the towerwise project is made possible by …taf.ca › wp-content › uploads › 2016 › 10 ›...
TRANSCRIPT
The TowerWise Project is made possible by financial contributions from
Natural Resources Canada and Enbridge Gas Distribution Inc.
Table of Contents Project Description ..................................................................................................................... 3
Goals .................................................................................................................................. 3
Project Timeline .................................................................................................................. 3
Resource Conservation Measures ............................................................................................. 4
Building Monitoring and Installation ............................................................................................ 5
Energy and GHG Performance .................................................................................................. 7
Domestic Cold Water Pump ................................................................................................ 7
Make-Up Air Units ............................................................................................................... 7
Low-flow Water Fixtures ...................................................................................................... 8
Boilers ................................................................................................................................. 9
Savings ..............................................................................................................................10
Boiler Efficiency and Analysis ............................................................................................11
Financial Performance ..............................................................................................................14
Conclusions ..............................................................................................................................16
Appendix A – Energy Savings Performance Agreement Structure .....................................18
Appendix B – Pre-retrofit Building Information ....................................................................19
Appendix C1 – Projected Resource Conservation Measure Costs .....................................20
Appendix C2 – Projected Resource Conservation Measure Savings .................................21
Appendix D1 - Equipment Details ......................................................................................22
Appendix D2 - Monitoring Details .......................................................................................22
Appendix E – Savings Tables ...................................................................................................23
3
Project Description
In 2012 Robert Cooke Co-op, located at 20 Garnett Janes Road, Toronto, was one of the first
projects financed through The Atmospheric Fund’s (TAF) Energy Savings Performance
Agreement (ESPA) for the implementation of resource conservation measures (RCMs).
An ESPA is a non-debt agreement where guaranteed energy savings are used to cover the
capital retrofit costs. Appendix A illustrates the structure of the ESPA. This approach allows
building owners to implement energy saving measures in their buildings without amassing any
upfront costs. Using the ESPA platform, TAF finances the design, construction, and equipment
costs, while sharing the savings with building owners over a 10 year term. At the end of the
contract, the building owners keep all of the energy savings. Since the savings are insured by a
third party, building owners are not penalized if the savings fall short of the original targets over
the contract term. Ultimately, the ESPA agreement provides a project platform where all parties
have a vested interest ensuring a project reaches its utility cost, energy, and greenhouse gas
reduction goals.
The retrofit measures aimed to maximize energy savings and address renewal problems with
the building mechanical systems. Along with reductions in utility consumption and greenhouse
gas (GHG) emissions, TAF recognized an opportunity to monitor the performance of key energy
consuming equipment such as the domestic hot water (DHW) and heating boilers. This case
study will detail the process, results, and insights garnered from this project.
Goals
TAF aimed to achieve at least 30% GHG emission reductions and $65,000 in annual utility
savings as well as address deferred maintenance priorities and improve the indoor environment
for residents. As part of the in-depth monitoring program of the mechanical systems, TAF also
aimed to measure the actual operating performance of the new boilers and quantify the
differences in performance between condensing and non-condensing boilers.
Project Timeline
In 2012, the Robert Cooke Co-op expressed interest in TAF’s ESPA as a financing platform for
investment in building energy retrofits. Based on the Level II and Level III ASHRAE audits
completed in 2011 and 2013, respectively, TAF provided a series of retrofit recommendations to
Robert Cooke.
In 2013, the ESPA was signed between TAF and Robert Cooke. In addition, an engineering
service provider, Finn Projects, was hired to implement the retrofit on a design-build basis, as
well as develop a measurement and verification plan. Through an insurance product available
from Energi of Canada, the engineering service provider guaranteed 90% of the expected utility
cost savings.
4
Between July 2013 and November 2013, the retrofit measures were implemented at Robert
Cooke and adjustments were made through the commissioning process. Over a 10 year
agreement between TAF and Robert Cooke, which started in December 2013, the majority of
the energy savings are transferred to TAF and the remaining are retained by the Co-op. The
annual utility savings are measured and verified against a reference baseline year that is
weather normalized. At the end of the 10 year agreement, 100% of the ongoing savings will be
retained by Robert Cooke Co-Op.
Resource Conservation Measures
Robert Cooke Co-op is a residential complex with 28 townhomes and 123 unit tower
constructed in 1992. The tower is thirteen storeys tall with a gross area of approximately 14,000
m2, and has two levels of underground parking. The building is centrally heated and ventilated.
Some residents have installed personal window-mounted air conditioning units and there is a
separate rooftop unit air conditioner in the offices. There is also an activity room and common
laundry facilities. Detailed building information can be found in Appendix B.
In 2013, TAF, Finn Projects, and the Robert
Cooke Co-op worked collaboratively to determine
the RCMs that would most effectively meet the
project goals. Measures which would address
the fresh air and heating systems that were
either not functioning properly or nearing the end
of their service life were prioritized. Of particular
concern was one malfunctioning make-up air unit
(MAU), which was causing the building to receive
only half of the intended fresh air supply. The
resource conservation measures implemented
are summarized below, detailed information can
be found in Appendix C.
1. Separate the DHW and heating systems;
2. Remove the existing boilers and install two
high efficiency boilers for domestic hot water
and one condensing boiler for space heating;
Robert Cooke approaches TAF with interest in
ESPA
ASHRAE Level III feasibility
study performed
ESPA signed
RCM equipment
installed
Energy and utility
consumption monitoring
2012 May 2013 July 2013 July - Nov. 2013 Dec. 2013 - Current
Top: low flow toilets awaiting installation; bottom: two high efficiency boilers for DHW.
5
3. Replace the motors on the two MAUs with models incorporating variable speed drives
(VFDs);
4. Replace the domestic cold water booster pumps with VFD equipped models;
5. Replace corridor lighting with lower wattage T8 fluorescent tubes and install motion sensors
in some common spaces;
6. Convert existing showerheads, faucet aerators and toilets to low-flow;
7. Replace original fridges and stoves with high efficiency models;
8. Weatherstrip exterior doors.
A few additional RCMs that were considered but ultimately not installed are tabulated below.
Table 1: List of RCMs Not Installed
A summary of the actual construction costs and projected utility savings are provided below.
Based on the outlined RCMs, the projected annual GHG emission reductions were 133 tCO2eq,
representing a 23% reduction.
Table 2: Projected Costs and Utility Savings
Project Performance Value
Total Project Cost1 $658,477
Total Incentives4 $185,151
Net Cost $468,326
Projected Utility Cost Savings $66,650
Building Monitoring and Installation
Table 3 summarizes the building sub-metering points, while Appendix D provides the equipment
and monitoring details. Data were collected at a variety of intervals starting on August 1, 2013,
1 The actual project costs and incentives vary from Appendix C1. The values contained in Appendix C1 are feasibility
study estimates prior to the start of construction.
RCM Rationale for Not Implementing
Solar hot water preheating/PV Requires significant amount of equipment on roof and roof area was insufficient.
Direct digital control system Building does not have sufficient equipment to warrant installation.
High efficiency motors
Motors were not near the end of their service life and replacement was not planned at this time.
Run time too low for high efficiency motors to be cost effective.
Replace thermostats with programmable models
Low projected gas savings.
Low gas rates and no cooling during the summer resulted in programmable thermostats not being financially attractive.
6
and collected consistently at one minute intervals since January 1, 2014. This report primarily
focuses on the analysis from January 1, 2014 onwards.
Table 3: Metering Parameters
To determine the pre-retrofit baseline, the 2010 calendarized building utility consumption was
plotted against the number of exterior heating degree days. The weather dependent variables
used for the regression analysis were natural gas consumption and garage electricity, which
includes ramp heating in the winter. Adjustments were made to the baseline to account for an
MAU being brought into operation and elevator room cooling which was added during the retrofit
process. The RCM savings are then calculated based on the difference between the forecast
baseline consumption and the billed consumption for each month in 2014 and 2015.
A summary of the RCM installations is provided in Table 4. Given the sequencing of
installations, there was an opportunity to determine impacts of individual RCM measures. These
impacts are discussed in the next section.
Table 4: RCM Installation Sequencing
Measure Start Date Completion
Date
Replace existing heating/domestic hot water boilers with high efficiency and condensing boilers.
29/07/2013 12/09/2013
Provide variable speed drives for the make-up air units. 24/07/2013 15/10/2013
Replace the domestic cold water booster pump motors and install variable speed drives.
06/08/2013 08/10/2013
Replace corridor lighting. 31/10/2013 31/12/2013
Install low-flow aerators, toilets and showerheads. 06/08/2013 12/09/2013
Replace fridges and stoves with new high efficiency models. 20/08/2013 20/08/2013
Weatherstrip exterior doors. 27/11/2013 04/12/2013
Metering Point Resource Metered
Whole building Natural Gas, Electricity, Water flow
Parking garage Electricity
Domestic cold water booster pumps Electricity
Condensing boiler Natural Gas
East MAU Natural Gas, Electricity
West MAU Natural Gas, Electricity
Gas dryers (laundry) Natural Gas
Supply & return water for condensing boiler Temperature
Return water for condensing boiler Water flow
Supply & return water for high efficiency boilers
Temperature
Return water for high efficiency boilers Water flow
High efficiency boilers Energy production
7
Energy and GHG Performance
This section presents the 2014 and 2015 energy and GHG performance of the RCM impacts.
Given the timing of the installations, it was possible to evaluate the individual performance of the
domestic cold water pump, make-up air units, and low flow fixtures. In addition, the boiler
performance and operating efficiencies are also evaluated separately and described in this
section.
Domestic Cold Water Pump
After the two new domestic cold water pumps controlled by variable speed drives were installed,
Figure 1 shows an immediate reduction in the electrical consumption beginning on October 7,
2013. The consumption was reduced by approximately 60%, from 50 kWh/day to 20 kWh/day.
This RCM resulted in a total of 10,950 kWh savings per year, corresponding well with the
feasibility study’s estimate of 9,600 kWh savings per year (see Appendix C2).
Figure 1: Daily booster pump electrical consumption.
Make-Up Air Units
Variable speed drives and new fan motors were added to the make-up air units in order to
match the amount of fresh air supplied with the building needs. Figure 2 shows the electrical
consumption of the two MAUs starting in July 2013. MAU #2, which was not previously working,
began operation on July 24, 2013. Between September 19, 2013 and November 21, 2013 the
graph shows declining electricity consumption for each make-up air unit from approximately 100
kWh/day to 40 kWh/day2. This resulted in savings of approximately 60% when compared to the
pre-retrofit operation.
2 The increase that occurred between October 2013 and November 2013 (20 kWh/day to 40 kWh/day) was likely due
to modifying the MAU settings as the heating season began. To be conservative, the percentage of savings was calculated based on the 40 kWh/day consumption.
0
10
20
30
40
50
60
28
/09
/13
29
/09
/13
30
/09
/13
01
/10
/13
02
/10
/13
03
/10
/13
04
/10
/13
05
/10
/13
06
/10
/13
07
/10
/13
08
/10
/13
09
/10
/13
10
/10
/13
11
/10
/13
12
/10
/13
13
/10
/13
14
/10
/13
15
/10
/13
16
/10
/13
17
/10
/13
Ele
ctri
city
Co
nsu
mp
tio
n
(kW
h/d
ay)
60% savings
8
Figure 2: Daily make-up air unit electrical consumption.
Since MAU #2 was not working for the majority of 2013, an adjustment of approximately 29,000
kWh/year was added to the baseline consumption to represent what the building would have
used if both MAUs were operating. After this adjustment, the total baseline consumption was
58,000 kWh/year. The total savings associated with the MAU retrofit, calculated as the
difference between the adjusted baseline consumption and the actual 2014 consumption, were
approximately 38,000 kWh/year3. The gas consumption of the MAUs was not analyzed since
they were retrofitted in the summer, a time when the air does not need to be preheated.
Low-flow Water Fixtures
The low flow water fixture retrofit consisted of installing 3 L toilets, 1.5 gpm low flow
showerheads, 1.0 gpm aerators in the bathrooms and 1.5 gpm aerators in the kitchens. A few
days after the RCM construction began on August 6, 2013 a reduction in water consumption
from approximately 100 m3/day to 70 m3/day can be observed in Figure 3. Annual water savings
were 12,057 m3 in 2014 and 11,629 m3 in 2015 - over double the 5,270 m3 in savings estimated
in the feasibility study (see Appendix C2).
3 The actual utility savings that the Robert Cooke sees are 9,000 kWh/year, calculated as the total savings minus the
adjustment associated with MAU#2.
0
20
40
60
80
100
120
11
/07
/13
18
/07
/13
25
/07
/13
01
/08
/13
08
/08
/13
15
/08
/13
22
/08
/13
29
/08
/13
05
/09
/13
12
/09
/13
19
/09
/13
26
/09
/13
03
/10
/13
10
/10
/13
17
/10
/13
24
/10
/13
31
/10
/13
07
/11
/13
14
/11
/13
21
/11
/13
Ele
ctri
city
Co
nsu
mp
tio
n (
kWh
/day
) Makeup Air Unit 1
Makeup Air Unit 2
MAU #2 turned on
60% savings
9
Figure 3: Daily water consumption.
The projected savings associated with the toilet replacement only took into account savings
when flushing the 3 L low flow toilets. Any savings stemming from reducing toilet leakage
through the flapper valves were not taken into account. These savings likely account for a large
portion of the difference between the actual savings achieved and the projected savings.
The hourly water consumption during the night was analyzed since water savings at that time
are largely due to flapper leakage reduction rather than a reduction associated with the flushes.
This analysis revealed that the water consumption was reduced by 50%-60% during the night in
many cases. These significant savings were not taken into account at the feasibility stage,
demonstrating that overly conservative estimates can result in significantly underestimating the
savings that can be realized. This can potentially lead to underinvestment in energy and water
efficiency retrofit projects.
Boilers
The existing oversized boilers were replaced with one 1,100 MBTU/h condensing unit serving
the heating system and two 1,100 MBTU/h high efficiency boilers serving the DHW load. Figure
4 shows two sharp declines in natural gas consumption on July 27-28, 2013 and August 9, 2013
– likely when the existing boilers were taken offline and replaced. Prior to August 9, 2013 the
average daily natural gas consumption was 187 m3 (excluding the drops). Post retrofit, the
average consumption was reduced to 147 m3, equivalent to a savings of approximately 21%. It
is important to note that these savings are due to improved efficiencies of the domestic hot
water system only, since the space heating was not turned on at this time. Gas savings
stemming from the MAU improvements as well as a comparison between the condensing and
high efficiency boilers is provided in the next section.
60
70
80
90
100
110
120
25
/07
/20
13
28
/07
/20
13
31
/07
/20
13
03
/08
/20
13
06
/08
/20
13
09
/08
/20
13
12
/08
/20
13
15
/08
/20
13
18
/08
/20
13
21
/08
/20
13
24
/08
/20
13
27
/08
/20
13
30
/08
/20
13
02
/09
/20
13
05
/09
/20
13
08
/09
/20
13
11
/09
/20
13
Wat
er
Co
nsu
mp
tio
n (
m3/
day
)
30% savings
10
Figure 4: Daily natural gas consumption.
Savings
Figure 5 shows the total utility savings resulting from all of the implemented RCMs. The actual
savings achieved in 2015 were nearly double compared to the estimated savings from the
feasibilty study. This is largely because of the water savings achieved. Reducing water leakage
by replacing the old flapper valves likely contributed to these higher than anticipated water
savings.
Figure 5: Utility Savings – gas and electricity (left), water (right).
Table 5 summarizes the amount of GHG and utility cost savings, per year, for each utility type.
These savings are based on the difference between the actual consumption and the adjusted
baseline. A full table of these parameters including the emission factors used can be found in
Appendix E. Gas savings represented the vast majority of GHG savings, however due to their
0
50
100
150
200
250
24
/07
/13
26
/07
/13
28
/07
/13
30
/07
/13
01
/08
/13
03
/08
/13
05
/08
/13
07
/08
/13
09
/08
/13
11
/08
/13
13
/08
/13
15
/08
/13
17
/08
/13
19
/08
/13
21
/08
/13
23
/08
/13
25
/08
/13
27
/08
/13
29
/08
/13
31
/08
/13
02
/09
/13
04
/09
/13
06
/09
/13
08
/09
/13
10
/09
/13
12
/09
/13
Nat
ura
l Gas
Usa
ge (
m3 /
day
)
0
200,000
400,000
600,000
800,000
1,000,000
Electricity Gas
Qu
anti
ty S
avin
gs (
kWh
or
ekW
h)
Projected 2014 2015
49%
14%
0
2,000
4,000
6,000
8,000
10,000
12,000
14,000
Water
Qu
anti
ty S
avin
gs (
m3 )
Projected 2014 2015
21% savings
94%
11
low utility cost, they resulted in the smallest cost savings. In comparison, the water measures
had the largest cost savings, but contributed minimally to the GHG emission savings. Overall,
the total utility cost savings averaged between the two years was 20%.
Table 5: Summary of GHG and Cost Savings
Year Resource GHG
(tCO2eq) Cost Savings ($)
2014
Electricity 66.1 $27,391
Gas 130.6 $21,194
Water N/A $36,860
TOTAL 196.7 $85,445
2015
Electricity 67.3 $33,330
Gas 154.1 $28,440
Water N/A $38,561
TOTAL 221.5 $100,331
Boiler Efficiency and Analysis
The existing boiler configuration included three 1,467 MBTU/h (input) Raypack boilers serving
the heating and domestic hot water systems, with estimated operating efficiencies lower than
70%. Prior to the retrofit, one of these boilers had failed and the second one was in very poor
condition. The DHW tank was heated via a heat exchanger on a secondary loop.
Boiler sizing analysis was performed, indicating that the boilers could be adequately replaced
with 1,100 MBTU/h boilers. However, concerns over providing sufficient heating in extended
cold winter periods and the desire to enable redundancy should any boilers fail resulted in the
two DHW boilers sized at 1,500 MBTU/h (input) and the condensing boiler for heating sized at
1,050 MBTU/h (input). The rated efficiencies for the condensing and non-condensing boilers
were 94% and 85%, respectively. A three way valve was installed to connect the DHW loop to
the heating loop via a heat exchanger in case additional heating is needed in the future. All
three boilers have a turndown ratio of 5:1 alleviating some concerns over potential inefficiencies
associated with installing oversized boilers which have no modulation capabilities.
Overall Efficiency
Table 6 summarizes the average boiler efficiency of the two DHW high efficiency boilers and the
condensing space heating boiler. The efficiency presented for the DHW boilers is averaged
between the two units. Two different data sets were used to evaluate the efficiency. Data Set 1
was supplied by Finn Projects through quarterly measurement and verification plans, while Data
Set 2 is from the building sub-metering points. The table below demonstrates that the
theoretically higher efficiency condensing boiler had considerable operational efficiency gains
over the non-condensing boilers.
12
Table 6: Summary of Boiler Efficiency
Average Efficiency High Efficiency Boilers4 Condensing Boiler
Data Set 1 73.4% 87.6%
Data Set 2 78.0% 89.2%
Differences between the two data sets can be attributed to different time periods, where the
Data Set 1 performance is based on data available between March 2014 and February 2015
while Data Set 2 includes data between May 2014 and October 2015. The gas meter output
was also modified in February 20155 which can also contribute to some of the differences found
in Table 6.
Condensing Range
A common claim is that condensing boilers may not have any efficiency gains over non-
condensing boilers when these systems operate outside the condensing temperature range.
The condensing range is typically accepted as having the return water temperature equal to
130°F or lower (with the peak being around 70°F).
Figure 6: Efficiency Diagram for Condensing Boiler Installed (Left) and Boiler Inlet Temperature vs. Boiler Efficiency
from ASHRAE 2008 Handbook (Right)
Data collected in 2015 were analyzed to determine the condensing boiler efficiency above and
below the 130°F threshold. This particular monitoring year was chosen because performance
data at 1-minute intervals was collected for the largest amount of time without any erroneous
4 Gas consumption of the high efficiency boilers was not sub-metered, it was calculated as the total gas minus all of
the other submetering gas points. In addition, the hot water flow rate of the high efficiency boilers was spot metered and assumed to be consistent when the boilers were on. The outcome of both of these modifications may lead to less accurate data used in the high efficiency boiler analysis.
5 The gas meter was initially configured to send a pulse reading every time 10 ft
3 of gas was used. The pulse
readings were then collected in 15 minute intervals. Since the supply and return temperatures changed very frequently, the resolution and interval were changed to 1 ft
3 and 1 minute, respectively, in February 2015.
13
readings. A direct comparison is not possible since the two types of boilers are servicing
different mechanical systems and the non-condensing boilers almost never enter the
condensing temperature range. However, it is still useful to examine the differences in
performance.
Table 76 shows the condensing boiler efficiency based on the temperature of the return water.
As expected, the condensing boiler performance is better within the condensing range (lower
than 130°F). This analysis further demonstrates that the condensing boiler operates at a
considerably higher efficiency than the non-condensing boilers shown in Table 6, even when the
temperature is outside the condensing range.
Table 7: Efficiency Based on Return Temperature for Condensing Boiler
Return Temperature Condensing Boiler
Efficiency
≥ 130°F 90.8%
< 130°F 91.1%
Analysis specifically looking at how cycling, efficiency, and return water temperature were
related was also undertaken. This analysis is based on data from February 20, 2015 to March
29, 2015, which was the longest uninterrupted interval where reasonable data were available.
Figure 7 shows the average hourly condensing boiler efficiency plotted against the average
hourly return temperature7. Blue points represent instances when the boiler cycled ≤10 times
per hour, while the red points represent instances when the boiler cycled >10 times per hour. A
cycle was considered to have occurred when the boiler down time was one minute long. The
sensitivity of the boiler down time was explored revealing that the condensing boiler infrequently
turned off for more than one minute and very rarely turned off for more than two minutes.
Figure 7: Average Hourly Efficiency vs. Average Hourly Return Temperature
6 The efficiencies shown in Table 7 are slightly higher than those in Table 6 due to the shorter time frame of the
analysis. The analysis in Table 7 is based on data collected between February 20, 2015 and March 29, 2015 7 Four of the points plotted had an operating efficiency over 100%. These points represented 0.4% of the data and
were deemed to be outliers.
80%
85%
90%
95%
100%
105%
110 115 120 125 130 135 140 145 150 155 160
Bo
iler
Effi
cie
ncy
(%
)
Return Temperature (°F)
Threshold 1
Threshold 2 0 - 10 Cycles/h 11 - 26 Cycles/h
14
The graph shows that time periods when the condensing boiler cycled more coincided with
lower return water temperatures and vice versa. This result was expected since a lower return
temperature would generally indicate less demand for heating and thus more occurrences when
the boiler turns off. However, there was no appreciable difference in the average efficiency
between the two thresholds of cycling. Although higher efficiencies might be expected at lower
return water temperatures, the modulation rate at those times is unknown and the increased
amount of cycling could offset those efficiency gains. Further research into how cycling,
modulation and return water temperatures affect condensing boiler efficiency should be
undertaken in order to better understand the relationship between these parameters.
Financial Performance
Actual savings achieved have outperformed projections for 2014 and 20158. This is because of
the greater than expected water savings stemming from the fixture and toilet replacement.
Figure 8 shows the cost savings breakdown by utility. The second largest factor in helping
achieve the high savings was the larger than expected gas savings.
Figure 8: Cost Savings Breakdown – by Utility
Figure 8 also shows that the 2015 savings were even greater than 2014 savings. An analysis
was performed to determine whether the costs savings increase was due to a quantity increase
(thus achieving higher savings) or due to a utility rate increase. The summary of this analysis is
shown in Figure 9. For gas and electricity, the additional savings are almost equally split
between the two factors. For water there were fewer saving realized due to a quantity increase
in 2015 compared to 2014. However, the increase in the water utility rates between these two
years more than offset this difference to generate a significant increase in cost savings.
8 The Projected Cost Savings in Figure 8 ($47,212) are different than the original Feasibility Study projections of
$66,650 shown in Table 2 and Appendix C1. This is because the in-suite lighting measure was ultimately not implemented. The projected savings were therefore updated to reflect this change.
$14,683 $21,194 $28,440
$18,227
$27,391
$33,330 $14,303
$36,860
$38,561
$0
$20,000
$40,000
$60,000
$80,000
$100,000
$120,000
Projected 2014 2015
Co
st S
avin
gs
Gas Electricity Water
15
Figure 9: Change in Cost Savings between 2014 and 2015
Table 8 summarizes the resulting internal rate of return (IRR), return on investment (ROI), net
present value (NPV)9 and simple payback. Based on these parameters, the project has fared
well financially. Table 8: Summary of Financial Parameters
Financial Summary
Simple Payback 5 years
IRR 16.6%
NPV (at a 4% rate) $352,328
ROI 218%
Figure 10 shows the annual cash flow and cumulative savings extrapolated over a 10 year
period. The actual savings achieved were significantly higher than the projections. This
difference is due to a combination of conservative estimations of measure performance (namely
the water savings) as well as conservative estimates of future utility cost increases. While a
certain degree of conservativeness is warranted, overly conservative savings estimations can
be detrimental long term. Energy retrofit projects should carefully estimate the savings at the
feasibility stage to avoid reducing the potential investment of future work.
Figure 10 - Annual Cash Flow from 2013 to 2023 (includes receipt of incentive rebates)
9 The 2014 and 2015 cost savings that are extrapolated over a 10 year period.
-50%
0%
50%
100%
150%
Electricity Gas Water Total
Ch
ange
in C
ost
Sav
ings
(%
)
Savings Due to Quantity Increase Savings Due to Rate Increase
-$600,000
-$400,000
-$200,000
$0
$200,000
$400,000
$600,000
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023
Cas
h F
low
Annual Cash Flow Cumulative Cash
16
Conclusions
A number of resource conservation measures have been implemented at Robert Cooke in order
to reduce utility consumption, energy, and greenhouse gas emissions. Through these retrofits,
there was also an opportunity to renew mechanical systems which were either malfunctioning or
near the end of their service life. These measures have been funded through the ESPA
platform, where all project parties have a vested interest in ensuring the project goals are met.
Annual savings in 2015 have exceeded the projections by 169% for water, 93% for natural gas,
and 82% for electricity. Higher than expected savings were largely due to large water savings
associated with the toilet leakage which was not included in the savings projections. Overall,
this project achieved 30% savings in greenhouse gas and 20% savings in utility costs.
Through the retrofit implementation and detailed monitoring of the boilers, a number of best
practice guidelines can be applied to future projects:
Residents at the building were opposed to an in-suite lighting retrofit using compact
fluorescent lights (CFLs), which resulted in foregoing significant electrical savings.
Future projects should involve residents early in the design process regarding in-suite
retrofit measures so there is an opportunity to address concerns and educate residents
on the benefits of a particular measure.
The boiler analysis relied on spot metering the non-condensing boiler flow during the
monitoring period. Given that these parameters can vary during operation, flow rates
should be directly monitored. In addition, future projects must carefully align the
individual sensor accuracy and logging capabilities with the level of accuracy required.
A common industry belief is that condensing boilers may not have any efficiency gains
over non-condensing boilers when operating conditions are outside the condensing
temperature range (i.e. above 130°F). This case study has shown that efficiency gains
with condensing boilers are possible even when the water temperatures are outside the
ideal condensing conditions. Future projects should consider installing condensing
boilers over high efficiency units, even if the return water temperatures are expected to
fall outside the ideal condensing range for a portion of the time.
The condensing space heating boiler was found to cycle more when the return water
temperature was lower, since this was a period of time when the building had a lower
heating demand. Although higher condensing boiler efficiencies are expected at lower
return temperatures, the increased amount of cycling could partly offset those efficiency
gains. To reduce cycling times and maximize the operating efficiency, oversizing heating
and DHW boilers by a significant margin should be avoided.
A combination of conservative savings estimates and assumptions about future utility
rate increases resulted in substantially underestimating the long-term savings potential
17
of this project. While a certain degree of conservativism in estimating utility cost savings
is warranted, overly conservative estimates can result in underinvestment in energy and
water efficiency retrofit projects. Conducting a detailed pre-retrofit investigation (e.g.
checking for toilet leakage) can result in better savings projections which will ultimately
increase the likelihood of retrofit projects being completed.
This case study used a multi-measure retrofit approach where water saving measures
that can result in large utility cost savings were implemented alongside gas saving
measures that can provide considerable GHG emission reductions. Simultaneously
implementing a variety of measures targeting the water, gas, and electricity consumption
can help retrofit projects achieve significant GHG and cost savings reductions. Financing
platforms like TAF’s ESPA are needed to provide an opportunity for building owners to
take advantage of energy and water saving opportunities across the multi-residential
sector.
18
Appendix A – Energy Savings Performance Agreement Structure
Robert Cooke
Co-Op TAF
Energi Insurance Provides savings warranty insurance policy
Engineering Firm Project manager Monitors and verifies savings Provides maintenance program for equipment
ESPA
Sub-Contractors
19
Appendix B – Pre-retrofit Building Information
Building Type Co-operative Name & Address
Robert Cooke Co-Operative Homes Inc. 20 Garnett Janes Road Toronto, ON M8V 3Z1
Year of Construction
1992 Major Renovations
N/A
Number of Floors 13 Parking Levels 2 (underground)
Number of Suites 123 (1-3 bedroom) Gross Area ~14,000 m2
Heating
4,400 MBTU/hr provided by three atmospheric boilers serving both heating and hot water. Building has a 750 gallon hot water tank. Primary loop is used for heating, secondary loop for domestic hot water.
Residences heated by two-pipe fancoils. Common areas heated by fancoils and electric unit heaters.
Cooling
No central cooling, window units estimated at 150 tonnes combined.
5 ton rooftop unit serves offices; 2 ton unit serves community room at 13th floor.
DHW Combined with space heating.
Ventilation
Two MAU rated at 8,000 CFM and 750 MBTU/hr, each.
Common areas ventilated by fractional HP exhaust fans, garage ventilated by four 2-HP exhaust fans.
Resident kitchen and sanitary exhaust fans discharge through wall-boxes.
Miscellaneous Equipment/Facilities
Activity room and common laundry facilities.
20
Appendix C1 – Projected Resource Conservation Measure Costs
Resource Conservation Measures
Gross Cost10
Incentives Net
Cost Annual Savings
Asset Lifetime11
Net Present Value
Replace the three existing boilers with condensing and high efficiency boilers.
Separate hot water and heating systems.
$270,000 $40,750 $229,250 $6,400 20 ($140,987)
Install variable speed drives on make-up air units.
$23,200 $16,150 $7,050 $7,750 15 $68,667
Replace domestic cold water booster pump with booster pump equipped with a variable speed drive.
$23,300 $11,550 $11,750 $1,250 15 $21,183
Replace existing T12 and T8 fixtures with reduced wattage T8 fixtures and electronic ballasts.
Replace existing in-suite incandescent lamps with compact fluorescent lamps.
$47,700 $17,000 $30,700 $16,300 10 $114,048
Install low-flow aerators and toilets. $72,800 $1,250 $71,550 $16,350 15 $198,843
Replace remaining original fridges and stoves with high efficiency models.
$192,100 $95,300 $96,800 $11,250 10 $150,725
Replace weatherstripping of entry/exit doors. $4,000 $400 $3,600 $550 10 $6,290
Monitoring, training and education. $25,000 $5,000 $20,000 $6,800 10 $54,428
Total $658,100 $187,400 $470,700 $66,650 - $473,197
10
Excludes engineering and design fees. 11
Lifetime of asset is estimated by Finn Projects.
21
Appendix C2 – Projected Resource Conservation Measure Savings
12
Annual utility savings are achieved through several measures. A web-based real time monitoring system displaying
the building utility consumption was installed in the common area so residents can see the real time savings. In
addition, Fin Projects has delivered a resident awareness program regarding resource conservation. Lastly,
operator training was conducted to ensure the new mechanical systems are operated as intended. These savings
are not included in the baseline savings.
Resource Conservation Measures
Projected Annual Savings
Electricity (kWh)
Natural Gas (m3)
Water (m3)
GHG (tCO2e)
Replace the three existing boilers with condensing and high efficiency boilers.
Separate hot water and heating systems.
- 22,090 - 41.8
Install variable speed drives on make-up air units.
8,750 22,910 - 44.3
Replace domestic cold water booster pump with booster pump equipped with a VSD.
9,600 - - 1.1
Replace existing T12 and T8 fixtures with reduced wattage T8 fixtures and electronic ballasts.
Replace existing in-suite incandescent lamps with compact fluorescent lamps.
127,350 - - 14.0
Install low-flow aerators and toilets. 7,750 3,680 5,270 7.8
Replace remaining original fridges and stoves with high efficiency models.
88,050 - - 9.7
Replace weatherstripping of entry/exit doors. - 1,950 - 3.7
Monitoring, training and education12. 28,700 4,140 710 11.0
Total 270,200 54,770 5,980 133.3
22
Appendix D1 - Equipment Details
Equipment Manufacturer Quantity Description
Boilers PK Mach PK Thermific Model
1 2
1.05 MBTU (condensing) 1.5 MBTU
Motors Century 2 Outdoor and indoor MAU supply fan motors
Appliances Frigidaire Whirlpool
140 148 11
Range Fridge Fridge
Toilets Proficiency 147 20
3 L – in units 3 L – accessible, in common areas
Showerheads AM Conservation Group
135 1.5 gpm
Faucet aerators
AM Conservation Group
99 140
1.0 gpm – bathrooms 1.5 gpm - kitchens
Lighting Various ~258 fixtures with ~413 lamps
48” T8-25W Elec. Ballast, 36” T8-25W Elec. Ballast, 24” T8-17W Elec. Ballast, LED 11W, LED 37W Outdoor
Appendix D2 - Monitoring Details
Monitoring Equipment Manufacturer Model Quantity
Facility Explorer web-based supervisory controller, sensors, boiler interface card, network controller and expansion module
Johnson Controls
FX-PCG2611-0, FX-PCX3711-0, LP-FX2021N-1, AFP-Version6
1
Data Industrial BTU System to measure flow through the boiler + temperatures and interface with the control system
Badger Meter Series 380 Impeller BTU Meter
1
Diaphragm gas meters with volume pulse for real-time metering
CM Co.
3.5M-285-MTCI gas meter c/w RVP-F1 pulser, ACM630TC 25 PSI gas meter c/w RVP-F1 pulser
3
23
Appendix E – Savings Tables
Utility Baseline Consumption
Actual Consumption
Projected Savings (Updated)
Actual Savings
Projected Cost Savings (Updated)
1
Actual Cost Savings
% Savings Utility Rate
2014 Electricity (kWh)
1,707,464 1,521,657 142,400 185,807 $18,227.20 $27,390.81 10.9% $0.15
2014 Gas (m3) 273,993 204,913 50,630 69,080 $14,682.70 $21,194.29 25.2% $0.31
2014 Water (m3) 36,527 24,686 5,270 11,841 $14,302.78 $36,860.01 32.4% $3.11
Total $47,213 $85,445 19.0% -
2015 Electricity (kWh)
1,705,390 1,503,552 142,400 201,838 $18,227.20 $33,329.62 11.8% $0.17
2015 Gas (m3) 260,771 179,257 50,630 81,514 $14,682.70 $28,439.67 31.3% $0.35
2015 Water (m3) 35,753 24,125 5,270 11,628 $14,302.78 $38,561.48 32.5% $3.32
Total $47,213 $100,331 20.4% -
2014 & 2015 Average - $92,888 19.7% -
Utility Baseline Emission Factors
Adjusted Baseline GHGs
Current Emission Factors
Post-Retrofit Emissions
Emission Reductions
Emission Reductions (%)
2014 Electricity (kWh) 0.00011 187.8 0.00008 121.7 66.1 35.19%
2014 Gas (m3) 0.00189 518.1 0.00189 387.5 130.6 25.21%
2014 Water (m3) - - - - N/A -
Total 705.9 - 509.2 196.7 27.9%
2015 Electricity (kWh) 0.00011 187.6 0.00008 120.3 67.3 35.88%
2015 Gas (m3) 0.00189 493.1 0.00189 339.0 154.1 31.26%
2015 Water (m3) N/A N/A N/A N/A N/A N/A
Total 680.7 - 459.3 221.5 32.5%
2014 & 2015 Average - - 484.2 209.1 30.2%
1 The Projected Cost Savings provided in this appendix ($47,212) are different than the original Feasibility Study projections of $66,650. This is because the in-
suite lighting measure was ultimately not implemented. The projected savings were therefore updated to reflect this change.