the croatian experience in the use of the interactive...
TRANSCRIPT
10 May 200510 May 2005 11IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005
The Croatian experienceThe Croatian experience ininthe use of the interactive the use of the interactive
design methoddesign method
Antun SzavitsAntun Szavits--NossanNossanMeho Saša KovačevićMeho Saša KovačevićUniversity of Zagreb, CroatiaUniversity of Zagreb, Croatia
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 22
ContentContent
• Incentives• Monitoring instruments• Five case histories• New developments• Final remark
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 33
IncentiveIncentives s The Croatian motorway project
• Large infrastructure projects
• Ground conditionsthat defy standard design methods (soft,fissured, jointed and heterogeneousrocks/soils)
• Risk management
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 44
Monitoring instrumentsMonitoring instruments
• Surveying• Borehole
measurements:– Inclinometers– Sliding micrometers– Piezometers
• Anchor load cells• Total pressure cells• Clinometers, etc.
Sliding micrometer,Solexperts, Switzerland
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 55
Case history Case history II –– St Mark’s tunnelSt Mark’s tunnel
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 66
St Mark’s tunnel St Mark’s tunnel (2)(2)• Tunnel:
– < 22 m overburden, length 264 m, two tubes
• Geology:– from 0 m – 20 m: layers of mixed
clay, sand, silt and sandstone lumps
– > 20 m: dolomites, irregularly disintegrated
• Requirements:– limit surface settlements
(preservation of cemetery)• Design:
– Pipe roof, short excavation segments, immediate closure of the support ring, reinforced shotcrete, self-boring anchors
+8.00
+2.80
±0.00
-0.20-1.95
Invert
+2.50
Kalota
Face protection core
Face protectionShotcrete 10cm(+1 renforcement mesh Q188 if required)
Elephant foot if required
IBO anchors l=6m4980
16000
9530
30
30
30 30
CROSS-SECTION B-B
A
A
Detail 2
12.0012.00
7.18
Face protectionShotcrete 10cm(+1 reinforcement mesh Q188 if required)
7
531
642
LONGITUDINAL SECTION A-A
Shotcrete C25, 30cm+two reinforcement meshes Q283
Detail 1Protective pipe dia.114.3mm, l=15m
8.00
Steel lattice girder PS 95/20/30
15
3.91°
±0.00
-1.95
-0.20
+2.50
+8.00
B
B
Pipe roof100°-114°
Shotcrete C25, 30cm,two reinforcement meshes Q283,steel lattice girder PS 95/20/30
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 77
St Mark’s tunnelSt Mark’s tunnel (3)(3)Inclinometer and sliding deformeter layout
settlement 1 cm 0 4-4 8-8mm0
depth (m)
1 2 3 4 5 6 7
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 88
St Mark’s tunnelSt Mark’s tunnel (4)(4)
• Observational method:– establishing acceptable limits of behaviour
(acceptable surface settlements)– initial design– monitoring surface settlements and strains
along boreholes; pressure cells; measuring anchors
– applying contingency actions (adjusted excavation method; added additional rock bolts)
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 99
Case history Case history IIII:: ZagradZagrad excavationexcavation
• Excavation– Vertical cut 14 m – 20 m
deep– Adjacent 5 storey old
brick apartment house • Geology
– Flysh deposits overlain by 5 m of irregular fill
• Design– Staged excavation, RC
box girder, rock bolts
POMERIO ST. No.19INCLINOMETER -VERTICAL
30
0L=16.0 m
50Horizontal distance (m)
1510 2520
L=12.0 m
Ele
vatio
n (m
)
15 Horizontal deformeterL=16.0 m
5
10
L=16.0 m20
25
DEFORMETER
POMERIO ST.
3530
SELF-DRILLING ROCKBOLTS
SELF-DRILLING ROCKBOLTS SELF-DRILLING ROCKBOLTS
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1010
ZagradZagrad excavation (2)excavation (2)• Observational
method:– Initial design → limits
of behaviour (strain distribution, anchor loads)
– Monitoring: inclinometer, slidingdeformeter, load cells on anchors; benchmark survey
– Contingency actions: anchor prestressing, additional anchors
0
1
1
2
2
3
3
4
0510152025distance from excavation face (m)
disp
lace
men
t (m
m)
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1111
Case history Case history IIIIII:: KauflandKaufland excavationexcavation
• Excavation: 17 m deep, adjacent 8 storey apartment building
• Geology: jointed and layered limestone partially degraded
• Design: staged excavation, reinforcedshotcrete, rock bolts 0
68
74
70
72
76
80
78
82
84
86
90
88
92
V - vertical inclinometer - deformeter L=18.00 mH - horizontal deformeter L=15.00 m
SELF-DRILLING ROCKBOLTSL=6.00 m
+75.30 terrace level
+73.30 foundation level
10 20 30
H
V
40
SELF-DRILLING ROCKBOLTS
SELF-DRILLING ROCKBOLTS
L=12.00 m
L=9.00 m
+84.50
CRNCIC ST.
Slope linebefore excavation
BUILDING
Horizontal distance (m)
Ele
vatio
n (m
)
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1212
KauflandKaufland excavation (2)excavation (2)
• Observational method:– Initial design– Monitoring: inclinometer,
horizontal slidingdeformeter
– Contingency actions due to non stabilizing deformations above the excavation section:
• shortening of excavation section
• additional layer ofshotcrete
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1313
Case history IV:Case history IV: LenacLenac excavationexcavation
• Excavation– 35 m to 55 m deep
• Geology– Weathered limestone,
breccia, flysh• Design
– Staged excavation,multilayered reinforcedshotcrete, rock bolts
Horizontal deformeterL=15.00 m
DEFORMETER L=40.0 m
25 20 10 5 040 35 30Horizontal distance (m)
Elev
atio
n (m
)
SELF-DRILLING
L=12.00 m
ROCKBOLTSL=9.00 m
ROCKBOLTSL=6.00 m
3540
3025
01 0
205
45
ROCKBOLTS
VERTICAL INCLINOMETER -
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1414
LenacLenac excavation (2)excavation (2)
• Observational method:– Initial design → limits of
behaviour (strain distribution, anchor loads)
– Monitoring: inclinometer, sliding deformeter
– Contingency actions:prestressed anchor, additional anchors, shortening of excavation sections
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1515
Case history V: WTC excavationCase history V: WTC excavation
• Excavation– 15 m deep
• Geology– Weathered limestone,
breccia, flysh• Design
– Staged excavation, reinforced shotcrete, rock bolts, prestressedanchors
45
3735
4139
43
47
5149
5553
0 10 20 30
V
H
V - vertical inclinometer - deformeter L=16.00 mH - horizontal deformeter L=15.00 m
ROCKBOLTSL=9.00 m
ROCKBOLTSL=6.00 m
ROCKBOLTSL=5.00 m
Elev
atio
n (m
)
Horizontal distance (m)
SELF-DRILLING
SELF-DRILLING
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1616
WTC excavation (2)WTC excavation (2)• Observational method:
– Initial design → limits of behaviour (strain distribution, displacements)
– Monitoring: inclinometer, sliding deformeter
– Contingency actions: additional shotcretelayer, additional anchors
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1717
New developmentsNew developments
• Initial research in acoustic emission as a means to detect rock bolt overstressing
0.00
20.00
40.00
60.00
80.00
100.00
120.00
0 20000 40000 60000 80000 100000 120000 140000
Number of counts/tensile force (n/kN)
Tens
ilefo
rce
(kN
)
1
4
7
10
13
16
19
22
25
28
31
34
37
40
43
46
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1818
Final remark on the initial design Final remark on the initial design for the observational methodfor the observational method
• Peck, R. B. (1969): Establish design based on a working hypothesis of behaviour anticipated under the most probable conditions(p = 0.5);
• Powderham, A. J. (1994): A moderately conservative initial design based on more probable conditions (p > 0.5);
• Muir Wood, A. (2000): A conservative initial design for tunnels based on a simplified economical analysis (usually p > 0.5) .
1 2 3Relative cost of contingency actions, k
0.0
0.5
1.0
Opt
imal
pro
babi
lity
for i
nitia
l des
ign,
p
Peck (1969)
Muir Wood (2000)
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 1919
ReferencesReferences
Muir Wood, A. (2000). Tunnelling: Management by design. E & FN Spon, London.
Peck, R. B. (1969). Advantages and limitations of the Observational Method in applied soil mechanics. Géotechnique, 44 (4), 619-636.
Powderham, A. J. (1994). An overview of the observational method: development in cut and cover bored tunnelling projects. Géotechnique,19(2),171-187.
10 May 200510 May 2005 IREX Symposium: The interactive design mnethod, Paris, 2005IREX Symposium: The interactive design mnethod, Paris, 2005 2020
Thank you for your attention