update on ctf3 installation and planning

16
2 nd CTF3 Committee meeting L. Rinolfi 15 th May 2008 Update on CTF3 installation and planning L. Rinolfi

Upload: elata

Post on 05-Feb-2016

53 views

Category:

Documents


0 download

DESCRIPTION

Update on CTF3 installation and planning. L. Rinolfi. Brief history of the CTF3 installation. CLEX 2008. TL2 2008. Photo injector tests for PHIN 2008. 2004 - 2008. 30 GHz production (PETS line) and Test Stand for CLIC structures. 2006 - 2007. 2006. 2005. TL1. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Update on CTF3 installation and planning

L. Rinolfi

Page 2: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Photo injector tests for PHIN

2008

TL2 2008

D FFD

D F D

D F D D F D

D F D

DF DF DF DF DF DF DF DF DF

D F D

F DF D

D FFFDD

D F DD F D

D F DD F D D F DD F D

D F DD F D

DF DF DF DF DF DF DF DF DF DFDF DF DF DF DF DF DF DF DF DF DF DF DF DF DF DF

D F DD F D

F DF DF DF D

Drive Beam AcceleratorDL

DL = Delay Loop (factor 2)

CR

CR = Combiner Ring (factor 4)

CLEX 2008

Injector with thermionic gun

2003

2004

20052006 - 2007

30 GHz production(PETS line)

and Test Stand for CLIC structures

2004 - 2008

Brief history of the CTF3 installation

2006

TL1

Page 3: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Conclusion of the 1st meeting

Installation into the Injector, Drive Beam Linac, Delay Loop, Transfer Line TL1 and Combiner Ring is completed.

Installation of the Transfer Line TL2 will be finished and connected to the Combiner Ring for the end of June 2008.

Installation into CLEX (Phase 0) will be finished for the end of June 2008.

Installation into CTF2 (for PHIN) will be finished for the end of August 2008. Tests with beam foreseen for September 2008 during the installation of the Tail Clipper into the TL2 line.

Page 4: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

RF deflectors in CR

Klystrons

3 GHz40 MW

3 GHz

30 MW

3 GHz

Gun

SHB2SHB1

PB2 B1A1 A2 A3 A4 A5 A6 A7 A8 A9 A10 A11 A12

LIPS BOC BOC

A13 A14

40 MW

3 GHz

LIPS

30 MW

3 GHz

30 MW

3 GHz

30 MW

3 GHz

30 MW

3 GHz

30 MW

3 GHz

30 MW

3 GHz

A17 A18

50 Hz 10 Hz50 Hz50 Hz 50 Hz 10 Hz 50 Hz 50 Hz 50 Hz50 Hz

SHB3

TDS SICA

BOCLIPS LIPS LIPS

40 MW

MKS 02

MKS 03

MKS 05

MKS 06

MKS 07

MKS 11

MKS 12

MKS 13

MKS 14

MKS 15

TWT 01

TWT 02

TWT 03

Photo-injector

CTF2

20 MW

1.5 GHz

50 Hz

MKL 02

1 RF deflector

RF deflectors2 RF deflectors

Combiner Ring

40 kW1.5 GHz

BW 200 MHz LIPS

Delay Loop

PHIN RF gun in CTF2

1 RF deflector

RF deflector in CLEX

CLEX

Page 5: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Combiner Ring

In order to cure the vertical instabilities, two new (3 GHz)

RF deflectors (in Al) have been designed by LNF (Frascati) and

are under construction.

RF deflectors CR. HDS 0150 & CR.HDS 1050

They are foreseen:- to be at CERN end of June, - to be tested with RF power beginning of July, - to be installed in the machine later on

See A. Ghigo talk

Beam current

V- BPM

H- BPM

Page 6: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Transfer Line TL2

SH

C 0

120

SH

D 0

110

QF

G 0

140

QD

G 0

160

QF

H 0

210

QF

H 0

180

QF

L 0

270

QD

L 0

280

QD

H 0

220

QF

H 0

230

QD

H 0

330

QF

H 0

350

QD

H 0

370

QD

L 0

430

QF

L 0

450

QD

L 0

470

QFL 0530QDL 0550

QFL 0570QFL 0620QDL 0650

QFL 0680

QFL 0730QDL 0750

QFL 0770

QD

D 0

820

QF

D 0

840

XLC 0580

XLC 0720

XLA 0630XLA 0670

BH

H 0

200

BH

G 0

500

BH

H 0

600

BH

H 0

700

BH

G 0

800

BV

A 0

300

BV

B 0

400

Magnets

Dipoles (Horizontal) 5

Dipoles (Vertical) 2

Quadrupoles 27Sextupoles 4

Correctors 12

Instrumentation

BPM 6 WCM 1

BPI 6 MTV 1

BPR 1

Vacuum

VPI 9

VVS 2

Combiner Ring

CLEX

e-

KH

C 0

250

Tail ClipperS

LV

025

5Collimator

Page 7: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

TL2 line

Tail ClipperCC.KHC 0250

CollimatorCC.SLV 0255

e- beamDoor 604

Tail clipper & Collimator

Page 8: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Apr May J unWk 14 15 16 17 18 19 20 21 22 23 24 25 26

Mo 31 7 14 21 28 5 12 19 26 2 9 16 23

Tu

We

Th

Fr

Sa

Su

J ul Aug Sep

Wk 27 28 29 30 31 32 33 34 35 36 37 38 39

Mo 30 7 14 21 28 4 11 18 25 1 8 15 22

Tu

We

Th

Fr

Sa

Su

Oct Nov Dec

Wk 40 41 42 43 44 45 46 47 48 49 50 51 52

Mo 29 6 13 20 27 3 10 17 24 1 8 15 22

Tu

We

Th

Fr

Sa

Su

CTF3

SHUTDOW

N

Ascen

Whit.

J eune G.

CTF3 stop

Beam in Combiner Ring with beam extraction to the CC dump only

Open Days

Start with beam in DL + CR

Installation Tail clipper with Dump

into TL2

During this period the Combiner Ring and CLEX will work with independent access control

During this period the Combiner Ring and CLEX will remain under access control altogether

Hardware tests forTL2 line

Beam in PETS

Connect TL2 line to CR

CTF3 - DL - CR - TL2 Schedule

Page 9: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

TL2

Two-BeamTest Stand

(TBTS)

Test Beam Line (TBL) decelerator

Space reserved for Instrumentation Test Beam

line (ITB)

RF gun

CALIFES

Drive Beame-

e-

Probe beam

e-

e-

Space re

serve

d for 1

6 PETS

CLEX Layout

TL2 '

Page 10: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

1) TL2, TL2', TBTS, TBL Nothing new regarding installation compared to the previous CTF3 meeting (18th April 2008)

Waiting for alignment from CERN surveyors (this week)

Vacuum chambers remains to be installed

CLEX status

2) CALIFES Put all the line at the atmospheric pressure

Waiting for alignment from CERN surveyors (this week)

Cabling all dipolar correctors by CEA (this week)

RF wave guides still foreseen to be at CERN mid-June

Finish the cabling of the Vacuum Control

Bake-out of the RF gun and laser chamber downstream

See F. Orsini talk

Page 11: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

CLEX hardware tests

1) Tests of power supplies (81 in total) 30 power supplies tested and operational

6 power supplies not tested (ripple, water leak, not connected to magnets)

45 power supplies for correctors not yet arrived at CERN

Remote control not yet OK for several devices

2) Polarity tests Done on all standard magnets

Found 10 wrong polarities

All dipolar correctors remain to be done

Page 12: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Apr May J unWk 14 15 16 17 18 19 20 21 22 23 24 25 26

Mo 31 7 14 21 28 5 12 19 26 2 9 16 23

Tu

We

Th

Fr

Sa

Su

J ul Aug Sep

Wk 27 28 29 30 31 32 33 34 35 36 37 38 39

Mo 30 7 14 21 28 4 11 18 25 1 8 15 22

Tu

We

Th

Fr

Sa

Su

Ascen

Whit.

J eune G.

Beam in Combiner Ring with beam extraction to the CC dump only

During this period the Combiner Ring and CLEX will remain under access control altogether

=> No installations in CLEX

Open Days

Start beam for CALIFES

RF conditioning for CALIFES

Laser Tests for CALIFES (2 slots)

Photo-cathodes production

Tests of the Safety chains (Laser,...)

Connect TL2 line to CR

CTF3 - CLEX Schedule 2008

Page 13: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Photo-injector PHIN into CTF2

A single klystron MKS 14 shared with RF reflectors

into the Combiner Ring and the RF deflector of

CALIFES

PHIN RF gun expected next week at CERN

and laser beam still under development

RF gun not yet in place here

Possibility to use MKS 14 klystron to test the 2 new Al RF deflectors coming from LNF if the wave guides are in place before connecting the PHIN RF gun

See K. Elsener talk

Page 14: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

CTF3 - CTF2 Schedule 2008

Apr May J unWk 14 15 16 17 18 19 20 21 22 23 24 25 26

Mo 31 7 14 21 28 5 12 19 26 2 9 16 23

Tu

We

Th

Fr

Sa

Su

J ul Aug Sep

Wk 27 28 29 30 31 32 33 34 35 36 37 38 39

Mo 30 7 14 21 28 4 11 18 25 1 8 15 22

Tu

We

Th

Fr

Sa

Su

Oct Nov Dec

Wk 40 41 42 43 44 45 46 47 48 49 50 51 52

Mo 29 6 13 20 27 3 10 17 24 1 8 15 22

Tu

We

Th

Fr

Sa

Su

CTF3

SHUTDOW

N

Ascen

Whit.

J eune G.

CTF3 stop

Start with beam for 30 GHz tests

Beam for PHIN tests

or30GHz tests

Open Days

Connect MKS 14 for PHIN

Beam in DL + CR + CLEX

Beam in PETS +DL + CR + CLEX

Start beam for CALIFES

Beam in PETSBeam for

30GHz tests

PHIN tests possible during

this period

Beam in Combiner RingCTF2 open under access control

Beam in PETS

Page 15: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Conclusion

Installation into the Injector, Drive Beam Linac, Delay Loop, Transfer Line TL1 and Combiner Ring => OK

Installation of the Transfer Line TL2 connected to the Combiner Ring for the end of June 2008 but:

- Indian dipole magnets ?

- Power supplies for dipolar correctors ?

Installation into CLEX (Phase 0) will be finished for the end of June 2008 but:

- Laser for CALIFES ?

Page 16: Update on CTF3 installation and planning

2nd CTF3 Committee meeting L. Rinolfi 15th May 2008

Conclusion (con't)

Installation into CTF2 for the photo-injector

- LAL proposed help during week 25 (Monday 16th June 2008)

- However this week is foreseen to be dedicated full time for 30 GHz

- Hardware tests for PO and CO not yet in the Schedule

- Installation expected to be finished for the end of August

- Tests with beam could take place in October 2008 during the installation of the Tail Clipper into the TL2 line.

- Strong request from CARE to finalize the test as deliverable for EU-FP6-JRA-PHIN