US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term
US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source TermAsian ISOE ALARA SymposiumTokyo, JapanAugust 26-27 2013
Asian ISOE ALARA SymposiumTokyo, JapanAugust 26-27 2013
Paper Data Contributors:R. Hite, AEP DC Cook C. Hardee, Exelon Peach Bottom-2,3P. Skinner, FPL Turkey Point Dr. D. Miller NATC, AEP DC Cook
Presented by:Patricia J. Robinson, (n,p) Energy, Inc.
![Page 2: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/2.jpg)
Presentation Outline
“Ideas that Inspire” TED Talks Website Focus On the “Right” Problem For Radiation
Source Term Challenge the Status Quo
Value of Reducing Radiation Source Term BWR Bad Case Study PWR Good Case Study
Results & Return on Investment Opportunities Reduce Critical Path Dose Reduction
![Page 3: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/3.jpg)
TED Talks:“ Ideas Worth Spreading”Simon Simek, On Inspired Leadership
TED is a nonprofit devoted to Ideas Worth Spreading. New Knowledge to Inspire Us. TED.com talks 18 min or less
“Leaders” versus “Those Who Lead” Leaders hold a position of power and authority Those Who Lead, Inspire Us. We follow those
who lead, not because we have to but because we want to.
Those who start with “Why”, Inspire those around them and find others who Inspire them.
Those who challenge “Status Quo” or “Accepted Condition” produce better results.
![Page 4: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/4.jpg)
TED Talk: Femtosecond Photography of Scattered Packet of Light – Photon 3:52
![Page 5: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/5.jpg)
Here’s What I Believe…
I believe in Radiation Protection as my Professional, and Ethical responsibility for health
and safety of Nuclear Power Plant workers. I am one of them.
I believe ALARA As an important guiding directive, because we don’t
know everything about radiation health effects
![Page 6: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/6.jpg)
It is Not Just Cancer Induction Risk Anymore Radiation Induced Cardio Vascular Damage from Low Dose Ionizing Radiation Lens of Eye Damage
Why Reduce Radiation Exposure? New Research
![Page 7: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/7.jpg)
Here’s What I Believe…
I believe in challenging “Status Quo” or Accepted State … because there are risks associated with
complexity, uncertainty and foremost, complacency.
Ted Talks Have Clarified that “New Knowledge” Inspires Me
I believe in Diverse Scientific Collaboration, Because many inspired minds, Can Manage
Complexity, Uncertainty, and Complacency “New Knowledge” on How to Reduce and Sustain Low
Dose Rates
![Page 8: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/8.jpg)
How do you Reduce Plant Radiation Source Term?
Reduce Source Term by 1) Reducing CRUD on Fuel and 2) Reducing CRUD In Primary Circuit
Sounds Simple --- But The Solution Required a “Challenge to the Status Quo”
New Engineered Solution and New Invention
Nuclear Fuel --Before Nuclear Fuel -After
![Page 9: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/9.jpg)
What is/was the “Status Quo” to Controlling Source Term
Belief… if we: Control Cycle Chemistry Control Cycle Corrosion Rates
Elevate pH Inject Zinc to Reduce Corrosion Rates Remove/Replace Materials with Lower
Corrosion Rate Materials, or No Stellite Use Ion Exchange Resin and Small Size RCS
Filters, 0.1 um for Coolant Purification Then Source Term will Decline Well…. That just didn’t happen
![Page 10: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/10.jpg)
Challenge to “Status Quo”
What we learned, about Reducing Source Term: You do NOT need to elevate pH
and risk increase in Primary Stress Corrosion Cracking You do NOT need to inject zinc,
and increase risk of fuel failures and risk increasing CRUD trap dose rates e.g. elbow,
valve, pump, HX and providing no mitigation of crack growth
You do NOT need to replace materials for lower general corrosion rate, it causes no harm, just expensive There is value in replacement of materials for crack
initation and growth, but that’s not source term action. If you understand the problem, then you can solve
Solve Source Term problem.
![Page 11: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/11.jpg)
We Learned 1 More Thing….…. You Cannot Be Complacent in Rx Operations
BWR Refueling Outage 2013 Failed at Shutdown to Maintain Reactor Water
Clean-Up (RWCU) Filter Demineralizers in Service Cavitated RWCU Pump Deposited Activity Everywhere Very High Smearable Contamination, and Dose
Rates Worse… Created Opportunity to Make Source
Term Conditions Really Bad through operational mistakes
Watch This…
![Page 12: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/12.jpg)
Vented RHR Heat Exchanger Through The Nuclear Core
![Page 13: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/13.jpg)
We Learned 1 More Thing….…. You Cannot Be Complacent in Rx Operations
Result on Cavity Dose Rates: 1- 2 mR/hr, 0.01 mSv- 0.02 mSv/hr 300- 400 mR/hr, 3-4 mSv/hr 300% increase
Final Cavity Decontamination Added 16 hours of Critical Path Time 7 REM of Additional Outage Exposure
Engineered Solution Includes: Right Technology Applied the Right Way
Right Operational Sequence
![Page 14: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/14.jpg)
To Reduce Source Term, You Must Manage Cold Shutdown Transport of CRUD
![Page 15: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/15.jpg)
Shutdown CRUD Composition Is Hard to Define and Variable…. …. But Easy to Removal from Coolant
If… you know what your doing
The Invention of PRC-01M Resin Combines All 3, Ion Exchange, Filtration and Colloid Polymer Filtration into 1 Technology Advancement
Ion Exchange
RCS Filter
Not Removed
![Page 16: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/16.jpg)
Collaboration
Los Alamos National Laboratory (LANL) Scientists Acquired a New Chemical Separation Science,
known as “Polymer Filtration” Engineered that Science Into a Product That Can be
Used in Nuclear Power Plant Purification Systems BWR: Reactor Water Clean-Up, Condensate
Polishers PWR: Chemical and Volume Control System
Demineralizers Partnered with NPP to Evaluate and Implement
Engineered Solution PRC-01M Resins Developed by LANL in Chemical
and Volume Control System During Shutdown Team Worked to Improve Shutdown Process
![Page 17: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/17.jpg)
Benchmark: Technology Innovation Used Correctly, Key to Success
Two Part Engineered Solution: Shutdown/Start-Up Protocol New Technology, PRC-01M
PWR Deep Bed Demineralizers
BWR RWCU Filter/Demineralizers Condensate Polishers Deep
Beds
Conventional
Mixed Bed
Resin-HOH
PRC-01 PRC-01
MediaMedia
PWR/BWRDeep Bed Vessel
![Page 18: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/18.jpg)
NPE Engineered Solution at USA, Mexico and CanadaPWR …120+ Refueling OutagesBWR …. 35+ Refueling Outages
= LEAD PLANTS
VC Summer
St Lucie 1,2
Turkey Point 3,4
MonticelloMonticello
Beaver Valley-1,2
DC Cook-1,2
Peach Bottom-2,3Peach Bottom-2,3
Pat-San LivesHerePat-San LivesHere
Braidwood-1,2Braidwood-1,2
Laguna Verde-1,2MexicoLaguna Verde-1,2Mexico
Davis BesseDavis Besse
9 Mile Pt-1,29 Mile Pt-1,2
Perry-1Perry-1 TMI-1TMI-1
![Page 19: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/19.jpg)
PWR Case StudyHow Source Term Reduction Reduced Outage Critical Path TImeTurkey Point-3,4
PWR Case StudyHow Source Term Reduction Reduced Outage Critical Path TImeTurkey Point-3,4
![Page 20: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/20.jpg)
FPL 1st Integration 13 years Ago#1 Turkey Point 3/2000, #2 St Lucie-1 4/2000 # 3 VC Summer
Pat-San
PRC-01
![Page 21: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/21.jpg)
Turkey Point-3,4 Source Term Approach
Turkey Point 3,4: Yes: U3R18 Chemistry pH(t) = 6.9 Modified Yes: PRC-01 Media Technology No: Zinc, No Fuel Cleaning, No Elevated pH
7.2 to 7.4 Fuel Duty: Middle Fuel Duty 13 to 18 EFPY SG, Inconel 600 TT
![Page 22: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/22.jpg)
FPL Turkey Pt-3R18 (1st PRC)RCS Shutdown Co-58100 hrs to Clean-Up Goal
Turkey Poin t U3Shut down Co-58 U3 R18 (1 st PRC ) and R2 1 (4th PRC)
1. 00E -03
1. 00E -02
1. 00E -01
1.00E +00
1.00E +01
0 1 0 2 0 3 0 4 0 5 0 6 0 7 0 8 0 9 0 1 0 0
Time from S hutdown, [hr]
Co-58, [µCi/cc]
U3R18 FULL RCS
EPRI CL EA N-UP GOAL
1 E-3 uCi/cc = 37 Bq/ cc
Last RCP O/SAfter H2O2T 1/2 = 8 hr.
3.8 uCi/cc; 140600 MBq/m3
Clean-Up Goal: 0.05 uCi/cc; 1850 MBq/m3
![Page 23: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/23.jpg)
FPL Turkey Pt-3 R20 (3rd PRC)Shutdown Co-5870 Hours to Clean-Up Goal
Turkey Poin t U3Shut down Co-58 U3 R18 (1 st PRC ) and R2 1 (4th PRC)
1. 00E -03
1. 00E -02
1. 00E -01
1.00E +00
1.00E +01
0. 00 10. 00 20. 00 30. 00 40. 00 50. 00 60. 00 70. 00 80. 00 90. 00 100. 00
Time from S hutdown, [hr]
Co-58, [µCi/cc]
U3R20 CORE/RHR ONLY
U3R18 FULL RCS
EPRI CL EAN-UP GOA L
YELLOW SY MBOLDENOTES LAST RCP O/ S
Last RCP O/SBefore H2O2T1/2 = 4 hr.
0.8 uCi/cc; 29600 MBq/m3
![Page 24: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/24.jpg)
FPL Turkey Pt-3R21 (4th PRC)Last RCP Off - Before Peroxide InjectionShutdown Co-58 56 Hrs to Clean-Up Goal
Turkey Poin t U3Shut down Co-58 U3 R18 (1 st PRC ) and R2 1 (4th PRC)
1. 00E -03
1. 00E -02
1. 00E -01
1.00E +00
1.00E +01
0. 00 10. 00 20. 00 30. 00 40. 00 50. 00 60. 00 70. 00 80. 00 90. 00 100. 00
Time from S hutdown, [hr]
Co-58, [µCi/cc]
U3R21 CORE/RHR ONLY
U3R18 FULL RCS
EPRI CL EAN-UP GOA L
YELLOW SY MBOLDENOTES LAST RCP O/ S
Last RCP O/SBefore H2O2T1/2 = 4 Hr
0.3 uCi/cc; 11000 MBq/m3
![Page 25: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/25.jpg)
Turkey Point-3, 4 Critical Path Savings by Reducing Radiation Source Term
Sustained Results Critical Path Reduced by 30 Hours EVERY
Refueling out $30,000 USD/ Critical Path Hour $900,000 USD/ Every Outage Unit 3: 3R21, 3R22, 3R23, 3R24, 3R25 Unit 4: 4R21, 4R22, 4R23, 4R24, 4R25
Total Critical Path Savings: $9.0 Million And Still Benefits Accruing
Return on Investment: 6.42 to 1 But…. Did Dose Rates and Outage
Exposure go Down?
![Page 26: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/26.jpg)
Effective Dose Rate Trending
Effective Dose Rate = Total dose for the job (mrem)
Total time for job (hour)
Good Analysis Tool for RFO to RFO Comparison Permits comparison between refueling outages
with different scope of work in containment Valid if shielding practice is consistent Valid if methods are consistent
RWP = Radiation Work Permit
![Page 27: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/27.jpg)
FPL Turkey Pt-3Sustained Decrease in Outage EDROverall Before/After PRC-01 = - 88.4%
Turkey Pt-3 Trend Analysis Total Outage EDR (All RWPS)
5.343
3.6612.975
1.22
0.619
0.1
1
10
U31998 R17 U32000 R18 PRC U32001 R19 PRC U32003 R20 PRC U32004 R21 PRC
EDR, [ RWP Exposure, mR / RWP Hours]
Total Outage EDR
Co-60 Decay Curve
-31%
-18.8%
-59%
-49.3%
![Page 28: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/28.jpg)
Turkey Point-3,4 Summary (cont.)
- 60.0% Reduction in number of High Radiation Area
- 35% Reduction in contract HP staff, $400,000 avoided costs
every RFO. - 76%
Reduction in Hot Spots - 49 X (fold)
Reduction in annual effluent activity discharged for Co-58 and 15 fold for Co-60
- 87.7 % Reduction in Ni-63 annual effluent activity discharge, and
70% for Fe-55 1st World Record Low Dose Performance for U4 in 2005.
5.407 REM (54.07 mSv) U4 RVH 2nd World Record Low Dose Performance for U3 in
2005.
![Page 29: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/29.jpg)
Can Results Be Duplicated at Other Stations?
The Source Term Problem is Never Really Solved, if you cannot duplicate results
Results Follow for: PWR: 3 Loop, VC Summer PWR: 4 Loop Ice Condense, DC Cook-1,2 BWR: Monticello BWR: Vermont Yankee BWR: Peach Bottom-2,3
![Page 30: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/30.jpg)
VC Summer - High Duty CoresCo-58 Peak Reduction- All PRC RFOs
0.06540.0520.0790.151
0.542
2.76
5.7
1.39
0.00
1.00
2.00
3.00
4.00
5.00
6.00
VCS R12 -PRC-01
VCS R13-PRC-01
VCS R14-PRC-01
VCS R15-PRC-01
VCS R16-PRC-01
VCS R17-PRC-01
VCS R18-PRC-01M
VCS R19-PRC-01M
Co-58 , [µCi/cc]
*R12 had 1 peak in AR 2.42 and a second at FO2 3.32 totalling 5.7 µCi/cc.
RCP OOS 16 Hrs Earlier
RCP OOS 24 Hrs Earlier
SUSTAINABLESource Term Reduction
RESULTS
RCP OOS 8 Hrs
Earlier
Duplicated at VC Summer
210900 MBq/m3
1924 MBq/m3
Factor of 100X Reduction
![Page 31: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/31.jpg)
Duplicated at VC Summer- 30 hoursCritical Path Savings from Source Term Reduction
![Page 32: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/32.jpg)
CZT Results - BenchmarksCo-58 SG Hot Leg Piping Deposited Activity
CZT Co-58 SG Hot Leg Pipe Deposition Results[ µCi/ cm2 ]
21.50
48.0045.67
4.91 5.907.78
-
10.00
20.00
30.00
40.00
50.00
60.00
Byron 1R17 Braidwood A1R15 Braidwood A2R15 VC Summer RF19 DC Cook 1C23 Turkey Pt 4R26
Deposted Activity Est, [ uCi/ cm2 ]
Byron 1R17
Braidwood A1R15
Braidwood A2R15
VC Summer RF19
DC Cook 1C23
Turkey Pt 4R26
Exelon Units Benchmark Units
![Page 33: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/33.jpg)
CZT Results - BenchmarksCo-60 SG Hot Leg Piping Deposited Activity
CZT Co-60 SG Hot Leg Pipe Deposition Results[ µCi/ cm2 ]
4.80
4.05
6.60
2.28
1.70
1.20
-
1.00
2.00
3.00
4.00
5.00
6.00
7.00
Plant 4- 4 Loop LISV Plant 1- 4 Loop LISV Plant 6 4 Loop LISV VC Summer DC Cook 1C23 Turkey Pt 4R26
Deposted Activity Est, [ uCi/ cm2 ]
Plant 4- 4 Loop LISV
Plant 1- 4 Loop LISV
Plant 6 4 Loop LISV
VC Summer
DC Cook 1C23
Turkey Pt 4R26
Elevated pH 7.4: Zn Inj: Ortho Macroporous pH 7.1 to 7.2: No Zn Inj; PRC-01M Resin
![Page 34: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/34.jpg)
Effective Source Term ResultsAchieved Through Implemented Proprietary 2 Part Engineered Solution
DC Cook Letdown Heat Exchanger Dose Rate Change U2C14 , U2C19, & U2C20
with NPE/ PRC-01 Engineered Source Term Reduction Solution
49.4
72.8
23.2
0
20
40
60
80
100
120
140
160
180
200
- 10.00 20.00 30.00 40.00 50.00 60.00 70.00 80.00 90.00
Time, [hr]
ED Dose Rate, [mR/hr]
U2C19 ED Dose Rate, (5th PRC-01)
U2C14 ED Dose Rate (Before PRC-01)
Normalized to Time of H2O2
U2C20 ED Dose Rate, (6th PRC-01)
5 per. Mov. Avg. (U2C14 ED Dose Rate (BeforePRC-01))5 per. Mov. Avg. (U2C19 ED Dose Rate, (5thPRC-01))10 per. Mov. Avg. (U2C20 ED Dose Rate, (6thPRC-01))
-32.1% }}- 52.6%
![Page 35: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/35.jpg)
Monticello R22 to R23 ResultsPRC Use R22 RFO, Cycle, R23
April 2007
-28% Decline in BRAC Points Main Circuit Piping- Standardized Locations 2003 to 2007: Declined 28.5 %
-38.5% Decline RPV Effective Dose Rate R22: EDR =1.45 mRem/RWP-hr R23: EDR = 0.89 mRem/RW-hr Change: - 38.5 %
-71.1 % Fuel Floor (Fuel Move/Inspection/CRB Replace) R22: 0.78 mRem/RWP-hr R23: 0.21 mRem/RWP-hr Change: - 71.1 %
![Page 36: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/36.jpg)
Vermont Yankee R25 to R26 ResultsPRC Use R25 RFO, Cycle, R25May 2007
-28% Decline in A Recirc Suction Main Circuit Piping- Standardized Locations 2005 to 2007: Declined 28.5 %
-48.% Decline IVVI RWP Dose 16.76 REM Planned IVVI RWP Dose 8.172 REM Actual IVVI RWP Dose Declined: -48%
-43.4 % Drywell RWP Dose 21.21 REM Planned RWP Drywell Dose 12.0 REM Actual RWP Drywell Dose
![Page 37: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/37.jpg)
Peach Bottom 2, 3
Peach Bottom 3R 15 and 2R16 Drywell Dose Rates Reduced Permited Drywell Down Post from Locked High
Radiation Area to High Radiation Area Support Outage Performance
Platform Post Removal Dose Rate 20 to 30 times Lower Dose Rate (when Benchmarked to Limerick-1)
Platform Contamination Levels 1000 times lower smearable contamination (when Benchmarked to Limerick-1)
PBAPS 3R17: Station Low Dose Record Achieved PBAPS 2R16: Station Low Dose Record Achieved
![Page 38: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/38.jpg)
Summarizing “Why” Reduce Source TermInitiative Value Proposition
Radiation ProtectionCollective Radiation Exposure ReductionFull Spectrum of Impact: Reduced…
Dose Rates, Contamination Levels, Hot Particles, Number of Locked High Radiation Areas
Component Reliability and Fuel Performance ImprovementReduces Root Cause for Stage #1 Seal Reactor
Coolant Pump (RCP) leak rateDecreases ….. CRUD Induced Power Shift (CIPS)
Margin Reduced Crud on fuel, improves Fuel Reliability (CILC)Less Curies Generated and Available for Transport
(CRUD)
![Page 39: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/39.jpg)
Summarizing “Why” Reduce Source TermInitiative Value Proposition
Increase Outage PerformanceCritical Path Time Reduced Incremental acceleration of every small task
interfacing with RP Controls Address Stakeholders: INPO-WANO/ Regulatory
Risk/ Public INPO/WANO RankingsNRC: CIPS Margin Improved, Risk Reduction RP
Related Violations Reduce Environmental Effluents (Radwaste)
Liquid Effluents -- Less Discharge of Curies --Solid Waste-- Less Filters, Less Curie Surcharge,
Less Costly Options for DisposalStakeholder Impact
![Page 40: US PWR and BWR Experience in Reducing Critical Path, by Reducing Radiation Source Term Asian ISOE ALARA Symposium Tokyo, Japan August 26-27 2013 Asian](https://reader038.vdocuments.site/reader038/viewer/2022103101/56649f345503460f94c5196b/html5/thumbnails/40.jpg)
Thank You Very Much for Your AttentionThank You Very Much for Your Attentionご清聴ありがとうございました