pmp cost formulas & cost process management overview in plain english (pmbok 5th edition). learn...
TRANSCRIPT
PMP Formulas & Cost Overview
Linkedin.com/in/jonathandonado
JONATHAN DONADO
…IN PLAIN ENGLISH
About me
Linkedin.com/in/jonathandonado
Twitter.com/donadosays
Bilingual senior general management executive with expertise in international
business and Mergers & Acquisitions (M&A)
If you like the Flashcards, please give
a ”Like” on SlideShare. It’s much
appreciated !
o Education: - Senior Executive Fellow – Harvard University- MBA – IESE
o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- PMP- PMI-ACP – Agile Certified Practitioner
Jonathan Donado
Instructions: PowerPoint
EV
Click on the “Slide Show Mode”
1. Download presentation - PowerPoint
2. Use “Slide Show Mode”
Earned Value = EV
The value of the work accomplished until this point in time. Cost is as per the original
budget.
Introduction:
o Project Cost Management is the knowledge use for managing costs. Ithelps to ensure a project is completed within the approved budget
o It includes the processes involving in estimating, budgeting andcontrolling costs
o These processes interact with each other and with processes in theother nine knowledge areas as well
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Developing a Cost/Schedule System:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Define work using
a WBS
Create work and resource
schedules
Develop a time-phased budget
Collect Cost Data (at the work
package level)
Compute variances
o Scopeo Work packageso Deliverableso Organization unitso Resourceso Budgets
o Schedule resources to activities
o Time-phase work packages into a network
o Use work packages included in an activity. Accumulate budgets (PV).
o Use work packages included in an activity. Accumulate budgets (PV)
o Compute the schedule variance (EV-PV) and the cost variance (EV-AC)
Cost Relationships Overview:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Development of Project Baselines:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Purposes of a Baselineo It is an anchor point for measuring performance
o A planned cost and expected schedule against which actual cost and schedule are measuredo A summation of time-phased budgets (cost accounts as summed work packages) along a project timeline
What Costs Are Included in Baselines?o Labor, equipment, materials, project direct overhead costs (DOC)
Rules for Placing Costs in Baselineso Costs are placed exactly as they are expected to be “earned” in order to track them to
their point of origin
o Percent Complete Rule
o Costs are periodically assigned to a baseline as units of work are completed over the duration of a work package
Linkedin.com/in/jonathandonadoJONATHAN DONADO
o Project Manager can use the information about the project progress to help control the schedule and cost to assess whether the project is on track through earned value management (EVM)
o EVM uses Variance Analysis methodology
o Other alternative methods are:o Ask team members for a % of the work completed in each work
package or activity
o Team member provides a simple “guess” of work performed
Earned Value Management (EVM):
Methods of Variance Analysis in EVM:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Comparing Earned ValueoWith the expected schedule value
oWith the actual costs
Assessing Status of a ProjectoRequired data elements
o Budgeted cost of the work scheduled (PV)
o Budgeted cost of the work completed (EV)
o Actual cost of the work completed (AC)
oCalculate cost and schedule varianceso A positive variance indicates a desirable condition,
while a negative variance suggests problems or changes that have taken place
Linkedin.com/in/jonathandonadoJONATHAN DONADO
oCost Variance (CV)o Indicates if the work accomplished using labor
and materials costs more or less than was planned at any point in the project
oSchedule Variance (SV)oPresents an overall assessment in dollar terms
of the progress of all work packages in the project scheduled to date
Methods of Variance Analysis in EVM:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Project Cost Management:
ESTIMATECOST
DETERMINECOST
CONTROLCOST
The process involved in planning, estimating, budgeting, and controlling costs so that the budget can be completed within the approved budget
Developing an estimate of costs of
the resources needed to complete a project
Allocating overall cost estimate to
individual work items “cost baseline”
Controlling change to project budget
PLANNING MONITOR & CONTROL
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Monitor & Control Costs : CONTROL COST
Cost Baseline
Project Funding Requirements
Performance Reports
Work Performance Information
Approved Change Requests
Project Management Plan
Cost Change Control System
Performance MeasurementAnalysis
Forecasting
Project Performance Reviews
Project Performance Software
Variance Management
Inputs Tools & Techniques Outputs
Cost Estimate Updates
Cost Baseline Updates
Performance Measurements
Forecasted Completion
Recommended Corrective Action
Organizational ProcessAssets Updates
Project Management PlanUpdates
o Monitor Cost Performanceo Ensure that changes are included in cost baselineo Inform stakeholders of authorized changes which impact cost
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Cost Budget Breakdown:
Project Reserves
Not Used in Earned Value Calculations
Used in Earned Value Calculations
Cost Budget
Management Reserve
Cost Baseline
Contingency Reserve
Project
Control Account
Work Package
Activity
Tasks
Project
WB
S
Sch
ed
ule
Work Breakdown Structure Schedule Information
Budget Breakdown
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Cost Budget Components:
Terms:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
EV Earned value for a task is simply the percent complete times its original budget. Stated differently, EV is the percent of the original
budget that has been earned by actual work completed.
PV The planned time-phased baseline of the value of the work scheduled. An approved cost estimate of the resources scheduled in a
time-phased cumulative baseline [BCWS—budgeted cost of the work scheduled].
AC Actual cost of the work completed. The sum of the costs incurred in accomplishing work. [ACWP—actual cost of the work
performed].
CV Cost variance is the difference between the earned value and the actual costs for the work completed to date where CV = EV – AC
SV Schedule variance is the difference between the earned value and the baseline line to date where SV = EV – PV
BAC Budgeted cost at completion. Total budgeted cost of the baseline or project cost accounts.
EAC Estimated costs at completion.
ETC Estimated costs to complete remaining work.
VAC Cost variance at completion. VAC indicates expected actual over- or under-run cost at completion.
Terms:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Performance Indexes:
• Cost Performance Index (CPI)• Measures the cost efficiency of work accomplished to date.
• CPI = EV/AC
• Scheduling Performance Index (SPI)• Measures scheduling efficiency
• SPI = EV/PV
• Percent Complete Indexes• Indicates how much of the work accomplished represents of the
total budgeted (BAC) and actual (AC) dollars to date.
• PCIB = EV/BAC
• PCIC = AC/EAC
Terms:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Index Cost (CPI) Schedule (SPI)
>1.00 Under cost Ahead of schedule
=1.00 On cost On schedule
<1.00 Over cost Behind schedule
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Cost /Schedule Graph:
Cost /Schedule Graphs:
Linkedin.com/in/jonathandonadoJONATHAN DONADO
SV = EV - PV
CV = EV - AC
EV
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Earned Value = EV
The value of the work accomplished until this point in time. Cost is as per the original
budget.
“ As of today, what is the estimated value of the work
actually accomplished? “
PV
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Planned Value = PV
Planned cost or value of the work to be done until this point
in time.
“ As of today, what is the estimated value of the work
planned to be done? “
AC
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Actual Costs = AC
The costs actually incurred to complete the work until this
point in time.
“ As of today, what is the actual costs incurred for the work
accomplished? “
BAC
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Budget At Completion = BAC
The total planned value or budget for completing the entire
project.
“ How much did we budget for the total project? “
CV
Cost Variance = CV
CV = EV - AC
o Positive is Under Budgeto Negative is Over budget
Linkedin.com/in/jonathandonadoJONATHAN DONADO
SV
Schedule Variance = SV
SV = EV - PV
o Positive is ahead of schedule
o Negative is behind schedule
Linkedin.com/in/jonathandonadoJONATHAN DONADO
CPI
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Cost Performance Index = CPI
CPI =
o We are getting $___ worth out of every $1 spent.
o Greater than 1 is good; less than 1 is bad
EV
AC
SPI
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Schedule Performance Index = SPI
SPI =
o We are progressing at ___% of the rate originally planned.
o Greater than 1 is good; less than 1 is bad
EV
PV
EAC
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Estimate At Completion = EAC
Prediction of what project will cost when completed..
“ What do we currently expect the total project to cost (a forecast)? “
There are 4 types:
EAC = AC + Bottom up ETC
BACCPI
EAC = AC + (BAC – EV)
EAC =
EAC =(BAC – EV)(CPI x SPI)
Used when the original estimate was flawed
Used when there are no variances from BAC. Most common one for exam
Used when the current variances are “atypical” of the future
Used when the current variances are “typical” of the future
ETC
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Estimate To Complete = ETC
From this point on, How much More do we expect it to cost to finish the
project ? (a Forecast)
How much more will the project cost?
ETC = EAC - AC
VAC
Linkedin.com/in/jonathandonadoJONATHAN DONADO
Variance At Completion = VAC
As of today, how much over or under budget will we be at the end of the
project ?
VAC = BAC - EAC
TCPI
Linkedin.com/in/jonathandonadoJONATHAN DONADO
To Complete Performance Index = TCPI
In order to stay within budget, what rate must we meet for the remaining
work?
TCPI =(BAC – EV)(BAC - AC)
o It divides the work remaining to be done by the money remaining to do it
o Greater than 1 is bad; less than 1 is good
Bilingual senior general management executive with expertise in international
business and Mergers & Acquisitions (M&A)
52
Connect with me
Linkedin.com/in/jonathandonado
Twitter.com/donadosays
If you like the Flashcards, please give
a ”Like” on SlideShare. It’s much
appreciated !
o Education: - Senior Executive Fellow – Harvard University- MBA – IESE
o Certifications:- Six Sigma Black Belt (CSSBB) – ASQ Certified- PMP- Agile (ACP) – PMI Certified
Jonathan Donado
THANK YOU