the toc centre of australia

29
000 The TOC Center of Australia Pty Ltd 1 Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 020801 01 The TOC Centre of Australia Pty Ltd The TOC Centre of Australia Resource Optimisation Using Critical Chain Buffer Management in the Multi Project Environment Presented by: David V Hodes Tel: 02 9293 2844 Mobile: 0409 789 034 Fax: 02 9315 5891 E-Mail: [email protected] www.tocca.com.au

Upload: althea-hill

Post on 01-Jan-2016

48 views

Category:

Documents


0 download

DESCRIPTION

The TOC Centre of Australia. Resource Optimisation Using Critical Chain Buffer Management in the Multi Project Environment Presented by: David V Hodes Tel: 02 9293 2844 Mobile: 0409 789 034 - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 1Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The TOC Centre of Australia

Resource Optimisation Using Critical Chain Buffer Management in the Multi

Project Environment

Presented by: David V Hodes

Tel: 02 9293 2844

Mobile: 0409 789 034

Fax: 02 9315 5891

E-Mail: [email protected]

www.tocca.com.au

Page 2: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 2Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The TOC Centre of Australia Product Suite

Page 3: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 3Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Critical Chain Projects

Page 4: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 4Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Some Critical Chain Results

• The first time out, we took 26 days out of a 71-day hypermarket re-fit, a 37% increase in capacity

Matador Refrigeration

• The industry standard to get the plant up and running to 90% capacity is about 46 months. The plant was recently completed and is up to 90% production in 13 months

Harris Semiconductor

• We succeeded in dropping our average turnaround time per aircraft visit from three months to two weeks…

Israel Aircraft Industries

• We originally scheduled to take 13 months to deliver – and the team did it in six months

Honeywell DAS

Page 5: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 5Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The Idea Factory

The reward

The Project

The Market

The Idea Operations

Page 6: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 6Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The Cash Flow Of An Idea

On time

$

TimeLate

Extra cost

Market follower pricing

disadvantage

Trapped resources

Early

Monopoly advantage

Market leader pricing

advantage

Cost reduction

The next new idea

Freed resources

Page 7: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 7Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

When Ideas Become Projects

• They are late

• They are over budget

• They frequently change in scope

• Standish Group (www.standishgroup.com )

• 30% of projects canceled before finished

• 75% of completed projects are late

• Average cost overruns are 189%

• Average time overruns are 222%

Page 8: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 8Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

What About The Measures?

• “Show me how you measure me, and I’ll show you how I perform. Measure me in an illogical way, and don’t be surprised if I behave illogically”

Dr Eli Goldratt

• Is the goal task conformance or project performance?

Page 9: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 9Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Global Versus Local Optima

• What we want to do is:• Finish projects on time• Finish projects on budget• Finish projects on scope• Shorten project lead

times• Finish more projects

• What we do is:• Manage to finish tasks

on time• Measure resources on

utilisation• Micromanage task flow• Detailed risk analyses• Detailed specifications

Page 10: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 10Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Uncertainty Is At The Heart Of The Problem

• Vendor performance is unreliable

• Required tasks are not fully known

• Time to complete any given task varies

• Delivery of needed tools, equipment, and

material is uncertain

• Resource availability cannot be guaranteed

Page 11: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 11Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The Issue of Duration Risk

10% probability

50% probability

95% probability

BC is not necessarily 2xAB

Task Duration

Page 12: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 12Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

How Risk Relates To How We Are Measured

When we put safety into each task…

• Projects seem to be longer than necessary • Parkinson’s Law: work expands to fill the time available• Tasks seldom finish early • “Student syndrome” prevails: 2/3 of work done in last 1/3 of time

Task start Task end

Activity

Page 13: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 13Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The Effect Of Multi-tasking

Page 14: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 14Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Unlevelled Schedule

Page 15: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 15Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Load to Capacity of C

Page 16: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 16Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The definition of the Critical Chain is the longest set of dependent steps, taking task precedence and resource contention into

account.

Critical Chain

Page 17: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 17Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Identify Critical Chain

Load levelled (finite capacity)

Critical Chain identified

Page 18: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 18Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Managing The Critical Chain

Shrink the times to 50% probability of completion – aggregate protection in the feeding and project buffers

Σ = Buffer

Page 19: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 19Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Types Of Buffers

Project buffer: • Placed before the customer, to protect our

commitment to the customer (the external constraint)

Feeding buffer: • Placed at each point where non-critical tasks join

the critical chain, to protect against precedence conflicts on non-critical tasks

Page 20: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 20Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

CC, Fb and Pb

Project buffer task 13

Feeding buffers tasks 3 and 8

Page 21: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 21Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Critical Ratio

• Critical Ratio =work to completion

time to completion

(work+buffer)

Page 22: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 22Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Scenario 1

Status date represented by red line (8am Sunday 4th November)

Purple bars represent projected start and finish times

Project buffer (Pb) penetrated

Feeding buffer (Fb) task 8 penetrated

Resource buffer (Rb) tasks 5 and10 scheduled against expected start

Task 4 most critical to work on, as a delay here causes immediate Pb penetration

Page 23: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 23Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

But How Do We Manage The Complex, Multi-Project Environment?

Project Portfolio

Portfolio Selection

The pacing resource

Individual Critical Chain

Projects

Buffer management policies

Project PipelineProject PipelineProject PipelineProject Pipeline

•Analyse•Resource•Decide

Page 24: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 24Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

The Classic Multi-Project

Page 25: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 25Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Classic Multi-Project Statistics

Page 26: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 26Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

TOC: Critical Chain, Drum and Buffer Management

Page 27: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 27Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

TOC Statistics

Page 28: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 28Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

Test Results

Page 29: The TOC Centre  of Australia

© 2000 The TOC Center of Australia Pty Ltd 29Critical Chain Overview – AIPM 2003 MktgCCSEAV01grh 0208010 2001 The TOC Centre of Australia Pty Ltd

So What’s the Choice?

• You manage the constraint…

•Or the constraint manages you