 weeks
3 weeks
3 weeks
Activity TRA -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Start 0w
Activity A 1w
Activity B 1d
Activity C 1d
Activity D 0d
Activity E 2d
Activity F 1d
Planned Completion 0d
Completion Date 0d
3 weeks
4 weeks
4 weeks
4 weeks
3 weeks
3 weeks
45
Time Risk Allowance
Activity TRA -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Start 0w
Activity A 1w 4 weeks
Activity B 1d
Activity C 1d
Activity D 0d
Activity E 2d
Activity F 1d
Planned Completion 0d
Completion Date 0d
4 weeks
4 weeks
3 weeks
3 weeks
3 weeks
Time Risk Allowanceof 1 week
Time Risk Allowance
Activity TRA -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Start 0w
Activity A 1w 4 weeks
Activity B 1d
Activity C 1d
Activity D 0d
Activity E 2d
Activity F 1d
Planned Completion 0d
Completion Date 0d
4 weeks
4 weeks
3 weeks
3 weeks
3 weeks
CE – 1 week delayed access to A
46
Time Risk Allowance
Activity TRA -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Start 0w
Activity A 1w
Activity B 1d
Activity C 1d
Activity D 0d
Activity E 2d
Activity F 1d
Planned Completion 0d
Completion Date 0d
4 weeks
4 weeks
3 weeks
3 weeks
3 weeks
3 weeks
X
Time Risk Allowance
Activity TRA -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
Start 0w
Activity A 1w
Activity B 1d
Activity C 1d
Activity D 0d
Activity E 2d
Activity F 1d
1 Week
Planned Completion 0d
Completion Date 0d
4 weeks
4 weeks
3 weeks
3 weeks
3 weeks
4 weeks
47
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w 5 weeks float
Activity H 5w
Planned Completion 0w
Completion Date 0w
3 weeks
4 weeks
3 weeks
3 weeks
4 weeks
3 weeks
3 weeks
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w 5 weeks float
Activity H 5w
Planned Completion 0w
Completion Date 0w Acceleration CE's
3 weeks
4 weeks
3 weeks
3 weeks
4 weeks
3 weeks
3 weeks
48
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w 5 weeks float
Activity H 5w
Planned Completion 0w ANYTHING ANYTHING
Completion Date 0w
3 weeks
4 weeks
3 weeks
3 weeks
4 weeks
3 weeks
3 weeks
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
Planned Completion 0w
Completion Date 0w
3 weeks
4 weeks
3 weeks
3 weeks
4 weeks
3 weeks
3 weeks
49
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 4w
Activity H 4w
Planned Completion 0w
1w
Completion Date 0w
3 weeks
4 weeks
3 weeks
5 weeks
3 weeks
3 weeks
4 weeks
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 5w
Activity H 5w
Planned Completion 0w
Completion Date 0w
3 weeks
4 weeks
3 weeks
3 weeks
4 weeks
3 weeks
3 weeks
50
Impacts on completion
Activity Float -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 0w
Activity B 0w 3 weeks
Activity C 0w
Activity D 0w
Activity E 0w
Activity F 5w
Activity G 6w 3 weeks
Activity H 6w
Planned Completion 1w
1w
Completion Date 0w
3 weeks
2 weeks
3 weeks
3 weeks
4 weeks
Dealing with Early Warnings
• The Contractor shows on each revised programme:
• The effects of implementedcompensation events
• So – what should be put onto a programme in terms of early warnings?
51
Dealing with Early Warnings
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
DIG HOLE 4w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
OBSTRUCTION ENCOUNTERED
EARLY WARNING NOTIFIED (WORK STOPPED)
RISK REDUCTION MEETING
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
DIG HOLE 4w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
OBSTRUCTION ENCOUNTERED
EARLY WARNING NOTIFIED (WORK STOPPED)
RISK REDUCTION MEETING
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
DIG HOLE 4w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
OBSTRUCTION ENCOUNTERED
EARLY WARNING NOTIFIED (WORK STOPPED)
RISK REDUCTION MEETING
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
DIG HOLE 4w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
OBSTRUCTION ENCOUNTERED
EARLY WARNING NOTIFIED (WORK STOPPED)
RISK REDUCTION MEETING
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
DIG HOLE 4w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
OBSTRUCTION ENCOUNTERED
EARLY WARNING NOTIFIED (WORK STOPPED)
RISK REDUCTION MEETING
Dealing with Early Warnings
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14
DIG HOLE 4w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
OBSTRUCTION ENCOUNTERED
EARLY WARNING NOTIFIED (WORK STOPPED)
RISK REDUCTION MEETING
• Risk reduction meeting actions:
• Designer revisits design of access road to consider 3 options
1. Relocate pipe route 2 weeks
2. Breakout section of obstruction 1 week
3. Breakout all of the concrete obstruction 6 weeks
• What is done and what is shown on the revised programme?
52
Dealing with Early Warnings
• We are in Week 4 and due to submit a revised programme
• Given the above – what would you show on the revised programme
that
• you are about to submit?
1. Show event on programme but with no effect on planned
Completion
2. Show event and when linked/rescheduled – affects planned
Completion by 1/2/3/4/6/7/8 weeks?
• Consider what time effect should be due this event…
Dealing with Early Warnings
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16
DIG HOLE 3w
EW001 0w
Risk reduction meeting 1w
EW001 Design review 1w
Complete Excavtion 1w
EW001 Additional Works 1w
INSTALL PIPE 2w
BACKFILL 2w
INSTALL ACCESS ROAD 4w
• Show 3 week delay to the excavation
• Programme narrative explains that EW is under review and further time may / may not result once more details are established
• Next submitted programme shows full effect of what is likely to be a compensation event
53
Dealing with Early Warnings
• INTENT
• To show realistic effect to contract on programme and get accepted as latest
Accepted Programme
• FACT
• Show minimum effect that this event will have on programme:
• HAVE already lost one week between EW notified and RR meeting
• WILL take minimum one week for designers to review options
• WILL take minimum one week for quickest solution
• SOLUTION
• Show three week delay to activity - programme
• Programme narrative explains that the event is under review and further time
effect may/may not result once more details established
• Next revised programme will show full affect of what is likely to be classed as a
compensation event at that stage
Assessing Time in CE’s – 63.3
A delay to the Completion Date is assessed as the lengthof time that, due to the compensation event, plannedCompletion is later than planned Completion as shown onthe Accepted Programme. A delay to a Key Date isassessed as the length of time that, due to thecompensation event, the planned date when theCondition stated for a Key Date will be met is later thanthe date shown on the Accepted Programme
54
Programme Example
Programme ExampleActivity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 4w
Activity B 2w
Activity C 4w
Activity D 2w
Activity E 2w
Activity F 4w
Planned Completion 0w
Terminal float 1w
Completion Date 0w
• Activities A-E are critical
• Activity F is non-critical
• Delay damages at £10,000 per week
55
Programme ExampleActivity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 4w
Activity B 2w
Activity C 4w
Activity D 2w
Activity E 2w
Activity F 4w
Planned Completion 0w
Terminal float 1w
Completion Date 0w
• Week 4 submission– A is three weeks behind and able to recover
– Unable to accelerate any future activities
– 1 week terminal float used up therefore pC is 2 weeks late
Programme ExampleActivity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 7w
Activity B 2w
Activity C 4w
Activity D 2w
Activity E 2w
Activity F 4w
Planned Completion 0w
Completion Date 0w
• Programme reviewed and accepted at week 5.
• Programme is Accepted and therefore is re-baselined
56
Programme ExampleActivity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 7w
Activity B 2w
Activity C 4w
Activity D 2w
Activity E 2w
Activity F 8w
Planned Completion 0w
Completion Date 0w
• At week 6 the Project Manager issues CE001 the doubles the scope of Activity F – from 4 weeks to 8 weeks
• What happens to planned Completion and the Completion Date
• Is the Contractor liable for any delay damages (£10k / week)?
Programme Example
• Planned Completion is week 17, Completion Date still week 15 and Contractor liable for £20,000 delay damages?
• Planned Completion week 17. Completion Date moves to week 19 and Contractor liable for £0 damages?
• Planned Completion week 17, Completion Date moves to week 17, and Contractor liable for £0 damages?
• Something else….?
57
Programme Example
63.3 A delay to the Completion Date is assessed as thelength of time that, due to the compensation event,planned Completion is later than planned Completionas shown on the Accepted Programme. A delay to a KeyDate is assessed as the length of time that, due to thecompensation event, the planned date when theCondition stated for a Key Date will be met is later thanthe date shown on the Accepted Programme
Programme Example
• Test under 63.3 is change to planned Completion
• Planned Completion is unaffected by the CE
• Answer is (1): Planned Completion is 17, Completion Date still week 15 and Contractor remains potentially liable for delay damages at £20,000
Activity Duration -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
Start services 0w
Activity A 7w
Activity B 2w
Activity C 4w
Activity D 2w
Activity E 2w
Activity F 8w
Planned Completion 0w
Completion Date 0w
58
Programme Example
• Be careful when a revised programme shows a delay to planned Completion Date
• Check there is nothing you can practically do, i.e.
– Increase resources
– Overlap activities to be a concurrent as possible
– Remember the programme needs to be realistically and achievable
• Remember liability for damages – hence back to RELATIONSHIPS
Summary
• General Overview & principles
• Payment
• Early warnings and compensation events
• Roles and responsibilities, Defects and the programme
59
The Cycle of (NEC) Life
The works Pay
EW’s
The works Pay
PayT&D
PayProg
PayCE’s
Questions ?