temporary flood resilient phaydemand shauchalay (ecosan) khagaria, 2016
TRANSCRIPT
Temporary flood resilient phaydemand shauchalay (ECO-san) @ Chaidha, a recent flood
affected village in Khagaria, Bihar
ByThe Sanitation Squad
(Residents of Chaidha, Khagaria; Thumbimpression Collaborative, Ahmedabad; National Centre for Peoples Action in Disaster Preparedness, Ahmedabad; People in Centre, Ahmedabad; Arghyam, Bengaluru; Samta, Khagaria and Megh Pyne Abhiyan, Delhi)
September 2016
Status of Chaidha between August 26 - September 05, 2016
Assessment and consultation was held before initiating work on the flood resilient and temporary
phaydemand shauchalay (Day 1)
Process – Procurement of raw materials (Day 2)
Bamboo/ Baas
Local Thread/ Fitta Oil Tin Split Bamboo
Water Drum
Process – Identifying human resources (skilled and unskilled)
Pits for erection of Bamboo column
Artisans working on Eco- san
Day 2…
Process (Day 2)
Digging pits
Sharpening the bamboo
Bamboo Joinery
Process (Day 2)
Wrapping the bamboo with plastic sheet before pitching it in the ground
Sharpening the bamboo
Bamboo Joinery
One of the bamboo columns being pitched
Process (Day 2)
Making Bamboo Pins
Making of Joinery Bamboo Joinery
Process
Erecting Bamboo Columns Making of Bamboo Frame
At the end of day 2…
Process - Making of compost drum (Day 3)
Compost Drum
Process - Making of compost drum (Day 3)
Process (Day 3)
Process
Using Split Bamboo as Flooring material
Installing drum for compost and fixing flooring
At the end of day 3…
Process (Day 4)
Installing Bamboo ladder
Installing Bamboo roof
Process (Day 4)
Cross Bracing the structureCovering the roof
At the end of day 4…
Process (Day 5)
Compost pit installed under split bamboo floor to collect excreta, urine and back wash water separately
Process (Day 5)
Bamboo floor
By the end of day 5
Temporary and flood resilient phaydemand shaucahaly aka ECO-san
Costing…
Item Quantity Rate CostingBamboo 20 pieces Rs 170/piece 3400
Lashing - Fitta 2 kg Rs 180/kg 360Plastic drum 2 Rs 300/piece 600Tin container 3 Rs 20/piece 60Thin plastic 10 pieces Rs 20/piece 200Syl-polene 459 sq feet 400Plastic bag 6 bags Rs 25/bag 150
Sand 3 bags Rs 60/bag 180Brick bats 25 pieces Rs 7/piece 175
Dabiya mistri (Bamboo worker) 6 human days Rs 350/day 2100
Labourer(Unskilled) 3 human days Rs 300/day 900
TOTAL 8525
The beginning…(As of September 10, 2016 @ 1822 hrs)