pmp cost formulas & cost process management overview in plain english (pmbok 5th edition). learn...

32

Click here to load reader

Upload: jonathan-donado

Post on 22-Jan-2018

2.255 views

Category:

Business


12 download

TRANSCRIPT

Page 1: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

PMP Formulas & Cost Overview

Linkedin.com/in/jonathandonado

JONATHAN DONADO

…IN PLAIN ENGLISH

Page 2: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

About me

Linkedin.com/in/jonathandonado

Twitter.com/donadosays

Bilingual senior general management executive with expertise in international

business and Mergers & Acquisitions (M&A)

If you like the Flashcards, please give

a ”Like” on SlideShare. It’s much

appreciated !

o Education: - Senior Executive Fellow – Harvard University- MBA – IESE

o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- PMP- PMI-ACP – Agile Certified Practitioner

Jonathan Donado

Page 3: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Instructions: PowerPoint

EV

Click on the “Slide Show Mode”

1. Download presentation - PowerPoint

2. Use “Slide Show Mode”

Earned Value = EV

The value of the work accomplished until this point in time. Cost is as per the original

budget.

Page 4: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Introduction:

o Project Cost Management is the knowledge use for managing costs. Ithelps to ensure a project is completed within the approved budget

o It includes the processes involving in estimating, budgeting andcontrolling costs

o These processes interact with each other and with processes in theother nine knowledge areas as well

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 5: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Developing a Cost/Schedule System:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Define work using

a WBS

Create work and resource

schedules

Develop a time-phased budget

Collect Cost Data (at the work

package level)

Compute variances

o Scopeo Work packageso Deliverableso Organization unitso Resourceso Budgets

o Schedule resources to activities

o Time-phase work packages into a network

o Use work packages included in an activity. Accumulate budgets (PV).

o Use work packages included in an activity. Accumulate budgets (PV)

o Compute the schedule variance (EV-PV) and the cost variance (EV-AC)

Page 6: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Cost Relationships Overview:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 7: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Development of Project Baselines:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Purposes of a Baselineo It is an anchor point for measuring performance

o A planned cost and expected schedule against which actual cost and schedule are measuredo A summation of time-phased budgets (cost accounts as summed work packages) along a project timeline

What Costs Are Included in Baselines?o Labor, equipment, materials, project direct overhead costs (DOC)

Rules for Placing Costs in Baselineso Costs are placed exactly as they are expected to be “earned” in order to track them to

their point of origin

o Percent Complete Rule

o Costs are periodically assigned to a baseline as units of work are completed over the duration of a work package

Page 8: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

o Project Manager can use the information about the project progress to help control the schedule and cost to assess whether the project is on track through earned value management (EVM)

o EVM uses Variance Analysis methodology

o Other alternative methods are:o Ask team members for a % of the work completed in each work

package or activity

o Team member provides a simple “guess” of work performed

Earned Value Management (EVM):

Page 9: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Methods of Variance Analysis in EVM:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Comparing Earned ValueoWith the expected schedule value

oWith the actual costs

Assessing Status of a ProjectoRequired data elements

o Budgeted cost of the work scheduled (PV)

o Budgeted cost of the work completed (EV)

o Actual cost of the work completed (AC)

oCalculate cost and schedule varianceso A positive variance indicates a desirable condition,

while a negative variance suggests problems or changes that have taken place

Page 10: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

oCost Variance (CV)o Indicates if the work accomplished using labor

and materials costs more or less than was planned at any point in the project

oSchedule Variance (SV)oPresents an overall assessment in dollar terms

of the progress of all work packages in the project scheduled to date

Methods of Variance Analysis in EVM:

Page 11: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Project Cost Management:

ESTIMATECOST

DETERMINECOST

CONTROLCOST

The process involved in planning, estimating, budgeting, and controlling costs so that the budget can be completed within the approved budget

Developing an estimate of costs of

the resources needed to complete a project

Allocating overall cost estimate to

individual work items “cost baseline”

Controlling change to project budget

PLANNING MONITOR & CONTROL

Page 12: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Monitor & Control Costs : CONTROL COST

Cost Baseline

Project Funding Requirements

Performance Reports

Work Performance Information

Approved Change Requests

Project Management Plan

Cost Change Control System

Performance MeasurementAnalysis

Forecasting

Project Performance Reviews

Project Performance Software

Variance Management

Inputs Tools & Techniques Outputs

Cost Estimate Updates

Cost Baseline Updates

Performance Measurements

Forecasted Completion

Recommended Corrective Action

Organizational ProcessAssets Updates

Project Management PlanUpdates

o Monitor Cost Performanceo Ensure that changes are included in cost baselineo Inform stakeholders of authorized changes which impact cost

Page 13: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Cost Budget Breakdown:

Project Reserves

Not Used in Earned Value Calculations

Used in Earned Value Calculations

Cost Budget

Management Reserve

Cost Baseline

Contingency Reserve

Project

Control Account

Work Package

Activity

Tasks

Project

WB

S

Sch

ed

ule

Work Breakdown Structure Schedule Information

Budget Breakdown

Page 14: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Cost Budget Components:

Page 15: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Terms:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

EV Earned value for a task is simply the percent complete times its original budget. Stated differently, EV is the percent of the original

budget that has been earned by actual work completed.

PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a

time-phased cumulative baseline [BCWS—budgeted cost of the work scheduled].

AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work. [ACWP—actual cost of the work

performed].

CV Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV – AC

SV Schedule variance is the difference between the earned value and the baseline line to date where SV = EV – PV

BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.

EAC Estimated costs at completion.

ETC Estimated costs to complete remaining work.

VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.

Page 16: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Terms:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Performance Indexes:

• Cost Performance Index (CPI)• Measures the cost efficiency of work accomplished to date.

• CPI = EV/AC

• Scheduling Performance Index (SPI)• Measures scheduling efficiency

• SPI = EV/PV

• Percent Complete Indexes• Indicates how much of the work accomplished represents of the

total budgeted (BAC) and actual (AC) dollars to date.

• PCIB = EV/BAC

• PCIC = AC/EAC

Page 17: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Terms:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Index Cost (CPI) Schedule (SPI)

>1.00 Under cost Ahead of schedule

=1.00 On cost On schedule

<1.00 Over cost Behind schedule

Page 18: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Cost /Schedule Graph:

Page 19: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Cost /Schedule Graphs:

Linkedin.com/in/jonathandonadoJONATHAN DONADO

SV = EV - PV

CV = EV - AC

Page 20: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

EV

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Earned Value = EV

The value of the work accomplished until this point in time. Cost is as per the original

budget.

“ As of today, what is the estimated value of the work

actually accomplished? “

Page 21: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

PV

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Planned Value = PV

Planned cost or value of the work to be done until this point

in time.

“ As of today, what is the estimated value of the work

planned to be done? “

Page 22: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

AC

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Actual Costs = AC

The costs actually incurred to complete the work until this

point in time.

“ As of today, what is the actual costs incurred for the work

accomplished? “

Page 23: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

BAC

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Budget At Completion = BAC

The total planned value or budget for completing the entire

project.

“ How much did we budget for the total project? “

Page 24: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

CV

Cost Variance = CV

CV = EV - AC

o Positive is Under Budgeto Negative is Over budget

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 25: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

SV

Schedule Variance = SV

SV = EV - PV

o Positive is ahead of schedule

o Negative is behind schedule

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Page 26: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

CPI

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Cost Performance Index = CPI

CPI =

o We are getting $___ worth out of every $1 spent.

o Greater than 1 is good; less than 1 is bad

EV

AC

Page 27: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

SPI

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Schedule Performance Index = SPI

SPI =

o We are progressing at ___% of the rate originally planned.

o Greater than 1 is good; less than 1 is bad

EV

PV

Page 28: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

EAC

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Estimate At Completion = EAC

Prediction of what project will cost when completed..

“ What do we currently expect the total project to cost (a forecast)? “

There are 4 types:

EAC = AC + Bottom up ETC

BACCPI

EAC = AC + (BAC – EV)

EAC =

EAC =(BAC – EV)(CPI x SPI)

Used when the original estimate was flawed

Used when there are no variances from BAC. Most common one for exam

Used when the current variances are “atypical” of the future

Used when the current variances are “typical” of the future

Page 29: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

ETC

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Estimate To Complete = ETC

From this point on, How much More do we expect it to cost to finish the

project ? (a Forecast)

How much more will the project cost?

ETC = EAC - AC

Page 30: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

VAC

Linkedin.com/in/jonathandonadoJONATHAN DONADO

Variance At Completion = VAC

As of today, how much over or under budget will we be at the end of the

project ?

VAC = BAC - EAC

Page 31: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

TCPI

Linkedin.com/in/jonathandonadoJONATHAN DONADO

To Complete Performance Index = TCPI

In order to stay within budget, what rate must we meet for the remaining

work?

TCPI =(BAC – EV)(BAC - AC)

o It divides the work remaining to be done by the money remaining to do it

o Greater than 1 is bad; less than 1 is good

Page 32: PMP Cost Formulas & Cost Process Management Overview in plain English (PMBOK 5th Edition). Learn the cost formulas for your PMP test

Bilingual senior general management executive with expertise in international

business and Mergers & Acquisitions (M&A)

52

Connect with me

Linkedin.com/in/jonathandonado

Twitter.com/donadosays

If you like the Flashcards, please give

a ”Like” on SlideShare. It’s much

appreciated !

o Education: - Senior Executive Fellow – Harvard University- MBA – IESE

o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- PMP- Agile (ACP) – PMI Certified

Jonathan Donado

THANK YOU