TUUL - SONGINO Water Resources Complex Project Overview 201 6 ULAANBAATAR PUMPED STORAGE POWER STATION LLC

Upload: ivaylo-velikov

Post on 23-Jan-2018

288 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Tuul-Songino Project Overview  22.05.2015

TUUL- SONGINO

Water Resources Complex

Project Overview

2016

ULAANBAATAR PUMPED STORAGE POWER STATION LLC

Page 2: Tuul-Songino Project Overview  22.05.2015

TUUL-SONGINO WATER RESOURCES COMPLEX

LOCATION

Tuul-Songino water resources complex project 2

Page 3: Tuul-Songino Project Overview  22.05.2015

CURRENT STATUS OF ULAANBAATAR CITY

WATER SUPPLY AND WASTE TREATMENT

Central waste water

cleaning facility

170 000 м3 / day :

Householder’s waste

Water 60%

Others 40%

TUUL

RIVER

Tuul-Songino water resources complex project

Thermal

power

station

25%

Others

30%

City

household

ers

45%

3

Page 4: Tuul-Songino Project Overview  22.05.2015

Municipal waste water treatment

facility

200 000 м3 per day

Pumped Storage Power Station

5 000 м3 per day

Thermal power plant 3 and 4

76 000 м3 per day

Хотын ногоон байгууламжид

15 000 м3 per day

Tuul River

50 000 м3 per day

New Thermal power plant 5

24 000 м3 per day

PROJECT IMPLEMENTATION

TUUL SONGINO WATER RESOURCES COMPLEX

MUNICIPAL WASTE WATER TREATMENT FACILITY

Tuul-Songino water resources complex project 4

Page 5: Tuul-Songino Project Overview  22.05.2015

MUNICIPAL WASTE WATER TREATMENT FACILITY FOOTPRINT

5Tuul-Songino water resources complex project

Page 6: Tuul-Songino Project Overview  22.05.2015

Specification

рН

EC

S/cm

COD

ХХХ

мг/л

BOD

БХХ

мг/л

SS

Умб

мг/л

NH4

мг/л

NO2

мг/л

NO3

мг/л

P

эрд

мг/

л

1, Urban waste water

treatment standard

nature of the Mongolian

MNS49436-9 - 50 20 50 6 0,1 2.5 1.5

2, Urban waste water

re-use GB 18918-2002

international standards 7 25-35 0-5 5-15 0.1 0.02 9 0.05

MUNICIPAL WASTE WATER TREATMENT FACILITY

Treated Water Quality Standards

Tuul-Songino water resources complex project6

Page 7: Tuul-Songino Project Overview  22.05.2015

ULAANBAATAR PUMPED STORAGE POWER

STATION / WATER TREATMENT TECHNOLOGY

This project will solve the city's wastewater treatment problem by re-using existing water resources.

Tuul-Songino water resources complex project 7

Page 8: Tuul-Songino Project Overview  22.05.2015

0

100

200

300

400

500

600

700

800

900

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

PRESENT CONDITION OF THE CENTRAL ENERGY SYSTEM

680 мВт

Tuul-Songino water resources complex project 8

Above the line shows imported electricity; green area under the line indicates exported or excess electricity

Page 9: Tuul-Songino Project Overview  22.05.2015

-200

0

200

400

600

800

1000

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

The Station will produce 100 MW of ElectricityDaily Load Consumption

Tuul-Songino water resources complex project

TUUL-SONGINO WATER RESOURCES COMPLEX PROJECT WILL INCLUDE A PUMPED STORAGE

POWER STATION

9

During the Export of electricity period, there will be 706 MW available and during the Peak Load period there will be 850 MW available for delivery to the Central Energy System.

Page 10: Tuul-Songino Project Overview  22.05.2015

PROJECT SITE: SONGINO KHAIRKHAN DISTRICT, 32 KHOROO

Tuul-Songino water resources complex project

Page 11: Tuul-Songino Project Overview  22.05.2015

TECHNICAL PARAMETERS OF THE ULAANBAATAR PUMPED STORAGE POWER

STATION

Tuul-Songino water resources complex project11

Capacity (Pump-Turbine) 2x50MW 100 ÌW

Annual electricity production 300 MKWh

Dam length 580 ì

Dam height 68 м

Dam Reservoir volume 1,850 Mln. ì3

Upstream water level max/min 1,490/1,1470 ì

Downstream water level max/min 1,245/1,242 ì

Rated head H = 245 ì

Unit number 2 Set

Vertical Francis type pump-turbine 51,5/57,5 МW

Water discharge Q = 27,94 м3/сек

Мах. operation time Т = 8,36 hours

Payback period with constriction period 14-15 years

Max. Working head Н = 224/249

Min. Working head Н = 209/219,3

Page 12: Tuul-Songino Project Overview  22.05.2015

Name of capital investment years

To projects investment / tangible assets 14.25 million 2014

Land $1.340 million 2007

Exploration, evaluation assets $7.850 million 2007-2009

Long-Term Investments $4.500 million 2001-2015

The project area includesInvestment funds

$474 thousand 2007-2010

Cars/Real Estate/Furniture $84.5 thousand 2007-2008

Total Project Unit Investments $28.5 Million

Tuul-Songino water resources complex project 12

“ULAANBAATAR-PUMPED STORAGE POWER

STATION ” LLC CURRENT INVESTMENT

Page 13: Tuul-Songino Project Overview  22.05.2015

Tuul-Songino water resources complex project

LOAN PROCESS AND REQUEST

CONCESSION OWNED

PPA & WPA

“EPC”

CONTRACTOR FOREIGN

BANK

DOMESTIC COMMERCIAL

BANK

13

The project requires a loan of US$ 300 million over 15 years

Page 14: Tuul-Songino Project Overview  22.05.2015

SUMMARY INFORMATION OF FEASIBILITY STUDY

IRR for both Projects 14.8%IRR for Power-Storage Power Station 12.4%IRR for Water Treatment Plant 20.3%

Sales Price of Power (USD per kWh) 0.113

Sales Price of Water (USD per ton) 0.33

Purchased Price of Power (USD per kWh) 0.011

Power Generation Capacity

(KW)110,000

Pumped Power Load

(KW) 110,000

Annually Power Production

(GkWh) 309

Annually Power Purchasing

(GkWh) 435

14Tuul-Songino water resources complex project

Page 15: Tuul-Songino Project Overview  22.05.2015

CONCESSION OWNER & EPC RELATIONSHIP

Concession owned

“ULAANBAATAR-PSPS” LLC

(EPC CONTRACTOR)

STATE-OWNED COMPANIES OF

CHINA

SUBCONTACTOR

MONGOLIAN AND CHINESE

COMPANIES

(PPA)

ULAANBAATAR CITY &

“TRANSMISSION NETWORK:” LLC

Tuul-Songino water resources complex project 15

Page 16: Tuul-Songino Project Overview  22.05.2015

Representation of the 100 MW Pumping Storage Power Station Regulates Daily Load Consumption

Tuul-Songino water resources complex project 16

Page 17: Tuul-Songino Project Overview  22.05.2015

Tuul-Songino water resources complex project17

ENVIRONMENTAL ADVANTAGEES

Detailed Environment Influence Evaluation Study was carried out in 2006 and updated in 2012.

Implementation of the project prevented 300,000 tons of coal from being burned and decreased greenhouse gas emissions by 150,000,000 m3.

Ground water pollution along the Tuul River Basin will be greatly decreased.

165 000 m3/day of purified waste water will reach surface water standards and can then be released into the Tuul River.

Page 18: Tuul-Songino Project Overview  22.05.2015

12.4.2016 г. 18

INCORPORATION

ADDRESS

1ST FLOOR YAMRAJ

BUILDING P.O. BOX 875,

ROAD TOWN ,TORTOLA ,

BRITISH VIRGIN ISLANDS

BUSINESS ADDRESS

CYPRUS, NICOSIA 5

VISANTIOU STREET

SPYRIDIES

TOWER,2064 STROVOLO

S ,+35722210000

BULGARIA ADDRESS

VARNA 9000

,BULGARIA,MIHALIL

KOLONI 6

,+359877758222,

[email protected]

CONTACT

DETAILS