UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
1
Capacity Development for CDM
Egypt, Second National Workshop
The Project Design Document (PDD)
Samir Amous, APEX, TunisiaSamir Amous, APEX, TunisiaRegional Centre for North Africa and Middle-EastRegional Centre for North Africa and Middle-EastTel : +216 71 848 094 --- Fax : +216 71 843 453Tel : +216 71 848 094 --- Fax : +216 71 843 453
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
2
OUTLINE
A. General Description of the Project Activity
B. Baseline Methodology
C. Duration of the Project Activity
D. Monitoring Methodology and Plan
E. Calculation of GHG emissions
F. Environmental Impacts
G.Stakeholder Comments
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
3
ANNEXES
Annex 1: Contact information on project participants
Annex 2: Information regarding public funding
Annex 3: New baseline methodology
Annex 4: New monitoring methodology
Annex 5: Table of baseline data
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
4
A. General Description of Project Activity
Project title
Short description of the project activity (purpose, contribution to SD)
List of Parties involved in the project activity.
Information allowing a unique identification of the project activity, including the location (Country, Region, State, City, etc.)
Specification of project activity category (see UNFCC CDM website)
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
5
A. General Description of Project Activity
Description of transfer of environmentally sound technologies
Explanation on how the GHG emission is reduced
Information on Public Fundingno diversion of ODA
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
6
B. Baseline Methodology Title and reference to the Baseline Methodology as
listed in the UNFCCC CDM Website
Justification of the choice of the methodology
Explanation on how & why the project is additional
Description of the project boundary
Details on the Baseline and its development
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
7
Baseline options Existing actual or historical emissions
Emissions from a technology that represents an economically attractive course of action, taking into account barriers to investment
Average emissions of similar project activities undertaken in the previous five years, in similar social, economic, environmental and technological circumstances, and whose performance is among the top 20% of their category
Small-Scale projects: Standardized baselines already in place
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
8
C. Duration of the project activity
Duration of the project activity:
o Starting date: implementation or construction or real action of project activity
o Operational lifetime in years and months
Choice of the crediting period, with starting date specified
o A period of maximum 10 years
o A period of maximum 7 years, with the potential for renewal for two additional periods at most
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
9
D. Monitoring Methodology/Plan
Name and Reference of the methodology listed in the UNFCCC Website
Justification of the choice of the Methodology
Name and Contact information of persons/entity determining the monitoring methodology
Table showing the data/indicators to be monitored, and quality required
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
10
Provisions of the Monitoring Plan
Collection and archiving data for calculating emissions within the project boundary
Collection and archiving data for determining baselines
Collection and archiving data for calculating Leakages
QA and Control Procedures
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
11
E. Calculation of GHG emissions Calculations of GHG emission reductions within the
project boundary (all emissions that are directly controlled or influenced by the project. Should carefully consider the following issues:
o Potential Leakage
o Emission factors, GWP,
Environmental impacts
Stakeholder Comments
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
12
F. Environmental impacts
What are the other environmental benefits ?
Any environmental concerns in relation with the project ? How they are addressed ?
Environmental Impact Assessment, any other assessment ? (to be annexed to the PDD)
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
13
G. Stakeholder Comments
PDD Publicly available
Stakeholder commentspart of the CDM gameofficial input
Comments should be invited by the DOE in charge of the validation, and compiled
To which extent comments have been taken into account?
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
14
ANNEXES
Annex 1: Contact information on project participants
Annex 2: Information regarding public fundingno ODA diversion
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
15
Annex 3: New baseline methodology Annex 4: New monitoring methodology
Only if it’s a new methodology
To be attached to a draft PDD
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
16
Annex 5: Table of baseline data
Key elements to determine baselines:
Variables
Parameters
Data Sources
Etc.
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
17
Small-Scale projectssame outline, but less detailed sections
A. General Description of the Project Activity
B. Baseline Methodology
C. Duration of the Project Activity
D. Monitoring Methodology and Plan
E. Calculation of GHG emissions
F. Environmental Impacts
G.Stakeholder Comments
UNEP Collaborating Centre on Energy and Environment
Capacity Development for CDM - Egypt, Second National Workshop - Phase II - Cairo, 12-13 January 2004
18
Reduced Annexes
Annex 1: Contact information on project participants
Annex 2: Information regarding public funding