useful formulas for pmp

Upload: ashrafkhimani

Post on 03-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Useful Formulas for PMP

    1/4

    KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX

    Effective Learning for Sure Success Page 1

    Earn Value FormulasPV (Planned Value) = BCWS (Budgeted Cost of Work Scheduled

    EV (Earned Value) = BCWP (Budgeted Cost of Work Performed)

    AC (Actual Cost) = ACWP (Actual Cost of Work Performed)

    SV = EVPV (minus is behind schedule)

    CV = EVAC (minus is over budget)

    SPI = EV/PV (Less than 1 is behind schedule)

    CPI = EV/AC (Less than 1 is over budget)

    EAC = AC + (BAC-EV) Use when variances are atypical

    EAC = AC + [(BAC-EV)/CPI] Use when variances are typical

    (Note: This is the same as EAC = BAC/CPI)

    VAC = BACEAC

    ETC = BACEV Use when variances are atypical

    ETC = (BACEV)/CPI Use when variances are typical

    ETC = EACAC Use when original estimates were flawed

    Network DiagramPrecedence Diagramming Method (PDM)

    Also called Activity on Node (AON): Activities are in boxes

    Most commonly used today

    Has 4 relationships: F-S, S-S, F-F, S-F

    No dummies (zero duration dependencies) allowed

    Can analyze using either Three-Point Estimates or CPM

    Arrow Diagramming Method (ADM)

    Also called Activity on Arrow (AOA)

    Only 1 relationship: F-S

    Can have dummies

    Can analyze using either Three-Point Estimates or CPM

    Graphical Evaluation and Review Technique (GERT) - Allows loops and repetitive activitiesThree Point Estimates, or PERTPERT = PROGRAM Evaluation and Review Technique

    Holds schedule and lets cost float

    3 estimates for each task: Optimistic, Pessimistic, and Most Likely

  • 7/28/2019 Useful Formulas for PMP

    2/4

    KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX

    Effective Learning for Sure Success Page 2

    Mean Estimate = (O + 4*ML + P)/6

    Standard Deviation (s) = (PO)/6

    Variance = s2 , or [(PO)/6]2

    Standard deviation of tasks on CP = Sum of variances

    Standard Deviation Ranges:

    If 95% is confidence rating. Range =(2 x ) to + (2 x )

    Powers of a Project Manager1. Expert: Best, earned on your own

    2. Reward: Next best. Based on PM position

    3. Formal: Power, based on PM position

    4. Referent: Referring to positions of others

    1. 5. Penalty: Worst. Based on PM position

    Sources of Conflict (Order of Priority)1. Schedules

    2. Priorities

    3. Manpower (Resources )

    4. Technical Opinions

    5. Procedures

    6. Personality7. Cost

    Channels of CommunicationBetween Team Members = N(N-1)/2

    Project Selection Financials

  • 7/28/2019 Useful Formulas for PMP

    3/4

    KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX

    Effective Learning for Sure Success Page 3

    NPV (Net Present Value) = FV/(1+r)n

    FV= Future Value, r= interest rate, n= no. of time periods

    Higher NPV is better

    IRR (Internal Rate of Return) = Solve the NPV equation for r

    Also called Hurdle Rate

    Higher IRR percentage is better

    BCR (Benefit/Cost Ratio)

    Higher BCR is better.

    Beware, exam can call it CBR, where lower is better

    ROI (Return on Investment) = Earnings/Investment

    Higher ROI is better

    Payback Period = Time to recover cost of the project

    Lower payback period is better

    Cash Flow = Cash InCash Out

    Calculating Stack or FloatTotal Float (also called Slack, Float, or Project Float) is the total amount of time an activity can be delayed

    without delaying the project finish date.

    Free Float/Slack is the amount of time an activity can be delayed without delaying its successor (following

    activity).

    LS ES: Calculates slack with forward pass

    LF EF: Calculates slack with backwards passLag Time: Inserted wait time between activities

    Lead Time: Overlapping activities, also called paralleling or fast tracking. Lead In; Lag Out

    Accuracy of EstimatesOrder of Magnitude:-50% to +50%

    Budget Estimate:-10% to +25%

    Definitive Estimate:-5% to +10%

    Conflict Resolution(Best to Worst)1. Problem Solving: Also called Confronting

    2. Compromising: Solutions satisfy both parties

    3. Withdrawal: Postponing a decision

    4. Smoothing: Emphasis on agreement

    5. Forcing: One viewpoint at expense of another.

  • 7/28/2019 Useful Formulas for PMP

    4/4

    KEY CONCEPT AND FORMULAS FOR PMP EXAM TUTOR CONFLUX

    Effective Learning for Sure Success Page 4

    Herzbergs Motivators1. Achievement

    2. Recognition

    3.

    Challenge of the work itself

    4. Responsibility

    5. Advancement

    6. Growth

    ClosingProject is closed when administrative closure is complete.

    Administrative closure is done at end of each Project Phase and at the end of the Project.

    Contract closure: verification that deliverables were acceptable; it is done once at the end of the

    contract.

    Contract Closure Procedure is produced under Close Project