1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction reports for projects in progress as of April 24, 2015, are attached for your information. Pay Applications for all Capital Construction Projects for the month of March, 2015 is estimated to total just over $10.1M. (This includes design, construction, project management, construction material testing, abatement, City fees and service utilities)

Upload: others

Post on 02-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

1

TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction reports for projects in progress as of April 24, 2015, are attached for your information.

Pay Applications for all Capital Construction Projects for the month of March, 2015 is estimated to total just over $10.1M. (This includes design, construction, project management, construction material testing, abatement, City fees and service utilities)

Page 2: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

2

Natrona County School District No. 1 Construction Project Report

April 17, 2015 Project: Roosevelt HS/CAPS (Center for Advanced and Professional Studies) Project Phase: Construction Architect: MOA Architecture, Casper, WY and Cunningham

Group, Minneapolis, MN Civil Engineer: Civil Engineering Professionals, Inc. (CEPI), Casper,

WY Structural Engineer: Structural Solutions, Martin/Martin, Cheyenne, WY Mechanical/Plumbing Engineer: Engineering Design Associates (EDA), Casper, WY Electrical Engineer: Engineering Design Associates (EDA), Casper, WY Commissioning Agent: Group 14 Engineering, Inc., Denver, CO Owners Representative: Consilium Partners, Denver, CO General Contractor: Contractor: Groathouse Construction, Casper, WY Access to Site WebCam: http://oxblue.com/open/Groathouse/CAPSRooseveltHS

or http://www.ncsdtransform.org/CAPSRooseveltHS

Milestone Schedule Date Comment CAPS & RHS Construction Complete

March 2016 Planned

CAPS & RHS Certificate of Occupancy

January, 2016 Planned

Moving into buildings Summer, 2016 Planned Structural Steel Framing April 2015 Planned Exterior Metal Framing July 2015 Planned Building Exterior Envelope (CMU/Framing/Sheathing/Roofing/ Insulation/Brick/Panels)

August 2015 Planned

Building Interior Framing and Drywall

September 2015 Planned

Mechanical, Electrical, Plumbing, Fire Sprinkler (MEP) Rough In

August 2015 Planned

Ceilings, Finishes, and Accessories October 2015 Planned Substantial Completion December 2015 Planned Project Complete (all parking lots and landscaping

March 2016 Planned

Major Contractors/material suppliers working on project: Earthwork, Site Utilities Ramshorn Construction, Casper, WY Drilled piers Elco Drilling, Casper, WY Building Concrete S2M, Glenwood Springs, CO Electrical Casper Electric, Casper, WY HVAC & Plumbing Sheet Metal Specialties, Casper, WY Structural Steel supplier Pepper Tank, Casper, WY Masonry Contractor Wright Masonry, Salem, UT Roofing Contractor Big Horn Roofing, Laramie, WY

Page 3: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

3

Doors & Hardware Doorways of WY, Cheyenne, WY Coiling Doors/Grilles Overhead Door, Casper, WY Metal Stud framing & Drywall Advanced Wall Systems, Casper, WY Wood Gym Flooring Whited Flooring, Casper, WY Operable Partitions SD Inc., Casper, WY Site Concrete & Asphalt Knife River, Casper, WY Groathouse self perform work $5,819,768 Groathouse Construction Total Sum to Date for both projects: $36,816,709 CAPS Construction: $23,470,652 (63.75% of total) RHS Construction: $13,346,057 (36.25% of total) Project Contingency: $5,347,781 Contingency Balance: $5,138,629 Amount earned to date: $15,418,507 (Includes Retainage) % Complete: 42% Architectural Design fees CAPS: $1,891,820 Paid to date: $1,586,822 % Complete: 85% Architectural Design fees RHS: $1,081,758 Paid to date: $916,276 % Complete: 85% CAPS FF&E Budget: $985,767 RHS FF&E Budget: $560,535 1. Project Description

New High School Campus for Roosevelt High School (RHS), and Center for Advanced Professional Studies (CAPS)

The CAPS facility allowable square footage is 83,835 square feet (SF), 500 student capacity The RHS facility allowable square footage is 42,240 SF, 220 student capacity

2. Activities in Progress

RHS: structural masonry ongoing RHS: 2nd floor steel erection (currently on hold due to masonry re-build) RHS: Mechanical and electrical rough-in “in progress” CAPS East: Ductwork in crawlspace complete CAPS East: Heating piping in progress in crawlspace CAPS East: Exterior wall metal framing in progress CAPS East: Presentation Platform “in progress” CAPS West: Heating piping in progress in crawlspace CAPS West: Lower level floors complete, main level deck ongoing

Project Schedule Progress:

RHS: Foundation Walls – complete CAPS: Foundation Walls - complete RHS: Structural Masonry – 4 weeks behind schedule RHS: Structural Steel Installation –4 weeks behind schedule CAPS Structural Steel – 2 weeks behind schedule RHS: 1st Floor Slab – complete RHS Crawlspace Ductwork – complete CAPS “link” to RHS: Foundation wall and main floor slab; complete. Structural steel

framing from main level and up “on hold” CAPS East: Structural Steel Erection complete on upper levels (with decking in place) CAPS East: 2nd floor; concrete slabs; complete CAPS East Foundation Walls – complete

Page 4: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

4

CAPS West Foundation Walls - complete CAPS West Structural Steel and decking– 4 weeks behind schedule CAPS West: Ductwork in crawlspace complete Campus: Site Work – 5 weeks behind schedule

Construction Challenges:

Uncoordinated architectural / structural design issues continue to be found. South masonry wall of RHS is having the top half of the wall re-build due to error in

masonry construction.

Page 5: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

5

CAPS EAST – South side of building - viewed Southeast to Northwest

RHS – South side of building – viewed Southwest to Northeast

CAPS EAST – North and West face – viewed from Northwest to Southeast

Page 6: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

6

CAPS EAST – North and West face – viewed from Northwest to Southeast

CAPS EAST – stairs wrapping elevator shaft

Page 7: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

7

Natrona County School District No. 1 Construction Project Report

April 17, 2015

Project: Kelly Walsh High School new Building Project Phase: Construction

Architect: RB+B Architects, Fort Collins, CO and Amundsen Associates, Casper, WY

Civil Engineer: Worthington Lenhart and Carpenter, Inc. (WLC), Casper, WY Structural Engineer: Lower & Company, PC, Casper, WY Mechanical/Plumbing Engineer: Engineering Design Associates (EDA), Casper, WY Electrical Engineer: Engineering Design Associates (EDA), Casper, WY Electrical Sub-Contractor: Casper Electric, Casper, WY MEP Sub-Contractor: KK Mechanical, SLC, UT Commissioning Agent: Beaudin Ganze Consulting Engineers, Inc., Avon, CO Owners Representative: Consilium Partners, Denver, CO CMAR: Sampson Construction Co., Inc., Cheyenne, WY Major Contractors/material suppliers working on project: Excavation Ramshorn Construction, Casper, WY Drilled piers Elco Drilling, Casper, WY Concrete forming & reinforcing Jack Daniels Construction, UT Concrete reinforcing supplier Teton Steel, Casper, WY Electrical Casper Electric, Casper, WY Structural Steel supplier Western Slope Iron and Supply, Grand Junction, CO Masonry Contractor Soderberg Masonry, Fort Collins, CO Sampson Construction GMP: $80,236,982 (SFD funded incl Alternates & Enhancements) Total Project: $86,243,083 (incl Change Orders + Enhancements) Project Construction Contingency: $1,640,828 Balance Remaining: $1,083,557 Paid: $40,154,579 % Complete: 43% Architectural Design fees: $5,067,860 Paid to date: $3,998,984 % Complete :79% FF&E Budget: $3,131,772

Access to Site WebCam: http://www.ncsdtransform.org/kellywalsh

Milestone Schedule Date Comment West Building Foundations & Foundation Walls

Complete 12/19/2014 On schedule

West Building Steel Erection Complete in April 2015 On schedule East Building Exterior Envelope (CMU/Framing/Sheathing/ Roofing/Spray Foam/Brick/Metal Panels)

Complete Fall 2014 East Building enclosed and “dried in” but

envelope incomplete. Brick veneer installation ongoing

West Building Exterior Fall 2015 Ongoing; ahead of schedule

Page 8: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

8

Envelope CMU/Framing/ Sheathing/Roofing/Spray Foam/Brick/Metal Panels) East Building Interior Framing & Drywall

Start Fall 2014 Complete Summer 2015

Ongoing; nearing completion Ahead of schedule

West Building Interior Framing

Start Summer 2015 Complete Early 2016

Starting ahead of schedule

East Building Mechanical, Electrical, Plumbing, Fire Sprinkler (MEP) Rough In

Start Fall 2014 Complete Summer 2015

Ongoing

West Building Mechanical, Electrical, Plumbing, Fire Sprinkler (MEP) Rough In

Start Summer 2015 Complete Early 2016

Planned

East Building Ceilings, Finishes, and Accessories

Start Early 2015 Complete Fall 2015

Planned

West Building Ceilings, Finishes, and Accessories

Start Summer 2015 Complete Spring 2016

Planned

East Building Closeout Activities (pre-punch, punch list, commissioning)

Start Fall 2015 Complete Spring 2016

Planned

West Building Closeout Activities (pre-punch, punch list, commissioning)

Start Spring 2016 Complete early Summer

2016

Planned

New building occupancy Summer 2016 Planned

Theatre renovation Spring 2016 - Fall 2016 Planned New Music wing Summer 2016 – Summer

2017 Planned

Project Complete (all parking lots and landscaping)

Summer 2018 Planned

Page 9: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

9

                      

   KWHS Campus Building Project                

      SF  SF   

   Existing building        342,778  

       

   New KWHS SFD Project (Funded)   263,913 263,913 Sampson GMP  $80,236,982   

    

  

Enlarged Gymnasiums and Lower Level PE/Running Track (enhancement) 

   41,695    NCSD Funded  $5,535,284   

   CTE (enhancement)  3,000 NCSD Funded  $570,000   

  Commons (enhancement)   

1,500 

NCSD Funded  $125,200   

   Total Enhancements      46,195 46,195    $6,230,484   

       

  Existing Pool/Locker Rms (enhancement) 

   16,236       TBD   

  Pool Area Expansion Space (enhancement)   

6,188 

NCSD Funded  TBD   

  Campus Storage Space (enhancement)   

2,730 

NCSD Funded  TBD   

   Total Existing (enhancements)  25,154 25,154    TBD   

       

   Grand total New + enhancements     335,262    $86,467,466   

                      

1. Project Description Kelly Walsh High School new building and demolition of existing building

on current site Student design capacity is 1,574 students (building additions are planned for future increase

in KWHS enrollment) Seating capacity is 2,320 seats for the main gym and 495 seats for the aux gym. Seating capacity in the renovated theater is 542; renovation includes 1 lift. Building design has been modified to include saving the existing theatre and incorporation

into the new building. (Existing theatre will be renovated during the last months of the completion of construction phase of the new building, starting Spring 2016 – Fall 2016)

2. Activities in Progress

Foundation walls forming and pouring in Area F ongoing Foundation wall damp-proofing/waterproofing and backfill West building ongoing Steel decking installation ongoing at roofs in Area D Structural Steel installation is continuing in Area F Doors and Windows- Interior storefront installation to start in Area H in 2-3 weeks Finishes- Priming and painting ongoing on 1st and 2nd floor Area H, Area G 2nd floor

painting started, Area G 1st and 2nd floor drywall installation & tape and finishing ongoing, and Wall tile installation ongoing at Area H bathrooms

Page 10: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

10

Fire Suppression- Fire sprinkler rough in appears complete at Area G Plumbing- Rough in Area G ongoing, Roof drain installation ongoing in Area A, B, & C, and

Rough in ongoing in Area A, C, G & H crawlspace HVAC- Rough in ongoing at in Area G and Rough in ongoing in Area G & H crawlspace Electrical- Pulling electrical wire in conduits in Area H, Rough in at Area G ongoing, Rough

in ongoing in Area G & H crawlspace Communication- Cable tray & J-hook installation ongoing in Area H & G and Pulling data

cabling in Area H Earthwork- Wall backfill and site rough grading ongoing intermittently at Area A, B, & C Utilities- Switchover of new permanent power feed to the KWHS scheduled with Rocky

Mountain Power to take place July 2015 Drywall installation ongoing in G Drywall tape and finishing ongoing on in Area G Priming and painting ongoing in Area H and G Roofing ongoing at Areas A and C Brick veneer for Area H and G ongoing

Project Schedule Progress 0 days behind

Construction Challenges: o Retaining the existing swimming pool; all new utility connections and closure walls (2) after

demolition of remainder of KWHS building directly attributable to retaining the existing Pool building will be paid for by the SFD. District will be responsible for any work in spaces retained by District for future use (existing Wood Shop and existing Metal Shop and any site work necessary for the retainage of these existing spaces).

o Existing Gyms will be demolished with remainder of existing building

Page 11: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

11

o

Page 12: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

12

 

   

Page 13: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

13

    

Page 14: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

14

CMU Installation at Ag Lab – Viewed from the north 

Area F steel erection and concrete forming and pouring – Viewed from the southeast

Area F steel erection – Viewed from the south

Page 15: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

15

MEP rough in and data cable installation in Area G & H crawlspace – Viewed from the east

Page 16: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

16

Natrona County School District No. 1 Construction Project Report

April 17, 2015

Project: Natrona County High School Renovations, Main Bldg Project Phase: Phase 3 Construction, Site Construction, Landscaping starting Architect: Bassetti Architects, Seattle, WA and

Amundsen Associates, Casper, WY Civil Engineer: Worthington Lenhart and Carpenter, Inc. (WLC), Casper, WY Structural Engineer: PSC Structural Solutions, Tacoma, WA Mechanical/Plumbing Engineer: WSP Group, Seattle, WA Electrical Engineer: WSP Group, Seattle, WA Theatre Consultant: PLA Designs, Inc., Aloha, OR Electrical Sub-Contractor: Casper Electric, Casper, WY Mechanical/Plumbing GW Mechanical/Sheet Metal Specialties, Casper, WY Sub-Contractor: Commissioning Agent: Group 14 Engineering, Inc., Denver, CO Owners Representative: Consilium Partners, Denver, CO CMAR: A-P WY, Cheyenne, WY A-P WY GMP: $93,902,186 (SFD funded) Total Project: $94,736,547 (incl Enhancement +

“unforeseen conditions”) AP GMP breakout by phase: Early site development and general conditions = $23,391,642 Phase 3 = $29,901,963 Phase 4 = $15,320,676 Phase 5&6 = $26,122,266 Phase 3: Paid $26,765,741 % Complete= 90% SFD Budget Contingency: $2,742,983 Balance remaining = $2,417,611 A-P Wyoming Construction Contingency = $2,404,644 Balance Remaining: $2,212,050 Architectural Design fees: $12,236,365 Paid to date: $8,898,260 % Complete :73% FF&E Budget: $3,943,892

Access to Site WebCam: http://oxblue.com/open/A-P/NatronaCSD or http://www.ncsdtransform.org/natronacountyhighschool

Milestone Schedule Date Comment Design complete

Fall 2014 100% Construction Drawings

issued on 11/24/2014 Phase 3; Demolition NE portion Main Bldg, Building new Northeast addition

Start Summer 2014 Completion Summer 2015

Phase 3 is on schedule

Phase 3 Structural Masonry Start November 2015 Complete February Started on Schedule

Page 17: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

17

Phase 3 Concrete Slabs Start November 2014 Complete February 2015

Majority of work completed on Schedule

Phase 3 Structural Steel Start Early December 2014 Complete February 2015

Majority of work completed on Schedule

Phase 3 Building Envelope Start January 2015 Complete Summer 2015

Started on schedule

Phase 3 Interior Framing & Drywall

Start January 2015 Complete May 2015

Started on scheduled

Phase 3 Mechanical, Electrical, Plumbing (MEP) rough in

Start January 2015 Complete April 2015

Started on schedule

Phase 3 Finishes Installation Start May 2015 Complete July 2015

Planned

Phase 3 Closeout (pre-punch, punch list, building commissioning)

Start July 2015 Complete August 2015

Planned

Phase 4; Construction Starts East & South portions of exist. Bldg. incl. Auditorium/Theatre, classrooms

Start Summer 2015 Planned

Completion Summer 2016

Phase 5 & 6; Construction Starts West and NW portions of exist. Bldg. incl. Band/Vocal, Classrooms, Courtyard, Arts and new Main gym

Start Summer 2016 Planned

Completion Early 2018

Phase 7; Final Site Development completion

Start Summer 2017 Planned

Completion Fall 2018

Page 18: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

18

                       

   NCHS Campus Building Project                

      SF  SF    

   Existing Main NCHS Building + VocEd  327,544   

        

  Main NCHS Bldg SFD (Funded) 

   302,644 302,644         

  Deduct SFAC** Permanent PE space (attributable to Main Bldg project) 

   41,920    SFD Funded  $11,163,739    

   Total Main NCHS Bldg   260,724 A‐P GMP  $93,902,186    

   Total Cost              $105,065,925    

     

  SFAC** Athletic/Fitness space (after 2018, enhancement) 

   59,880    NCSD Funded  $4,985,760    

   CTE (enhancement)  2,205 NCSD Funded  $630,000    

   Total Enhancements      62,085 62,085    $5,615,760    

   **Total SFAC = 101,800 SF    

        

  Grand total New NCHS + SFAC 

      364,729    $110,681,685    

                       

1. Project Description

Natrona County High School Renovations, including detailed work to preserve the integrity of the historic building while accommodating the learning needs of today’s students.

Student design capacity is 1805 students Seating capacity in the main gym is 1,764 and seating capacity in the theater is 837

2. Activities in Progress

Concrete- Slab on grade and concrete benches prep & pour ongoing at South commons area Masonry- CMU veneer and brick installation ongoing at all aspects of CTE labs and the East

building elevation Metals- Exterior framing and sheathing ongoing at commons area, Interior soffits and hard lid

ceiling framing complete at ground and 1st floor level, and Interior wall framing appears nearing completion at 2nd floor

Wood, Plastics, and Composites- In wall blocking at 1st & 2nd floor appears complete Thermal and Moisture Protection- Fluid applied air barrier installation ongoing at 3rd floor

mechanical penthouse and Roofing installation ongoing Openings- Interior hollow metal frames being installed in conjunction with interior framing and

Curtain wall installation ongoing at commons area Finishes- Bathroom wall tile installation ongoing at ground level, Grid ceiling installation

ongoing at ground level & 1st floor, Painting ongoing at ground level and started at 1st level,

Page 19: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

19

Drywall finishing ongoing at 1st floor, Drywall installation nearing completion at 1st floor and ongoing at 2nd floor, and Epoxy flooring install appears complete and is protected on ground level

Fire Suppression- Fire sprinkler rough in ongoing at ground and 1st floor and Fire sprinkler drops to ceiling grid started at ground level

Plumbing- Rough in ongoing on ground (at CTE), 1st & 2nd floor and Rough in starting at 2nd and 3rd floor mechanical rooms

HVAC- Rough in ongoing on ground (at CTE), 1st & 2nd floor, Rough in ongoing at 2nd and 3rd floor mechanical rooms, and equipment being installed on roof.

Electrical- Rough in ongoing on ground, 1st & 2nd floor and Rough in ongoing at 2nd and 3rd floor mechanical rooms

Communications- Cable tray installation ongoing at 1st & 2nd floor and Data cabling (all types) being installed at ground level

Exterior Improvements- Irrigation and landscaping installation started around SFAC building- This work was not scheduled to start until summer, but advantageous weather has allowed the contractor to start early.

Project Schedule Progress 0 days behind

Construction Challenges: All existing infrastructure; electrical, mechanical, plumbing, intercom, fire alarm, etc. has to

remain in place along with all new items until each phase is completed and new infrastructure is brought “on line” and accepted

Moving to the “Swing Space” at each phase then moving back to the renovated/new portions of the Main building between phases will be completed with each phase through 2018

NCHS staff has requested a storage room be converted to a training room for athletics which is estimated to cost $35,000. SFD will not fund changes in project scope. Recommend tabling this programming and use change until the construction project is complete.

AP Wyoming has submitted a request for additional pre construction fees for services beyond September 30th when Design was originally scheduled to complete. SFD and District are researching request.

Page 20: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

20

Northeast building expansion brick and masonry veneer installation – Viewed from the southeast

Structural steel erection at south commons – Viewed from the north

Page 21: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

21

MEP rough in and drywall installation at 2nd floor – Viewed from the north

Commons area viewed from the north from the 2nd floor corridor

Page 22: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

22

Natrona County School District No. 1 Construction Project Report

April 17, 2015

Project: Lincoln Elementary School Project Phase: Construction 945 N. Jane St

Casper, WY

Architect: MOA Architecture, Casper, WY Civil Engineer: Inberg-Miller, Casper, WY Structural Engineer: Martin/Martin, Cheyenne, WY Mechanical Engineer: Engineering Design Associates, Casper, WY Electrical Engineer: Engineering Design Associates, Casper, WY Plumbing Engineer: Engineering Design Associates, Casper, WY Commissioning Agent: Beaudin Ganze Consulting Engineers, Inc., Avon, CO Owners Representative: Consilium Partners, Denver, CO General Contractor: A-P WY, Cheyenne, WY Major Contractors/material suppliers working on project: Excavation, Utilities Barnum Construction, Buffalo, WY Asphalt & site concrete Knife River, Casper, WY Landscape Stoner, Casper, WY Concrete forming & reinforcing S&S Builders, Gillette, WY Concrete reinforcing supplier Teton Steel, Casper, WY Concrete slabs Total Concrete Services, Denver, CO Electrical Casper Electric, Casper, WY Plumbing CK Mechanical, Casper, WY HVAC CK Mechanical, Casper, WY Structural Fabrication Pepper Tank, Casper, WY Structural Steel erector Building Construction, Gillette, WY Masonry Contractor Division IV, NE Roofing Big Horn Roofing, Laramie, WY Windows/Glazing Overhead Door, Casper, WY Flooring Carpet One, Casper, WY Drywall RDJ Brothers, CO Ceilings Innovative Interiors, Fire Sprinklers Rapid Fire, Casper, WY A-P Contract Amount: $11,981,896 (Inc Alternates) Construction Contingency: $2,950,407 Balance Remaining: $2,713,611 Paid: $10,861,416 (includes retainage) % Complete: 91%

Architectural Design fees: $1,135,890 Paid to date: $1,104,507 % Complete = 97 % FF&E Budget: $503,240

Page 23: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

23

Milestone Schedule Date Comment Construction Start February 2014 Final Site Development December 2014 90% Complete Exterior Envelope (Structural Stud Framing, Insulation, Windows, Metal Panels)

December 2014 98% Complete

Drywall December 2014 Complete Tape Finish Walls and Soffits

January 2014 Complete

Drop Ceiling Tile February 2014 99% Complete Install Doors and Hardware March 2015 Complete Substantial Completion April 16, 2015 Scheduled Closeout Activities (pre-punch, punch list, commissioning)

To complete May 16, 2015 To complete within 30 days of Substantial Completion

Overall project completion May 2015 Scheduled 1. Project Description

Elementary school K-5, designed for 4/3 model Approximately 384 student capacity Approximately 53,211 square feet

2. Activities in Progress

• Playground equipment installation • Landscaping • Testing and Balancing HVAC systems • Architectural and Owner punch of interior spaces • Engineering punch of interior spaces • Mechanical and Electrical; Commissioning of systems • Final Building inspections by City of Casper for Temporary CO • Final cleaning • GYM floor; painting of stripes • Fencing and Gates • Interior signage • Site signage

Project Schedule Progress

Exterior Framing & Building Envelope – complete HVAC – complete Drywall – complete Controls and communication cabling complete Site work – 2 weeks behind schedule • Utilities – Complete • Monument sign and minor masonry complete • Interior Drywall complete • Gymnasium painting complete • Area A and B painting complete • Wall tile on corridor walls complete

Page 24: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

24

• Rough in plumbing complete • Plumbing – fixture installation complete • Rough-in electrical complete • Lighting complete • Metal wall panel installation complete • Window installation complete • Sidewalks and flatwork complete • Grid Ceiling complete Lay-in ceiling tiles (99% complete) Sod has been installed, site work on-going

Construction Challenges

o No current challenges.

Page 25: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

25

Administrative Offices / Front Desk Area

South and West face of building

Page 26: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

26

Teacher’s entry (Viewed from South)

Page 27: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

27

Natrona County School District No. 1 Construction Project Report

April 17, 2015

Project: Pineview Elementary School Project Phase: Design 639 Payne Avenue Casper, WY

Architect: Stateline No. 7, Casper, Wyoming Civil Engineer: WLC, Casper, Wyoming Structural Engineer: Lower & Company, Casper, Wyoming Mechanical Engineer: Engineering Design Associates, Casper, Wyoming Electrical Engineer: Engineering Design Associates, Casper, Wyoming Plumbing Engineer: Engineering Design Associates, Casper, Wyoming

Milestone Schedule Date Comment 10% SFD VE Design Review January 10, 2014 Completed

35% SFD VE Design Review August 5, 2014 Completed 65% SFD VE Design Review November 25, 2014 Completed without SFD Review 95% SFD VE Design Review March 2015 Completed without SFD Review

Architectural Design fees: $913,429 Paid to date: $ 624,877 % Complete = 68% 1. Project Description

Elementary school K-5, 3/2 model including 6 additional classrooms for District Gifted & Talented students

Approximately 384 student capacity Approximately 53,197 square feet Project currently funded for design only – (Project has not been funded for Construction)

2. Activities in Progress 65% Design is 100% complete 65% Design Review by NCSD Staff completed 1/6/2015 SFD issued notice to proceed to 95% design January 8,2015 95% Kick off Meeting Scheduled for Wednesday January 21, 2015 65% Design Review comments reviewed by Architect and returned to District Staff. 95% Design ongoing. Submittal scheduled for March 26, 2015 95% Design Submitted. Currently undergoing NCSD Review. Review comments to be returned to Stateline No. 7 April 28

Construction Challenges No Construction funding allocated by the Legislature at this time.

Page 28: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

28

Concept Drawing Pineview Elementary

Page 29: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

29

Natrona County School District No. 1 Construction Project Report

April 17, 2015

Project: Dean Morgan Renovations and Campus Planning Project Phase: Phase 2D

Funding Sources: Major Maintenance Funding (Estimated $4 million/year for the completion of the building renovation project, currently in third year of 4 year project) This does not include the site work (new PE & athletic fields and new parking lot, this will be an additional Phase, not yet funded)

Architect: MOA Architecture, Casper, WY and Denver, CO Civil Engineer: Civil Engineering Professionals, Inc., Casper, WY Electrical Engineer: Engineering Design Associates, Casper, WY Mechanical Engineer: Engineering Design Associates, Casper, WY Structural Engineer: Daigle Engineering, Casper, WY CMAR Groathouse Construction, Casper, WY Major Contractors/material suppliers working on project: Electrical ITC, Casper, WY Plumbing GW Mechanical, Casper, WY HVAC Sheet Metal Specialties, Casper, WY Glazing/Windows Overhead Door, Casper, WY Data, Intercom, Fire Alarm Comtronix, Casper, WY Flooring Hub Flooring, Casper, WY Paid: $10,186,462.15 % Complete: TBD based on final phase GMP

Milestone Schedule Date Comment Phase 1 Construction Started May 16, 2012 Completed

Phase 2 Construction Started June 1, 2013 Complete June 2014

Phase 3A Construction Start June 2, 2014 Complete August 2014

Phase 3B Construction Start September 2014 Complete October 2014

Phase 3C.1 Construction Start November 2014 January 2015

Phase 3C.2 Construction Start November 2014 January 2015

Phase 3D Construction Start January 2015 February 2015

Phase 3E Construction Start March 2015 May 2015

Phase 3F Construction Start May 2015 July 2015

1. Project Description

Complete Renovation of existing building and Campus planning

Page 30: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

30

2. Activities in Progress

Project is on schedule Classroom renovations are being completed during the school year in phases with the use of

the 4 portable classrooms located in the parking lot Upcoming renovation phases include: Media Center, Home Ec area & classrooms, Kitchen

and additional new elevator, and Administration area Phase 3D completed 3/5/2015 Phase 3E Demolition Started 3/10/2015. Phase 3E Scheduled completion 5/10/2015 Bid for Phase 4 Construct 3/19/2015, Includes renovation of Production Kitchen new

Loading Dock & Ramp, Renovation of Family And Consumer Science , Installation of new Exterior Door System & New Front Security Entrance. Remodel of Last 2 Classroom Spaces.

Phase 4 Guaranteed Maximum Price $4,134,517 approved by the board 4/13/2015 Material procurement in progress.

Construction Challenges:

o Complete interior building renovation during school year with students attending school; work is being completed after school hours and weekends

o Scheduling the movement of classes as the renovation continues in the building continues with the use of the temporary four-classroom portable in existing north parking lot

o Moving Administration and keeping them functional during demolition & construction o Abatement of hidden material during construction, and in an occupied space, completed o Creation of swing space in the school to house the Media Center and Administration areas to

maintain access during renovation. o Phasing of moves for renovation Media Center, Administration Area, Family and Consumer

Science Areas. o Demolition of concrete school safe in administration area.

Page 31: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

31

DMJH PROGRESS DRAWING

Page 32: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

32

Heating Duct installation Phase 3E Admin Offices

Paint prep Phase 3E Admin Offices

Page 33: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

33

Grid ceiling installation Phase 3E Admin Offices

Above ceiling prep for Phase 4 first floor cross hall

Page 34: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

34

Natrona County School District No. 1 Construction Project Report

April 17, 2015

Project: Bar Nunn Elementary School Addition Project Phase: Planning 2050 Siebke Dr. Bar Nunn, Wyoming 82601

Funding Sources: SFD Planning Architect: GSG Architecture, Casper, WY Planning Allocation: $24,580 Construction Allocation: $4,092,089 Final Design Allocation: $563,021 Description

Construct an addition to Bar Nunn Elementary School to allow it to convert to a 4/3 model to support a new capacity of 384 students with a 16,479 square foot addition

Total number of classrooms will be twenty-two, not including rooms for other District programs. GSG Architecture, Casper, was selected for the “Planning Phase.” RFP will be issued for the “Design Phase” services after “Planning Phase” has been accepted

Activity:

Planning report complete and provided to SFD Cost estimate presented to NCSD & SFD December 2, 2014

o Estimated cost $7.7 million (construction cost), Over Budget o SFD Budget is $3.7 million (construction cost)

SFD budget does not include cost to reconfigure existing space to support 4/3 model school, 384 students and bring building up to code

SFD budget doesn’t reflect school program that includes SpEd & PreK SFD budget doesn’t reflect construction costs in current environment

Next steps: o SFD has agreed to fund value engineering on the planning design to identify cost savings o SFD & NCSD to meet (not yet scheduled) to identify and discuss options

Page 35: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

35

Natrona County School District No. 1 Construction Project Report

April 17, 2015 Project: New Capacity Elementary School (old CYJHS Site) Project Phase: Design

2211 Essex Ave Casper, WY 82604

SFD Construction Allocation: $13,310,333 SFD Design Allocation: $1,000,000 Architect: RB+B Architects, Fort Collins, CO SFD Abatement & Demolition Allocation: $2,560,208 Project Description:

Demolish all of existing CYJH except for main and auxiliary gyms and original locker rooms. The gyms will be renovated for temporary use while NCHS is under construction (approximately

4 years). A new 4/3 elementary school with a capacity of 384 students will be constructed on the existing

site after existing building demolition. The new elementary school will be based on other existing elementary schools previously

designed by a yet to be selected architectural firm. Tentative Schedule:

o Site Demolition drawings complete July, 2015 o HazMat Abatement complete Early May, 2015 o Demolition start Aug, 2015 o Demolition complete Oct, 2015 o School design complete- project out to bid November 2015 o Construction bid award December 2015 o School construction complete June 2017 o School occupancy July 2017

Activity: Hazardous Materials (Asbestos) abatement started 2/4/15, contractor is about 3 weeks behind

schedule. It does not have impact on other activities Demolition design contract executed; demolition design underway. Demolition design and

demolition schedule revised to coordinate the final grades on the new school with the demolition. Demolition scheduled to start Late Aug 2015 and finish in Oct 2015. Existing Gymnasiums & locker room minor renovations complete. This project is an

Enhancement approved by the NCSD Trustees, June 23, 2014. Design contract awarded to RB+B for Capacity ES design, design underway Design complete: Oct 2015, Bid Nov 2015, Award Dec 2015 Construction final completion June 2017 FF&E/Occupancy July 2017

Page 36: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

36

Major Maintenance

A list of all projects follows. Highlights from Major Maintenance Projects

174 projects totaling $5.7 million ($208,500 in 10% funds) 23 security related projects Planning secure front entrance for Evansville Design bids for Manor Heights Elevator to be received 4/23 Frontier HVAC control system to be replaced this summer Asphalt maintenance plan phase 1 complete, $100K of asphalt maintenance planned for summer New intercom installed @ Summit

Major Maintenance Projects

Facility  WO  Status  Scope  Budget 

($)  Balance ($)10,664,086 

1224 Club  055438  Complete  Renovate for bus hub  150,000  10,514,086 

1224 Club  056715  Execute  Abate and replace floor covering    50,000  10,464,086 

Alcova  056373  Execute  Asphalt assessment and maintenance plan   2,000  10,462,086 

Alcova  057412  Pending  ADA / Truncated Dome Installation   1,500  10,460,586 

Bar Nunn  055472  Complete  Fall protection material for playgrounds   556  10,460,030 

Bar Nunn  057409  Pending  Crack seal, seal coat, restripe asphalt    20,000  10,440,030 

Bar Nunn  056374  Execute  Asphalt assessment and maintenance plan   2,000  10,438,030 

Bar Nunn  056296  Execute  Install wireless computer managed locks    40,000  10,398,030 

Centennial  054408  Execute  Replace roofing over center section  125,000  10,273,030 

Centennial  056515  Execute  Replace 2 15 ton rooftop AC units    40,000  10,233,030 

Centennial  056516  Execute  Replace compressor in Walk‐In cooler    40,000  10,193,030 

Centennial  056517  Execute  Replace compressor in Walk‐In Freezer    40,000  10,153,030 

Centennial  055258  Execute  Replace boiler flue vent   9,500  10,143,530 

Centennial  056545  Execute  Lighting retrofit  200,000  9,943,530  

Centennial  056009  Execute  Improve Drainage in Parking Area    15,000  9,928,530  

Centennial  056283  Execute  Install exterior security cameras    20,000  9,908,530  

Centennial  056293  Execute  Install wireless computer managed locks    40,000  9,868,530  

Cottonwood  057405  Pending  Crack seal and seal coat, restripe asphalt    18,000  9,850,530  

Cottonwood  056375  Execute  Asphalt assessment and maintenance plan   2,000  9,848,530  

Cottonwood  056518  Execute  Replace heating & cooling valves    75,000  9,773,530  

Crest Hill  056537  Execute  Repair concrete heaving @ front entry    10,000  9,763,530  

Crest Hill  053636  Complete  Emergency water main repair   6,700  9,756,830  

Crest Hill  055473  Complete  Fall protection material for playgrounds   667  9,756,163  

Crest Hill  055362  Complete  Replace Federal Pacific Switchgear   2,500  9,753,663  

Crest Hill  056079  Execute  6' chain link fence & vehicle gate   7,500  9,746,163  

Crest Hill  054306  Execute  Analysis & repair of water infiltration of bldg envelope    10,000  9,736,163  

Crest Hill  054410  Execute  Repair soffits & fascia    50,000  9,686,163  

CSF  Multiple  Execute  Medicine Cabinets    20,000  9,666,163  

CSF  056592  Execute  Security Gate    25,000  9,641,163  

CSF  057470  Pending  Repair roof on bus barn    10,000  9,631,163  

CSF  056521  Execute  Replace IT cooling AC   8,000  9,623,163  

CSF  056522  Execute  Replace compressor in walk‐in cooler    40,000  9,583,163  

Page 37: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

37

CSF  056523  Execute  Replace compressor in walk‐in freezer    40,000  9,543,163  

CSF  Multiple  Execute  Install bollards @ trash enclosures    15,000  9,528,163  

CSF  054428  Execute  Add parapet, repair roof  150,000  9,378,163  

CYMS  054301  Complete  Engineering analysis of crawlspace drainage    30,000  9,348,163  

CYMS  056376  Execute  Asphalt assessment and maintenance plan   2,000  9,346,163  

CYMS  054427  Execute  Synthetic field pulling away from anchor   5,000  9,341,163  

CYMS  057404  Pending  Crack seal and restripe as needed   250  9,340,913  

CYMS  055594  Complete  Correct Athletic Field Drainage    80,000  9,260,913  

CYMS  055595  Execute  Correct Perimeter Drainage    80,000  9,180,913  

CYMS  054066  Execute  Design & install new sound system  150,000  9,030,913  

CYMS  054983  Complete  Evaluate Athletic Field Drainage   5,500  9,025,413  

DMJH  Execute  Building wide renovation  4,500,000  4,525,413  

DMJH  056253  Execute  Replace retaining walls    50,000  4,475,413  

DMJH  055929  Complete  Remove motorized partitions    15,000  4,460,413  

Driving Range  055724  Complete  Crack Seal & Concrete Pads    10,000  4,450,413  

Evansville  056285  Execute  Install exterior security cameras    45,000  4,405,413  

Evansville  056324  Execute  Plan relocation of front entrance    10,000  4,395,413  

Evansville  056323  Execute  Remote buzz‐in & intercom system   5,000  4,390,413  

Evansville  056593  Complete  Install fence on north side of playground    15,000  4,375,413  

Evansville  054407  Complete  Replace main electrical switch gear    15,000  4,360,413  

Evansville  055475  Complete  Fall protection material for playgrounds   445  4,359,968  

Fairgrounds  056377  Execute  Asphalt assessment and maintenance plan   2,000  4,357,968  

FCA  057406  Pending  Crack seal, seal coat, restripe asphalt    18,000  4,339,968  

FCA  056713  Complete  Replace commercial dishwasher    45,000  4,294,968  

FCA  056378  Execute  Asphalt assessment and maintenance plan   2,000  4,292,968  

FCA  053779  Complete  Replace ADA truncated dome    10,000  4,282,968  

FCA  054411  Complete  Repair Washout & Drainage    20,000  4,262,968  

FCA  054157  Execute  Replace or repair York chiller  100,000  4,162,968  

FMS/CCA  056524  Execute  Replace DDC controls  100,000  4,062,968  

FMS/CCA  054206  Complete  Replace VFD in FMS HVAC   5,000  4,057,968  

FMS/CCA  056525  Execute  Replace ductwork in kitchen    25,000  4,032,968  

FMS/CCA  056244  Execute  Replace roof @ main & aux gym  200,000  3,832,968  

FMS/CCA  056635  Execute  Repair Aux Gym HVAC controls   5,000  3,827,968  

FMS/CCA  054426  Execute  Repair roof scuppers, envelope drain system    25,000  3,802,968  

FMS/CCA  056294  Execute  Install wireless computer managed locks    40,000  3,762,968  

Food Service  054093  Complete  Repair approach ramp on loading dock   3,000  3,759,968  

Grant  056096  Execute  Medicine Cabinets   600  3,759,368  

Grant  056284  Execute  Install exterior security cameras    20,000  3,739,368  

Grant  056245  Execute  Replace roof  450,000  3,289,368  

KW Stadium  056716  Execute  Replace steps from stadium locker room to the field    25,000  3,264,368  

KWHS  056139  Execute  Replace pipe gate with key access gate    10,000  3,254,368  

KWHS  056080  Execute  Medicine Cabinets   600  3,253,768  

KWHS  056526  Complete  Replace boiler base pump    10,000  3,243,768  

KWHS  056591  Execute  Pave ADA parking, extend ADA access ramp to stadium  200,000  3,043,768  

KWHS  054194  Complete  Repair KW Power to main gym    10,000  3,033,768  

KWHS  056317  Execute  Replace compressor in VoEd Spaces   6,000  3,027,768  

KWHS  054347  Complete  Repair light fixtures in KWHS auxiliary gym    15,000  3,012,768  

Manor Heights  056286  Execute  Install exterior security cameras    15,000  2,997,768  

Manor Heights  056714  Execute  Design elevator for ADA access    50,000  2,947,768  

Manor Heights  055800  Complete  Plan elevator for ADA compliance    10,000  2,937,768  

Page 38: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

38

Manor Heights  054288  Execute  Replace carpet in Rms 101, 102, & 105    11,250  2,926,518  

Manor Heights  054412  Execute  Repair soffit  50,000  2,876,518 

Manor Heights  055240  Complete  Replace air handler unit   9,500  2,867,018  

Manor Heights  054566  Complete  Replace trough urinals in 125C & 114A   5,000  2,862,018  

Midwest  055366  Complete  Replace Federal Pacific Switchgear   2,500  2,859,518  

Midwest  056379  Execute  Asphalt assessment and maintenance plan   2,000  2,857,518  

Midwest  056424  Execute  Replace kitchen ovens repair hood    50,000  2,807,518  

Midwest  054424  Execute  Install monitoring manholes at underground storage tanks    25,000  2,782,518  

Midwest  056178  Execute  lighting & ventilation in shops  250,000  2,532,518  

Midwest  055275  Complete  Spray on roof over pool    55,000  2,477,518  

Midwest  055274  Complete  Spray on roof over school  195,000  2,282,518  

Midwest  056168  Execute  Install unit heaters in shops    10,000  2,272,518  

Midwest  056527  Execute  Replace compressor in walk‐in    40,000  2,232,518  

Midwest  054535  Execute  Design pool roof, including asbestos    10,000  2,222,518  

Mills  054415  Execute  Repair roof fascia over older section of building & above gym    25,000  2,197,518  

Mills  056380  Execute  Asphalt assessment and maintenance plan   2,000  2,195,518  

Mills  057410  Pending  Crack seal, seal coat, restripe asphalt    15,000  2,180,518  

Mtn View  054290  Execute  Replace carpet in Rm 3   4,000  2,176,518  

Mtn View  056381  Execute  Asphalt assessment and maintenance plan   2,000  2,174,518  

NCHS  055969  Complete  Modify bldg wiring for emergency power   7,500  2,167,018  

NCHS  056083  Execute  Medicine Cabinets   600  2,166,418  

NCHS  056043  Execute  Replace emergency backup generator    50,000  2,116,418  

NCHS  053756  Complete  Rewire Stadium lighting    28,500  2,087,918  

NCHS  056021  Complete  Clean KI panels in SFAC    10,000  2,077,918  

North Casper  055481  Execute  Fall protection material for playgrounds   444  2,077,474  

North Casper  053755  Complete  Install carpet in room 213   4,000  2,073,474  

North Casper  054423  Execute  Replace floor mnt urinals upper & lower bathrooms    20,000  2,053,474  

Oregon Trail  056291  Execute  Install exterior security cameras    45,000  2,008,474  

Oregon Trail  055482  Execute  Fall protection material for playgrounds   444  2,008,030  

Oregon Trail  056382  Execute  Asphalt assessment and maintenance plan   2,000  2,006,030  

Oregon Trail  057408  Pending  Crack seal, seal coat, restripe asphalt    19,000  1,987,030  

Oregon Trail  056297  Execute  Replace trash enclosure    40,000  1,947,030  

Oregon Trail  054291  Execute  Replace carpet in Rm 139, 140, 154   4,200  1,942,830  

Oregon Trail  054429  Complete  Repair basketball court asphalt    25,000  1,917,830  

Park  056288  Execute  Install exterior security cameras    35,000  1,882,830  

Park  056077  Execute  ADA lift for stage access    50,000  1,832,830  

Pineview  055485  Execute  Fall protection material for playgrounds   333  1,832,497  

Pineview  057455  Pending  Replace tile in custodian closets    12,000  1,820,497  

Pineview  032832  Execute  Replace north to south sewer line.     35,000  1,785,497  

Planetarium  056384  Execute  Asphalt assessment and maintenance plan   2,000  1,783,497  

Poison Spider  056295  Execute  Install wireless computer managed locks    40,000  1,743,497  

Poison Spider  57403  Pending  Crack seal & restripe as needed   600  1,742,897  

Poison Spider  056385  Execute  Asphalt assessment and maintenance plan   2,000  1,740,897  

Poison Spider  05633  Execute  Replace exterior security lighting   6,000  1,734,897  

Powder River  056391  Execute  Asphalt assessment and maintenance plan   2,000  1,732,897  

Powder River  053758  Complete  Remove & Replace roofing lower 82 addition    19,560  1,713,337  

PV  056383  Execute  Asphalt assessment and maintenance plan   2,000  1,711,337  

PV  056287  Execute  Install exterior security cameras    35,000  1,676,337  

PV  055508  Pending  Secure Main Entrance    ‐  1,676,337  

PV  054286  Execute  Replace carpet in Rm 170   700  1,675,637  

Page 39: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

39

PV  056325  Execute  Install remote buzz‐in on main entrance   5,000  1,670,637  

PV  054409  Execute  Replace roof  450,000  1,220,637  

PV  054422  Execute  Replace Lennox rooftop unit near hatch  120,000  1,100,637  

PV  054421  Execute  Replace ADA tactile mats   5,000  1,095,637  

PV  055483  Execute  Fall protection material for playgrounds   555  1,095,082  

Red Creek  056392  Execute  Asphalt assessment and maintenance plan   2,000  1,093,082  

Roosevelt  055960  Complete  Repair elevator   6,000  1,087,082  

Sagewood  056292  Execute  Install exterior security cameras    35,000  1,052,082  

Science Depot  053777  Complete  Install condensers & cooling units in furnaces    10,000  1,042,082  

Science Depot  054304  Complete  Replace furnaces   5,000  1,037,082  

Southridge  055488  Complete  Fall protection material for playgrounds   222  1,036,860  

Summit  056536  Complete  Repair fire sprinkler riser line    10,000  1,026,860  

Summit  054052  Execute  Design & install new intercom system for entire school  150,000   876,860  

Summit  055017  Complete  Replace compressor   6,500   870,360  

University Park  055489  Complete  Fall protection material for playgrounds   444   869,916  

University Park  056335  Execute  Install exterior security lighting    10,000   859,916  

University Park  054294  Execute  Replace carpet in library, & lounge    12,800   847,116  

University Park  056126  Execute  Security Cameras, Misc Repair    50,000    797,116  

Verda James  056505  Execute  Install security fencing    50,000    747,116  

Verda James  057383  Pending  Repair concrete @ entrance    25,000    722,116  

Verda James  055490  Complete  Fall protection material for playgrounds   444    721,672  

Westwood  055491  Complete  Fall protection material for playgrounds   444    721,228  

Westwood  056334  Execute  Replace exterior security lighting    10,000    711,228  

Westwood  054413  Execute  Replace Bradley sinks in lower boys' restroom & upper girls   5,000    706,228  

Westwood  054420  Execute Replace all exterior doors & frames. Continual maintenance problems. 

110,000    596,228  

Westwood  054419  Execute  Exterior Security Cameras    25,000    571,228  

Westwood  054417  Execute  Install chain link fence along playground & city park    10,000    561,228  

Willard  054296  Execute  Replace carpet in 19, 23, 101    16,450    544,778  

Willard  056584  Execute  Cost share with Casper for Intersection    10,000    534,778  

Willard  056336  Execute  Replace exterior security lighting    10,000    524,778  

Willard  055565  Complete Modify interior vestibule for ADA compliance and enhanced security. 

  15,000    509,778  

Willard  Complete  Improve drainage with valley pan by main playground doors   5,000    504,778  

Willow Creek  056393  Execute  Asphalt assessment and maintenance plan   2,000    502,778  

Woods  055492  Complete  Fall protection material for playgrounds   333    502,445  

Woods  054295  Execute  Replace carpet in Office   4,000    498,445  

Woods  054416  Execute  Replace floor tiles throughout building    25,000    473,445  

Security Related Projects

School  WO#  Status  Description  Budget  Notes 

Centennial  055504  Pending  Secure Main Entrance            ‐    Waiting on SFD funds 

Centennial  056283  Execute  Install exterior security cameras 20,000  Design 

Centennial  056293  Execute  Install wireless computer managed locks 40,000  Execute in summer 

Page 40: TO: Board of Trustees · 1 TO: Board of Trustees FROM: Dennis Bay, Executive Director Business Services DATE: April 24, 2015 SUBJECT: Construction Projects Reports The construction

40

Crest Hill  055505  Pending  Secure Main Entrance            ‐    Waiting on SFD funds 

Crest Hill  056079  Execute  6' chain link fence & vehicle gate     7,500  Complete 

CSF  056592  Execute  Security Gate 25,000  Planning for summer 

Evansville  055278  Pending  Secure main entrance            ‐   

Evansville  056323  Execute  Remote buzz‐in & intercom system     5,000  Awarded and scheduled 

Evansville  056324  Execute  Plan relocation of front entrance 10,000 

Request for proposal issued 

Evansville  056593  Complete  Install fence on north side of playground 15,000  Awarded and scheduled 

FCA  055507  Pending  Secure Main Entrance            ‐    Waiting on SFD funds 

Frontier/CCA  056294  Execute  Install wireless computer managed locks 40,000  Execute in summer 

KWHS  056139  Execute  Replace pipe gate with key access gate 10,000  Awarded and scheduled 

Manor Heights 

056286  Execute  Buzz in system for front entrance  

15,000  Planning for summer 

Oregon Trail  056291  Execute  Install exterior security cameras 45,000  Design 

Park  056288  Execute  Install exterior security cameras 35,000  Design 

Poison Spider 

05633  Execute  Replace exterior security lighting     6,000 Execute in summer 

Poison Spider 

056295  Execute  Install wireless computer managed locks 40,000  Execute in summer 

PV  055508  Pending  Secure Main Entrance            ‐    Waiting on SFD funds 

PV  056325  Execute  Install remote buzz‐in on main entrance     5,000  Awarded and scheduled 

Sagewood  056292  Execute  Install exterior security cameras 35,000  Design 

SESC  055277  Pending  Secure main entrance            ‐    Waiting on SFD funds 

University Park 

056335  Execute  Install exterior security lighting  

10,000  Planning for summer 

University Park 

056126  Execute  Security Cameras, Misc Repair  

50,000  Awarded and scheduled 

Verda James  055509  Pending  Secure Main Entrance            ‐    Waiting on SFD funds 

Verda James  056505  Execute  Install security fencing 50,000  Planning for summer 

Westwood  056334  Execute  Replace exterior security lighting 10,000  Planning for summer 

Westwood  054419  Execute  Exterior Security Cameras 25,000  Awarded and scheduled 

Willard  056336  Execute  Replace exterior security lighting 10,000  Planning for summer 

Willard  055565  Complete Modify interior vestibule for ADA compliance and enhanced security. 

 15,000  Complete