1 The Signalling Programme Danish Onboard set-up, Freight trains & Cross Border solution 07.05.2015 Presented by Morten Søndergaard Date of meeting keeper of the minutes

Upload: dinhthuan

Post on 04-Jun-2018

221 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

1

The Signalling Programme

Danish Onboard set-up, Freight trains & Cross Border solution

07.05.2015 Presented by Morten Søndergaard

Date of meeting

keeper of the minutes

Page 2: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

2

Agenda

– Signalling programme on-board set-up

– DK goverment support fund

– Signalling programme contract set-up

– Cross border solution in the Øresund region

– Cross border solutions Germany - Denmark

Page 3: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

3

The Danish Onboard set-up

– All trains on state contract financed by the state

– New trains must be financed by operators (eg. DSB)

– Finance includes First of Class, design, safety approval,

training etc.

– All operators in Denmark can buy on our framework contract

– Commercial trains – typical freight – are not financed by state

All trains employed for public service transport will be equipped with BDK cobtracted Onboard equipment

Page 4: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

4

Freight Railway Undertakings

Who can apply and allocation

– All Freight RU’s which operate on Banedanmarks network and

own ATC fitted vehicles

– The total fund is DKK 44 million + 11 million for new entries

(2013) prices

– Maximum allocation is 50% of direct cost for purchase and

installation of ETCS

– If the applicant also applies CEF (TEN) funds – the maximum

funding is up to 50% of direct cost for purchase and installation

The Danish Government Support Fund

Page 5: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

5

Freight Railway Undertakings

Criterias:

– Rolling Stock with Danish ATC and Trafikstyrelsens permission for

use

– It will – on ”one to one” basis – be possible to interchange one

vehicle with ATC with another vehicle without ATC

– The installation takes place within the following period: 2015-

2021

– New entries: Min. 70,000 km/year and min.20,000 km/year for

the specific locomotive

The Danish Government Support Fund

Page 6: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

6

Freight Railway Undertakings

Outstanding issues

– Banedanmark is awaiting final approval of the application set-

up from the European Commission

– Locomotives: without ATC which are operating today –

typically for infrastructure works

– Shunting locomotives

The Danish Government Support Fund

Page 7: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

7

BDK contracts overview ETCS non-compensated

7

Supplier Alstom

Railway Undertaking

Signal- programmet

Onboard

Main Contract FoC

-design -installation

BtB-agreement

FoC

Subcontract 18A Series

-installation -maintenance

•Generic Design •Installation and Test of FoC trains (including approvals) •Training concepts and tools •System Tests •Safety Approvals •Software maintenance

•Equipment delivery •Installation and Test of Rollout trains (including approvals) •Decommissioning of STM •Actual training •Maintenance, spare parts

Page 8: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

8

BDK frame agreement overview STM-DK non-compensated

8

Supplier Siemens

Railway Undertaking

Signal- programmet

Onboard

Frame agreement -design

-purchase FoC

BtB-agreement

FoC

Bilag 1 -purchase Series

-purchase spareparts

STM-DK prices are negotiated by BDK

Integration with Alstom EVC paid by BDK via main contract but installation paid by RU via subcontract

Page 9: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

9

Procedure to participate in the Signalling Programme

9

1. Signing the Subcontract A with Alstom

It triggers the start of FoC activities in the Main Contract

2. Signing a Back to Back with BDK to cover the FoC activities

Note: Both to take place at the same time

Page 10: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

10

The Signalling Programme

We deliver:

– An onboard ETCS system integrated with DK-STM and SE-STM and a

solution for onboard integration with PZB

– A DK-STM integrated and approved with DK-ATC lines

– Integration of Alstom ETCS onboard with DK trackside(s)

We do not deliver:

- Integration of SE-STM with Swedish trakside (covered by Trafikverket)

- Integration of PZB onboard and German trackside (to be covered by RU

in cooperation with DB if needed)

- Approval of rolling stock in other contries (secure interoperabilty though)

Scope concerning cross border

Page 11: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

11

Øresund border

Established formal cooperation TRV/ÖSB/BDK Joint working groups during 2+ years SE roll-out now to be based on B2.3.0. SE consider B3

Page 12: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

12

Øresund border

Integrated operational system, border crossing at 180 km/h

• Existing signalling border at Peberholm

• Radio border asymmetrical due to Swedish GSM-R introduction

• GSM-R solution under migration

• Interference issues and shared GSM-R frequencies

• Unknown signalling supplier on Swedish side

Page 13: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

13

Migration on Øresund

Infrastructure existing situation

ATC ZUB123 Transition zone ZUB123 - ATC2

ATC2

Page 14: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

14

Öresund Link Migration stage when ERTMS

onboards are introduced 2016/17

ATC ZUB123 Transition zones ZUB123-ATC2

&

STM DK – STM SE

ATC2

Principles being validated on test line in Sweden now

Page 15: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

15

Öresund Link Migration stage

June 2019. SP roll-out completed on Øresund

ERTMS B3

ATC 2

Transition zone L2 - STM SE

Page 16: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

16

Öresund Link Infrastructure final step

2020(?)

ERTMS B3

ERTMS B3(?)

Transition zone L2 – L2

Page 17: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

17

Borders to Germany

Much lower traffic level than Øresund

Mainly Freight traffic

Manual transitions at low speed/standstill on existing connections

Attempts from SP at setting up a permanent cooperation with DB, so

far with little success

Germany has not current plans to investing in ERTMS lines bordering

to DK

RFC3/Corridor B is not highest priority in Germany

Page 18: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

18

Padborg border today

• Physical border South of the station

• Manual transition ”border” at platform

• German trains allowed to operate into shunting area with PZB only

• German deployment of ERTMS in this area uncertain

• Station locally operated today (Both German and Danish Signaller)

• Change of Catenary system at standstill

• Manual change between ZUB & PZB at standstill.

Page 19: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

19

Padborg station

– Remote controlled from Fredericia TCC

– ERTMS Level 2 without daylight signals (like the rest of the

DK network)

– Access from German side to ETCS shunting area with unfitted

trains based on PZB and German shunting signals (to be

confirmed feasible)

Planned future state

Page 20: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

20

Padborg border

Area to be accessible for German freight locos without ERTMS

Page 21: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

21

Femern border

Immersed tunnel, signalled by DK (ERTMS L2, Alstom)

• New ”border” at North entry to Burg

• Tunnel projekt/DK runs approval in Germany

• Uncertain upgrade of line and deployment of ERTMS from German side to Burg st.

• Special tunnel evacuation procedures (19 km long). Planned use of ETCS Reverse mode with special OR rule.

Page 22: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

22

Tønder border

• Physical border on the block south of Tønder station

• No line block between Tønder and Niebüll

• Mechanical interlocking at Niebüll (owned by DB)

• Line operated by private company NEG AG

• Trains operating are Danish (Arriva trains)

• Danish ATC balises used in Niebüll on German side today

Page 23: The Signalling Programme - Banekonference Freight... · Freight Railway Undertakings Who can apply and allocation – All Freight RU’s which operate on Banedanmarks network and

23

Tønder border

Proposal developed by DK SP based on discussions with German private line