u.s. virgin islands wind energy update, edin-usvi energy workshop, 6-2012
TRANSCRIPT
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
1/34
USVI Wind Energy UpdateIan Baring-Gould, NRELbased on research by Eric Lantz, Adam Warren, Owen Roberts,Vahan Gevorgian, & Dan Olis
Credit: Warren Gretz, NREL
EDIN-USVI Energy Workshop
June 11, 2012Bjerget House, St. Croix
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
2/34
Wide Range of Power System Options
Renewable power systems can be used to cover a wide
range of needs, including: Dedicated Use: Power being used at point
sources without regulation
Small or Simple Systems: Power systems forindividual buildings and dispersed generationwhere high level of reliability is not required
Community Power Systems: Utility-providedpower to larger communities or group ofbuildings with larger loads
Wind-Diesel Systems: Large communities orfacilities with large loads
Integrated Systems: Large islanded systemsincorporating conventional and large-scalerenewable generation
PhotoCredit:KentBullard
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
3/34
High Contribution Renewable Technology
Does notrequire additional capacity
Doeschange the way that the balance of system capacity is utilizedDoesrequire expanded system flexibility
10000
8000
6000
4000
2000
0
MW
160140120100806040200
Hours (1 week)
800
600
400
200
0
-200
-400
-600
-800
Ram
p(MW/hour)
Net load (load-wind)
Additional ramping needs with wind
Maximum/MinimumLoad Peak Load
There are a number of ways from the demand and supply side to helpsupport this flexibility, with expanded use of inelegant grids important
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
4/34
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
5/34
Wind Development - SROPTTC
SROPTTCTM framework for project development
Site:A suitable location to implement the projectAccess to transmission,removed from population centers, limited environmental impact
Resource:An economically viable resource to exploitWind resources inSt. Croix, St. Thomas, and St. John that can be developed
Off-take: Someone that can use the powerWAPA and other local
organizations interested in using wind technologiesPermitting: The ability to implement projects understanding community
need and competing uses60% goal and community acceptance ofwind development
Technology: Suitable technologyWind turbines that can beimplemented and operated in the USVI (grid integration, challenginginfrastructure and weather)
Team: Team of people that will implement the projectPublic and privateparties willing and able to pursue the implementation of wind projects
Capital:Availability of capital to develop a utility-scale windAttractingneeded capital from private and public sources
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
6/34
Wind Development SROPTTC Site
Initial siting requires an assessment of many critical issues, some ofwhich are identified in other aspects of the SROPTTC process:
Access to transmission Removed from population centers Limited environmental impact Roads and other infrastructure
Areas with land slope less than 20% and good access Limited visual, sound, cultural heritage impacts
Sites have been identified that could support wind development: St. CroixRidges to the south west of Christiansted, in the
agricultural land on the southern coast or east of the refinery
St. ThomasSeveral potential but Bovoni Point most appropriatebased on initial screening
St. JohnNo currently viable sites identified
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
7/34
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
8/34
Identified Locations for Potential Development
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
9/34
Siting Bovoni Point, St. Thomas
Currently used for various public and private generally industrial useswith residences primarily along Route 30
No identified near or long-term conflicting uses on largely private lands
Access to 13.8-kVA transmission and about 2 miles from the East End
Substation
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
10/34
Wind Development SROPTTC Resource
Long-term data demonstrates wind resource for economically viablewind development in the USVI and is likely bounded by recordedairport and satellite-based SSMI data
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
11/34
Wind Development SROPTTC Resource
Site-specific measurement tower and SODAR-based resourceassessments being undertaken to help further understand the
available wind resource and its characteristics
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
12/34
Resource Bovoni Point St. Thomas
Virtual Meteorological Mast (VMM) data obtained from AWS
TruePower to allow initial assessment of potential windVMM data developed from global atmospheric models, surface
observations, satellite observations, and weather balloon data
6.3 m/s annual average with +/- 0.8 m/s accuracy, largely due tothe absence of wind shear data above 30m height
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
13/34
Resource Bovoni Point St. Thomas
Similar in nature to other locally observed wind data
Very directional datagood for turbine spacing
Consistent winds exceed 5.0 m/s for 70% of the timegood forpower quality
Diurnal profile indicates stronger winds early morning through noon
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
14/34
Illustrative Site Layout Bovoni Point St. Thomas
Illustrative layout of potential ~12 MW wind farm at Bovoni Point
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
15/34
Comparative Estimated LCOE Bovoni Point
Initial estimate of LCOE for potential wind development, includingcurrent federal incentives but excluding detailed integration andsystem balancing requirements
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
16/34
Wind Development SROPTTC Off-Takeand Capital
For utility wind development, WAPA is the only viable off-taker in theabsence of an interconnection to Puerto Rico
Two ownership options exist:
WAPA owner/operator through contracted development Project conducted on WAPA balance sheet Likely disqualified from federal incentives Access to federal low-cost loans Would require a new bond issuance for up to $40 million
WAPA conducts Power Purchase Agreement (PPA): WAPA does not own infrastructure, thus IPP shoulders most risks Method used for solar PV development Common model used throughout U.S. for wind development Able to take advantage of PTC and other federal incentives Typically treated as a liability on a utilitys balance sheet Likely higher capital cost due to higher risk, likely leading to higher
overall power costs
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
17/34
Wind Development SROPTTC Permitting
Many federal, territorial, and local permits usually apply to wind projects
AirspaceFAA, DoD, and other agencies Clean WaterActEPA Coastal resource reviewU.S. Army Corps of Engineers, Council on
Environmental Quality, U.S. Coast Guard National historic preservation (location and character of place)
Impacts to wildlife, including birds, bats, and marine mammalsF&Wand DPNR
If a federal nexus occur, compliance with the National EnvironmentalPolicy Act (NEPA) is also necessary
Coastal management and/or marine spatial planning
Territorial zoning and planning (at the territorial or local level), whichincludes safety setbacks, noise, and construction issues
The key is early, frequent, and supportive engagement with all potentialregulatory organizations.
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
18/34
Wind Development Environmental Impact
Every form of development has impact
Impacts on isolated islanded communities can be more problematicdue to threatened species, more limited habitat that is already highlyfragmented, and increased local stress
Pre- and post-construction impact assessments can greatly reducepotential impacts
Many impact mitigation strategies have been identified toreduce impact
Early consultation with U.S. Fish and Wildlife and DPNR willbe critical
Although no threatened species have been identified at Bovoni Point, fullassessments should be conducted to identify concerns, such as potentialimpacts on the mangrove swamp east of the area
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
19/34
Wind Development Public Acceptance
The general publicincluding residents in the USVIare relatively
supportive of wind power, assuming it is appropriately implementedwith community involvement. Wind projects, however, will havecommunity impacts:
Visualturbines will be seen; the impacts on the community,including, tourism must be considered
Noiseturbines create noise which can impact homes
Flickerthe shadow caused by turbine blades
All of these items should be analyzed as part of the projectdevelopment process in close collaboration with the local and islandcommunity
There is a great deal of misinformation available about wind energy(especially on the Internet)open dialog based on trust and progressto mutual goals is important to foster a successful project development
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
20/34
Key to Public Acceptance Good Information
Common wind myths
Wind energy is more expensive than conventional
energy Wind energy requires huge government incentives to
achieve these economics
Its being forced by an overreaching government
The economic benefits of wind energy arent local
Wind energy is unpredictable and must be backed
up by conventional generation.
If wind energy displaces energy from existing fossilfuel plants, then rates will go up
Wind projects will negatively affect my propertyvalues
Large, utility-grade wind turbines cant be installed onthe distribution grid without expensive upgrades andpower-quality issues
Projects with fewer turbines, that might be suitable forco-ops or small municipal utilities, are not economical
Wind turbines kill birds and bats and fragment habitat
Sound from wind turbines is annoying and will disruptsleep; it may also cause health impacts
The general issue:
As with most things, there are strong beliefs on
the wings of every issue and a large quietmajority that is open to learning. The question ishow to engage the middle majority effectively,providing credible and respectful information
The NIMBY myth:
The concept of NIMBY is rather outdated andgenerally does not capture all of the complexity
of the social issuesThe discussion is not even:
Most people (news organizations and others)want to provide a balanced perspective, even ifthe number of people representing the differentviews is not even (Fox Island Maine: only 26 outof 499 respondents have a negative view since
installation, according to the Island Institute)The key:
Open, clear, and informed dialog in anatmosphere of trust and mutually agreedpurpose
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
21/34
Public Acceptance Bovoni Point Visualizations
Areas where the hub of the turbine is likely to be visible in the absenceof tree or other local obstructions
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
22/34
Public Acceptance Bovoni Point Visualizations
Using the WindProsoftware, visualizations were completed usingphotographs from several locations likely to have direct views of the
turbine sites. These were conducted with different turbine types and sizes.
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
23/34
Public Acceptance Bovoni Point Visualizations
Visual simulation of a six-turbine project (~12 MW) from Water GateRoad (Point E)
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
24/34
Public Acceptance Bovoni Point Visualizations
Visual simulation of a six-turbine project (~12 MW) from Bolongo Bay(Point F)
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
25/34
Public Acceptance Bovoni Point Visualizations
Visual simulation of a six-turbine project (~12 MW) from close to VirginIslands Ecotours on Rt. 32 (Point H)
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
26/34
Public Acceptance Bovoni Point Noiseand Flicker
Noise, safety, and flicker impacts of turbines are assessed with setbackstandards and computer simulation
Although there are no typical distance standards defined for noise andflicker, the above figure shows a 1,500-ft radius around a purelyhypothetical turbine layout
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
27/34
Wind DevelopmentSROPTTC Technology
Utility-scale wind technology is commercial and generally highlyregulated (IEC 64000), although many regulations are voluntary and
not all turbines have gone through testing
IEC type certification defines turbines based on the loads expectedunder certain conditions:
Class I - 10 m/s annual average, Class II - 8.5 m/s, andClass III - 7.5 m/s
Turbine class relate to annual average wind speed, siteturbulence, and maximum wind speedall three should helpdictate turbine choice
Type certification does not account for extreme events, such ashurricanes, cold and hot climates, which must receive special
consideration
In island settings other issues will all determine turbine applicability
Size and quality of port and local lifting capabilities
Available space for installation and equipment laydown
Size, quality, and steepness of roads Ability of the turbines to provide grid support services
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
28/34
Wind Development Hurricane Considerations
Hurricanes have a potential to greatly
impact wind projects in the USVIfinance and insuring a wind turbineon Bovoni Point are expected todepend on the individual designstandards of specific original
equipment manufacturers Vestas and Vergnet offer anti-
cyclonic technical enhancements
Enercon has a history of installingturbines in extreme climates
Existing projects in Jamaica, Cuba,and Aruba all indicate that projectscan be installed and insured
ReturnPeriod(years)
Extreme WindSpeed(mph)
50 130
100 143
700 167
1700 176
Bovoni Point extreme wind speedsand period of return
Vergnet1-MW HP
turbine with
lowering huband generator
Photo fromVergnet Eolien
LLC
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
29/34
Wind Development Bovoni Point Logistics
Lift and road requirements will be dependent on turbine selection
Crown Bay Cargo Port would seem to be an obvious potential off-loadingpoint but requires extensive road upgrades
Other options include:
Beach-side drop point,likely in the vicinity of
Bovoni Bay Red Hook Bay
But would requireequipment staging andthe use of ship-based
crane supportInstallation crane andlocal access will also berequired but are not seenas major roadblocks
Possible equipment drop points and overlandtransport routes, including likely problem turns
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
30/34
Wind Development Wind Integration Concerns
Reliable power system operation
requires balance between load andgeneration within acceptable statisticallimits
Output of wind plants cannot becontrolled and scheduled with high
degree of accuracy Larger wind plants on Isolated grids
have measurable impact on systemoperating cost
System operators concerned thatadditional variability introduced bywindplants will increase systemoperating cost
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
31/34
Wind Development Grid Integration
Integration of high contributions of renewables into the St. Thomas and St.Croix grids will require careful consideration, especially at higher contributions
Studies have looked at several options including integration into the PuertoRico grid Steady-state and short-circuit analysis by Siemens did not reveal major
issues that can prevent incorporating the renewable resource Dynamic stability studies conducted by Siemens confirm that careful
consideration of grid impacts will be required at higher renewable energycontributions absent a PR interconnection
Careful turbine selection and the potential use of energy-smoothingtechnologies will need to be used at higher wind contributions
Further studies when turbine selection is ongoing will be required
Contribution 10% 20% 30% 40%
Resource Wind PV Wind PV Wind PV Wind PV
St. Thomas 8 MW 3 MW 16 MW 6 MW 25 MW 8 MW 32 MW 12 MW
ST. Croix 5 MW 2 MW 10 MW 4 MW 15 MW 6 MW 20 MW 8 MW
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
32/34
Wind Development SROPTTC Team
As there are no utility-scale wind power projects currently in operation
in the USVI, it is likely that the most efficient means of completing awind power project will involve some level of external expertise from acompany already engaged in wind power development in the UnitedStates or elsewhere in the world
Leveraging the experience of a developer who has worked in other
island locales may bring additional relevant capability to the projectteam; however:
Close coordination with VIEO and WAPA and will be required
Significant local leadership and actions will be required
Potential activities to reduce project risk (and thus PPA price) include:
Resource assessment (1-year site and high-speed resource data) Open public acceptance dialog facilitated by the EDIN-USVI working
groups
Initial investigations: environmental impact , grid integration,logistics, geotechnical, and land ownership
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
33/34
Summary of Wind in the U.S. Virgin Islands
SROPTTC analysis indicates several good locations on St. Thomas andSt. Croix for expanded wind development
Installations in Jamaica and Aruba demonstrate other commercially viablewind project developments in the Caribbean
Estimated LCOE is in the range from roughly $0.10/kWh to $0.20/kWh
Bovoni Peninsula/Point on St. Thomas has been identified as a very likelylocation for initial development of a multi-MW wind installation
Although the SROPTTC process identified several key local challenges, theinitial critical flaw analysis was positive, with key issues remaining:
Local infrastructure development needs including roads, offloading, andother civil work
More detailed resource data collection
Community acceptance, including visualization, noise, quality of place,
and flicker Integration into the local distribution infrastructure
Selection of turbines, including consolidation of all system requirements
Development of a commercially viable financing and team approach tobring project to fruition
-
7/31/2019 U.S. Virgin Islands Wind Energy Update, EDIN-USVI Energy Workshop, 6-2012
34/34
Carpe Ventem
(303) 554 6230
mailto:[email protected]:[email protected]:[email protected]:[email protected]