LISD Board of Trustees

Construction Committee Meeting

Tuesday, December 11, 2001

Farias Elementary School

Construction Committee Meeting

Tuesday, December 11, 2001

THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.

THIS VIEW IS LOOKING NORTH WEST AT THE BUILDING PAD. PAD IS WET DUE TO RECENT RAINS.

THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR

THE BUILDING.

THIS VIEW IS LOOKING NORTHEAST AT THE BUILDING PAD. SURVEYORS ARE SETTING THE CORNER PINS FOR

THE BUILDING.

Santa Maria Elementary SchoolSanta Maria Elementary School

Construction Committee MeetingConstruction Committee Meeting

Tuesday, December 11, 2001Tuesday, December 11, 2001

PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.

PLUMBING SUBCONTRACTOR TRENCHING FOR THE INSTALLATION OF PLUMBING LINES.

THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.

THE PLUMBING LINES PREFABRICATED ON SITE FOR INSTALLATION IN THE PLUMBING TRENCH.

PREPARATION OF THE BUILDING PAD AT THE BUILDING.

PREPARATION OF THE BUILDING PAD AT THE BUILDING.

Dovalina Elementary SchoolDovalina Elementary School

Construction Committee MeetingConstruction Committee Meeting

Tuesday, December 11, 2001Tuesday, December 11, 2001

VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING

CONSTRUCTED.

VIEW LOOKING NORTH WEST AT THE CONCRETE FOUNDATION. MASONRY BLOCK WALLS BEING

CONSTRUCTED.

SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.

SOUTHEAST VIEW OF THE COMPLETED FOUNDATION SYSTEM.

Project:Christen Middle School

Architect: Sepulveda Associates Architects, Inc.

Status: Design Development

Budget: $7,193,380.

Timeline:

Start of Final Design Phase: Jan 2002

Present Final Contract Dwgs: Mar 2002

Completion of Construction: Dec 2003

Project: Martin High School

Architect: Sepulveda Associates Architects, Inc.

Status: Design Development

Budget: $7,823,946.

Timeline:

Start of Final Design Phase: Dec 2001

Present Final Contract Dwgs: Feb 2002

Completion of Construction: May 2003

Ochoa/T. Sanchez Elementary School

Construction Committee Meeting

Tuesday, December 11, 2001

THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.

THIS VIEW IS LOOKING SOUTH EAST AT THE BUILDING PAD.

EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.

EXISTING CITY SEWER LINE BEING REROUTED. NEW SEWER LINE BEING INSTALLED.

Project: K.Tarver Elementary School

Architect: Cavazos & Associates Architects

Status: Design Development

Budget: $ 4,606,191.00 Dlls.Timeline:

Start of Final Design Phase: Feb 2002

Present Final Contract Dwgs: April 2002

Completion of Construction: June 2003

C.L. Milton Elementary School

Construction Committee Meeting

Tuesday, December 11, 2001

THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS.

THIS IS A SOUTH EAST VIEW.

THIS VIEW IS OF THE PAD PREPARATION FOR THE NEW PORTABLE CLASSROOMS.

THIS IS A SOUTH EAST VIEW.

NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.

NORTH EAST VIEW OF THE PAD PREPARATION FOR THE PORTABLE BUILDINGS.

Project: J.C. Martin Elementary School

Architect: Ashley Humphries & Sanchez ArchitectsStatus: Preliminary Design

Budget: $1,997,044.

Timeline:

Start Design Development : Feb 2002

Start of Final Design Phase: April 2002

Present Final Contract Dwgs: June 2002

Completion of Construction: Aug 2003

Project: Lamar Middle School

Architect: Cavazos & Associates Architects

Status: Final Design Phase

Budget: $ 7,358,620.

Timeline:

Start of Final Design Phase: Aug 2001

Present Final Contract Dwgs: Feb 2002

Completion of Construction: June 2003

J.W. NIXON HIGH SCHOOL

Construction Committee Meeting

Tuesday, December 11, 2001

THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.

THIS IS A VIEW LOOKING WEST AT THE CANOPY ON THE SOUTH END OF THE PORTABLE BUILDING.

THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.

THIS VIEW IS LOOKING NORTH ALONG THE NEW SIDE WALK FOR THE STUDENTS.

THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.

THIS VIEW SHOWS THE FENCING ON TOP OF THE EXISTING BLOCK WALL.

MAIN PATIO DECK. MAIN ENTRANCE TO BUILDINGS.MAIN PATIO DECK. MAIN ENTRANCE TO BUILDINGS.

Project: Daiches Elementary School

Architect: Turner Hickey & Associates, Inc.

Status: Design Development

Budget: $5,191,225.Timeline:

Start of Final Design Phase: Dec 2001

Present Final Contract Dwgs: March 2002

Completion of Construction: April 2003

Project: Heights Elementary School

Architect: Pending

Status: Pending

Budget: Pending

Timeline: Pending

Project: Santo Nino Elementary School

Architect: Frank Architects Inc.

Status: Final Design Phase

Budget: $5,191,225.

Timeline:

Start of Final Design Phase: Sept. 2001

Present Final Contract Dwgs: Jan 2002

Completion of Construction: March 03

Project: Kawas Elementary School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $4,211,386.

Timeline:

Start of Final Design Phase: July 2001

Present Final Contract Dwgs: Oct 2001

Completion of Construction: Dec 2002

Project: H.B. Zachry Elementary School

Architect: Design Group International, Inc.

Status: Construction Documents Phase

Budget: $1,456,725.Timeline:

Start of Final Design Phase: Oct 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: Dec 2002

Project: H. Ligarde Elementary School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $3,388,153.

Timeline:

Start of Final Design Phase: Oct 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: Dec 2002

Project: Cigarroa Middle School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $3,314,867.Timeline:

Start of Final Design Phase: July 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: June 2003

Project: Cigarroa High School

Architect: Ashley Humphries & Sanchez Architects Status: Construction Documents Phase

Budget: $8,168,516. Timeline:

Start of Final Design Phase: July 2001

Present Final Contract Dwgs: Dec 2001

Completion of Construction: June 2003