u.s. army corps of engineers regulatory program regulatory program

20
U.S. Army Corps of U.S. Army Corps of Engineers Engineers Regulatory Regulatory Program Program

Upload: melanie-oleary

Post on 27-Mar-2015

228 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

U.S. Army Corps of EngineersU.S. Army Corps of Engineers

Regulatory ProgramRegulatory Program

Page 2: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Regulatory Authorities• Section 10 of the

Rivers & Harbors Act of 1899– Structures and work in

navigable waters of the United States

• Section 404 of the Clean Water Act– Discharge of dredged or

fill material and mechanized landclearing in all waters of the U.S., including wetlands

Page 3: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Section 10 of the Rivers and Harbors Act of 1899

Regulated Activities

Work in Navigable Waters of the U.S. (Lake Champlain, Lake Memphremagog, and major rivers in VT)

-Dredging-Structures in, over, or under a navigable waterway

-Private docks-Water intake lines-Aerial transmission lines-Submarine cables-Marinas

Page 4: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Section 404 of the Clean Water ActRegulated Activities

Any activity that would involve the permanent or temporary placement of dredged or fill material into any waterway or wetland, including:

- Pond construction- Mechanized landclearing- Landscaping -Land Development (i.e., housing, commercial, industrial, etc.)- Cofferdams

Page 5: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Section 404 of the Clean Water Act

Regulated Activities

- Roads, culverts, bridges- Bedding and backfill for utility lines- Shoreline stabilization-Sidecasting of material from excavation of new drainage ditches- Installation of drainage tile

Page 6: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Forms of Authorization

• VT General Permit– Minimal Impact Projects – impacts

not to exceed one acre• Individual Permit

– Projects with greater than minimal impacts or in excess of one acre of impact

South Bay, Lake Memphremagog, Newport, VT

Page 7: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

VT General PermitMinimal Impact Projects

•Direct/Indirect Impacts under 3000 sq. ft.

–Project May Proceed without Notification to Corps Provided Terms & Conditions of VTGP have been met

•Direct/Indirect Impacts from 3000 sq. ft. to one acre

–Notification to Corps Required

•Determination of Eligibility for VT GP usually within about 30 days

Batten Kill, Arlington, VT

Page 8: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

REMEMBER!!!

- VT GP is only used to authorize projects that will have a minimal individual and cumulative impact on the aquatic environment.

- Project can have a “good” impact and not meet the minimal threshold.

- A project with less than 3000 sq. ft. of impact can have more than a minimal impact and be ineligible to proceed under the VTGP.

Page 9: U.S. Army Corps of Engineers Regulatory Program Regulatory Program
Page 10: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Information Required for VTGP• Wetland Delineation

• Data sheets to support wetland delineation

• Brief description of wetland functions and values

• Plan, drawn to scale, showing property boundaries, wetland boundary and area of proposed impact(s)

• Grading plan (as appropriate)

• Narrative description of the project including area (in sq. ft.) of proposed direct and indirect impacts

Page 11: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Individual Permit

- Projects with direct/indirect impacts to waters of U.S. in excess of one acre- Projects which do not meet the criteria of the VT GP

Page 12: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Pre-Application Meetings

Joint site visit with Corps, VT DEC, USEPA and USF&WS

- Flushes out major concerns prior to investment of time and money in permit process

- Can result in recommendations for project modifications to minimize impacts to waters of the U.S. and facilitate permit issuance

Page 13: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Information Required for Individual Permit

• Wetland Delineation

• Data sheets to support wetland delineation

• Narrative describing wetland functions and values

• Completed Application Form (ENG 4345)

• Plan, drawn to scale, showing property boundaries, wetland boundary and area of proposed impact(s)

• Alternatives analysis

Page 14: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Alternatives Analysis

• Only the Least Environmentally Damaging Practicable Alternative (LEDPA) to accomplish the basic project purpose can be permitted

Page 15: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Alternatives Analysis/Mitigation Sequencing

AVOID impacts to waters of the U.S. to the maximum extent practicable (off-site alternatives analysis; leads to LEDPA site)

MINIMIZE impacts to waters of the U.S. (at the LEDPA site) to the maximum extent practicable

MITIGATE for the unavoidable impacts of the project

Page 16: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

That’s your crash course on the Corps’ Regulatory Program.

Page 17: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Vermont Project Office

Current Responsibilities, Staffing and Resources

Page 18: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Responsibilities• Administration of Corps of Engineers

Regulatory Program in VT– Section 10

• Navigable Waters of the U.S. = Lake Champlain, Lake Memphremagog and Major Rivers

– Section 404• All wetlands• Non-Section 10 lakes and ponds• Non-Section 10 rivers and stream up to the

headwaters

Page 19: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Responsibilities

• Administration of Regulatory Program includes:– Jurisdictional determinations– Processing VT GP’s – Processing individual permits– Investigation of alleged unauthorized work– Compliance inspections of work under

permits– Public outreach

Page 20: U.S. Army Corps of Engineers Regulatory Program Regulatory Program

Staffing/Resources

• Based at VT Project Office– Two Full-Time Senior Project Managers– One Full-Time Legal Instrument Examiner

• Based at District Office in Concord, MA– Branch Chief – Division Chief– Environmental Resource Unit Staff– Office of Counsel