    Auxiliary transformers (3.5)

    Oct. 2012

    TRAINING MANUAL

    Vol. III: BALANCE of PLANT

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    2/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Contents

    1.General introduction

    2.Major technical data

    3.Design

    4.Outline and installation

    5.Operation

    6.Inspection and maintenance

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    3/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    General introduction

    1.New Bong Escape Hydropower Plant is equipped with two (2) sets of auxiliary transformers

    of identical construction

    2.The auxiliary transformers are of dry type design installed on mounting rails provided with

    steel enclosure of IP20

    3.The steel enclosures are painted in colour of RAL7032

    4.The insulation class is F

    5.The transformers are accessible via lockable swinging doors

    6.The transformers are equipped with temperature monitoring and control device mounted on

    the front panel of the transformers

    7.The transformers are design for natural air cooling during operation

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    4/12

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    5/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Major technical data

    Rated voltage ratio: 112x2.5% / 0.4 kV

    Rated capacity: 1600 kVA

    Rated impedance voltage: 6%

    Vector group: Dyn11

    Temperature rise: 80 K

    Cooling type: AN

    Degree of protection: IP20

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    6/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Design

    1.Each of the transformers has been dimensioned to carry full plant loads

    2.High voltage side is made for connections of single-phase cables of 240mm2

    3.Low voltage side is made for connections of copper busbar to 400VAC switchgear directly

    4.Neutral point of low voltage windings grounded directly through a ring-type current transformer

    for earth fault protection

    5.NLTC of 2 x 2.5% on HV side

    6.Arranged directly adjacent to the incoming feeder cubicles of 400VAC switchgear to facilitate

    busbar connections

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    7/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Design

    LV connection to 400VAC switchgear by

    copper busbar

    HV connection to generator switchgear

    by XLPE cable

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    8/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Outline and installation

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    9/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Outline and installation

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    10/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Operation

    1.The two auxiliary transformers are energized from the busbars of generator

    switchgear

    2.Each of the transformers are fed from two feeders via cable in parallel

    3.One of the two transformers will be connected to loads for normal operation

    4.Design calculation shows that normal loading of the transformer shall be in the

    range of 60 80% of rated capacity when all 4 units in operation

    5.Over-capacity operation shall be avoided

    6.Normal operation does not require attendance of any operational personnel

    7.Core and winding temperature can be read at LED display on the transformerenclosure at LV side

    8.Alarm signals of over-temperature is receivable at operator station in central

    control room

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    11/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Inspection and maintenance

    1.Daily visual inspection is required to disclose abnormal temperature, noise,vibration, and cleanness of the ventilation shield

    2.Annual maintenance is sufficient if the transformers are operating in a dry and

    clean environment, otherwise depending on the actual status the transformers

    shall be maintained in an interval of 3 6 months

    3.Before maintenance please make sure that the transformer is de-energized from

    both HV side and LV side, and manually switch over the loads to the other

    transformer.

    4.The following work shall be done for maintenance:

  • 7/28/2019 Training NBE AuxiliaryTransformer R0

    12/12

    New Bong Escape Balance of Plant

    Auxiliary transformers

    Inspection and maintenance

    Cleaning of transformer enclosure, surface, inside enclosure, and ventilation shield

    Visual inspection including surface damage on transformer body and crack of cast-

    resin layer of the winding

    Check of the electric-conductive elements and other parts free from dust, corrosion,

    trace of carbonization and electrical flash-over

    Please make sure that all tool and materials are removed from the transformer after

    maintenance before putting the transformer back into operation

    Please refer to NBE-203-08-201 for detailed instruction for handling, installation,

    operation, and maintenance