AFRICAN DEVELOPMENT BANK GROUP THE GAMBIA RURAL WATER SUPPLY AND SANITATION PROJECT PROJECT COMPLETION REPORT (PCR) RDGW/AHWS May 2019 Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 17-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

AFRICAN DEVELOPMENT BANK GROUP

THE GAMBIA

RURAL WATER SUPPLY AND SANITATION PROJECT

PROJECT COMPLETION REPORT

(PCR)

RDGW/AHWS

May 2019

Pu

bli

c D

iscl

osu

re A

uth

ori

zed

P

ub

lic

Dis

clo

sure

Auth

ori

zed

Page 2: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

1

I BASIC DATA

A Report data

Report date Date of report: September, 2018

Mission date (if field

mission)

B Responsible Bank staff

Positions At approval At completion

Regional Director F.PERRAULT M.L.AKIN-OLUGBADE

Country Manager N/A A.AMOUNOUN

Sector Director S.JALLOW W.G.GICHURI

Sector Manager/OIC A.BAMBA M.TARHOUNI

Task Manager R.MWASAMBILI B.CISSE

Alternate Task

Manager

A.ATTOUT R.LUBUNGA

PCR Team Leader B.CISSE

PCR Team Members NA

C Project data

Project name: The Gambia Rural Water Supply and Sanitation Project-

Project code:

P -GM-E00-003

Instrument number(s): RWSSI-TF NO. 5800155000751; ADF NO.

2100155022173; RWSSITF NO. 5800155001851

Project type: Sector: Water and Sanitation

Country: Gambia Environmental categorization (1-3):Category 2

Processing milestones – Bank

approved financing only

Key Events (Bank approved financing only Disbursement and closing dates

Financing source.1: ADF Grant Financing source.1 ADF Grant Financing source.1 ADF Grant

Date approved:June 19th 2012 Amount: 1,100,000 UA Original disbursement deadline:

December 31st , 2015

Date signed: March 14th 2013 Supplementary financing:N/A Original closing date: 31

December 2015

Date of entry into force: March 14th

2013

Restructuring (specify date & amount

involved): N/A

Revised disbursement deadline:31

December 2017

PROJECT COMPLETION REPORT (PCR) FOR PUBLIC SECTOR OPERATIONS

AFRICAN DEVELOPMENT

BANK GROUP

Page 3: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

2

Date effective for 1st

disbursement:August 13th 2012.

Extensions (specify dates):from

31 December 2015 to 31 December 2016

31 December 2016 to 31 December 2017

Revised (if applicable) closing

date:December 31st 2017

Financing source.2: RWSSI Grant Financing source.2 RWSSSI Grant Financing source.2 RWSSI Grant

Date approved:June 19th 2012 Amount: 3,580,000 UA (4,000,000 EUR) Original disbursement deadline:

December 31st , 2015

Date signed: March 14th 2012 Supplementary financing:402,000.00 UA

(500,000 EUR)

Original closing date: December

31st 2015

Date of entry into force: March 14th

2012

Restructuring (specify date & amount

involved): N/A

Revised disbursement deadline:31

December 2017

Date effective for 1st

disbursement:August 13th 2012

Extensions (specify dates):from

31 December 2015 to 31 December 2016

31 December 2016 to 31 December 2017

Revised (if applicable) closing

date: 31 December 2017

Financing source/instrument

(add/delete rows depending on the

number of financing sources):

Disbursed amount(amount,

UA):

Percentage

disbursed

(%):

Undisbursed

amount (UA):

Percentage

undisbursed

(%):

Financing source: ADF Grant 1,009,771.02 90.97% 82,739.17 9.03%

RWSTF 3,552,677.47 99.24% 79,158.65 0.76%%

Supplementary RWSTF 314,645.40 78.27% 152,467.31 21.76%

Government of the Gambia 0 0% 150,000 100%

Community Beneficiaries 0 0% 110,000 100%

TOTAL 4,877,093.89 91,13% 474,906.11 8.87%

Financing source/instrument

(add/delete rows depending on the

number of financing sources):

Committed amount (UA): Percentage

committed

(%):

Uncommitted

amount (UA):

Percentage

uncommitted

(%):

Financing source/ instrument1: ADF

Grant

1,014,356.50 91.38% 95,643.50 8.62%

RWSTF 3,503,630.00 97.87% 76,370.00 2.13%

Supplementary RWSTF 316,256.21 78.67% 106,646.51 21.33%

Government of the Gambia 0 0 150,000 100%

Community Beneficiaries 0 0 110,000 100%

TOTAL 4,877,596 91.14% 474,404 8,86%

Co-financiers and other external partners: N/A

Executing and implementing agency (ies): Ministry of Fisheries, Water Resources and national Assembly Matters

Page 4: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

3

D Management review and comments

Report reviewed by Name Date

reviewed

Comments

Country Manager/OIC A.AMOUMOUN

Sector Manager M.TARHOUNI

Regional Director (as chair of

Country Team)

M.L.AKIN-OLUGBADE

Sector Director W.G.GICHURI

II Project performance assessment

A Relevance

1. Relevance of project development objective

Rating* Narrative assessment (max 250 words)

4 The project’s development objectives are (i) To improve access to safe drinking water and improved sanitation

in the rural areas of The Gambia from the 2009 level of 70% to 72% (65,000 additional people) in 2015 for

water supply and from 40% in 2009 to 44% (20,000 additional peole) for sanitation by December, 2015.

These objectives are in line with the Country Strategy Paper (CSP) for The Gambia and the Gambia Poverty

Reduction Strategy II (PRSP.II), which have a focused pillar of infrastructure and rural development. At the

time the Government was still preparing the successor Program for Accelerated Growth and Employment

(PAGE) , for the period of 2012-2015, as a successor to the PSRP II. The PAGE built on the thrust of PSRP II

, with the main focus on governance but also includes greater focus on infrastructure investments, including

water and sanitation. The Rural Water Supply and Sanitation Project(RWSSP) is also in line with the Bank’s

Strategic Plan, which considers water supply and sanitation, as one of the key sectors with mainstreaming of

the cross-cutting issues of gender, environment and private sector involvement to strengthen the foundation for

sustainable development. Furthermore, the project is in line with with the following relevant Bank strategies:

the Medium Term Strategy (MTS) (insfrastructure and governance focus ), the Joint Assistant Strategy for the

Gambia (2008-2011), and the integrated Water resources Management (IWRM) policy. It is also inline with

the Rural Water Supply Sanitaion Initiative and contributed to the Bank’s commitment to assist member states

achieve the MDG targets for water supply and sanitation. The project is specified in the JAS as one of the

operations identified for financing with the lending cycle of (ADF12).

The project is in line with the Millenium Development Goals, the Sustainability Development Goals,the Bank

Ten Year Strategy (2013-2022) and the Hi-5s for transforming Africa on Improving the Quality of Life of

Africans.

* For all ratings in the PCR use the following scale: 4 (Highly satisfactory), 3 (Satisfactory), 2 (Unsatisfactory), 1

(Highly unsatisfactory)

Page 5: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

4

2. Relevance of project design

Rating* Narrative assessment (max 250 words)

4

The Bank’s intervention in the Rural Water Supply and Sanitation Sector (RWSS) in the Gambia was

grounded in the extensive experience that the Bank acquired in supporting similar projects in the region

through the Rural Water Supply and Sanitation Initiative (RWSSI). The project considered a few options,

taking into account the available water resources, various technologies water supply and sanitation,

investment and operation and maintenance costs, availability of spare parts, as well as staffing

reuirements. The bulk of the work of the project involved drinking water and sanitation infrastructures.

The technology solution was also driven by the country’s experiences, user acceptability, and investment

and operation and maintenance costs of these solutions.

For the water supply infrastructures, the technical solutions retained were solar powered multi-village or

stand alone schemes, boreholes, and storage tank and distribution network, widely used in Gambia.

The sanitation component focused on Community-Led Total Sanitation (CLTS), sanitation social

marketing, promotion of hand washing in schools and communities. The CLTS as a community-based

approach aimed at stopping open defecation through the use of social/peer pressure education, collective

community action to assist vulnerable people and support public facilities. Household latrines were

promoted and VIP latrines were built in schools and public places for their safety and hygiene.

The solar powered Sysems turned out to be cost effective, efficient and were adopted by the communities.

Also the experience with theses systems in the Gambia made it easy to maintain and operate. However,

the CLTS solution did not yield expected results in all communities. There were situations where trained

masons who were supposed to assist communities in the building of Household latrines moved to nearby

urban areas in search of higher wages and there were also cases of beneficiaries that were provided all

the materials but could not complete the Latrines by the end of the project. The main supplier of materials

for house Hold Latrines also under performed and had to be replaced. The completion rate of the CLTS

component was still above 98% with 982 Household latrines completed out of a target 1000.

During the Project changes were made to the Water Supply Infratructure component. Six(6) sites (2

additional sites) out of 22 were connected to the national electricity grid following the extension of the

national electricity Grids due to the increase in population size and demand from these communities.

These changes didn’t in any way affect the development objectives.

Page 6: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

5

3. Lessons learned related to relevance

Key issues

(max 5, add rows

as needed)

Lessons learned Target audience

1. Use of

Solar

pumped

System.

The unreliability of electricity supply was the main reason behind the choice

of solar powered pumps.This coupled with the availability of spare part,

user acceptability, the cost of the solution and operation and maintenance

practices made it the best approach in rural Gambia.The same approach

should be kept for the Climate Smart WASH development Project.

During the course of the project 6 communities were connected to the a

national grid.(4 rehabilitated network and 2 communities at their own

request)

At times as expected this unreliability of electricity caused shortage of water

in communities when enough water was not stored in the tank and the

power cut took a long time.The running cost for these system on the grid is

higher than on solar powered especially during the first five years.

However, the long term maintenance cost is lower for grid because there is

no need to replace panels when efficiency reduces. The System allows for

a connection on both the grid and the solar powered System and this should

be explored for the 6 communities connected to the NAWEC grid.However

as electricity supply becomes more reliable the systems in the 6

communities can be left as such.

DWR,Bank

NAWEC, and

Communities

2. Participatory

approach to

project

design

The project was designed through extensive consultations with all the

stakeholders. Those consulted included policy makers in government

agencies, health and local government officials, beneficiay community

groups, village water committees and NGOs, the consultative process was

important to get stakeholder feedback about the project and also incorporate

views in the design. At appraisal, the mission undertook field vist to validate

the data and information provided at the central level, and to assess the level

of involvement of the potential beneficiaries. It was then noted and

confirmed by the communities, that the selection of sites was conducted in

a participatory manner involving all stakeholders, guided by very clear

selection criteria developed by the government.

This approach was successful and was also used during the preparation of

the Climate Smart WASH Development Project.

DWR, Bank

3. Focus on the

Community

Led Total

Sanitation

Approach.

The used of CLTS approached for the construction of Household Latrines

led to a healthy increase of demand in some communities. However in other

communities especially in the West Coast Region it led to delays due to the

unavailability of trained masons and lack of commitment of somme

beneficiaries also the choice of a single supplier for construction materials

of the House Hold Latrines led to additional delays. Despite the high rate of

implementation (above 95% ) of this component it is important to assess the

CLTS approach for new operations.

COTG, Bank

Page 7: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

6

B Effectiveness

1. Progress towards the project’s development objective (project purpose)

Comments

Provide a brief description of the Project (components) and the context in which it was designed and implemented. State

the project development objective (usually the project purpose as set out in the RLF) and assess progress. Unanticipated

outcomes should also be accounted for, as well as specific reference of gender equality in the project. The consistency of

the assumptions that link the different levels of the results chain in the RLFshould also be considered. Indicative max

length: 400 words.

During the Project Preparation, the overall Water Sector Development Goal was “effective and sustainable management

of water resources and improved climate risk management to support socio-economic development and environmental

sustainability in the Gambia”.

The objective of the project is to improve access to safe drinking water and improved sanitation in the rural areas of

The Gambia from the current level of 70% (2009) to 72% (65,000 people) for water supply and from 40% (2009) to

44% (20,000) for sanitation by December,2017.

Progress –project components

New Water Supply Systems: The installation of all the 16 solar systems and 2 grid-connected pumping systems

has been completed.Tank erection completed in all the 18 sites.

Rehabilitation of Existing Water Reticulation Systems in 4 Sites The 4 Water Sysastems were rehabilitated

and connected to the extended NAWEC network.

Sanitation infrastructures:50 Institutional VIP latrines completed;Construction of the 1000 household VIP

latrines is largely completed with 982 latrines fully completed; The remaining 18 latrines are at various stages of

construction.

Hygiene promotion and education:Activities for the component fully executed with positive result.

Institutional support and capacity building/training: Activities for the component fully completed.

In a large part, These project objectives were met : Access to water supply is met about 65,000 people have access to

safe drinking in the targeted communities. Access to Sanitation is also largely met. In the project intervention sites

approximately 19,750 people have access to improved sanitary facilities. Broad hygiene promotion and education

campaign conducted at communities levels, schools and public markets and it has paid dividen in many places.

Water and sanitation working group and Joint sector review reviewed and sub-committees created. Partner institutions

were strengthened. The trained artisans were equipped with the necessary equipment to further replicate the household

latrine technology for those not covered by the project.

During Implementation, there were minor changes in the water supply insfrastructure power source for 2 multi village

Water Supply Systems. These 2 sites were connected to the national electyricity grid and the other 16 systems remained

on the solar powered as initially planned. The 4 sites on the rehabilitation sites are all connected to the extended national

grid . The changes was effected during one of the supervision mission as per the demands of the communities and due

to the continuous increase in population size in those communities. However, this did not change the scope of work

neither the attainment of the development objective. Activities in the sanitation component was fully executed except

for the household latrine construction which were completed at a rate of 98.2%.

Activities under the hygiene promotion and education and institutional strengthening and capacity building are all fully

implemented with remarkable achievement in some instances.

Page 8: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

7

2. Outcome reporting

Outcome

indicators (as per

RLF; add more

rows as needed)

Baseline value

(Year)

Most recent

value

(A)

End target (B)

(expected value

at project

completion)

Progress towards

target

(% realized)

(A/B)

Narrative assessment

(indicative max

length: 50 words per

outcome)

Core

Sector

Indicator

(Yes/No)

Outcome1

Increase in # of

people with

access to water

supply and

sanitation:

1A. Access to

safe drinking

water supply

1B. Access to

improved

sanitation

(%pop.).

70% (63,194

People)

(2009)

40%

(36,111

people)

(2009)

72%(65,000

People)

43.45%

(19,750 pep)

(2017)

72%(65,000

People)

(2017)

44%

(20,000pep)

(2017)

100% (65,000

people including

33,800 women )

98.2%

(19,750 people

including

10,270 women)

The target was

reached however

with a considerable

delay due to the

retendering of the

main work contract

YES

YES

Outcome 2:

Increased

number of people

practicing

improved

hygiene

behaviors:

2A.% reduction in

diarrheal diseases

20% (2006)

20%

10% (2017)

50%

(health indicator

survey 2013)

A planned end of

project evaluation on

the indicator is still

underway to

determine the

reduction in diarreal

diseases in the

Project area

Meanwhile, we are

already noticing a

great improvement in

hygiene practices.

YES

Rating* (see IPR

methodology)

Narrative assessment

4.0 All stated outcome in the project’s logical framework were fully achieved except for the increase in

access to sanitation given the fact that 18 latrines are still not completed.

Page 9: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

8

3. Output reporting

Output indicators

(as specified in the

RLF; add more

rows as needed)

Baseline

value

(Year)

Most

recent

value

(A)

End target (B)

(expected value

at project

completion)

Progress

towards

target

(% realized)

(A/B)

Narrative assessment

(indicative max length: 50 words per

output)

Core

Sector

Indicator

(Yes/No)

Output 1:

1.1 Number of

new water

points/system

s installed.

0 18 18 100% Provide brief assessment narrative

information here

Yes

Output 1:

1.1a number of

boreholes drilled.

0 22

2

22 100% The project was able to construct 23

boreholes. Because of the iron

present in Bullock; two shallow

boreholes was sunk with the view of

addressing the presence of iron later.

YES

Output : 1.1b

number of sites

with solar

systems installed

0

16

18®

88.8%

The planned 18 solar pumping

systems was revised to 16 after 2

sites were connected to the national

grid as opted by these communities.

These communities are rural growth

and NAWEC’s network was

extended to these comunities.

YES

Output 1.1c

Number of sites

connected to the

national grid.

.

0 6 4 150% Initially only the 4 rehabilitated sites

had to be connected to the national

grid but, given NAWEC’s extension

of the electricity networks

communities for 2 sites asked that

they be connected to the network.

These requested were granted by the

Departement of Water resources.

NO

Output 1.1d

Number of site

with Piped Water

Distribution

Networks.

0 18 18 100% Civil works have been completed by

the contractor in all the 16 sites with

all the solar pumping installations

completed and tested on functionality

which indicate positive results.

However due to budgetary constraint

the tanks to be installed have been

downsized from 60 to 40m3 and 90 to

50 m3 respectively

YES

Output 1.2

Number of water

points/ systems

upgraded/

rehabilitated.

4 4 4 100% All 4 systems wee ugraded with no

change to the initial specifications.

YES

Output 1.3

Additional

Institutional

Latrines

0 50 50 100% All 50 instututional latrines were built

however this component has

experienced somme delays because

there were somme defects that the

contractor corrected .

YES

Page 10: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

9

Output 1.4

Additional

Household

Latrines

0 1000 982 Not all household latrines could be

completed some beneficiaries were

did not complete their latrines by the

end of the Project despite having

received the necessary training and

the materials

Also, some of the trained masons had,

for economic reasons, migrated to

urban areas therefore slowing dow

the building of the PIT for some

benficiaries.The involvement of

community land local leaders in the

process ended up driving up that

number to 982 household latrinesl.

Output 2.1

Effective

collaboration

work in place

through the

Water and

Sanitation

Working Group

(WSWG).

0 1 1 100% The working group was reactivated in

2013 and held its first biannual

meeting for the year in May 2014.The

meeting constituted three technical

sub-committees in water supply,

sanitation and hygiene and health

education. Having facilitated the

reactivation and holding of the first

meeting, the Project had handed over

responsibilities for organizing the

group’s meetings to the Department

of Water Resources (DWR) whose

mandate it is. The Joint Sector

Review (JSR) was merged with

WSWG activities.

However during the PCR mission it

was not clear how DWR intended to

keep the WSWG functional

Yes

Output 2.2 Joint

Sector Review

mechanisms

established.

0 1 1 100% Yes

Output :2.3

National O&M

strategy/ financial

plan in place.

0

1 1 100% The consultancy for the O&M plan is

completed and the manual produced

was used by the consultant for the

community training and capacity

building. The recommendation of the

O&M plan was validated and adopted

at a national workshop.

Yes

Output: 2.4

Number of new

VWC formed and

trained.

0 22 22 100% A total of 22 VWC comprised of

1025 members have been

trained/sentised, out of which 47%

were female. Formed and trained

covering all the project sites. These

VWC display and disseminate good

hygiene practices.

Yes

Output 3.1

Number of

people sensitized

/trained on

hygiene &

sanitation

0 2025 2000 101% The Department of Community

Development (DCD) completed the

training of trainers (TOT) in CLTS

and is, as mentioned above, involved

Yes

Page 11: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

10

in the supervision of the erection of

the household latrines.

Output:3.2

Number of

demonstration

HH facilities

installed.

0 22 22 100% All demonstration HHL were built

prior to the supply of materials to the

beneficiaries

Yes

Output 3.3

Total number of

household VIP

latrines

constructed

0 982 1000 98.2% 982 household latrines were

constructed This target was almost

completely met but experienced

considerable delays due to the

absence of trained masons in some

communities some of them migrated

to wealthier and more urbanized

communities also there were some

delays in the supply of construction

materials

Yes

Output 3.4

Number of

artisans trained.

165 176 94% The Project has trained 2masons and

2 carpenters from each community

amounting to a total of 165 artisans(

83 masons and 82 carpenters).

NO

Output 3.5 IEC

materials

reviewed,

selected.

NO YES YES 100% The consultancy contract to

undertake this activity was awarded

to HePDO HePDO conducted

hygiene promotion and education

training for all the 22 WATSAN

committees in the project areas.

Output 3.6

Number of

communities with

CLTS.

0 30 30 100% The Department of Community

Development (DCD) completed the

training of trainers (TOT) in CLTS

and is, as mentioned above, involved

in the supervision of the erection of

the household latrines this was done

in all communities despite some

beneficiaries being late on their

commitment

Yes

Output 3.7

Sanitation

baseline survey

updated.

0 1 1 100% The sanitation baseline was updated

and even used as a guideline for the

construction of the 50 institutional

latrines

Yes

Output 4.1a

Annual Work

plan

0 5 5 100% The annual Work Plan were made

available to the Bank by the Project

Yes

Output 4.1b

Procurement

plan

0 4 4 100% All procurements were completed.

The bank had to retender the

procurement of the 18 new multi

village water supply systems due to

the termination of the main contract.

Yes

Page 12: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

11

Output 4.2

Number of

timely annual

audits

0 4 5 80% All annual audits were conducted and

approved by the Bank. The last audit

should hve included the 3 months

grace period which it did not. The

audit report was however approved

with recommendation made for

upcoming operations

Yes

Output 4.3

Number of

progress

report/yr.

0 20 21 95% All reports were submitted to the

Bank in due course with the last

report coinciding with the drafting of

the PCR.

Rating* (see IPR

methodology)

Narrative assessment

4 The Rating is highly Satisfactory. Only one output in the appraisal report was affected by

the revision of list of good and services (LGS) at the beginning of the project namelythe

number of sites with solar systems installed. Initially it was planned that this time of pump

was going to be installed on 18 sites however due to high population growth in the west

coast region which led to the extension of the Nawec electricity grid. Communities in 2

sites informed DWR of their preference for a pump system connected to the national grid.

As regards the Household latrines 982 of them were completed out of a total of 1000

initially planned these delays were mostly due to beneficiaries 18 were not able to finalized

their latrines by project completion.

4. Development Objective (DO) rating

DO rating

(derived from

updated IPR)*

Narrative assessment (indicative max length: 250 words

4 As stated above, the project’s main development objectives were to:

improve access to safe drinking water and improved sanitation in the rural areas of The Gambia from the

current level of 70% (2009) to 72% (65,000 people) for water supply and from 40% (2009) to 44%

(20,000) for sanitation by December, 2017.

In a large part, These objectives were met . About 65,000 additional people have access to safe drinking

water in the targeted communities. In the project intervention sites approximately 19,750 people have

access to improved sanitary facilities. Broad hygiene promotion and education campaign conducted at

communities levels, schools and public markets and it has yielded positive results in many

places.However the assessment of the impact on the incidences of waterborn diseases is still ongoing and

is expected to also yield positive results .

Water and sanitation working group and Joint sector review reviewed and sub-committees were created.

Partner institutions were strengthened. The trained artisans were equipped with the necessary equipment

to further replicate the household latrine technology for those not covered by the project. However some

of these artisans already migrated to urban areas were their new skills can help them earn higher wages.

Page 13: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

12

5. Beneficiaries (add rows as needed)

Actual (A) Planned

(B)

Progress towards

target

(% realized) (A/B)

% of

women

Category (e.g. farmers, students)

65,000 people in rural got access

to save drinking water

65,000

100% 52

rural population

19,750 people got access to

improved sanitation

20,000 98% 52 982 out of a 1000 VIP latrines at

household level and 51 institutional

latrines.

Trained macons 165 175 94% 0% Artisans

6. Unanticipated or additional outcomes (add rows as needed)

Description Type (e.g. gender,

climate change,

social, other)

Positive

or

negative

Impact on

project (High,

Medium, Low)

1. Access to improved sanitation in the schools also contributed to

increase in class attendance.

The construction of sanitation facilities in the selected beneficiary

schools affected class. At the provision of the toilet facilities,

absenteeism were curtailed as school children could access

sanitary facilities in their school compounds easily. Regular class

attendance has improved in the following academic year in such

schools.

Education postive Medium

2. Following the availability to access to safe drinking water in

schools. The water is not only use for human consumption but for

plant watering at household level and school gardens thus

promoting the nutrition value in schools.

Education and

food supply

Positive Medium

3. The termination of the contract for r the construction of 18 new

water supply system at the request of the contractor SAM-

BROCHO led to additional delays,somme revision of the list of

good an services, and request odf supplementary RWSSI fund

Implementation

delay/budget

constraint

Negative High

4. The 2016 closure of the country’s border with Senegal delayed

the delivery of the equipment of the main contractor leading to

second extension of the project’s closing date.

Implementation

delay

Negative Medium

5. The provision of Household latrines to less previleged and

vulnerable family in the project intervention sites, this has yielded

additional results, in that some members of the communities who

did not benefit from the project provision of building materials

have replicated the technology in the household or have improved

on the household latrine design by making septic tanks.

Health and

Hygiene

Positive High

6. The extension of the NAWEC electricity network in the West

Coast Region led 2 communities to ask for a grid connection

instead of a solar powered system.

Cimate negative Low

Page 14: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

13

7. Lessons learned related to effectiveness (add rows as needed)

Key issues (max 5, add rows as

needed) Lessons learned Target audience

1. Termination of contracts for water

supply and supply of materials for

house hold latrines

The termination of contracts in the water supply

infrastructure component and supply of materials was

requested by the contractor after its main partener in the joint

venture went under liquidation in France. This led to some

delays due in part to the absence of a procurement officer

whose contract had expired by then. Future projects should

keep a Procurement officer throughout the life of the project.

The Bank, DWR

2. Request for supplementary

funding to avoid scope reduction

Folowing the termination of the works contract , there was a

major setback due to the increased bid price of the new

contractors thus creating a scenario where the project had to

request additional resources to cover for the Gap. Therefore,

contengencies should be rightly funded for future operations.

The Bank,DWR

3. Procurement of materials at

national level for the household

larines

The procurement of household latrine materials at national

level was not an effective strategy . Trasportation and storage

issues affected effectiveness of this component as such

community based approach shoul be adopted in future.

DWR

C Efficiency

1. Timeliness

Planned project duration –

years (A) (as per PAR) Actual implementation time – years

(B) (from effectiveness for 1st disb.) Ratio of planned and actual

implementation time (A/B)

Rating*

4 December 2015 6 December 2017 66.67% 2

Narrative assessment (indicative max length: 250 words)

The initial closing date of the project was December 31st 2015. The project accumulated a delay of 2 years. Start up delays,

a border closure, and challenges encountered in procurement of works contracts at the early stages of the project

implementation affected timely achievement of project outputs.

After the award of contract for sometimes to a joint venture business for the water supply works; during the contract period

the main partner of the joint venture went under liquidation and the other partner asked for the termination of the coontract.

The re-tendering process took almost one year to reach completion.

The winner’s bid was in excess of the approved budget which coupled with the 2016 border closure led to an aditional

postponement of the date of last disbursement. Despite all these delays, and other challenges, the project ouputs and

outcome were generally achieved.

2. Resource use efficiency

Median % physical implementation

of RLF outputs financed by all

financiers (A) (see II.B.3)

Commitment rate (%) (B)

(See table 1.C – Total

commitment rate of all financiers)

Ratio of the median percentage

physical implementation and

commitment rate (A/B)

Rating*

99.5% 91.14% 109.17% 3

Narrative assessment(indicative max length: 250 words)

Despite the delays in the project and other setbacks, the project achieved most of its objectives, the planned output were

achieved namely: (i) All 51 public latrines ; (ii) 982 out of 1000 household latrines(iii) installed and 4 rehabilitation and

upgrading water points installed (iv) construction of 18 multivillage water supply Systems. Broad hygiene promotion

campaign carryout and patner institutions strengthening with logistic support.

Page 15: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

14

3. Cost benefit analysis

Economic Rate of Return

(at appraisal)

Updated Economic Rate of Return

(at completion)

Rating

*

21.48 % 17.60% 3

Narrative assessment

The economic assessment of the Rural Water Supply and Sanitation Project, is based on incremental methodological

approach. However, the economic evaluation is undertaken from a perspective which measures net benefits to the Gambian

economy as a whole. Where distortions exist, to convert financial prices to the real resource values of project inputs and

outputs, appropriate adjustments are made in financial flows to reflect economic values.

The resources mobilized during project implementation (4.88 million UA) were used to build 18 new multivillage water

supply systems, rehabilitate 4 multivilliage systems ,build 51 institutional sanitation facility and 982 household toilets.

At compleion, Project Benefits still consist of health benefits resulting from a decline in waterborne deseases , times savings

and a general improvement of health conditions and increase in productivity. These benefits were used to calculate the

Economic Rate of Return (EIRR). Other non-quantifiable benefits such as increase of school attendance,increased revenues

earned by artisans trained by the project, and other environmental and social benefits.

The Project had a satisfactory impact on tbeneficiaries (65,000 additional people for access to Water , 19750 people for access

to improved saniation and 165 new artsans trained). However, although the project was physically completed it was affected

by 2 years of delays .

The absence of a financial analysis at appraisal made it irrelevant at completion.

The costs and benefits analysis at completion of the project, estimated over the 25 year economic life yielded an Economic

Internal Rate of Return (EIRR) of 17.60 % compared to opportunity cost of capital (EOCK) in Gambia of 10 %. The reason

for lower rate is because of long implementation period, resulting in delayed accrued benefits However the rate is still above

EOCK of 10 % . This indicates that the project is still economically acceptable at completion.

4. Implementation Progress (IP)

IP Rating

(derived from

updated IPR) *

Narrative comments (commenting specifically on those IP items that were rated Unsatisfactory or

Highly Unsatisfactory, as per last IPR). (indicative max length: 500 words)

3

Although the IP rated the project satisfactory some of the issues which lowered the rating were the initial

delay that the project encountered and which escalated to 2 years of delay . The project costing at appraisal

took into account 260,000 UA contribution (150,000 UA from the Government and 110,000 UA from the

beneficiaries. The said contribution never materialiased and created a budget issue that is yet to be solved. It

must however be noted that none of the project objectives were jeopardised. All of them were achieved.

5. Lessons learned related to efficiency

Key issues (max 5, add

rows as needed) Lessons learned Target

audience

1. Start-up delays The project experienced delays in the recruitment of key staff , however use of an

existing PMU within the EA was a a major asset to get key milestones in place, such

as effectiveness and Project launching, Where possible,.in future the team should be

put in place before the appraisal mission it will allow members of the project team

to participate in the appraisal mission for better understanding.

The Bank,

DWR

2. Payment delays

The poject experienced delays in the payment process.This is in part due to the fact

that the project had 4 Task managers during its lifespan that caused some delays

because each task manager takes a while to understand the project issues. It is

mportant to have a stable task manager and Assistant Task Manager to over if the

lead is not around.

The Bank

Page 16: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

15

3. Procurement

delays

The project experienced delays in the procurement process. This is due to the fact

that after all procurements were cleared and a major contract was terminated, the

Project didn’t have a procurement expert anymore.

This led to additional delays in the retendering af the main work contract.It is

important for the upcoming operations to have a procurement expert for the life span

of the Project.

TheBank,

DWR

4. Works

Construction

delays

Various issues affected the water supply works construction such as contract

termination resulting in increased bid prices for the new contract and additional

funding required. The project was also affected by the 2016 Senegal Gambia border

closure.

The GoTG

5. Insufficient

Contingency

Funding

The Project financing plan was not properly costed since it considered the

Government contribution ( 260.000 UA) in monetary terms and not in kind as such

major error was made in the calculation of the contingency. In the costing of future

projects thus it is important to consider both the physical and price contingencies

and also to secure Government contribution.

The Bank,

MoFEA

D Sustainability

1. Financial sustainability

Rating* Narrative assessment (indicative max length: 250 words)

4 Financial sustainability has been enhanced by: (i) track record of maintenance of other government provided

insfrastructure; (ii) ability of project communities to deposit a sum of GMD 25,000.00 (equivalent USD$853)

before the start of drilling towards a maintenance fund which was a criteria for selection and is fulfilled in all the

communities. There are few communities that did even better with GMD150,000.00 (equivalent USD$7,200) in

their bank account.

2. Institutional sustainability and strengthening of capacities

Rating* Narrative assessment (indicative max length: 250 words)

3 The formation of a Project Management Team (PMT) under the the Ministry of Fisheries, Water resources and

National Assembly Matters and the deparment of Water Resources as the executing agenecy. The executing,

implementing partners and PMT has contributed immensely in resolving the challenges to project

implementation.

Institutional sustainability of the project has been reinforced through a combination of the following factors:

a) Ownership by the Borrower and Sanitation sub-sector through broad stakeholder consultation during

project design.

b) Adequate institutional capacity building for management and operation of the sewerage system vis-à-

vis institutional continual training and provision of renewing operational equipment and software

development.

The Government has approved reform of the sector during the course of project implementation. Legislative

instruments were introduced and passed to parliament for enactment for the introduction of Water Authority

and Meteological agency. However these reforms have still not been implemented.

Page 17: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

16

3. Ownership and sustainability of partnerships

Rating* Narrative assessment (indicative max length: 250 words)

4 Ownership and sustainability of partnerships vis a vis institutional arrangements were considered adequate.

During implementation of the project a number of stakeholders were indirectly involved in the project, a Project

Steering Committee (PSC) was established which comprised senior officials from MOFWRNAMs, MOFEA,

DCD, NEA, DWR, Womens Bureau and TANGO. The Committee was chaired by the Permanent Secretary

MOFWRNAMs. The role of the Committee was advisory and provided policy and general managerial guidance

during project execution. The Committee sat every quarter during the start-up period and thereafter at least twice

in a year to review implementation plans, budgetary provisions, project progress and any implementation

difficulties in order to offer advice and suggestions to enhance smooth implementation of the project. Ownership

and sustainability of partnerships Ownership were considered satisfactorily.

To many ordinary inhabitants, the project is a real game changer in their individual economic endeavours. The

project has therefore engendered a strong sense of ownership amongst all beneficiaries to ensure the continuous

maintenance and management of project outputs.

4. Environmental and social sustainability

Rating* Narrative assessment (indicative max length: 250 words)

3 By its nature the Project was classified under category 2 of ESAP. Project facilities are located on multiple sites

throughout the Gambia none of which are in protected or sensitive areas.

At completion this was confirmed and the project was not found to have had any detrimental effects and any impact

including permanent ones like the installation of water tank infrastructures were mitigated through the

implementation of the Environmental and Social Management Plan (ESMP). The Gambian National Environnment

Agency ((NEA) monitored the e project implementation on the basis of the ESMP.

5. Lessons learned related to sustainability

Key issues (max 5, add rows as

needed)

Lessons learned Target

audience

1. Provision for Counterpart

Funding from the

Government

Lack adequate counter part funding on the part of Government resulting in

budgetary constraints on the Project. The GoTG should in future operations

prosper measures are taken to address this issue.There was a confusin from

Appraisal as to whether this contribution was an inkind contribution or not

MoFEA/DW

R/The Bank

2. Comminities ability to

mobilize maintenance

It was really refreshingto see communities willingness to deposit into the

und DWR should mainstream this practice and assess the use of these

maintenance fund across the country

DWR

3. Adequate Maintenance Three main elements influence the sustainability of network namely: i)

quality of works delivered; ii) the manner of usage; and iii) the level/quality

of maintenance. To ensure quality standards during construction, works

supervision and monitoring was undertaken by reputable consulting

engineering firm with experience in similar projects. The maintenance of

the 22 multivillage water systems as well as the 51 institutional should stay

the responsibility DWR while DCD should review of the quality of

Hosehold latrines built within the different communities during the course

of this Project.

DWR

Page 18: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

17

III Performance of stakeholders

1. Bank performance

Rating

*

Narrative assessment by the Borrower on the Bank’s performance, as well as any other aspects of the project

(both quantitative and qualitative). See guidance note on issues to cover.(indicative max length: 250 words)

The Bank performed satisfactorily in overall project implementation. In specific terms, there were no

significant deficiencies in the following areas of operation;

i) The Bank performed satisfactorily by preventing and resolving project’s issues;

ii)The Bank in most cases was quick in their responses and approvals to correspondences.

iii) The Bank however has been late in effecting prompt payment , mostly due to the budget constraint

described above and during the readvertisement and re-tendering of the main water supply works infrastructure

which took a period of nine months before contract signature.

iv) The Bank performed creditably by organizing procurement, fiduciary and disbursement workshops and

seminars for borrower staff and also as per individual coaching whenever issues arose.

Key issues (related to Bank performance, max 5, add rows

as needed) Lessons learned

1. Procurement and Disbursement Issues – Bank providing

guidance to the executing agencies

Issues relating to procurement and disbursement arise

primarily due to a deficit in knowledge on part of the

implementation agencies on the Bank’s procurement rules.

Although in the past some training has been conducted for

PMU members, a continuation/intermittent repeat of the

training is recommended.

Generally satisfactory except that there were 4 and 5 IPCs

for Lot1 and Lot 2 respectivelydelayed for between 1 to 3

months beyond the 56 day period allowed under the

contracts.

2. One –Bank Approach Bank staff from various departments based in the Senegal

Country Office and HQ worked in as a team to prepare,

appraise, supervise to deliver a successful project

highlighting the implementation of the one-bank concept.

4 Project supervision by the Bank Supervision was continuous, hands on and within the

prescribed “twice in a year” due to expert staff being at the

field office. This allowed continual assessment of progress,

interaction with stackeholders and timely and realistic

technical solutions in resolving issues that could possibly

lead to delays or hinder the success of the project. Most of

the donor partners in the WATSAN sector faced similar

issues that confronted this project.

5. Submission of Progress Report Throughout the life span of the project there has been timely

submission of all project reports.

Page 19: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

18

2 Borrower performance

Rating* Narrative assessment on the Borrower performance to be inserted by the Bank (both quantitative and

qualitative, depending on available information). See guidance note.(indicative max length: 250 words)

3 The RWSSP was approved by the Boards of Director in June 2012 but entered into force 8 months after approval

in March 2013. Conditions of First Disbursement were met in August 2013 which is 14 months after boards

approval. In addition to these initial start up delays, in 2016 the main contractor the errection of the 22

multivillage water supply system was terminated at the request of the contractor. The retendering process was

greatly affected by the absence of a procurement expert then and led to additional delay of more than a year.

Key issues (related to Borrower performance, max 5, add

rows as needed) Lessons learned

1 Effectiveness of the PMU The setting up of the existing PMU within the Directorate of

Water Resources allowed the smooth implementation of the

project

2 Involvement of stakeholders All the Project Stakeholders were represented within the

Project Steering Committee (PSC)

There were thorough and extensive consultations held with

project stakeholders and the communities to clearly capture

their needs particularly in the design of the community

Water Supply Systems and these created a sense of

ownership for all and at the slightest opportunity community

dwellers expressed their gratitude for the project addressing

their needs.This led to even more keenness when it was time

to prepare andappraised thesend Water Supply Project in the

Gambia.

3. Delays in in the retendering of the main work contract

and Budget Issue

After the completion of all initial procurement the project did

not have a procurement officer in the team anymore . This is

when the main work contract related to the errection of 22

multivillage water supply was terminated and had to be

retendered. That retendering process caused additional

delays and a id in excess of the available budget qwhich was

partially solved by the approval of additional RWSSI

resources. However the non availability of the Government

contribution meant that the Project dragged ythis budget

issue to the close of the Project.

Page 20: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

19

3 Performance of other stakeholders

Rating* Narrative assessment on the performance of other stakeholders, including co-financiers, contractors

and service providers. See guidance note on issues to cover.(indicative max length: 250 words)

3 The other stakeholders of this project are contractors,suppliers,consultancy firms.This project did not have any

cofinancier.

ADF and RWSSSI resources covered all completed project activities. Resources from the Governement of The

Gambia were not made available.Most activities were paid by Direct Payment from the Bank which turned out

to be advantageous to Project implementation.

The contractors’executed their duties satisfactorily with the exception of SAM/BRONCHO jointventure and

MANTEX.

SAM/BRONCHO was initially hired to construct 22 multivillage water supply Systems. It contract terminated

at SAM’s request because its partener was being liquidated. This led to the retendering and the contract waslater

awarded to SINCO Spa with a bid price above the Budget. SINCO spa, however performed satisfactorily.

MANTEX was hired by the project to supply materials to communities for the building of household latrines.Its

contract was terminated by the PMT for failure to fulfil its contractual duty. MMANTEX was replaced by

Marong Fabrication which performed satisfactorily 18 beneficiaries could not complete their lqatrines for

reasons unrelated to the supplier.

.The consultants also discharged their assignments satisfactorily.

During the supervision, the main work Consultant displayed appreciable knowledge of the project objectives

and strategies to achieve them. he consultant ensured approvals were sought on any major changes in design,

time and management of the project. Supervision of contractors were effectively done and issues arising out of

the project were promptly brought to the attention of all stakeholders. Progress reporting was on schedule.

Reports were submitted to the Bank in good time.The Contractors, to a large measure, also co-operated with

the Consultant and other stakeholders of the project to ensure speedy progress of work.

Key issues (related to

performance of other

stakeholders, max 5, add rows

as needed)

Lessons learned (max 5) Target audience (for

lessons learned)

1.A good coordination between

the different stakeholders

Coordination between stakeholders was very good throughout

project implementation. Although there were some difficulties

for the OMU and DCD to co-supervise the construction of the

Household latrines in somme communities

DWR/DCD/Contract

orsOther

Stakeholders

2. . Baseline Data

It has been very difficult for the Project to obtain baseline Data

in some communities. GBOS ansd DWR should work on

national and regional sectoral indicators for future operations

DWR/ADB/GBOS

Page 21: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

20

IV Summary of key lessons learned and recommendations

1. Key lessons learned

Key issues (max 5, add rows as

needed) Key lessons learned Target audience

Use of Solar pumped System.

And unreliability of electricity

supply

The choice of the solar powered pumping system for

the supply of water was driven by the country’s

experiences in the use of this technology, the

availability of spare part, user acceptability, the cost

of the solution and operation and maintenance

practices, and finally the unreliability of electricity

supply across the country. The same approach should

be kept for the Climate Smart WASH development

Project.

DWR,Bank

Participatory approach to project

design

The project was designed through extensive

consultations with all the stakeholders. Those

consulted included policy makers in government

agencies, health and local government officials,

beneficiay community groups, village water

committees and NGOs, the consultative process was

important to get stakeholder feedback about the

project and also incorporate views in the design. At

appraisal, the mission undertook field vist to validate

the data and information provided at the central level,

and to assess the level of involvement of the potential

beneficiaries. It was then noted and confirmed by the

communities, that the selection of sites was conducted

in a participatory manner involving all stakeholders,

guided by very clear selection criteria developed by

the government.

This approach was successful and was also used

during the implementation of the Climate Smart

WASH Development Project.

DWR

Focus on the Community Led

Total Sanitation Approach.

The used of CLTS approached for the construction of

Householsd Latrines led to a healthy increase of

demand in some communities. However in other

communities especially in the West Coast Region it

led to delays due to the unavailability of train masons

and lack of commitment of somme beneficiaries also

the choice of a single supplier for construction

materials of the House Hold Latrines led to additional

delays. Despite the high rate of implementation (above

95% ) of this component it is important to assess the

CLTS approach for new operations..

COTG,Bank

Start-up delays The project experienced delays in the recruitment of

key staff , however use of an existing PMU within the

EA was a a major asset to get key milestones in place,

such as effectiveness and Project launching, Where

possible,.in future the team should be put in place

before the appraisal mission it will allow members of

the project team to participate in the appraisal mission

for better understanding.

The Bank, DWR

Page 22: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

21

Procurement delays The project experienced delays in the procurement

process. This is due to the fact that after all

procurements were cleared and a major contract was

terminated, the Project didn’t have a procurement

expert anymore.

This led to additional delays in the retendering af the

main work contract.It is important for the upcoming

operations to have a procurement expert for the life

span of the Project.

TheBank, DWR

Payment delays

The poject experienced delays in the paymentt

process.This is in part due to the fact that the project

had 4 Task managers during its lifespan that caused

some delays because each task manager takes a while

to understand the project issues. It is mportant to have

a stable task manager and Assistant Task Manager to

cover when the lead is not around.

The Bank

Insufficient Contingency

Funding and lack of Government

Contribution

The Project financing plan was not properly costed

since it considered the Government contribution (

260.000 UA) in monetary terms and not in kind as

such major error was made in the calculation of the

contingency. In the costing of future projects thus it is

important to consider both the physical and price

contingencies and also to secure Government

contribution.

The GoTG should infuture operations secure its

counterpart funding or request for a waiver when

appropriate.

The Bank, MoFEA

2. Key recommendations (with particular emphasis on ensuring sustainability of project benefits)

Key issue (max 10, add rows as needed) Key recommendation Responsible Deadline

The multi village water Supply Systems ae

now managed by the DWR and the

communities the nbiggest threat to the

sustainability of these systems are related to

their proper maintenance and the replacement

of the solar panel when efficiency decreases.

While it was really refreshing to see

communities willingness to deposit into

the fund, DWR should mainstream this

practice, assess the use of these

maintenance fund across the country and

continue to provide technical assistance to

the communities when needed.

DWR

The use of CLTS approache induced

additional demand and was largely

completed(98.8% completion rate.However,

the biggest threat is the ability for

communities to maintain their latrines and

also the risk that the new acquired hygiene

practices are not sustained overtime. Another

threat to the CLTS approach is the migration

of trained masons to urban areas

It is crucial DWR and CD continue

sensitizing communities good hygiene

practices and train new artisans that can

assist those who will be inticed toward

building their own HHL

As regards Institutional latrines some of them

is not being well managed and in somme

communities users are not used to pay for

sanitation

DWR should continue sensitizing users in

rural Gambia. Communities should also

agree on a minimum fee per user these

fees will be used to ensure public toilets

are maintained.

Page 23: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

22

V Overall PCR rating

Dimensions and criteria Rating*

DIMENSION A: RELEVANCE 4

Relevance of project development objective (II.A.1) 4

Relevance of project design (II.A.2) 4

DIMENSION B: EFFECTIVENESS 4

Development Objective (DO) (II.B.4) 4

DIMENSION C: EFFICIENCY 2.75

Timeliness (II.C.1) 2

Resource use efficiency (II.C.2) 3

Cost-benefit analysis (II.C.3) 3

Implementation Progress (IP) (II.C.4) 3

DIMENSION D: SUSTAINABILITY 3.75

Financial sustainability (II.D.1) 4

Institutional sustainability and strengthening of capacities (II.D.2) 3

Ownership and sustainability of partnerships (II.D.3) 4

Environmental and social sustainability (II.D.4) 4

OVERALL PROJECT COMPLETION RATING 3.63

Page 24: THE GAMBIA RURAL WATER SUPPLY AND SANITATION …...communities can be left as such. DWR,Bank NAWEC, and Communities 2. Participatory approach to project design The project was designed

23

VI Acronyms and abbreviations

Acronym (add rows as

needed)

Full name

ADF African Development Fund

AFDB African Development Bank Group

AWF African Water Facility

CLTS Community Led Total Sanitation

CSP Country Strategy Paper

DCD Departement of Community Development

DWR Deppartement of Water Resources

EA Executive Agency

EIRR Economic Internal Rate of Return

GBOS Gambian Bureau of Statistics

GOTG Governement of The Gambia

JSR Joint Sector Review

MOFEA Minstry of Finance and Economic Affairs

MOFWRNAM Ministry of Fisheries , Water Resources and National Assembly Matters

M&E Monitoring and Evaluation

NAWEC National Water and Electricity Company

NPV Net Present Value

NSC National Steering Comittee

PAGE Program of accelerated Growth and Employement

RWSSP Rural Water Supply and Sanitation Project

RWSSSI-TF Rural water Supply and Sanitation Initiative Trust Fund

UA Unity of Account

US$ United Stestes Dollars

VDC Village Development Committee

VWC Vilage Water Committee