us 12/nine mile hill to frenchtown vic. – build new ...€¦ · bob hooker, pe. south central...
TRANSCRIPT
Bob Hooker, PESouth Central Region Design Project EngineerAugust 20, 2019
US 12/Nine Mile Hill to Frenchtown Vic. –Build New Highway Project
Vo lun ta ry Proposers Mee t ing
Roger Millar, Secretary of TransportationKeith Metcalf, Deputy Secretary of Transportation
Todd Trepanier, South Central Region Administrator
Agenda
• Safety
• Introductions
• Project Overview
• ITP Highlights
• RFP Highlights
• Procurement Schedule
2
Project Overview
3
Location – Vicinity Map
Nine Mile HillMP 317
FrenchtownMP 328
B E G I N P R O J E C T E N D
P R O J E C T
Project Overview
Design and construct a new four lane, divided highway on US 12
4
WSDOT desires a four-lane, divided facility with reduced conflict points
The current road has many slow-moving vehicles and conflict points, resulting in often-hazardous conditions
ITP Highlights
5
Goals
3.3.3 Goal 1 – Safety: Reduce crash frequency and severity
WSDOT desires a Proposal that, at a minimum, provides the following design elements that enhance safety along the corridor by reducing crash frequency and severity:
• Minimizes usage of barrier to maximize obstruction-free Design Clear Zones• Provides traversable slopes and adequate recovery zones• Minimizes or mitigates obstructions/fixed features within clear zones• Maximizes shoulder widths, lateral clearances, and turning roadway widths
Submit: Provide a detailed commitment and description of how and where design elements will be provided to enhance corridor safety by reducing crash frequency and severity. Include plan sheets, location descriptions, and typical sections that demonstrate these design elements.
3.3.3.1 Evaluation CriteriaOf the $6,000,000 of technical credits available for Goal 1, as shown in Table 3.3.8, $2,000,000 will be scored quantitatively and $4,000,000 will be scored adjectively as described below:
Up to $2 Million calculated
Up to $4 Million adjectival
Goal 1 – Calculated Evaluation Example:Commitment of the following obstruction-free Design Clear Zones included in the proposed design in excess of Technical Requirements baseline requirement.30,000 feet EB outside shoulders x $15,000/1,000 feet increments = $450,00025,000 feet WB outside shoulders x $15,000/1,000 feet increments = $375,00030,000 feet EB median x $15,000/1,000 feet increments = $450,00030,000 feet WB median x $15,000/1,000 feet increments = $450,000
Earned Calculated Technical Credits: $1,725,000
ITP Highlights
6
Goals
RECORD OBSTRUCTION-FREE LENGTHS
ON FORM T
3.3.3 Goal 1 – Safety: Reduce crash frequency and severity (continued)
Adjectival Evaluation Criteria:A Proposal that adequately provides each of the minimum design element requirements discussed in Section 3.3.3 will receive a maximal rating in the Very Good range. To get full value, commitments need to be clearly articulated in the Proposal. An approach may receive a higher rating when the Proposal exceeds the applicable design element requirements or provides additional design elements that improve corridor safety. Specific commitments made to achieve this Project Goal will be considered Betterments.
ITP Highlights
7
Goals
8
ITP Highlights
UnobstructedClear Zone
Added safety element to obtain higher adjectival score Quantitatively-evaluated solutions are found in Forms T & U
Curve Alignment (Enhanced)
Curve Alignment(Design Minimum)
GoalsGoal 1 – Safety: Reduce crash frequency and severity
ITP Highlights
9
Goals
3.3.4 Goal 2 – Safety: Accommodates the safe merging and diverging of slower vehicles
WSDOT desires a Proposal that, at a minimum, provides the following design elements that enhance safety along the corridor by optimizing the design for a rural context:• Safely accommodates the merging and diverging of slower vehiclesSubmit: Provide a detailed commitment and description of how and where the Proposal provides the above intersection improvements. Include plan sheets and typical sections that demonstrate these elements.
3.3.4.1 Evaluation Criteria
Of the $3,000,000 of technical credits available for Goal 2, as shown in Table 3.3.8, all $3,000,000 will be scored quantitatively.
ALL $3 Million calculated
Goal 2 – Calculated Evaluation Example:Qualifying proposal commitments that include acceleration and deceleration lanes at the following specified locations will be awarded Technical Credits at the following rate. Technical Credits will not be awarded for partially meeting these criteria:
• $1,000,000 for providing both acceleration and deceleration lanes at Touchet North Road intersection for both EB and WB directions of travel of US 12.
• $1,000,000 for providing both acceleration and deceleration lanes provided at Woodward Canyon Road intersection for both EB and WB directions of travel of US 12.
• $1,000,000 for providing both acceleration and deceleration lanes provided at Lower Dry Creek Road intersection for both EB and WB directions of travel of US 12.
ITP Highlights
10
Goals
RECORD IMPROVEMENTS
ON FORM U
ITP Highlights
11
Goals
3.3.5 Goal 3 – Safety: Provide a safe and sustainable roadway design/operation
WSDOT desires a Proposal that, at a minimum, provides the following safe and sustainable safety improvements along the corridor, but is not limited to:
• Minimizes maintenance needs along corridor (barrier, drainage structures, weed control, etc.)• A design that optimizes life-cycle costs for the long-term maintenance/operation of the highway• Adequate access and pull-outs for maintenance activities
Submit: Provide a detailed commitment, description, and life-cycle cost analysis as applicable for design elements that will be provided to enhance corridor safety, sustainability, or operational efficiency. Include plan sheets and typical sections as applicable to demonstrate these elements.
3.3.5.1 Evaluation CriteriaOf the $2,000,000 of Technical Credits available for Goal 3, as shown in Table 3.3.8, all $2,000,000 will be scored adjectivally.Adjectival Evaluation Criteria:A Proposal that adequately provides each of the minimum design element requirements discussed in Section 3.3.5 will receive a maximal rating in the Very Good range. To get full value, commitments need to be clearly articulated in the Proposal. An approach may receive a higher rating when the Proposal exceeds the applicable design element requirements or provides additional design elements that improve corridor safety. Specific commitments made to achieve this Project Goal will be considered Betterments.
ITP Highlights
12
Goals
3.3.6 Goal 4 – Community Engagement: Impacts to Project Stakeholders
WSDOT desires a Proposal that, at a minimum, provides the following items to proactively identify and address potential Project Stakeholder impacts and risks for each potentially affected stakeholder.
Submit: Provide the following detailed table, plans, and schedule:• A Project Stakeholders Table that includes, at a minimum:
– Residents in the communities of Touchet and Lowden, wineries and local businesses– Adjacent property owners and farming operations in areas surrounding the Project. – Impacted utilities and irrigation districts– Traveling public
• Impact mitigation plan/strategies• Preliminary schedule for impacts to critical path activities may occur, and mitigation strategies
3.3.6.1 Evaluation CriteriaOf the $300,000 of Technical Credits available for Goal 4, as shown in Table 3.3.8, all $300,000 will be scored adjectivally.
Adjectival Evaluation Criteria:A Proposal that adequately provides each of the minimum requirements discussed in Section 3.3.6 will receive a maximal rating in the Very Good range. To get full value, commitments need to be clearly articulated in the Proposal. An approach may receive a higher rating when the Proposal exceeds the applicable design element requirements or provides additional design elements that improve corridor safety. Specific commitments made to achieve this Project Goal will be considered Betterments.
ITP Highlights
13
Goals
Goals 4 & 5 – Community Engagement: Working with Project Stakeholders
Various project stakeholders WSDOT has identified – wineries, small businesses, farmers, local residents, etc.
ITP Highlights
14
Goals
3.3.7 Goal 5 – Community Engagement: Approach to working with Project Stakeholders
WSDOT desires a Proposal that, at a minimum, provides a proactive approach and communication plan to communicate identified impacts and risks with Project Stakeholders and the community.
Submit: Provide a detailed Project Stakeholder Communication Plan and commitments detailing your plan to engage the community and mitigate impacts to project stakeholders including the following:
• Details which project staff and how frequently staff will participate in community engagement/Project Stakeholder communication activities
• Describes how you will communicate project updates and upcoming impacts to project stakeholders• Discusses your plan to actively retrieve feedback/input from project stakeholders• Describes how you will collaboratively coordinate public updates and outreach with WSDOT
3.3.6.1 Evaluation CriteriaOf the $200,000 of Technical Credits available for Goal 5, as shown in Table 3.3.8, all $200,000 will be scored adjectivally.Adjectival Evaluation Criteria:A Proposal that adequately provides each of the minimum requirements discussed in Section 3.3.7 will receive a maximal rating in the Very Good range. To get full value, commitments need to be clearly articulated in the Proposal. An approach may receive a higher rating when the Proposal exceeds the applicable design element requirements or provides additional design elements that improve corridor safety. Specific commitments made to achieve this Project Goal will be considered Betterments.
ITP Highlights
15
Goals
A Communication Plan is key in effectively engaging & working with Project Stakeholders – a critical WSDOT emphasis
ITP Highlights
16
Goals – Technical Credits
TOTAL OF $11,500,000 IN TECHNICAL CREDITS AVAILABLE
RFP Highlights
Basic Configuration - The following required elements shown in the Conceptual Plans, Pre-Approved Design Analyses, or both as such elements may have been modified (with WSDOT’s permission) in the Proposal:
• Number and width of proposed US 12 roadway lanes and shoulders (12-foot min. lane, 10-foot min. right shoulder, 4-foot min. left shoulder)
• US 12 divided multilane highway that is physically separated (barrier/median)• US 12 Grade-separated intersections that provide full access to the following roads:
Touchet North Road, Woodward Canyon Road, and Lower Dry Creek Road.• US 12 eastbound intersection that provides eastbound access to and from existing US
12 at Nine Mile Hill intersection.• Right-turn pockets on mainline US 12 at Nine Mile Hill, Touchet North Road,
Woodward Canyon Road, and Lower Dry Creek Road intersections• Right of Way and Area Impact Line limits • Limited Access Classification• Design speed of US 12 (70 mph)• Existing highway removal• Number and location of US 12 median crossovers (2)
17
Chapter 1 – General Provisions
Kennewick
RFP Highlights
• Co-location of WSDOT project staff and Design-Builder project staff is required.
• The Design-Builder’s DesignProject office shall be located within 5 miles of the WSDOT Richland Project Engineering Office
18
Chapter 2.1 – General Information
5 miles5 miles
CO-LOCATION ZONE
Richland
Pasco
WSDOT RICHLAND PEO
PE – ALEX SANGUINO
RFP Highlights
19
Chapter 2.8 – Environmental
DESIGN-BUILDER OBTAINED
Structure identified containing ACM
RFP Highlights
• Touchet River has a net-zero rise requirement due to Walla Walla County Shorelines Permit requirements.
• Conceptual design incorporates a 1000 ft. bridge and minor grading to provide net-zero rise in base-flood elevation.
• No work in riparian areas
• No in-water work is permitted
• NPDES Permit is to be obtained by the Design Builder
20
Chapter 2.8 – Environmental Key Points
Riparian zone surrounds the Touchet River in the project area
STAY OUT OF THE WATER!
RFP Highlights
21
Chapter 2.10 – UtilitiesContinue for further explanation…
RFP Highlights
22
Utilities
Any previously identified utilities are found in the Existing Utility Listing (Appendix U)
Completed Relocation• All major irrigation district lines have been
relocated.
Anticipated Relocation• WSDOT is currently coordinating with power,
cable, and fiber companies to relocate prior to NTP.
• Private irrigation relocations will be completed prior to NTP.
Targeted Relocation (pending DB design input)• 4 utility crossings with opportunities for DB
relocation input to minimize constraints Pre-relocation is finished on major district lines as of RFP
Irrigation District Mainline Relocation
RFP Highlights
23
Chapter 2.11 – Roadway
• Work occurring on roadway sections to be relinquished to Walla Walla County shall be constructed according to Walla Walla County Road Design Standards
• Fill slopes no steeper than 3:1 unless protected by barrier
• Total 60,000 ft minimum required obstruction-free Design Clear Zones.
RFP Highlights
24
Chapter 2.13 – Bridges and Structures
Myra Rd. Crossing – Existing US 12 (Phase 6) and example of minimum clearance box
• 12 bridge structures
• Minimum clearance boxes for each crossing details in Section 2.13.4
Y’
X’
RFP Highlights
• Items of note throughout the project:
– Two different water crossings (Touchet River and Dry Creek)
– All hydraulic designs and reports to be completed by the Design-Builder
– Preliminary Hydraulic Design reports are provided for Touchet River and Dry Creek
– Chapters 2.14 Hydraulics and 2.32 Fish Passage –pending WSDOT HQ changes
25
Chapter 2.14 – Hydraulics
Touchet RiverFloodplain
Proposed US 12 can only cross the Touchet River with net-zero rise –and must completely span the Touchet River floodway
CHAPTER 2.14 TO BE ADDED LATER
BY ADDENDUM
RFP Highlights
26
Chapter 2.15 – Roadside Restoration
Key Requirements of 2.15 located in Appendix L
• No plantings (no trees or shrubs required)
• Seeding is required for all disturbed surfaces (drill seeding)
US 12 near Walla Walla (Phase 6)
RFP Highlights
27
Chapter 2.16 – Illumination
• Design-Builder is responsible for illumination design
• Design-Builder is responsible for providing services as necessary
Intersection illumination on US 12 near Walla Walla (Phase 6)
RFP Highlights
28
Chapter 2.18 – Intelligent Transportation Systems
• 2 Environmental Sensor Stations
• 4 Wildlife Monitoring cameras– 2 at Touchet River crossing– 2 at Dry Creek crossing
• New fiber-optic along project length
• 2 CCTVs
Images of wildlife crossing I-90 are captured on a monitoring camera
Deer family using undercrossing
Existing CCTV Camera at Nine Mile Hill on US 12
RFP Highlights
29
Chapter 2.24 – Right of Way
Project Commitments List of WSDOT obligations – located in Appendix R
• All ROW for the project has been purchased!
• Required Project Commitments (Appendix R)
• Source commitments from Findings and Order, EA, and Construction Memos
RFP Highlights
30
Chapter 2.25 – Control of Materials
• Design-Builder is responsible for all HMA acceptance testing
– Reference Chapter 2.7/Chapter 2.25
Testing HMA in the field – DB is responsible for all HMA acceptance testing
Procurement Schedule
Action DatesStep 1 - SOQ Phase
RFQ Issue Date 5/23/19Voluntary Submitters Meeting 6/5/19Deadline for submitting RFQ questions 6/18/19Deadline for WSDOT response to RFQ questions 7/2/19SOQ Due Date 7/16/19Notify short-listed submitters 8/9/19
Step 2 - Proposal PhaseIssue RFP 08/19/19Voluntary Proposers Meeting 08/20/19Deadline for Submitting Proposers' questions 11/01/19Deadline for WSDOT response to Proposers' questions 11/19/19Deadline for ATC Submittal 11/21/19Deadline for WSDOT ATC Response 12/11/19Proposals Due 12/19/19Announce Best Value Proposer 01/29/20Estimated Notice to Proceed 03/19/20
31
Key Dates
• Initial meeting will be held Tuesday, August 20th, 2019. Subsequently, meetings will be held on each Tuesday through November 21st, 2019.
• All meetings will be held at the WSDOT Project Engineer Office – North Conference Room
Building #26South Central Region Headquarters 2809 Rudkin Road Union Gap, WA 98903-1648
• Schedule is as follows: ◦ 8:00 am – 10:00 am◦ 11:00 am – 1:00 pm◦ 2:00 pm – 4:00 pm
Recommend submitting any Q&A by COB Thursday prior to each One-on-One
32
Procurement ScheduleOne-on-One Meetings