Page 1 of 17

THE HONG KONG INSTITUTE OF SURVEYORS

QUANTITY SURVEYING DIVISION

ASSESSMENT OF PROFESSIONAL COMPETENCE

PART I ASSESSMENT – SEPTEMBER 2012

WRITTEN TEST

Page 2: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 2 of 17

NOTES TO CANDIDATES A. Headings to questions are for ease of identification only and do not form part of the

questions. B. The number of questions are as follows: (1) Section A – Ten (10) multiple choice questions each of 2 marks each. The

recommended time for attempting the multiple choice questions is approximately 20 minutes.

(2) Section B – FOUR (4) short questions each of 6 marks each. The

recommended time for attempting the short questions is approximately 60 minutes.

(3) Section C – One (1) question on Measurement of 56 marks. The

recommended time for attempting this part is approximately 120 minutes. C. All Multiple Choice Questions, Short Questions and the tasks on

Measurement are compulsory. D. The total mark is 100. The overall pass mark is 55. E. Refer also to INSTRUCTIONS TO CANDIDATES which were issued to you in

advance. NOTE: (a) Whenever the term HKSMM is used, it shall mean the Hong Kong Standard Method

of Measurement of Building Works, Fourth Edition 2005. (b) Whenever the term SFC is used, it shall mean the Agreement & Schedule of

Conditions of Building Contract for use in the Hong Kong Special Administrative Region, Private Edition - With Quantities 2005 Edition or Without Quantities 2006 Edition, as appropriate.

ASSESSMENT CRITERIA Candidate is expected to demonstrate his/her acquisition of practical skills and theoretical knowledge in quantity surveying at the technical level and the ability to correctly and precisely express his/her understanding on some specific areas of quantity surveying practice at the technical level.

Page 3: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 3 of 17

SECTION A – MULTIPLE CHOICE QUESTIONS [TOTAL 20 MARKS] Candidate is required to choose his / her answers to the questions by writing “A”, “B”, “C” or “D” in the answer sheet for the Multiple Choice questions. [2 marks each]

A1 The payment interval under the SFC, if none stated, shall be:

A weekly

B fortnightly

C monthly

D Quarterly

A2 Within how many days, under the SFC, the Contractor shall pay the Nominated

Supplier after receiving payment from the Employer?

A 14 days

B 21 days

C 28 days

D 56 days

A3 If a Quantity Surveyor wants to make some deviations to the measurement

method as stated in the HKSMM, he / she shall draw tenderers’ attention on:

A Conditions of Tender and/or Special Conditions of Tender

B Conditions of Contract and/or Special Conditions of Contract

C Form of Tender and/or Annexes to the Form of Tender

D Preambles and/or Special Preambles Notes

A4 Under the SFC, the period of defects liability period, if none stated, shall be:

A 1 month

B 6 months

C 12 months

D 24 months

Page 4: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 4 of 17

SECTION A – MULTIPLE CHOICE QUESTIONS

A5 For a building contract with Contract Sum at HK$40,000,000, the retention

money was stated to be 10% and subject to maximum retention of 5% of the

Contract Sum in the Appendix to the Conditions of Contract. In Interim Payment

No. 7, the gross certified amount was HK$25,000,000.

If the ascertained value of extra work done for the forthcoming Interim Payment

No. 8 is HK$1,000,000, the amount of retention to be withheld in this Interim

Payment No. 8 shall be:

A HK$100,000

B HK$2,000,000

C HK$2,500,000

D HK$2,600,000

A6 Which of the following shall not be included in the Interim Payment Certificate?

A Concrete works casted on site

B Reinforcement at the bending yard on site

C Formwork delivered on site

D Reinforcement stored off site which are expressly approved by the Architect to be paid in the interim payment

A7 If a Quantity Surveyor goes to a building construction site, by local statutory

regulations, he / she must wear

A Safety Belt

B Safety Goggles

C Safety Helmet

D Safety Shoes

A8 If a Quantity Surveyor evaluates a variation for the supply of a proprietary

product at a total amount of HK$2,875 which includes a mark-up of 15%, the

amount of the Contractor’s mark-up for that proprietary product will be:

A HK$375.00

B HK$431.25

C HK$2,443.75

D HK$2,500.00

Page 5: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 5 of 17

SECTION A – MULTIPLE CHOICE QUESTIONS

A9 Which of the following parties are the signing parties to a Nominated Supply

Contract?

(1) Architect

(2) Employer

(3) Main Contractor

(4) Nominated Supplier

A (1) & (4)

B (2) & (4)

C (3) & (4)

D None of the above

A10 Please arrange the following certificates in accordance with the sequence of

occurrence from the earliest to the latest.

(1) Substantial Completion Certificate

(2) Final Certificate

(3) Certificate of Making Good Defects

A (1), (2), (3)

B (1), (3), (2)

C (2), (1), (3)

D (3), (1), (2)

Page 6: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 6 of 17

SECTION B – SHORT QUESTIONS [TOTAL 24 MARKS]

Candidate is required to state his / her answer to the question in the answer book

separately provided. [6 marks each]

Question B1

Based on the following information for the Main Contract of a 32-storey single tower

residential development at Mongkok:-

(i) Completion Date – 12 December 2011

(ii) Date of Substantial Completion – 8 March 2012

(iii) Extension of Time granted – 69 calendar days

(iv) Amount of Liquidated and Ascertained Damages – HK$23,200 per calendar day

(a) Calculate the number of days of delay. [2 marks]

(b) Calculate the amount of the liquidated and ascertained damages. [2 marks]

(c) Under the SFC, what actions does the Architect have to take as a pre-requisite

condition for the Employer to deduct liquidated and ascertained damages from

amounts due to the Contractor. [2 marks] Question B2

The following information is shown in a lump sum fixed price contract based on Drawings

and Specification. SFC is adopted in this project.

(i) Ten (10) wash basins were shown on Contract Drawings.

(ii) Twelve (12) wash basins each at HK$960/No. was measured and priced by the

Contractor in the Schedule of Quantities and Rates.

(a) If ten (10) wash basins are ultimately supplied and installed on Site, is there any

cost adjustment required in the final account. [1 mark]

(b) If there is an Architect’s instructed variation work to add two (2) wash basins, is

there any cost implication to the Contract. [1 mark]

(c) State the reasons for the answers in Item (a) and (b) above. [3 marks]

(d) If there is an Architect’s instructed variation work to delete all the wash basins as

shown on the Contract Drawings, calculate the omission amount for this variation.

[1 mark]

Page 7: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 7 of 17

SECTION B – SHORT QUESTIONS Question B3

The following is an extract from the preambles on Prime Cost rates (herein referred to as

“PC rate”):

“Where prime cost rates are included in the description of items in these Bills of

Quantities, these prime cost rates are for the material cost of that item delivered to site

( street level ) only and the Main Contractor shall allow in addition for all wastage, fixing,

all ancillary materials ………… The contract rate will be adjusted by the net difference

between the prime cost rate and the actual price (supply cost) and will be applied to

the net quantity of the items measured as fixed in position.”

Based on the rules of adjustment of PC rate above and the attached Bills of Quantities

(refer to Attachment for Question B3), please answer the following questions.

(a) For tiling (Finish F6), the actual supply tiling confirmed is “Barby” homogeneous

tiling at a supply cost of $260/m2, what is the revised unit rate of homogeneous

floor tiling (Finish F6) after adjustment of the PC rate? [2 marks]

(b) What is the amount of saving or extra expense as a result of the adjustment of the

PC rate in Item (a) above and based on the quantities as stated in the Bills of

Quantities of homogeneous floor tiling (Finish F6)? [2 marks]

(c) After the adjustment of the above PC rate item, an Architect’s instruction is given for

Room X with floor finishes changed from F3 to F6. The measured floor area of

Room X in accordance with the Contract is 15m2. What is the amount of addition

or omission as a result of this instruction? [2 marks]

Question B4

Describe the definitions and applications of the following terms appearing in the

construction contract: (a) Provisional Quantities (b) Provisional Sum (c) Prime Cost Sum.

[2 marks each, total 6 marks]

Page 8: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 8 of 17

Attachment for Question B3

Page 9: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 9 of 17

Project: ABC Development Bill No. 3 Main Contract Plasterer Item Description Quantity Unit Rate

(HK$) Amount (HK$)

A 20mm Cement and sand screed (1:3) to floor to receive homogeneous tiling

765 m2 80.00 61,200.00

B Non-slip “Euro” homogeneous tiling to floor including colored slurry to backs of tiles and colored cement grouting (Finishes F3)

480 m2 460.00 220,800.00

C Homogeneous tiling (P.C. rate $300/m2 supply only) to floor including colored slurry to backs of tiles and colored cement grouting (Finishes F6)

285 m2 480.00 136,800.00

“ “ “

G Lime cement plaster as described to wall & columns (Finishes W2)

850 m2 100.00 85,000.00

“ “ “

K Ceramic tiling (P.C. rate $250/m2 supply only) to walls & columns including colored slurry to backs of tiles and colored cement grouting (Finishes F8)

420 m2 450.00 189,000.00

Carried to Collection $ XXXXXXXX

Page 10: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 10 of 17

SECTION C1 – QUESTIONS ON MEASUREMENT (TOTAL 56 MARKS)

The Owner of a recreation centre intends to build an extension. The Architect has

produced the architectural plans (Drawing A-01 and A-02). The Structural Engineer has

produced the framing plans (Drawing S-01 and S-02) but the reinforcement details are

not yet finalised. Previously during preliminary design stage, the Structural Engineer has

provided indication of steel ratio as follows:

(i) Ground slab – 150 kg/m3

(ii) Column and beam – 200 kg/m3

(iii) Roof slab – 100 kg/m3

(iv) Curb – 100 kg/m3

As the Owner wants to have the extension built and completely fitted out before next

summer, he would like to invite some contractors to tender for the works now and

requests his Quantity Surveyor to prepare Bills of Quantities based on the drawings

produced.

You are the project quantity surveyor and responsible for producing the Bill of Concrete

Works.

(a) Based on the structural drawings (Drawing S-01 & S-02) provided, prepare a

take-off list (items that need to be measured) for concrete and formwork. [8 marks]

(b) Your senior quantity surveyor has spotted some discrepancies in the architectural

and structural drawings. Please prepare tender queries to the Architect and the

Structural Engineer to clarify the discrepancies before taking off. [4 marks]

(c) Take off concrete and formwork based on Drawing S-01 & S-02. [27 marks]

(d) Based on the steel ratio given by the Structural Engineer, your senior asks you to

calculate the total approximate quantity of reinforcement. [7 marks]

(e) Prepare Bills of Quantities for Concrete Works (concrete and formwork only). Use

bill papers to answer this question. Each bill item shall include descriptions of work,

unit and quantity. Your senior has provided some sample bills of Concrete Works (2

pages) for your reference. [10 marks]

Attachment to Question C1:

1) Architectural Drawing A-01 and A-02

2) Structural Drawing S-01 and S-02

3) Sample Bills of Quantities – Concrete Works (2 pages)

Page 11: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 11 of 17

Attachment for Question C1

Page 12: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

Page 12 of 17

Page 13: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

Page 13 of 17

Page 14: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

Page 14 of 17

Page 15: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

Page 15 of 17

Page 16: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 16 of 17

Sample Bills of Quantities Concrete Works Item Description Quantity Unit Rate

(HK$) Amount (HK$)

4.0 CONCRETE WORKS IN-SITU CONCRETE WORK Concrete grade 20D/20 Bases under bathtubs 4.1 generally 10 m3 REINFORCED IN-SITU CONCRETE WORK Concrete grade 20D/20 Non-structural walls 4.2 125 mm thick 180 m3 4.3 150 mm thick 200 m3 4.4 200 mm thick 100 m3 4.5 250 mm thick 20 m3 Curbs

4.6 generally 5 m3 Concrete grade 30D/20 Suspended slabs and roof

4.7 130 mm thick 1,030 m3 4.8 150 mm thick 35 m3

4.9 200 mm thick 108 m3

4.10 250 mm thick 20 m3 Beams and the like

4.11 generally 435 m3 Steps and staircases including strings

4.12 generally 12 m3 Concrete grade 45D/20 Piers, columns and the like

4.13 generally 225 m3 Walls

4.14 150 mm thick 20 m3

4.15 200mm thick 560 m3

4.16 225mm thick 556 m3

4.17 300mm thick 103 m3 Curbs

4.18 generally 10 m3

Carried to Collection $ .

Page 17: THE HONG KONG INSTITUTE OF SURVEYORS … · quantity surveying division assessment of professional competence ... written test . the hong kong institute of surveyors quantity surveying

THE HONG KONG INSTITUTE OF SURVEYORS QUANTITY SURVEYING DIVISION ASSESSMENT OF PROFESSIONAL COMPETENCE PART I ASSESSMENT – 18th SEPTEMBER 2012 WRITTEN TEST

Page 17 of 17

Sample Bills of Quantities Concrete Works Item Description Quantity Unit Rate

(HK$) Amount (HK$) FORMWORK FOR IN-SITU CONCRETE WORK Formwork Soffit of slabs and the like

4.19 generally 5,063 m2 4.20 ditto and strutting 3.5 -5.00m 1,027 m2 4.21 cantilevered 54 m2 Soffits of slabs and the like; 250 mm thick 4.22 generally 58 m2 Soffits of landings 4.23 generally 9 m2

Sloping surfaces; soffits of slabs, staircases and the like

4.24 generally 27 m2 Vertical surfaces

4.25 walls and the like 16,556 m2

4.26 piers, columns and the like 1,905 m2 Sides & soffits of beams; vertical sides; flat soffits

4.27 generally 1,024 m2 4.28 ditto and strutting 3.5 - 5.00m 560 m2

4.29 cantilevered 20 m2 Edges & breaks in suspended slabs and the like

4.30 not exceeding 300mm wide 136 m Edges of walls, sides of opening in walls and the like

4.31 not exceeding 300mm wide 1,069 m Soffits of opening in walls and the like

4.32 not exceeding 300mm wide 306 m Sides of bases under bathtubs

4.33 not exceeding 300mm wide 57 m Risers, up-stands and curbs

4.34 not exceeding 300mm wide 168 m Over strings of stairs

4.35 over 300mm wide 16 m2

4.36 not exceeding 300mm wide 5 m

Carried to Collection $