modified charleston method (mcm) brenda a. archer, regulatory program u.s. army corps of engineers,...

24
Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Upload: jesus-blaisdell

Post on 15-Dec-2015

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Modified Charleston Method(MCM)

Brenda A. Archer, Regulatory Program

U.S. Army Corps of Engineers,

New Orleans District (CEMVN)

Page 2: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

What is the MCM?

Page 3: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Modified Charleston Method (MCM)

An Assessment Methodology for evaluating

unavoidable wetland impacts associated with Section 404 Clean Water Act permits and

projects that are proposed as mitigation for those unavoidable impacts

Page 4: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

MCM – Conditional Assessment Model

Measures wetland functional loss indirectly by

considering the quality of wetland functions of the impacted site weighed against

the perceived increases of wetland functions of the mitigation project.

Evaluates only the site as it exists at the time of evaluation.

Page 5: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

History of the MCM

Page 6: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Regulatory was tasked with developing an assessment model that: Produced comparable mitigation

requirements as other Corps Districts in Louisiana and

Promoted consistency among New Orleans District regulatory project managers with diverse backgrounds

Page 7: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Interagency Review Team

Federal and state resource/regulatory agencies involved in the decisions for the assessment model included:

US Environmental Protection Agency US Fish and Wildlife Service National Marine Fisheries Service Louisiana Department of Wildlife and

Fisheries Louisiana Department of Natural

Resources, Office of Coastal Management

Page 8: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Modified Charleston Method

The Charleston Method was developed by the Charleston District in collaboration with an Interagency Review Team in that District; Used by Vicksburg District

Provides comparable mitigation requirements from the other Districts adjacent to the New Orleans District.

After minimal training and practice, project managers are able to easily apply the method with a minimal about of field data collection and a high degree of consistency.

Allows unlimited mixing of mitigation locations, and types (e.g. restoration, preservation, enhancement).

Allows mixing of mitigation banks and permittee-responsible mitigation projects.

Page 9: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Modified Charleston Method (conti-)

• Only required slight modifications for it to be used in the New Orleans District. These modifications were to account for

• Regional wetland differences• CEMVN Mitigation Standard Operating

Procedures• 33 CFR 332: New Mitigation Rule

Page 10: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Who can use the MCM?

Page 11: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

MCM Operators

CEMVN permit and mitigation bank project managers for Section 404 CWA permits including restoration and/or enhancement projects

Applicants/agents to estimate the amount of mitigation that will

be required to compensate for various project scenarios (avoidance and minimization), and

to compare mitigation options

Page 12: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

How does the MCM work?

Page 13: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

MCM Factors

MCM evaluates a suite of factors that are used to assess the potential of the site to perform wetland functions.

A factor is an element, circumstance, or influence which contributes to the overall quality of the site.

Each factor is defined by a list of options that qualify the factor based on conditions at the evaluated site.

The functional value of the site is determined by selecting the options that best fit the site conditions for each factor and then summing all the factor values.

Page 14: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

MCM Workbook

MCM workbook is an excel spreadsheet consisting of four worksheets: “Summary Worksheet”, “Adverse Impact Worksheet”, “Mitigation from Bank Worksheet”, and “Proposed Restoration/Enhancement

Mitigation Worksheet”.

Page 15: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

MCM Guidebook

Definitions of terms used in the model Discussions of the use of each worksheet Definitions for each factor and option

associated with that worksheet, and Examples using each worksheet.

Page 16: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

1. Assessment of Adverse Impacts

The model considers;

The habitat rarity or difficulty to replace, Site wetland quality, Work involved and the extent to which that

work will impact wetland functions, Duration of the impact Potential for project to result in cumulative

impacts.

Page 17: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Adverse Impacts Worksheet

Page 18: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

2. Assessment of Mitigation Project

The model considers:

Net improvement Negative impacts on the site that can not be

remediated, Protection type, Temporal loss, Credit availability versus Credit use. Replacement with in-kind/out-of-kind Location of impact versus mitigation.

Page 19: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Restoration Worksheet

Page 20: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

3. Kind and Location Factors

These factors are included when evaluating an permit project with a particular mitigation bank and/or permittee responsible mitigation project

The value for these Factors adjust the required mitigation amount depending upon the degree of variance from the most to least preferred option of in-kind/on-site to out-of-kind/out-of-watershed.

Page 21: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Additional Information

Page 22: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Resource for MCM Guidebook and Workbook

Located in the Regulatory In-Lieu Fee and Bank Information Tracking System (RIBITS)

Go to RIBITS from the following website: https://ribits.usace.army.mil

Once in RIBITS, Choose “New Orleans District” in the lower, left-hand side of the screen and then the “Assessment Tools” tab in the upper, left-hand side of the screen.

Page 23: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

Contact Information

Dr. James A. Barlow, Section Chief

Special Projects and Policy Team

(504) 862-2250 or [email protected]

Page 24: Modified Charleston Method (MCM) Brenda A. Archer, Regulatory Program U.S. Army Corps of Engineers, New Orleans District (CEMVN)

QUESTIONS??