Luling TRANSPORTATION STUDY
Summary Report – July 2019
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page ii
ACKNOWLEGEMENTS
Lead Agency
Capital Area Metropolitan Planning Organization
3300 N Interstate 35, Suite 630
Austin, Texas 78705
Lead Staff – Nirav Ved, Special Assistant to the Executive Director
Agency Stakeholders
Luling City Council
Caldwell County Commissioners Court
TxDOT Austin District – Bastrop Area Office
Luling Transportation Study Steering Committee
Consultant Team
RPS Group
4801 Southwest Pkwy #150
Austin, TX 78735
CD&P
2233 W North Loop Blvd
Austin, TX 78756
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page iii
CONTENTS 1 INTRODUCTION .......................................................................................................................... 1 1.1 Study Background ........................................................................................................................ 1 1.2 Steering Committee ...................................................................................................................... 1 1.3 Study Goals and Objectives ......................................................................................................... 1 1.4 Study Area .................................................................................................................................... 3 1.5 Project Timeline ............................................................................................................................ 3 2 DATA AND DISCOVERY ............................................................................................................ 5 2.1 Review of Previous Plans and Studies ........................................................................................ 5 2.1.1 Caldwell County Transportation Plan ........................................................................................... 5 2.1.2 2040 RTP ..................................................................................................................................... 6 2.1.3 Luling Master Plan ........................................................................................................................ 8 2.1.4 Railroad Plans .............................................................................................................................. 8 2.2 Data Sources and Findings .......................................................................................................... 9 2.2.1 Demographics .............................................................................................................................. 9 2.2.2 Average Annual Daily Traffic Counts ......................................................................................... 11 2.2.3 Peak Period Intersection Traffic Counts..................................................................................... 13 2.2.4 Travel Patterns ........................................................................................................................... 14 2.2.5 Crash Data ................................................................................................................................. 17 2.2.6 Environmental Constraints Mapping .......................................................................................... 19 2.3 Public Outreach .......................................................................................................................... 21 2.3.1 Outreach Goals .......................................................................................................................... 21 2.3.2 Approach .................................................................................................................................... 21 2.3.3 Round 1 Outreach Results ......................................................................................................... 22 2.4 Identified Issues ......................................................................................................................... 23 3 POTENTIAL IMPROVEMENT OPTIONS .................................................................................. 26 3.1 Option Profiles ............................................................................................................................ 26 3.1.1 Potential Near-Term Improvements ........................................................................................... 26 3.1.2 Long-Term Improvement Options .............................................................................................. 29 3.1.3 Cost Estimates ........................................................................................................................... 31 3.2 Performance Measure Development ......................................................................................... 32 3.3 Round 2 Outreach Results ......................................................................................................... 33 3.4 Performance Measure Results Comparison .............................................................................. 34 3.5 Recommended Improvements ................................................................................................... 38
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page iv
4 IMPLEMENTATION ................................................................................................................... 39 4.1 Next Steps .................................................................................................................................. 39 4.2 Funding Sources ........................................................................................................................ 40 4.2.1 Federal ....................................................................................................................................... 40 4.2.2 State ........................................................................................................................................... 41 4.2.3 County and Local Level .............................................................................................................. 41
APPENDICES A Previous Plans and Studies
B Local and Regional Demographics
C Traffic Counts
D Travel Pattern Data
E Crash Data
F Public Outreach
G Cost Estimates for Potential Improvement Options
H Performance Measure Definitions and Descriptions
I Performance Measure Methods and Results
J Traffic Demand Forecasting
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page v
ACRONYMS
AADT Average annual daily traffic
ADT Average daily traffic
CAMPO Capital Area Metropolitan Planning Organization
CARTS Capital Area Rural Transportation System
EPA Environmental Protection Agency
FHWA Federal Highway Administration
LOS Level of service
OD Origin-destination
ROW Right of way
RTP Regional transportation plan
TCDS Traffic count database system
TMC Turning movement count
TxDOT Texas Department of Transportation
UPRR Union Pacific Railroad
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 1 of 42
1 INTRODUCTION The City of Luling, Texas, sits at the crossroads of several major highways – US 183, US 90, and SH 80 – and is bisected by a key east-west line of
Union Pacific Railroad (UPRR). The highways connect with IH 10 at the City’s southern extents, linking with key domestic and international freight
routes.
Historically, oil production has been the chief industry in Luling and the surrounding rural lands in Caldwell, Guadalupe, and Gonzales Counties.
While Luling’s oil production peaked in the 1920s and declined through the 1990s, a resurgence occurred in the early 2010s in response to rising
global oil prices. Amid this recent resurgence, pass-through truck traffic volumes intensified on Magnolia Avenue (US 183) and Austin Street (SH
80), particularly around the UPRR crossing near the Magnolia Avenue / Pierce Street intersection (US 183 / SH 80 / US 90) intersection. Since 2014,
the stabilization of global oil prices and decreases in regional production have caused traffic growth to recess to pre-boom levels, but traffic levels
are beginning to rise again. Notably, Luling is a common pass-through point for recreational trips between Central Texas cities and the Texas Gulf
Coast, so traffic levels tend to spike on weekends from the late spring to the early fall. Under these conditions, Caldwell County and Luling officials
established the need for a Transportation Study to explore potential solutions for existing transportation issues as well as issues that may arise during
the next oil boom.
1.1 Study Background
In 2011, Caldwell County and Luling officials began discussing the potential for transportation improvements to ease congestion within central Luling,
prevent conflicts between vehicle and rail movement, and improve safety / comfort for downtown visitors. Caldwell County committed to study the
feasibility of various transportation improvements on the major routes entering and exiting Luling, as well as the potential for new roadway corridors.
In 2018, Caldwell County entrusted CAMPO to lead the Luling Transportation Study.
1.2 Steering Committee
A Steering Committee made up representatives from Caldwell County, the City of Luling, the Luling Economic Development Corporation, and the
Texas Department of Transportation (TxDOT) was assembled to guide the development of the Luling Transportation Study. Steering Committee
members provided input from their respective State, County, and local perspectives. Steering Committee feedback was used to shape and affirm
study goals / objectives, identify area transportation issues, and assess the viability of improvement options. The Steering Committee also actively
assisted in reaching stakeholders and other targeted outreach opportunities throughout the public engagement process.
1.3 Study Goals and Objectives The purpose of the Luling Transportation Study (“Study”) is to evaluate transportation conditions and needs in Luling, to identify potential
improvements, and to set an implementation plan for one or more recommended improvements. Four project goals and associated objectives,
displayed on the following page, were established through coordination with the project Steering Committee and used to guide the Study.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 2 of 42
Goals Objectives – Evaluate and Consider…
• Traffic crash data
• Pedestrian movement and safety
• Union Pacific Railroad corridor and crossings
• Local emergency response services and evacuation routes
:
• Local travel, freight travel, and recreational through travel
• Near- and long-term improvements
• Ease of travelling public and emergency response to cross railroad tracks
• Future impacts with and without an alternate route
• Various future growth scenarios for Luling
• Effects on businesses
• Types and ranges of visitors to downtown Luling
1
2
3
4
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 3 of 42
1.4 Study Area
The study area for the Study is comprised of the primary roadways approaching / departing Luling, including US 183, US 90 and SH 80, and five key
intersections within the City:
1. Magnolia Avenue (US 183) / FM 86 / Lincoln Street
2. Magnolia Avenue / Austin Street (US 183 / SH 80)
3. Magnolia Avenue / Pierce Street (US 183 / SH 80 / US 90)
4. Hackberry Avenue / Austin Street (SH 80)
5. Hackberry Avenue / Pierce Street (US 90)
Drivers entering Luling will typically pass through at least one of these intersections in route to their destination. Nearly all trips that pass through
Luling cross the Magnolia Avenue / Pierce Street intersection. A map of the study area is shown in Figure 1.
1.5 Project Timeline
The Luling Transportation Study began in fall 2018 with stakeholder discussions, data collection, and identification of local transportation issues.
Through the first half of 2019, the project team evaluated various potential improvement options using community input and technical analysis. This
report represents the culmination of the Study and provides a summary of the upfront data collection and evaluation processes as well as
recommendations and materials to guide the next steps of implementation.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 4 of 42
Figure 1 – Study Area
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 5 of 42
2 DATA AND DISCOVERY The first step in understanding current transportation conditions and needs in Luling was the comprehensive review of existing planning work,
community opinions, and available data. Combined with newly collected data, this body of information helped identify a list of transportation issues
and frame the evaluation of potential improvement options.
2.1 Review of Previous Plans and Studies
This section contains a literature review of previously adopted plans and studies with relevance to the Luling Transportation Study. Several planned
and funded transportation improvements in and around Luling were identified in the Caldwell County Transportation Plan and the 2040 Regional
Transportation Plan (RTP). Additionally, the City of Luling Master Plan identified several transportation issues related to mobility through Luling and
within downtown. Several other sources, including the TxDOT Unified Transportation Program, Statewide Transportation Improvement Program,
CAMPO four-year Transportation Improvement Program, TxDOT Letting Schedule, the 2009 Austin Area Freight Transportation Study, and the 2016
Texas Rail Plan, were reviewed, but these plans did not contain information pertinent to the Luling Transportation Study. Appendix A provides a
detailed review of each plan and maps of both funded and unfunded roadway capacity projects in the Luling area.
2.1.1 Caldwell County Transportation Plan
The Caldwell County Transportation Plan was adopted in March 2013 and was a collaboration between Caldwell County and CAMPO. Portions of
the analysis and recommendations pertained to major roadways in Luling and the surrounding area.
An analysis of the existing conditions (year 2010) indicated that most of Caldwell County’s roadway system operated at a level of service (LOS) C or
better. However, US 183 in downtown Luling was identified as LOS D. For forecast year 2035 with the existing roadway network and committed
projects, US 183 in downtown Luling and SH 80 and US 90 to the west of Luling exceeded LOS C. The analysis also included a 2035 scenario with
a relief route through Luling from US 183 north of downtown to IH 10, which resulted in better operations on US 183 through downtown but did not
improve LOS on SH 80 or US 90. The Plan recommends additional studies to compare LOS and environmental impacts before a preferred alternative
is chosen.
Table 1 provides a list of projects near Luling as document in the Caldwell County Transportation Plan. Each of these projects was envisioned to
occur over a long-term timeframe. In addition to the relief route alternatives, the Plan includes the widening of SH 80 to the Luling city limits.
In addition to capacity / operational improvement projects, the Caldwell County Transportation Plan identifies and prioritizes County roadway
maintenance projects based on the pavement condition, crash history, environmental considerations, and connectivity. N Hackberry Avenue is in the
top half of the prioritized list of County roadway segments needing maintenance. No other County roadways in the Luling area appear on this list.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 6 of 42
Table 1 – Luling Area Roadway Projects in Caldwell County Transportation Plan
Road Limit Improvement Type of
Improvement Jurisdiction
Estimated
Cost
(Millions)
SH 80 CR 111 / Political Road to
Luling City Limits Widen to four lanes
Existing
Roadway TxDOT $18.51
CR 309 /
US 183
US 183 to FM 2984, start
of West Relief Route Upgrade to 4-lane divided
Existing
Roadway County $0.72
US 183 Luling West Relief Route Proposed 4-lane divided
roadway
Proposed New
Roadway TBD $66.99
US 183 Luling East Relief Route Proposed 4-lane divided
roadway
Proposed New
Roadway TBD $71.81
2.1.2 2040 RTP
The CAMPO 2040 Regional Transportation Plan (RTP) was adopted in May 2015 and includes the long-term transportation vision for the six-county
region, including Caldwell County. The RTP included several recommendations within the City of Luling under “Chapter 5 Action Plan and Projects.”
Table 2 summarizes the Luling Area projects included in the RTP. Several projects in Caldwell County lacked allocated funds or sponsors. Unfunded
Luling projects include construction of a new four-lane divided highway identified as the Luling East Relief Route Alternative and the widening of SH
80 to four lanes from CR 111 / Political Road to the City Limits of Luling. Additionally, the Capital Area Rural Transportation System (CARTS) has
several near- and long-term projects that would expand transit service between Luling and neighboring jurisdictions.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 7 of 42
Table 2 – Luling Area Projects in CAMPO 2040 RTP
County Sponsor Location Project /Description Let Year
Estimated
Cost
(Millions)
Caldwell Caldwell US 183 North of Luling to US
183 / SH 80 South of Luling
Alternatives analysis for
relief route 2017 $0.3
Caldwell N/A* Luling East Relief Route
Alternative
Construct new 4-lane
divided highway N/A* N/A*
Caldwell N/A* SH 80 from CR 111/Political Rd
to Luling City Limit Widen to 4 lanes N/A* N/A*
Caldwell CARTS Caldwell County Fixed Routes to connect
cities in Caldwell County 2029 $5.1
Caldwell CARTS Luling to Lockhart Intercity Express Bus /
Luling Express 2023 $1.3
Caldwell / Hays CARTS Luling to San Marcos Intercity Express Bus 2030 $3.6
Caldwell CARTS Lockhart / Luling Intermodal Facility to serve
Lockhart / Luling Area 2021 $0.9
* Illustrative project without identified sponsor or funding
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 8 of 42
2.1.3 Luling Master Plan
The City of Luling Master Plan was adopted in 2012 and includes chapters on the topics of land use, housing, economic development, street and
drainage, water, wastewater, and recommendations for capital improvements.
The economic development section predicts an increase in traffic congestion, particularly from freight traffic, on SH 80 between Luling and San
Marcos and increase in delays on segments of US 183 from Lockhart to IH 10. The Master Plans recommends conducting a transportation study to
assess the long-term needs of the community, evaluate the viability of a relief route for traffic passing through the City, and establish a recommended
alternative.
A Central Business District (CBD) Analysis performed by this Plan identified segmented sidewalks, lack of crossings at some intersections (Magnolia
Avenue / Davis Street), parking issues during lunch time between Magnolia and Laurel Street, and rising traffic volumes within the CBD. The Plan
recommends adding crosswalks, sidewalks, and a transit circulator route within the CBD.
The recommended capital improvements list contains projects funded by the City from 2012 to 2017. Roadway improvements such as seal coat,
pavement rehabilitation, and resurfacing with curb and gutter were recommended for several City streets. A total pavement rehabilitation with curb
and gutter construction on Hackberry Street from the north City limits to Pierce Street was scheduled for 2015. However, as of 2019, no maintenance
projects have occurred on this roadway.
2.1.4 Railroad Plans
The 2016 Texas Rail Plan and Austin Area Freight Transportation
Study did not contain any planned rail safety or capacity projects that
would impact the number of train crossings per day or function of at-
grade crossing locations in Luling. According to discussions with the
Luling Chamber of Commerce and City of Luling staff, the Union
Pacific Railroad maintains the right to double-track through downtown
and has occasionally contacted the City to discuss closures of existing
at-grade crossings in exchange for infrastructure improvements and
quiet zone status. Though a scientific count of train activity in Luling
has not been conducted, City of Luling staff indicate that
approximately 40 to 50 trains pass through daily, with an average gate
closure time of 4 to 5 minutes per train.
Trains crossings can delay traffic approaching and departing the north leg of 183 / US 90 / SH 80 intersection by several minutes.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 9 of 42
2.2 Data Sources and Findings
Several data sources were used to develop a better understanding of existing transportation conditions and issues in Luling:
• Demographic data from the 2010 Census and American Community Survey.
• Economic data related to oil production in Luling and the surrounding Eagle Ford Shale region.
• Current and historical average annual daily traffic (AADT) volumes within the study area.
• PM peak hour turning movement counts at the five key intersections identified in Figure 1.
• Travel pattern and travel time metrics derived from aggregated cell phone and vehicle navigation data.
• Multi-year vehicle crash data.
• Environmental constraints including municipal and natural resources, floodplains, and other hazards.
2.2.1 Demographics
The 2018 estimated population of Luling is 5,954, a 10% increase from the 2010 Census count. The annual estimates suggest a fairly consistent
population growth rate of about 1% over an eight-year period, both during and after the oil boom. The population of the surrounding region has grown
somewhat faster than Luling. During the same period, the populations of Caldwell County and the Austin-Round Rock Metropolitan Area increased
by 14% and 26%, respectively. These data points, shown in Table 3. suggest that local population growth is not likely driving the recent increase in
traffic congestion on Luling roadways, but population and industrial growth in the surrounding region is leading to more trips passing-through Luling.
Table 3 – Population Data from 2010 - 2018
Location 2010 2011 2012 2013 2014 2015 2016 2017 2018
Luling 5,411 5,505 5,530 5,604 5,659 5,701 5,814 5,919 5,954
Caldwell
County 38,066 38,472 38,690 39,215 39,721 40,442 41,169 42,425 43,247
Austin-Round
Rock MSA 1,716,309 1,780,605 1,834,926 1,883,901 1,943,409 2,002,591 2,062,211 2,115,230 2,168,316
Notes: 2010 data based on the 2010 Census. All other years are estimated as part of the Populations Estimates Program.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 10 of 42
Socio-demographics information in Luling was compiled as part of the Environmental Justice analysis in the 2040 Regional Transportation Plan.
The land within the Luling City limits is considered an Environmental Justice area due to high concentrations of aging population (>9%), persons
with disabilities (>15%), limited English proficiency populations (>10%). Detailed demographic data and the Environmental Justice
sociodemographic maps are provided in Appendix B.
The Eagle Ford Shale Region and its Impact on Luling
The Eagle Ford Shale is a hydrocarbon-producing geological region with the capability of producing both natural gas and oil at higher yields than
traditional shale oil fields. The rising cost of oil in the early 2010’s resulted in a significant increase in oil production throughout the Eagle Ford Shale.
However, the decline and accompanying stabilization of oil prices in recent years has reduced both the issuance of drilling permits and overall oil
production within the Eagle Ford region (Figure 2).
Workers and freight traveling between San Marcos / Austin and the Eagle Ford Shale region will typically pass through Luling on SH 80 or US 183.
As is discussed in the next section (Average Annual Daily Traffic Counts), traffic on these corridors tends to fluctuate with production activity in the
Eagle Ford region.
Figure 2 – Drilling Permits Issued vs. Oil Production in the Eagle Ford Shale Region
Source: Texas Railroad Commission Production Data and Drilling Permit Query, accessed March 2018.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 11 of 42
2.2.2 Average Annual Daily Traffic Counts
Historical and existing traffic counts were collected for the study area to better understand the changing traffic characteristics of the region. Average
annual daily traffic (AADT) counts from the TxDOT Traffic Count Database System (TCDS) were compiled and summarized for the study area
roadways entering and exiting the City of Luling, shown in Figure 3. Figure 4 illustrates citywide AADT trends from 1999 to 2017 as well as major
events that may have influenced the rise and fall of traffic volumes. A detailed table of AADT and truck counts from the TCDS is provided in Appendix
C.
Over the 18-year period, AADT volumes grew by an
average of 1% across all locations. However, growth
spiked from 2011 to 2013 at two locations – SH 80 west
of Wall Street and US 183 east of Blanco Avenue. This
rapid traffic growth coincided with the peak of oil
production in Luling and the Eagle Ford Shale, as traffic
traveling between San Marcos and must traverse Luling
from SH 80 to US 183 to access the Eagle Ford Shale
and the Texas Gulf Coast. Volumes at these two
locations then decreased after the opening of the SH
130 extension between Lockhart and Seguin and after
Eagle Ford shale drilling permits began to decline.
Overall, the historical trends indicate that, while traffic
growth has been fairly low on most entering / exiting
roadway during the past two decades, volumes on SH
80 west and US 183 east may spike under “oil boom”
conditions.
Figure 3 – Roadways Entering/Existing Luling (use with Figure 4)
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 12 of 42
Figure 4 - Historical Counts Entering/Exiting Luling (use with Figure 3)
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 13 of 42
2.2.3 Peak Period Intersection Traffic Counts
Peak period traffic turning movement counts (TMCs) were collected for the five study area intersections identified in Figure 1. Based on input from
the Steering Committee and other community stakeholders, counts were conducted during the PM peak period of both a typical weekday
(Thursday) and a Friday. Stakeholders suggested that Friday traffic volumes were higher, particularly during the late spring through early summer,
due to recreational travel between Central
Texas cities and the Gulf Coast.
The Thursday and Friday TMCs were compared
for the PM peak period between 4 and 6 PM,
with the total entering count for each
intersection and the sum of all five intersections
calculated for each 15-minute period. Results
are summarized in Figure 5 and show that PM
peak traffic volumes in Luling are approximately
20% higher on Friday than during the same
period on a typical weekday. Due to the higher
traffic volumes and more congested conditions
observed on Friday, all operational and level of
service (LOS) analysis (discussed in the
Performance Measures section) was conducted
for Friday PM peak hour conditions.
Appendix C provides the detailed peak hour
TMCs at each intersection.
Figure 5 - Traffic Count Comparison at Study Intersections
~20% increase
SH 80 at
Hackberry
Avenue
US 183 &
SH 80 &
US 90
US 183 &
SH 80
US 183 &
SH 86
US 90 at
Hackberry
Avenue
Total (15-
minutes)
SH 80 at
Hackberry
Avenue
US 183 &
SH 80 &
US 90
US 183 &
SH 80
US 183 &
SH 86
US 90 at
Hackberry
Avenue
Total (15-
minutes)
16:00 241 381 346 236 179 1383 277 472 425 291 197 1662
16:15 217 351 347 254 108 1277 247 462 424 299 111 1543
16:30 189 383 348 259 98 1277 261 456 444 314 104 1579
16:45 205 368 348 253 102 1276 199 442 385 289 117 1432
17:00 178 382 333 243 108 1244 253 446 415 310 111 1535
17:15 190 378 349 266 111 1294 249 420 426 301 98 1494
17:30 191 379 345 241 104 1260 245 459 422 266 79 1471
17:45 201 344 310 200 108 1163 240 421 428 309 120 1518
Thursday, September 27th Friday, September 28th
Period
Start
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 14 of 42
2.2.4 Travel Patterns
Historic travel pattern and activity data was obtained and analyzed to better understand peak Friday travel conditions and the most common
routes of travel through Luling for automobiles and heavy trucks. StreetLight Data provided anonymized travel pattern data derived from GPS
enabled smart devices and in-vehicle navigation systems.1
Activity data was extracted for an average weekday and an average Friday between November 2016 and October 2017, which was the most recent
full year of data available at the point of extraction. Activity data was also characterized by vehicle classification (personal automobile, medium
duty commercial vehicle, and heavy commercial vehicles), day parts (including 3-hour PM peak period, 1-hour PM peak, and all day), and average
duration.
Figure 6 shows the estimated number of daily vehicles and heavy trucks on each of the roadways leading into/out of Luling on a typical Friday. The
three locations with the highest traffic demand are US 183 east of Blanco Avenue, US 183 north of FM 86, and SH 80 west of Wall Street. Heavy
trucks comprise a large proportion of total daily traffic at these locations – with SH 80 west of Wall Street consisting of almost 20% heavy trucks.
Nearly half of all daily trips traveling on SH 80 west of Wall Street traverse central Luling in route to / from US 183 east of Blanco Avenue. About a
third of daily trips at US 183 north of FM 86 make this same traversal. As shown in Figure 7, these traffic streams combine for a three block stretch
in downtown Luling between SH 80 and US 90, directly north of the Union Pacific Railroad crossing. While the total number of daily trips making
this traversal from SH 80 and US 183 north is about equal, about 70% more trucks go to / come from SH 80. Detailed outputs from the travel
pattern analysis are provided in Appendix D.
1 The device sample size used by StreetLight captures an average of 23% the travelling population.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 15 of 42
Figure 6 - Average Daily Traffic - 2017 (Friday Average) Total & Heavy Vehicles
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 16 of 42
Figure 7 - Average Daily Traffic - 2017 (Friday Average) Total & Heavy Vehicles Traversing Luling to/from SH 80 and US 183
* 47% of total trips entering/exiting at
SH 80 west of Wall Street; 58% of
heavy vehicle trips
** 32% of total trips entering/exiting at
US 183 north of FM 86; 53% of heavy
vehicle trips
*
**
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 17 of 42
2.2.5 Crash Data
Six years of crash records from the TxDOT Crash Records Information System (CRIS) were compiled for sections of US 183, US 90, and SH 80
within the Luling jurisdictional boundaries. The data, shown in Figure 8, indicate that the total number of crashes along these corridors in 2017 was
about equal to 2013 oil boom peak levels (despite the lower average daily traffic loads in 2017) and that crashes have increased every year since
2015. Also, serious and fatal injuries now make up a greater
share of crashes compared to several years ago.
Crashes on US 183, US 90, and SH 80 within central Luling were
mapped in Figure 9, showing the manner of the crash and totals
at major intersections. Over twice as many crashes occurred at
the Magnolia Avenue / Pierce Street Intersection (US 183 / SH 80
/ US 90) than at any other intersection in the mapped area. Over
70% of these crashes were rear-end or left-turn related, possibly
due to congestion and insufficient passage time from the traffic
signal. Additionally, three crashes involving railroad trains
happened at the at-grade crossing adjacent to this intersection.
Crashes involving a pedestrian occurred at two intersections –
Magnolia Avenue (US 183) / Davis Street and Pierce Street (US
90) / Walnut Avenue. The Magnolia Avenue / Davis Street
intersection is a major dividing point / barrier in the otherwise
walkable and active Davis Street corridor. Despite major
attractors to the east and west of Magnolia Avenue, there are no
marked crosswalks or protected crossing points across Magnolia
Avenue at Davis Street or Pierce Street. The Pierce Street /
Walnut Avenue intersection is a four-way controlled stop but had four crashes involving pedestrians over the six-year data period. As the primary
crossing point for residents walking from the northern half of Luling to the schools, hospital, and grocery store, a protected, signalized crossing may
be needed to improve pedestrian visibility and safety.
Appendix E includes a map of citywide crashes and a summary table of the crash types.
Figure 8 – Crashes on US 183, US 90, and SH 80 within Luling
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 18 of 42
Figure 9 – 2012-2017 Crashes in Central Luling
9
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 19 of 42
2.2.6 Environmental Constraints Mapping
Environmental constraints mapping is the process of identifying features related to land use, ecology, and geography that need to be considered
during conceptual design and feasibility of a transportation project. Watersheds and floodplains were obtained from the Federal Emergency
Management Agency (FEMA), and other sites were obtained from the Environmental Protection Agency (EPA) NEPAssist Tool. Parcel data was
obtained from the Caldwell County Appraisal District. The list below provides definitions for special features contained on the map:
• Historic Sites – sites contained on the National Register of Historic Places.
• National Pollutant Discharge Elimination System – sites with federal permit to discharge pollutants into waters of the United States.
• Hazardous Waste Resource Conservation and Recovery Act Information – sites registered as having generators, transporters, treaters,
storers, and disposers of hazardous waste.
• Toxic Releases Inventory – sites with toxic chemical releases and waste management activities reported annually by certain industries as
well as federal facilities.
• Threatened and Endangered Species Occurrence – potential habitat of specifies classified as threatened or endangered by the
Environmental Protection Agency.
• 100-year floodplain2 – land with a 1% annual chance of flood hazard.
• 500-year floodplain – land with a 0.2% annual chance of flood hazard.
• Parcels – division of property boundaries.
Figure 10 shows the environmental constraints map, with all the features described above. Floodplains and oil/gas pipelines are very prominent
on the map, with the 100-year floodplain covering large portions of land directly to the south, east, and north of Luling. Oil / gas pipelines
traverse much of the land to the north of the City.
2 Floodplains defined by FEMA do not account for new rainfall data in the Atlas 14 study. Areas in Central Texas that have modelled floodplains using the Atlas 14 data typically report
larger 100-year and 500-year floodplains than those defined by FEMA.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 20 of 42
Figure 10 - Environmental Constraints Map
10
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 21 of 42
2.3 Public Outreach A key component of the Luling Transportation Study was to engage the community and collect input from local stakeholders to develop a plan that reflects the values of the area and considers multiple perspectives. The goals, approach, and findings of this effort are summarized below with detailed notes and results provided in Appendix F.
2.3.1 Outreach Goals
• Create public awareness of the study and facilitate active and
collaborative participation
• Maintain an open and transparent process throughout the
engagement effort and provide timely and engaging project
updates
• Engage and collect input from a wide range of stakeholders,
including the local community, those visiting downtown Luling,
and through travelers
• Use public input and comments in the development and
refinement of the study
2.3.2 Approach
The Steering Committee made up of representatives from Caldwell
County, the City of Luling, the Luling Economic Development
Corporation, and TxDOT guided the study outreach process. Members
provided information on existing conditions and future plans and
assisted in the public engagement process.
Outreach was conducted in two rounds and utilized multiple tools to
notify and engage the community, including: email notices, social
media campaigns, signage, and a direct mailing. Outreach was conducted through local businesses and community organizations, open house
meetings were held, and two surveys were shared online and in paper format to collect input and feedback. To engage the Spanish speaking
population, materials were translated and bilingual team members visited with churches and building supply stores to distribute surveys.
Round 1 – General background information and traffic data was shared with the community and outreach focused on gathering input on existing
conditions and needs for transportation in Luling. A summary of results is provided in the next section.
Round 2 – Using input from round one, the study team developed potential near and long-term transportation solutions for Luling, and outreach was
focused on collecting input on potential improvements. Results of this outreach round are summarized in the Alternatives Analysis chapter.
Table 4 – Community & Stakeholder Meetings
Sept. &
Nov. 2018
• Meetings held with City Market, Caldwell County,
City of Luling, Luling Tire Service, Luling EDC, Big
Iron Trucking
• Steering Committee Meeting
Dec. 2018
• Visited 20+ businesses and groups in downtown
Luling
• Public Open House Meeting
Jan. 2019
• Meeting with Main Street Board of Directors
• Pop-up event at Mom’s Front Porch
• Steering Committee Meeting
• Focus group with EMS, City of Luling, and Seton
• Round 1 survey
Feb. 2019
• Pop-up events at Apple Lumber
• Visited 20+ businesses and groups in downtown
Luling
• Pop-up event at City Market
April 2019
• Mailer to 2300+ residents
• 2 Public Open House Meetings
• Round 2 survey
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 22 of 42
The project team and steering committee visited with many community members to share information and get their feedback during the study. Input was collected on maps, in surveys, in general comments, and in meetings. A summary of outreach activities conducted through the course of the project is provided in Table 4.
2.3.3 Round 1 Outreach Results
A community survey was developed in both English and Spanish and was administered between January 13, 2019 and February 24, 2019. The
purpose of this survey was to determine people’s perception of transportation conditions and issues within Luling and gauge opinions of the Luling
Transportation Study Goals. In total, 252 responses were completed. Detailed results are contained within Appendix F. Overall, more than 70% of
respondents agreed with the goals of the study. Other major findings and a sampling of written comments from the survey are provided below.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 23 of 42
2.4 Identified Issues
A list of current transportation issues in the Luling study area was compiled using the previous plans / studies, data analysis findings, public input,
and discussions with the Steering Committee. Table 5 provides a description of each issue, the source by which the issue was identified, and initial
thoughts on potential improvement methods. Figure 11 shows the locations of identified issues.
The identified issues served as a basis for the conceptualization and development of potential improvement options. This process is described in
the following section.
Figure 11 – Luling Transportation Issues Map
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 24 of 42
Table 5 – Luling Transportation Issues
# Issue Source Potential Improvement Methods
1 Queuing at southbound and westbound approaches to US 183 / US 90 / SH 80 intersection during peak periods.
• Insufficient capacity of two-lane approaches compared to traffic volume.
• Signal timing scheme provides equal green time to through, right, and left turn movements (split signal phasing) though peak demand is from southbound left and westbound right movements.
• Add capacity at US 183 / US 90 / SH 80 intersection.
• Improve signal timing and lane utilization scheme.
• Provide relief route around northeast quadrant.
2 Diversion of traffic onto local streets during periods of peak congestion. Some local streets were not built to accommodate high volumes or heavy vehicles.
• Eastbound traffic on SH 80 diverts to parallel streets ahead of US 183 intersection if increased queuing is perceived.
• Westbound traffic on US 183 / US 90 diverts to parallel streets (Cedar Avenue, Oak Avenue) ahead of US 183 / US 90 / SH 80 intersection if increased queuing is perceived.
• Degradation of pavement quality due to unanticipated heavy vehicle use.
• Round 1 public outreach mentioned cut-through and speeding traffic near Luling High School and the Seton Edgar B. Davis Hospital.
• Add capacity at US 183 / SH 80 / E Austin Street and US 183 / US 90 / SH 80 intersections.
• Traffic calming countermeasures on local streets.
• Improve wayfinding and route signage.
• Provide relief route around northwest and northeast quadrants.
• Improve Hackberry Avenue so that some heavy truck and vehicle traffic reroutes from US 183 between US 90 and SH 80.
• Provide direct grade-separated connection between SH 80 and US 90 (west of Hackberry Avenue).
3 Train crossings delay traffic approaching and departing north leg of 183 / US 90 / SH 80 intersection by several minutes.
• Several closures of at-grade crossing near 183 / US 90 / SH 80 intersection each hour and upwards of 50 closures every day, lasting around four to five minutes each.
• Grade-separation at railroad crossing on alternate route.
• Provide relief route around northwest and northeast quadrants; provide dynamic display signs to influence route choice for drivers.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 25 of 42
Table 5 – Luling Transportation Issues
# Issue Source Potential Improvement Methods
4 Occasionally, trains stall within downtown, blocking multiple crossing locations and limiting vehicle and emergency service.
• Feedback from Steering Committee and stakeholder outreach.
• During these events, options for crossing the railroad are often limited to the Davis Street crossing (west) and Elm Avenue (east).
• Grade-separation at railroad crossing on alternate route.
• New at-grade crossing and auxiliary route outside of downtown; UPRR typically request closures of at least two at-grade crossing to approve a new at-grade crossing.
5 Unsafe conditions for pedestrians on US 183 between US 90 and SH 80. Frequent vehicle collisions on this stretch of road can exacerbate traffic congestion.
• Feedback from Steering Committee and stakeholder outreach.
• No marked crosswalk currently exists at Davis Street / US 183 and no continuous sidewalks link to the nearest protected crossings.
• Crash data from 2012 – 2017 shows high concentration of rear-end, left-turn, and right-angle crashes. Two crashes involving a pedestrian at US 183 / Davis occurred during this time span.
• Improve Hackberry Avenue so that some heavy truck and vehicle traffic reroutes from US 183 between US 90 and SH 80.
• Provide relief route around northwest and/or northeast quadrants.
• Provide direct grade-separated connection between SH 80 and US 90 (west of Hackberry Avenue).
• Pedestrian crossing treatments at US 183 / Davis Street or at US 183 / SH 80 / US 90. Extend sidewalks along US 183.
6 Heavy freight traffic headed east-west via SH 80 and US 183, encounters bottleneck at US 183 / SH 80 / Austin Street and US 183 / US 90 / SH 80 intersections.
• StreetLight data indicates that this is movement with the heaviest daily and peak hour freight demand.
• Improve Hackberry Avenue so that some heavy truck and vehicle traffic reroutes from US 183 between US 90 and SH 80.
• Provide direct grade-separated connection between SH 80 and US 90 (west of Hackberry Avenue).
• Reconfigure lane assignment and signal timing at US 183 / US 90 / SH 80 intersection.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 26 of 42
3 POTENTIAL IMPROVEMENT OPTIONS Guided by the issues outlined in Table 5, the project team developed several conceptual infrastructure packages (“improvement options”) that could
improve transportation in Luling. The improvement options fell under two categories: near-term and long-term. Near-term options were judged to be
achievable within the next 5 – 7 years, while the long-term options, due to probable engineering and environmental complexities, were estimated to
require 10 – 20 years to implement. The near-term and long-term improvement were compared against each other and a “No Build” condition using
a set of performance measures agreed upon by the Steering Committee. During Round 2 public outreach, people who live and / or work in Luling
were surveyed to determine which improvement options they preferred. The project team then selected a set of recommended improvement options
using results of the performance measures comparison, input from Round 2 outreach, and discussions with the Steering Committee.
Detailed profiles of the potential improvement options, results of the performance measures analysis and Round 2 outreach; and the identification of
recommended improvements are contained in the following sections.
3.1 Option Profiles
A set of potential near-term improvements and three long-term improvement options are profiled in the following sections. The near-term
improvements can generally be described as upgrades to the existing roadway network in Luling. Because the near-term improvements consist of
projects with low-to-moderate design complexity and construction cost, they could likely be implemented within 5 – 7 years, depending on funding
availability. The three long-term improvement concepts – Options A, B, and C – consist of new location roadway corridors with complex design
features such as bridges and grade-separated railroad crossings (overpasses). Because each option would require considerable design,
environmental documentation, right-of-way (ROW) acquisition, funding procurement, and political effort, implementation would likely take 10 – 20
years.
3.1.1 Potential Near-Term Improvements
The potential near-term improvement would address several of the identified transportation issues by upgrading existing street, sidewalks, and traffic
control systems. Improvements would be concentrated in two locations – along Hackberry Avenue between Austin Street (SH 80) and Pierce Street
(US 90); and at the Magnolia Avenue / Pierce Street intersection (US 183 / SH 80 / US 90).
Hackberry Avenue is the city-designated truck route for trucks approaching / departing Luling on Austin Street (SH 80). If heavy trucks to / from
Austin Street were diverted onto Hackberry Avenue, traffic volumes would decrease at the congested southbound-left and westbound-right
movements of the Magnolia Avenue / Pierce Street intersection. Trucks entering Luling on Austin Street and headed towards the Eagle Ford Shale,
Texas Gulf Coast, and Houston would turn right onto Hackberry Avenue, turn left onto Pierce Street (US 90), and continue eastbound through the
Magnolia Avenue / Pierce Avenue intersection (US 183 / SH 80 / US 90). Trucks entering Luling from the east on Pierce Street would avoid the
westbound right-turn queuing at Magnolia Avenue / Pierce Street and the challenging northbound left-turn at Magnolia Avenue / Austin Street by
continuing westbound through at Magnolia Avenue, turning right onto Hackberry Street, and left onto Austin Street towards San Marcos. Trucks
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 27 of 42
coming to / from Lockhart on Magnolia Avenue (which are fewer in number than those to / from San Marcos) would continue to use the southbound-
left and westbound-right turning movements at Magnolia Avenue / Pierce Street, but the vehicle and heavy truck volumes at each intersection
movement would be more balanced overall.
A package of improvements that could encourage the use of Hackberry Avenue as a viable truck route, provide additional traffic flow improvements
at Magnolia Avenue / Pierce Street, and expand sidewalk connectivity and crosswalks, is described below.
Hackberry Avenue Improvements (Figure 12)
1. Install new traffic signals at Austin Street and Pierce Street and stripe crosswalks
across each approach. Signals would enable protected turning movements for
vehicles turning northbound-left at Hackberry Avenue / Austin Street and
southbound-left at Hackberry Avenue / Pierce Street, facilitating the diversion of
traffic flow. The signals and added crosswalks would also provide protected
crossings for pedestrians across both Austin Street and Davis Street, where
north-south crossing can be challenging and potentially dangerous during periods
of heavy traffic flow.
2. Repave the roadway between Austin Street and Pierce Street. Poor pavement
conditions on this stretch of roadway were noted by the Caldwell County
Transportation Plan, Luling Master Plan, and public feedback. Stakeholders
mentioned that uneven surface and potholes on Hackberry Avenue are the
primary reasons that truck drivers avoid the designated route.
3. Stripe the roadway centerline and intersection approaches. Clear indication of
north-south travel lanes and stop bars on stop-controlled side-streets (Watkins
Street, Fannin Street, Davis Street).
4. Construct sidewalks and reconstruct curbs on both sides of Hackberry Avenue
between Austin Street and Bowie Street. Sidewalks could be added either within
the easements on either side of the roadway or by narrowing the roadway
width. Combined with the new signals/crosswalks at Austin Street and Pierce
Street, pedestrians would have a protected walking route between the
northern half of Luling and the schools, hospital, and grocery store south of Pierce Street.
5. Install advance warning and truck route signage on Austin Street eastbound leading up to Hackberry Avenue and Pierce Street westbound
(east of Magnolia) to inform truck drivers of the designated truck route.
Figure 12 – Hackberry Avenue Near-Term Improvements
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 28 of 42
Magnolia Avenue / Pierce Street (US 183 / SH 80 / US 90) Improvements (Figure 13)
1. Stripe left-turn lanes on Magnolia Avenue / Pierce Street and modify signal heads to allow for a
protected left-turn phase. The existing signal runs on a pattern called split phasing (described on the
following page). By striping dedicated left-turn lanes for the southbound, eastbound, and westbound
left-turn movements at Magnolia Avenue / Pierce Street, a more efficient style of signal timing called
protected-permissive phasing would be possible. Protected-permissive phasing would provide green
time for protected left-turns and provide a new phase not possible under split phasing where through
traffic (east-west or north-south) is able to proceed through the intersection simultaneously. Eastbound
and westbound left-turn lanes would be able to fit on Pierce Street without widening the road or
repurposing through-lanes. Because Pierce Street is 60 feet wide from curb-to-curb, five 12-foot lanes3
could fit on each approach (two approach through lanes, one left-turn lane, and two departure lanes).
2. Stripe dedicated westbound right-turn lane on Pierce Street. Even with the reroute of trucks to
Hackberry Avenue, a high volume of trucks and automobiles would need to turn right from westbound
Pierce Street to northbound Magnolia Avenue. To accommodate the wide turning radius heavy truck,
minor roadway curb widening and right of way (ROW) acquisition may be needed on the northeast
corner of the intersection.
3. Construct sidewalks along both sides of Magnolia Avenue between Pierce Street and Davis Street.
Sidewalks do not currently exist on Magnolia Avenue between Pierce Street and Davis Street, which is
next to many of Luling’s most popular businesses and attractions.
4. Stripe crosswalks and construct/reconstruct curb ramps at each intersection approach; add
pedestrian countdown timer to north and west legs. Magnolia Avenue is a major dividing point/barrier
in the otherwise walkable and active Davis Street corridor. It is currently very difficult to cross Magnolia
Avenue and access Davis Street as a pedestrian, with the only protected crossing point at Austin Street
(SH 80).
3 TxDOT preferred standard lane width.
Figure 13 – Magnolia Avenue / Pierce Avenue Improvements
All proposed changes represented in magenta
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 29 of 42
What is Split Phasing?
Traffic signals can be timed in a variety of ways, with numerous combinations of protected turning movements in various sequences. In split phasing,
a street approach is given green time for all its movements concurrently (left, through, and right) while the three other street approaches are shown
red / required to stopped. The signal proceeds in this sequence for each of the three other approaches. Split phasing is a good option for intersections
that do not have the space for dedicated left-turn lanes but can be very inefficient when more than one approach has high traffic demand. Additionally,
if a vehicle is unable to clear the intersection on the green phase provided by a split phase signal, the time it will need to wait until the next green
phase is typically much longer than under most other signal timing schemes.
Additional Near-Term Studies
1. Neighborhood traffic calming study. Several Round 1 survey respondents mentioned that the streets surrounding the Luling High School,
Leonard Shanklin Elementary School, and Seton Edgar B. Davis Hospital felt unsafe due to cut-through traffic and speeding. A traffic calming
study would identify the extent of the cut-through and speeding issues, propose traffic calming treatments or other programs to address the
cut-through / speeding issues, and provide other information that may be needed to inform the design process and to pursue grants.
2. Safe routes to school plan. Round 1 survey respondents were concerned with the connectivity and safety of the sidewalk and crosswalk
network surrounding Luling High School and Leonard Shanklin Elementary School. A safe route to school plan would assess and prioritize
various improvements, monitoring and education programs, and potential funding sources.
3. Four-way stop sign evaluation at Walnut Avenue / Pierce Street intersection. This evaluation would determine the appropriateness of
removing and/or modifying the east-west stop-control at the Walnut Avenue / Pierce intersection. Following the installation of a new traffic
signal and crosswalks at Hackberry Avenue / Pierce Street, the east-west stop signs at Walnut Avenue / Pierce Street may no longer be
needed for pedestrian safety or traffic control, particularly if pedestrian crossing demand shifts to Hackberry Avenue. Removal of the east-
west stop-control may encourage more cross-town drivers to divert onto Hackberry Avenue.
3.1.2 Long-Term Improvement Options
The three long-term improvement options, shown in Figure 14, would provide new roadway connections to divert drivers through or around Luling,
alleviate traffic near downtown, and create a grade-separated crossing (roadway overpass) over the UPRR railroad tracks. Each long-term option
would come with considerable design, environmental, right-of-way (ROW), funding, and political challenges and would likely take 10 – 20 years to
implement.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 30 of 42
Option A
Construct a new roadway connection to the west of central
Luling from Austin Street (SH 80) to Pierce Street (US 90).
An overpass would span Davis Street and the UPRR tracks,
connecting with ramps at Pierce Street. The corridor would
essentially function as a realignment of Austin Street to
connect directly into Pierce Street (though the portion of
Austin Street east to Magnolia Avenue).
Option A would take over the function of Hackberry Avenue
as the primary truck route for drivers approaching / departing
Luling from SH 80 west. Similar to the potential near-term
improvements, vehicles would still pass through the
Magnolia Avenue / Pierce Street intersection (US 183 / SH
80 / US 90), but because the approaching traffic volumes
would be more balanced (less southbound, more
eastbound), intersection operations would improve
substantially compared to existing conditions. Option A
would not direct pass-through travelers (e.g. trucks,
recreational trips) away from central Luling, and businesses
oriented towards Pierce Street and Davis Street would be
visible to all pass-through trips on this route.
Option B
Construct a new roadway connection from Austin Street (SH
80) west to Pierce Street (US 183) east, passing north of
downtown and south of Salt Branch (the creek running south
of Trinity Street). An overpass would span FM 1322 and the UPRR tracks east of the city limits. New intersections would be created at Hackberry
Avenue and Magnolia Avenue (US 183) with a new traffic signal likely needed at Magnolia Avenue.
Option B would divert traffic from several cross-town routes that currently go through the Magnolia Avenue / Pierce Street intersection – including
heavy truck traffic from San Marcos and Lockhart to IH 10, the Eagle Ford Shale, and Texas Gulf Coast (and vice-versa). The path of Option B would
be slightly longer than routes on the existing roadway network, but design traffic would travel at somewhat higher speeds, encounter fewer signals,
and be unimpeded by trains. Traffic volumes and peak hour congestion levels would decrease at several of the primary intersections in central Luling.
Figure 14 – Long-Term Improvement Options
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 31 of 42
Option C
Construct a new roadway connection from Austin Street (SH 80) west to Pierce Street (US 183), passing north of downtown and Salt Branch. An
overpass would span FM 1322 and the UPRR tracks east of the city limits. east) north of town and north of Salt Branch, the creek running north of
Goliad Street and south of Trinity Street, from SH 80 to US 183 east of Blanco Avenue. New intersections would be created at Hackberry Avenue
and Magnolia Avenue (US 183) with a new traffic signal likely needed at Magnolia Avenue.
Option C’s impact on traffic diversion and congestion would be very similar to Option B. However, the alignment for Option C would require at least
two bridges over Salt Branch – one west of Hackberry Avenue and one east of Magnolia Avenue. From the perspective of right-of-way needs, Option
C would require more land, but the land would be further away from central Luling, generally less developed, and possibly less challenging to acquire.
3.1.3 Cost Estimates
Planning level costs estimates were prepared for the package of potential near-term improvements and each long-term improvement option. Table
6 summarizes the estimated range of costs for each option. Appendix G contain a full schedule of the items and assumptions used to generate the
cost estimates. It should be noted that costs were estimated with the project defined only at the conceptual level and in the absence of any detailed
design work.
Table 6 – Planning Level Cost Estimates
Improvement Option Cost (in thousand $)
Low High
Near-Term Improvements 1,180 1,290
Option A 6,800 9,900
Option B 20,900 25,200
Option C 27,700 35,050
Notes: Near-term improvements included all items discussed in Section 3.3.1. Full schedule
of items and assumptions is contained in Appendix G.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 32 of 42
3.2 Performance Measure Development
Multiple performance measures were developed in coordination with the Steering Committee as a means of analyzing and comparing the near-term
and long-term options. Performance measures were structured to capture the relative benefit or dis-benefit of a given option relative to the goals and
objectives of the project. The performance measures are listed in Table 7 as they relate to each of the four Study goals. Appendix H contains
additional information about the development of each performance measures, including units of measurement, general calculation method, and data
sources.
Table 7 – Performance Measure by Study Goal
Goal 1
Identify needed safety
improvements
Goal 2
Enhance mobility in downtown
for local and through traffic
Goal 3
Evaluate feasibility of an
alternate route for through
traffic
Goal 4
Promote the unique character
of downtown and economic
development opportunities
• Predicted annual crash rate
• Presence of new or improved
street crossings or walking
paths for pedestrians
• Provision of new grade-
separated (overpass) railroad
crossings
• Improvement to travel time
and reliability for evacuation
and emergency responders
• Estimated daily entering
traffic at Magnolia Avenue /
Pierce Street intersection
• Average cross-town travel
time, Friday PM peak
• Intersection level of service
(LOS), Friday PM peak
• Total railroad crossing delay
during Friday PM peak
• Planning cost estimate
• Environmental impacts in
terms of network fuel
consumption, Friday PM peak
• Overall environmental
suitability of improvements
• Number of vehicles passing
through Luling via Magnolia
Avenue / Pierce Street
intersection
• Improvements to pedestrian
connectivity along Magnolia
Avenue
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 33 of 42
3.3 Round 2 Outreach Results
A second public survey to understand community preferences about the potential near-term and long-term improvement options was administered
between April 15, 2019 and May 15, 2019. The opening of this survey coincided with public open houses and tabling held in multiple locations around
Luling on April 15. In total, 170 completed surveys were returned. Results show that nearly 80% of respondents think the proposed near-term
improvements will help make it easier and safer to travel in Luling. Additionally, a majority of respondents (56%) believe Option A will best serve
long-term transportation needs in Luling. About a third of respondents (33%) preferred options that would circumvent central Luling (Options B and
C). Preferences for the long-term improvement options are summarized in Table 8. Detailed survey results are contained in Appendix F.
Survey Question: Which of the potential options, if any, do you believe would best
serve long-term transportation needs in Luling?
Answer Choice Responses
Option A 56%
Option B 12%
Option C 21%
None of these 11%
Table 8 – Long-Term Improvement Preferences from the Second Public
Survey (Round 2 outreach)
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 34 of 42
3.4 Performance Measure Results Comparison
A performance measures matrix, shown in Table 9, was created to visually convey how each option compares to a No Build conditions, as well as
to each other, in future year 2045. The performance measures were calculated using the methods and data sources decribed in Appendix I. “Low”
and “high” traffic growth scenarios were both analyzed to account for uncertainty and to create create a range of performance for each option. The
“low” growth scenario used the average traffic growth rate experienced during the last 20 years in Luling while the “high” growth scenario accounted
for greater population and employment growth, approximating a sustained oil boom condition.
Generating “High” and “Low” Traffic Forecasts
The project team recognizes that there is not a clear indication of how transportation conditions will change through Luling over the next 25 years.
The oil boom ended several years ago, so some of the historical data indicates that traffic and truck growth will proceed at the moderate rates
observed during much of the last 20 years. However, it could be argued that the oil market is cyclical, and new production technologies or increase
in domestic/global demand could result in more booms like the one experienced between 2011 and 2014.
Several data sources and traffic models were reviewed to determine a potential range of growth rates (low and high):
• Historical traffic counts from TxDOT Traffic Count Database System (TCDS)– for locations with two or more years of available AADT data, a logarithmic (trendline) growth rate was calculated. All study location had data spanning 1999 – 2019.
• CAMPO 2040 Regional Transportation Plan (RTP) Model – CAMPO maintains a regional transportation plan model for long range traffic forecasting. CAMPO provided directional ADT and peak hour volume outputs for the City of Luling for years 2010 and 2040. Growth rates between these two years were calculated for each approaching/departing roadway.
Growth rates were averaged for the eight major roadways approaching/departing Luling. The average growth rate for the TCDS historical data is 1%,
and the average growth rate for the CAMPO RTP model outputs is 2.7%. The TCDS growth rate accounts for nearly 20 years of variation in traffic
volumes, including the emergence and dissipation of the oil boom between 2011 and 2014. The CAMPO RTP model may have somewhat higher
growth rates than the TCDS counts due to the expectation that population and employment growth in Caldwell County will begin to pick up as the
areas surrounding Austin continue to develop. To capture a range of potential traffic growth scenarios, the 1% annual growth rate from the TCDS
was assumed as a “low” scenario and the 2.7% CAMPO RTP rate as a “high” scenario. A detailed description of the travel demand forecasting
methodology and output is provided in Appendix J.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 35 of 42
Table 9 – Performance Measure Results Matrix
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 36 of 42
The bullet list below summarizes how the improvement options compare to each other for each performance measure.
• Predicted annual crash rate – The number of predicted annual crashes would decrease slightly compared to the No Build for
all improvement options. The difference in predicted crashes between the options would be small, though the long-term options
would have fewer crashes since the new connections would spread out traffic and reduce railroad conflicts.
• Presence of new or improved street crossing or walking paths for pedestrians – Only the near-term improvements would
add sidewalks and crosswalk network in the part of Luling where people are likely to walk.
• Provision of new grade-separated (overpass) railroad crossings – Due to complexity and cost, railroad overpasses were
only included for the long-term options. This is one of the main areas of need that the near-term improvements do not address.
• Improvement to travel time and reliability for evacuation and emergency responders – The analysis measures how many
acres of land can be accessed within a five-minute drive of the Luling Fire Department on Pecan Street. The analysis accounts
for predicted congestion at existing and proposed intersections and reductions in delay due to new roadways and overpasses.
Maps showing the coverage for each option are provided in Appendix I. By reducing congestion in central Luling, all the options
would significantly increase the amount of land that is accessible within 5 minutes. Despite the railroad overpasses included in
the long-term options, the coverage area would only be 5% greater than the near-term improvements, indicating that reducing
traffic congestion would have a more significant impact on evacuation/emergency response than grade-separation of the railroad.
• Daily entering traffic at Magnolia Avenue / Pierce Street intersection – Daily entering traffic at Magnolia Avenue / Pierce
Street would not change compared to No Build under near-term or Option A conditions, though traffic would be more distributed
among the intersection approaches. Options B and C would reduce entering traffic at the intersection by about 5,000 to 7,000
daily vehicles, a decrease of approximately 20%. Additionally, heavy truck traffic at the intersection would reduce by nearly 70%
under Options B and C (entering heavy truck estimates are shown in Appendix I).
• Average cross-town travel time, Friday PM – The average cross-town travel time represents the average amount of time it
would take, under 2045 PM peak conditions, to travel between the west and north Luling city limits and the east and south City
limits. All the studied improvement options would reduce cross-town peak travel time by at least half compared to No Build
conditions. Options A, B, and C would be result in slightly faster cross-town travel times because the new roadway corridors
would support slightly higher speeds and have fewer intersections than the existing cross-town roadways.
• Intersection level of service (LOS), Friday PM peak –TxDOT designs guidelines specify that intersections improvements
should operate at LOS D or better for at least 20 years after completion. All the improvement options would operate at LOS C
under the “low” growth scenario and D or better under the “high” growth scenario. Compared to a LOS C intersection, the average
car approaching a LOS D intersection would take about 20 more seconds to clear the intersection.
• Total railroad crossing delay during Friday PM peak – The railroad crossing delay analysis assumed an average of three
trains passing through Luling during the PM peak hour (compared to about 50 during an average day). The PM vehicle hours of
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 37 of 42
delay due to passing trains would decrease under all improvement options. Though the near-term improvements would not
provide an overpass of the UPRR tracks, the diversion of heavy truck traffic from Magnolia Avenue to Hackberry Avenue would
reduce traffic queue lengths on Magnolia Avenue during crossing events, so queues would dissipate faster after the reopening of
the guard-arms. Crossing delay would further decrease under the long-term options due to the overpass, with Options B and C
resulting in the highest decrease due to diversion of traffic from both SH 80 west and US 183 north.
• Planning cost estimate – The near-term improvements would require the least complex design and lowest implementation cost
of all the improvement options analyzed. The total cost for all near-term improvements defined in Section 3.1.1 would likely be
only a fraction of the cost of any of the long-term improvements. The long-term options, in addition to being larger in scale, would
also require more design, environmental, right-of-way (ROW), and political effort. Because Option A would have the shortest
route length, fewest environmental conflicts, and least ROW requirements, the total cost would be approximately half that of
Option B and one-third of Option C.
• Environmental impacts in terms of network fuel consumption, Friday PM – The amount of greenhouse gas emitted by
automobiles is a direct function of fuel consumption. In turn, automobile fuel consumption is dependent on distance travelled and
acceleration/deceleration (due to turns, stops, and interrupted traffic flow). PM peak fuel consumption would decrease under all
options due to improved traffic flow. Consumption would be lowest under Option A conditions because the new alignment
connecting Austin Street to Pierce Street would be a shorter distance than the existing shortest path (down Hackberry). Fuel
consumption for Options B and C would be slightly higher than Option A because the cross-town route, though faster, would be
longer than the existing path through central Luling.
• Overall environmental suitability of improvements – The near-term improvements would be contained almost entirely within
the existing ROW of TxDOT and local roadways, so few environmental impacts should be anticipated. Option A could be aligned
to avoid floodplains and oil / gas pipeline, though some consideration would need to be given to the proximity of pollutant and
waste discharge sites (active and former industrial businesses). Options B and C would approach or cross multiple floodplains,
pipelines, and several EPA-listed sites that might require remediation/mitigation. Option B could possibly avoid the floodplains,
but this route may come into conflict with civic amenities, historic sites, and waste discharge sites.
• Number of vehicles passing through Luling via Magnolia Avenue / Pierce Street intersection – This measure is an estimate
of the number of daily trips that pass-through Luling via the Magnolia Avenue / Pierce Street intersection, excluding trips that are
local, i.e. start and end in Luling. This is an approximate measure of how much exposure / visibility downtown Luling businesses
have to out-of-town drivers. Total pass-through traffic would remain the same compared to No Build under near-term and Option
A conditions, though more drivers would view downtown Luling from Pierce Street rather than Magnolia Avenue due to changed
routes. Under Options B and C, between 5,000 – 7,000 drivers (45 – 55% of No Build pass-through traffic) would be diverted from
downtown Luling on the new roadway corridors. However, drivers entering / leaving Luling on Pierce Street west (US 90) and
Magnolia Avenue south (SH 80 south) would still pass-by downtown.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 38 of 42
• Improvements to connectivity along Magnolia Avenue – Only the near-term improvements would add sidewalks and protected
crossing along the Magnolia Avenue corridor near downtown.
3.5 Recommended Improvements
Based on the results of the performance measures analysis, and Round 2 public survey, and Steering Committee input, this Study recommends the
continuation of project development for the near-term improvements and long-term Option A. The near-term improvements are recommended for
the following reasons:
• Significant community support
• Would relieve traffic congestion in central Luling for the next 25 years, but would not reduce the visibility of downtown Luling to pass-through
traffic
• Would improve pedestrian safety and connectivity within central Luling for both residents and visitors
• Least complex design effort and lowest cost of all the improvement packages analyzed
The long-term Option A improvements is recommended for continued project development for the following reasons:
• Most community support among the long-term options
• Would provide an overpass of the UPRR railroad for potentially half the cost of the other long-term options
• Fewer environmental constraints between Austin Street (SH 80) and Pierce Street (US 90)
• Would relieve traffic congestion in central Luling but would not reduce the visibility of downtown Luling to pass-through traffic
The near-term improvements would complement the new traffic patterns expected under Option A conditions, and the projects could be pursued
either concurrently or in sequence. The next section outlines next steps for the various stakeholders and some funding sources that could help
advance various stages of implementation.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 39 of 42
4 IMPLEMENTATION
4.1 Next Steps
Based on the results of the performance measures analysis, and Round 2 public survey, and Steering Committee input, this study has developed
several recommendations for near-term and long-term transportation improvement projects in Luling. The following bullet list summarizes these
recommendations and steps that will be necessary to progress implementation.
○ Recommendations for near-term transportation improvements (5 – 7 year timeframe)
• Incorporate near-term transportation improvements as defined in Section 3.1.1 into, at least, the 2045 Regional Transportation
Plan and Regional Arterials Study.4
• Determine lead agency and partnerships structure for project development.
• Create partnerships with State and local agencies and UPRR on project development for Hackberry Avenue repaving and
sidewalks improvements; Austin Street (SH 80) and Pierce Street (US 90) signal and crosswalk improvement at Hackberry
Avenue; advance warning truck route signage; and Magnolia Avenue / Pierce Street (US 183 / SH 80 / US 90) striping,
signal, crosswalk and sidewalk improvements.
• Coordinate with TxDOT and CAMPO to identify potential funding sources for project design and/or construction. Work with TxDOT
to pursue Categorical Exclusion for environmental documentation. As is beneficial, funding may be pursued for individual
components of the near-term improvements package. For example, the sidewalk and crosswalk improvements and the traffic
calming study may be eligible for Safe Routes to School grants, while roadway components would not be eligible.
• Consider local funding sources such as bond measure or Tax Increment Reinvestment Zone to fund upfront phases of project
development (i.e. preliminary engineering), local match requirements, and/or liquid capital for reimbursement-based programs.
○ Recommendations for long-term transportation improvements (10 - 20 year timeframe)
• Incorporate the Option A concept as defined in Section 3.1.2 into, at least, the 2045 Regional Transportation Plan and Regional
Arterials Study.4
• Determine lead agency and partnerships structure for project development.
• Explore funding opportunities for concept refinement, preliminary engineering, and environmental documentation.
• Coordinate with UPRR to ensure all activities align with their internal processes
4 The Regional Arterials Study will serve as an update to the current Caldwell County Transportation Plan.
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 40 of 42
4.2 Funding Sources
Securing funding can often be the most challenging aspect of project development. Transportation funding programs and tools are available at all
levels of government. The follow sections provide several options at the federal, state, and local level that could be available to Luling to fund either
the near-term or long-term recommended improvements.
4.2.1 Federal
Build Grants – Better Utilizing Investments to Leverage Development (BUILD), previously TIGER Discretionary Grants, are highly competitive grants
allocated annually by the US Department of Transportation (USDOT) to invest in transportation infrastructure projects. Any public entity is eligible for
a BUILD Grant and may use the funding for road and bridge, rail transportation, public transportation, port infrastructure, and research projects.
Projects can obtain from $5 million to $25 million with a state maximum of $90 million. Rural projects may be granted a minimum of $1 million and
transportation planning projects have no minimum. Federal share of costs may not exceed 80% for urban-area projects but may be increased for
rural projects. Project award will be based on the project’s ability to address safety, state of good repair, economic competitiveness, environmental
sustainability, and quality of life. The application and award process happen on an annual cycle, with the application period typically opening each
summer.
Federal Loan – The Transportation Infrastructure Finance and Innovation Act (TIFIA) provides fixed interest rate loans granted by the USDOT Build
America Bureau. The loans can be up to 49% of the project’s eligible costs and are offered at below market interest rates. Eligible projects include
roads, bridges, and pedestrian and bicycle infrastructure. Total project costs must be between $10 million and $75 million. TIFIA offers secured
(direct) loans, loan guarantees, and standby lines of credit.
MPO Distributed – CAMPO distributes federal and state funds from the Transportation Alternative Set-Aside (TASA), Surface Transportation Block
Grant (STBG), and Mobility and Congestion funding approximately every 2 years. Awarded projects are added to the regional Transportation
Improvement Program (TIP). The Mobility and Congestion funding, or Metropolitan and Urban Corridor Projects, are selected in consultation with the
TxDOT and, as such, criteria is regulated by TxDOT. The criteria for TASA and STBG have been established by the federal government. If seeking
construction funds, projects must be ready for construction within 4 years and be eligible for at least one of the three funds. TASA has the most
stringent criteria while STBG is the most flexible. TASA funds may be used for transportation projects or programs related to the construction,
planning, and design of safety measures for non-drivers, such as safe routes to school programs (23 U.S.C. § 213, 2012). It should be noted that
CAMPO administers TASA funds for jurisdictions within the Census-defined Large Urbanized Area5, and TxDOT administers funds for jurisdiction
outside this boundary. Because the Large Urbanized Area excludes Caldwell County, Luling would need to apply to TxDOT to receive TASA funds.
Eligibility for STBG includes, but is not limited to, construction of highways, bridges, operational improvements, and safety infrastructure
improvements. The project may not be located on a local road or rural minor collector, with some exceptions (23 U.S.C. § 133, 2012). This program
operates on a reimbursement basis, with the funds reimbursing up to 80% of the total project cost.
5 A map showing the Large Urbanized Area can be accessed at: http://ftp.dot.state.tx.us/pub/txdot-info/ptn/maps/austin.pdf
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 41 of 42
4.2.2 State
Safe Routes to School – The TxDOT Public Transportation Division administers Federal Highway Administration (FHWA) funds for locally
sponsored infrastructure projects that facilitate walking and biking to school. The funds are distributed by TxDOT for projects located within two miles
of a K-8 grade school. Eligible projects for Safe Routes to School (SRTS) include sidewalk improvements, pedestrian and bicycle crossing
improvements, bike facilities, traffic diversion improvements, and bike parking. No local contribution is required. A joint call for projects (TASA and
SRTS) is currently being deployed with funds awarded at the end of 2019.
Community Development Fund – The Texas Community Development Block Grant (TxCDBG) fund, also known as the Community Development
Fund, is a US Department of Housing and Urban Development fund for local community development used at the discretion of state and local
governments. Biennial applications to the Texas Department of Agriculture provide annual funds between $75,000 and $800,000 for affordable
housing, anti-poverty programs, and infrastructure development (including the construction of, and improvements to, water, sewer, and streets). The
project must benefit low- and moderate-income persons, prevent or eliminate slums, or address urgent community development needs posing a
serious and immediate threat to health or welfare of community for which other funding is not available. Cities with populations less than 50,000,
unless designated as a principal city of a Metropolitan Statistical Area, are eligible.
State Infrastructure Bank – The State Infrastructure Bank (SIB) offers access to federal and state funds for loans at or below market interest rates.
The project must be included in the State Transportation Improvement Program (STIP) and eligible for funding under existing federal highway rules
located in Title 23. There is no minimum amount and the maximum loan size varies. The funds may be used for all costs incidental to the construction
or reconstruction of public highways.
4.2.3 County and Local Level
Bond Measure – Fixed rate bonds are a common way to fund transportation projects at a local level. General obligation bonds are backed by income
tax, sales tax, and other levied taxes and would be placed on a ballot for residents to vote for or against the proposed tax increase. Revenue bonds
are supported through any tolls or fares generated from the proposed project.
Transportation Impact Fee (TIF) – TIF are fee charged to developers for the improvement of local transportation systems, required to be paid prior
to receiving construction permits. The fee is intended to recover incremental impacts of each new development while contributing to a list of local
improvements defined by the community. A TIF must be adopted locally by ordinance and usually requires an upfront study to evaluate total future
transportation system costs and calculate impact fee rates by development type and intensity. TIF systems are currently in place in Round Rock,
Hutto, and New Braunfels and are under consideration in Georgetown.
Tax Increment Reinvestment Zone (TIRZ) – Through a TIRZ, a city or county in Texas may set-aside tax money from existing property-based
taxes, relative to the annual increase in property values. This means residents will not see an increase in tax rates, but the entities that would collect
the tax would give a portion, or all, of future tax revenue above the amount collected at the time of implementation. The money collected from the
TIRZ can be used to fund infrastructure, landscaping, streetscaping, and other types of public enhancement. The proposed TIRZ area must be
LULING TRANSPORTATION STUDY SUMMARY REPORT – JULY 2019
Page 42 of 42
predominantly open or undeveloped, in a federally assisted new community, or in an area in which at least 50 percent of the appraised property
owners have petitioned for designation as a reinvestment zone (Texas Comptroller of Public Accounts, 2018, p. 2-3).