The HCP (Hidden Critical Paths) Method: Shortening projects schedules and more… The HCP (Hidden Critical Paths) Method: Shortening projects schedules and more… Tal Levanon, MSc, PMI-SP Founder & CTO HCP Project Management Consulting www.hcp-consulting.com Tal Levanon, MSc, PMI-SP Founder & CTO HCP Project Management Consulting www.hcp-consulting.com

Upload: doanque

Post on 07-Sep-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

The HCP (Hidden Critical Paths) Method:

Shortening projects schedules and more…

The HCP (Hidden Critical Paths) Method:

Shortening projects schedules and more…

Tal Levanon, MSc, PMI-SP

Founder & CTO

HCP Project Management Consulting

www.hcp-consulting.com

Tal Levanon, MSc, PMI-SP

Founder & CTO

HCP Project Management Consulting

www.hcp-consulting.com

Page 2: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

Tal Levanon - Founder & CTO

Developer of the Hidden Critical Paths method (US patent #US7,769,618 B2)

15 years of international project management experience

PMI-SP (PMI-Schedule Professional)

Lecturer at the Engineering Department of Tel Aviv University

M.Sc. Industrial Engineering –Tel Aviv University (Israel)

www.hcp-consulting.com 2 ©Tal Levanon - HCP

Page 3: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 3

AgendaMotivation for listening

What is HCP?

Insights Revealed by HCP

HCP Case Studies

Page 4: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 4

Objectives of theHCP Method (Patented)

Predict the ability to complete the project on time, on spec and on budget

Pinpoint action items for schedule improvement

Identify hidden risks in the project

Page 5: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

Who is our Clientele?

www.hcp-consulting.com © HCP Project Management Consulting -Proprietary

5

Asset Owners & Investors

Contractors

SubjectSubjectSubjectSubject

HCP deep schedule analysis for schedules from outside sources

� � � �

Writing schedules for tenders, projects � �

Monthly monitoring projects’ schedules by performance and by HCP analysis

� � �

Risk Management � � �

Lectures, Training � � �

Project Managers

Parties to Claims & Disputes

Legend

Page 6: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 6

What is the HCP (Hidden Critical Paths) Method?Unique algorithmic approach to analyzing a project

schedule

Reveal critical aspects of any project schedule:

� Locate opportunities to shorten schedule

� Locate hidden risks in the schedule

� Know the success expectation rate of the project

� Compare between two schedules:of two different contractors or of the same contractor.

� And more…

Page 7: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 7

What are Hidden Critical Paths?

Your project duration is: 12 months.

� Q: What is the duration of the critical path?

� A: Normally, 12 months.

In this project, there is a path 11.5 months long:

� Is it critical?

� Not according to CPM! But it’s not hard to get behind

schedule by two weeks in real life…

� So what is this path?

� This is a Hidden Critical Path!

Example:

Page 8: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 8

Hidden Critical Paths

Critical Path I

Critical Path II

Hidden Critical Path I

Hidden Critical Path II

DurationAugust September October November

ID

Page 9: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 9

Insights Revealed by HCP

� Locate opportunities to shorten schedule

� Locate hidden risks in the schedule

� Know the success expectation rate of the

project

� Compare between two schedules

� And more…

� Locate opportunities to shorten schedule

� Locate hidden risks in the schedule

� Know the success expectation rate of the

project

� Compare between two schedules

� And more…

Page 10: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 10

HCP Critical PathHCP Critical Path

Identical to CPM Critical Path?

Opportunities for Bringing Forward the Schedule's End Date!

RealProject

“Two Paths”SampleProject

Page 11: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 11

Real Project

1,100 activities, 600 work days

Duration Float of Total Project Duration

No. of Paths

20% 50,000~

10% 9,000~

5% 1,500~

?

?

?

Display format:

Activity Network (Primavera)

PERT Network (MS Project)

Page 12: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 12

“Two Paths” Sample Project

9sf+2days

10sf+2days

13sf+2days

14sf+2days

HCP-Critical-Path identical to CPM Critical Path?

Opportunities for Bringing Forward the Schedule's End Date!

The Difference between Total Float/Slack and Duration Float/Slack

Page 13: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 13

Activities in HCP Critical Paths

Activities in HCP Critical Paths

Page 14: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 14

Opportunities for Bringing Forward the Project’s End Date

Opportunities for Bringing Forward the Project’s End Date

Page 15: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 15

Schedule ShowingTotal Float/Slack and HCP Duration Float/Slack

9sf+2days

10sf+2days

13sf+2days

14sf+2days

Page 16: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 16

Highway 6: Section 18

Jerusalem

Tel

Aviv

Highway 6:

•Toll road

•121 km long

•BOT (Build-Operate-Transfer)

•Budget: ~$1 Billion

•Length: 18.2 km long including 14 bridges, 2 tunnels

•Budget: ~$200 million

•Contract: 33 months (June 2007 – March 2010)

Egypt

Lebanon

Jordan

Haifa

Beer

Sheva

Page 17: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 17

Hwy 6, Section 181,488 Tasks

Start DateStart DateStart DateStart Date

12121212,,,,920 920 920 920 paths found!paths found!paths found!paths found!

Finish DateFinish DateFinish DateFinish Date

DS ≤ DS ≤ DS ≤ DS ≤ 40404040% · T% · T% · T% · T

345 345 345 345 slack daysslack daysslack daysslack days

The network duration:The network duration:The network duration:The network duration:572.5 572.5 572.5 572.5 daysdaysdaysdays

Project Duration: Project Duration: Project Duration: Project Duration: 862.5 862.5 862.5 862.5 days = Tdays = Tdays = Tdays = T

0 0 0 0 paths found!paths found!paths found!paths found!

DS < DS < DS < DS < 33333333% · T% · T% · T% · T

290 290 290 290 slack daysslack daysslack daysslack days

Project Slack ����

Page 18: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 18

The HCP Critical Path

216216216216

290 290 290 290 slack daysslack daysslack daysslack daysCP duration: CP duration: CP duration: CP duration: 572.5 572.5 572.5 572.5 daysdaysdaysdays

• Possible timeline reductions

• Parallel tasks in the CP (risk)26 HCP critical tasks

Page 19: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 19

Hidden Critical Activities

Hidden Critical Activities

Manage the HCP activities as

you manage the CPM activities!

Risk management assessment

Hidden critical resources

Redundant PathsRedundant Paths

Page 20: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 20

Bridge of Strings, Jerusalem, Israel

Architect: Santiago Calatrava

L: 380 meters

W: 4,500 tons

Pylon Height: 119 meters

66 Cables, each ~150 meters.

Materials: Stainless steel Concrete

Cost: ~$65 Million

Page 21: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 21

Redundant paths

Path X is redundant to Path Y if all the tasks exist in Path X also exist in Path Y.

A B C D E F

Path X: A�B�E�F

Path Y: A�B�C�D�E�F

Page 22: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 22

Project Success Expectation

Project Success Expectation

Page 23: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 23

Schedules Comparison

Tenders: Comparison between two (or more) different schedules of different contractors

The same project: Comparison between two (or more) schedules of different months

Project: Mysterious

HCP analysis comparison: Month #1, Month #2

Project: Mysterious

HCP analysis comparison: Month #1, Month #2

Relevant to:

PMs, Expert Inspectors, Specialists , Lawyers, CEOs, etc.

Relevant to:

PMs, Expert Inspectors, Specialists , Lawyers, CEOs, etc.

Page 24: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 24

Mirroring the Project StructureMore than 8,500 activities, 8 different Primavera files combined

Date XDate XDate XDate X Project Duration: Project Duration: Project Duration: Project Duration: 460 460 460 460 work days =Twork days =Twork days =Twork days =T1111

2222,,,,813 813 813 813 paths found!paths found!paths found!paths found!((((17171717,,,,502 502 502 502 total)total)total)total)

Over Over Over Over 50505050,,,,000 000 000 000 paths paths paths paths found (total)found (total)found (total)found (total)

Too muchToo muchToo muchToo much

Date YDate YDate YDate Y

Date ZDate ZDate ZDate ZProject Duration: Project Duration: Project Duration: Project Duration: 439 439 439 439 work days =Twork days =Twork days =Twork days =T2222

M #1

851 851 851 851 paths found!paths found!paths found!paths found!((((9999,,,,179 179 179 179 total)total)total)total)

M #21 Month buffer

DS ≤ DS ≤ DS ≤ DS ≤ 5555% · T% · T% · T% · T1111

23 23 23 23 float daysfloat daysfloat daysfloat days

DS ≤ DS ≤ DS ≤ DS ≤ 10101010% · T% · T% · T% · T1111

46 46 46 46 float daysfloat daysfloat daysfloat days

DS ≤ DS ≤ DS ≤ DS ≤ 20202020% · T% · T% · T% · T2222

87 87 87 87 float daysfloat daysfloat daysfloat days

Page 25: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 25

HCP: Project SuccessExpectation

M#1

M#2

Page 26: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 26

M #1 M #2

Paths Histogram Comparison

Page 27: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 27

The HCPs

•7 paths with 1 day DS – 3 tasks

•19 paths with 10 days DS – 23 tasks

•19 paths with 11 days DS

•1376 paths with 15 days DS – 87 tasks

•1380 paths with 16 days DS – 10 tasks

•3 paths with 17 days DS

•2 paths with 20 days DS – 2 tasks

•2 paths with 21 days DS

Total of 167 HCP tasks (21DS days):

42 Critical Tasks

125 Hidden Critical Tasks

•1 path with 5 day DS – 4 tasks

•1 path with 8 days DS – 10 tasks

•1 path with 16 days DS – 13 tasks

•1 path with 17 days DS – 12 tasks

•2 paths with 18 days DS – 22 tasks

•1 path with 20 days DS – 14 tasks

•1 path with 22 days DS – 2 tasks

•2 paths with 23 days DS – 19 tasks

Total of 150 HCP tasks (23DS days):

54 Critical Tasks

96 Hidden Critical Tasks

M #1 M #2

Page 28: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 28

The CP by the HCP Analysis

6 different Critical

Paths – 42 tasks

All identical to CPM

Critical Paths

8 cases of overlapping

tasks (higher risk)

No Options for timeline

reductions

M #1

3 different Critical

Paths – 54 tasks

All identical to CPM

Critical Paths

9 cases of overlapping

tasks (higher risk)

No Options for timeline

reductions

M #2

Page 29: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 29

Identify weak control points

� Project threshold: 27.8 days.

� 234 activities with duration longer than 28 days were located

M #2

� Project threshold: 90 days.

� 461 activities with duration longer than 90 days were located

M #1

Page 30: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 30

Technical Insights…�Schedule Integrity Issues

�HCP Histogram

�Risk Management Issues:

� Overlapping Activities in the

HCP Critical Path

� Difficult-to-Track Activities

�Key Schedule and Analysis Dates

Page 31: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 31

Schedule Integrity Issues Schedule Integrity Issues

Tasks which should have finished or

should have started

•Summary Tasks Directly Linked from Predecessors•Summary Tasks Directly Linked to Successors •Only Earliest/Latest Tasks within Summary Tasks Linked to Other Tasks

opportunities to reduce the overall schedule duration

Page 32: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 32

Critical and Near-critical HCP Paths

Histogram

Critical and Near-critical HCP Paths

Histogram

Page 33: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

Case studies: HCP Histograms

www.hcp-consulting.com ©Tal Levanon - HCP 33

What do you think?

Which one is a betterproject schedule?

Path duration slack / float

Number of Paths“Cardio”

Page 34: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

Case studies: HCP Histograms – cont.

www.hcp-consulting.com ©Tal Levanon - HCP 34

Basic schedule – May 2011 Update schedule – Dec 2013

What do you think?

What happened in the project?

Path duration slack / float

Number of Paths

Path duration slack / float

Number of Paths

Page 35: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 35

Case study: Route 9, Jerusalem

• 11 sections

• 11 contractors

HCP involved from October 2005

• 3.6 km

• 3 bridges

• 2 tunnels (400m)

• ~$125 million

• Total time: 6 years (2001-May 2007)

Page 36: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 36

Risk management (1): Overlapping Activities in the

HCP Critical Path

Risk management (1): Overlapping Activities in the

HCP Critical Path

Parallel activities in the HCP critical path significantly increase the overall risk of completing the

project on schedule.

Page 37: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 37

Difficult-to-Track Activities

Difficult-to-Track Activities

Activities whose duration is longer

than a certain threshold*:

Divide into smaller sub-activities

*The HCP Method calculates this threshold per project

Page 38: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 38

Key Schedule and Analysis Dates

Key Schedule and Analysis Dates

The effective date of

analysis can be today, or can simulate any other date!

The ‘start date of

analysis’ can be later than the project start date.

Page 39: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 39

Unique Insights…!

�� Two or more schedules in One!

�� A major change in the schedule does

NOT have to result in a loss of control

�� Proactive management

Page 40: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 40

Case Study: ?

The subject of the project: Unknown…

All tasks names were removed, only WBS numbers left!

Page 41: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 41

SuccessorPredecessorstart finishdurationTaskID SuccessorPredecessorstart finishdurationTaskID

The process…

Dec 18th, 2006

Dec 18th, 2006

Dec 25th, 2006

Dec 31st, 2006

Jan 28th, 2007

Feb 4th, 2007

Received Schedule ‘2006-12-17’

Sent ‘HCP Free Analysis report’

Received Schedule ‘2006-12-21’

‘HCP Full Analysis report’ ready.

Received Schedule ‘2007-01-28’

‘HCP Full Analysis report’ ready.

PredecessorStart FinishDurationTaskID

Page 42: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 42

Project’s structure

Jan 28th, 2007

1 Critical Path

(Partially Identical to MS-

Project)

10 HCPs with

Duration Slack=8 days

Dec 21st, 2006

10 Critical Paths

(Identical to MS-Project)

1 HCP with

Duration Slack=13 days

Page 43: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 43

Hidden Critical Paths

Page 44: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 44

Project stages:Construction of building for new lineInstallation of capital equipmentProduction startup

MAX IEGConsulting & management company

Allegro Microsystems – MA, USA A Silicon wafer fabrication facilitylocated in MA, USA

Case Study:Semiconductor Factory

Expansion

Page 45: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 45

Project ProfileStart date: Aug 2004

End date: May 2005

(198.7 work days)

HCP analysis was

performed in Oct

2004 (after 2 months of work)

Schedule included

165 tasks

Page 46: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 46

HCP Analysis Results

Duration Slack=20%, 118 paths found: 2 Critical Paths

2 HCP with 2 days DS

2 HCP with 3.2 days DS

1 HCP with 5.3 days DS

But that’s not all…

Page 47: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 47

HCP Analysis Results(cont.)

Project scheduled duration: 198.7 days

Project actual duration: 173.1 days

� 25.6 25.6 25.6 25.6 work days without any work scheduled work days without any work scheduled work days without any work scheduled work days without any work scheduled in the HCP critical path!in the HCP critical path!in the HCP critical path!in the HCP critical path!

� The HCP Method discovered this by identifying a task which caused a delay due to a constraint

Hidden critical path with DS=5.3 days hasn’t started yet, concealing potential problems!

Page 48: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 48

The Impact of HCP

Project completed 3 weeks early!

Contingency budget untouched!

Project total cost: $1.8M

Proactive Management

Project’s due date: May 11th, 2005

$250,000 contingency budget

Project budget: $2.5M

Reactive management

The client: “HCP is a very powerful tool for PMs at all levels!”

Page 49: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 49

How does your project reflect in the HCP mirror?

Page 50: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 50

Thank you for Listening!

Questions?We’ll be happy to answer!

Comments?We’d like to hear from you!

Page 51: The HCP (Hidden Critical Paths) Method: Shortening ... Tal... · Paths) Method: Shortening projects schedules and more ... Your project duration is: ... Activities Manage the HCP

www.hcp-consulting.com ©Tal Levanon - HCP 51

Contact Information

Name Tal Levanon

Title Founder & CTO

Company HCP Project Management Consulting

Email [email protected]

Phone 1-888-HCP-2080+972-72-250-1394 (outside USA)

Web-site www.hcp-consulting.com