uc irvine energy efficiency energy storage energy optimization
TRANSCRIPT
Matt Gudorf CEM, LEED AP Assistant Director Energy, Engineering, and Inspection
UC Irvine • Energy Efficiency • Energy Storage • Energy Optimization
Quick Facts
• Established in 1965 • Comprehensive Research
University • 13 Lab buildings past two
decades • 8-24MW Load
• 1,526 Acres • 10M+ Square feet • 7.5M Sqft District Utilities • 24,489 Undergraduates • 6,268 Postgraduates • $20,754,196 Utility Budget
PROCUREMENT ELECTRICITY
• Distribution Service by SCE
• TOU-8-S
• Departing Load
• Direct Access Cost Responsibility Surcharge
• Generation
• Purchased through an energy service provider (ESP)
• Day ahead market
• Distributed Generation
• Power Purchase Agreements
• 20 and 25 year contracts
• Predetermined rates and escalation
NATURAL GAS
• Commodity
• DGS contract with BP
• Buy futures up to 75%
• NYMEX Henry Hub
• CA Citygate price
• Delivery
• SoCal Gas
• CA border to UCI
Key: Flexibility with managed risk
4
UCI Substation 66kV/12kV
Edison MacArthur Substation
66kV
Campus Utilities
UCI Substation 66kV/12kV
Edison MacArthur Substation
66kV
Central Plant: 8 chillers
Gas turbine: 13.5 MW Steam turbine: 5.6 MW
Campus Utilities
SOLAR TITAN 130 COMBUSTION TURBINE 13.5 MW AT 12,000 VOLTS
SOLAR TURBINE ASSEMBLY BEFORE BEING PLACED INTO ENCLOSURE
UCI Substation 66kV/12kV
Edison MacArthur Substation
66kV
Central Plant: 8 chillers
Gas turbine: 13.5 MW Steam turbine: 5.6 MW Solar Rooftop PV
3.575 MW
TES
Campus Utilities
Social Science Parking Structure
Social Science Parking Structure 935kW Equivalent Generation in a year - 140 US Homes
Student Center Parking Structure
Student Center Parking Structure 725kW Equivalent Generation in a year - 110 US homes
Mesa Parking Structure
Mesa Parking Structure 909kW Equivalent Generation in a year - 136 US homes
UCI Substation 66kV/12kV
Edison MacArthur Substation
66kV
Central Plant: 8 chillers
Gas turbine: 13.5 MW Steam turbine: 5.6 MW Solar Rooftop PV
3.575 MW
TES
CPV 113kW
Campus Utilities
UC IRVINE’S 12KV DISTRIBUTION SYSTEM 10 - Distribution circuits 136 - 12kV transformers 77 - SF6 Switches
UCI Substation 66kV/12kV
Edison MacArthur Substation
66kV
Central Plant: 8 chillers, 4 Boilers
Gas turbine: 13.5 MW Steam turbine: 5.6 MW Solar Rooftop PV
3.575 MW
CPV 113kW
Campus Utilities
Central Plant: 8 chillers
Serve 82 Buildings TES
Thermal Storage 4,500,000 Gal
60,000 Ton-Hour
Campus Utilities
BOILER DATA
• Boiler #1& #2 – Babcox & Wilcox 250PSI • 29,000lbs/hr, 1964
• Oil & Gas Burner
• Boiler #3 - Nebraska 300PSI • 30,000lbs/hr, 1970
• Boiler #4 - Trane Murray 300PSI • 30,000lbs/hr, 1978
Manufacture Rating in Tons Refrigerant Year Installed
Chiller #1 Trane 1000 R-123 1992
Chiller #2 Trane 1000 R-123 1997
Chiller #3 Trane 1000 R-123 1997
Chiller #4 York 2000 R-134a 2002
Chiller #5 Trane 2500 R-123 1999
Chiller #6 Trane 2500 R-123 2004
Chiller #7 York 3000 R-134a 2007
Chiller #8 York 3000 R-134a 2007
Chiller Plant Details
16,000 Tons of nominal chiller capacity
Chilled Water System
• AHU coils designed for 39°F supply
• System ΔT of 20-23°F
• PIC-V or Flow Limiters at each AHU
• Average load 3,100 tons
• Peak load 13,000 tons
• 74,400 Ton-Hours per day
• Flow Capacity @ 30” header is 35,600 gpm
• Secondary pump capacity 25,200 gpm @ 100 feet of head
• TES pump capacity is 22,700 gpm @ 90 feet of head
• Delivered 0.7kW per ton
Chilled Water Load Side Optimization
1997-2016 the campus changed out AHU coils to provide a ΔT minimum of 20°F.
The system makes use of Pressure independent control valves and flow limiters to minimize use and maximize energy efficiency
Monitoring the hydronic system at the building level
Tank holds 4.5 million gallons of chilled water
Tank is 107’ tall by 88’ in diameter
When chilled to 39°F, rated storage is 186,400 kWh
0-8MW of load can be shifted
Originally built to shift load to off-peak rates
Thermal Energy Storage
45%
UC Irvine Drastically Reduces Load
Operating Limitations 1 The interconnection agreement is for inadvertent export of power only.
2 Curtailment of the CTG is limited to 7.5MW due to emissions
3 Solar power production cannot be curtailed (PPA)
4 Efficiency of the CTG drops as output is reduced
5 Import electricity cost more than self generation
Load Generation Import
Electricity
So how is the near perfect management as shown on the right achieved? UC Irvine uses TES as an electrical battery to flatten and shape load to match generation!
909 kW Solar Rooftop PV
(Mesa Parking)
725 kW Solar Rooftop PV (SC Parking)
935 kW Solar Rooftop PV (SS Parking)
Central Plant NGCC
13.5 [MW]
GT
4.5 [MW]
ST
Ten 12 [KV]
circuits
3,575 [KWpeak]
PV
Load PV
UCI Campus
66 [KV] circuit
SCE
7 Electric Chillers
GT = Gas Turbine ST = Steam Turbine
NGCC = Natural Gas Combined Cycle SCE = Southern California Edison
Balancing Load and Generation
TES
Storage
MONITORING THE MICROGRID
Generation
• Import
• Combustion Turbine
• Steam Turbine
• Solar PV
Load
• Plant
• Building
• Sub Building
• Circuit
Building Management
• HVAC
• Lighting
Storage
• Tank Charge
Over 100,000 data points Trend, Analyze, Optimize
24 Hours
0-1
8 M
W
Solar PV
Morning Building Load
PV drops off, peak cooling demand Ideally, utilize the chillers and TES to flatten the load shape
Flattest possible load shape Matched to Generation
24 Hours
0-1
8 M
W
Utilize Solar
Maximize Base Loaded CTG
Import as little as possible
Actual Load and Generation Graph From UCI Campus
$-
$0.20
$0.40
$0.60
$0.80
$1.00
$1.20
$1.40
$1.60
$1.80
2008 2009 2010 2011 2012 2013 2014 2015
Energy Cost Per Square foot
Financial Savings
Optimization of load and generation results in financial savings • Minimal import of expensive electricity • Solar offsetting peak demand
Next steps Implement a ½ MW, 2 MWh battery (In construction) Deploy full SCADA system from SEL across campus grid (In construction Engineer, implement, and test islanding of the campus Additional optimization of the balance between, load and generation