technical paper-sam.doc -final 1
TRANSCRIPT
TECHNICAL PAPER
CONTRACTS ADMINSTRATION ON LUMP SUM CONTRACT IN EPC CONSTRUCTION FIELD
(PROJECTS)
Page # 1 of 13
I N D E X
Introduction………………………………………………….. …………..Page 3
About my Technical Paper………………………………………………..Page 4
Roles and Responsibilities of Contracts Administrator (Projects)………..Page 5
About my Project………………………………………………………….Page 6
Contract Plan……………………………………………………………....Page 7
Reference Contractual Documents………………………………………..Page 7
Variations and Claim……………………………………………………...Page 8
Schedule Delay……………………………………………………………Page 11
Progress Measurement and paymensystem………………………………Page 12
Conclusion………………………………………………………………..Page 13
Page # 2 of 13
INTRODUCTIONThe construction field is a very extensive and unique in each project. In this world nearly
80% of projects are managed by contracts. To manage the projects effectively, the
projects are executed under contracts. In this instant you may ask what is the meaning
of contract?. The Contract is simply an agreement between two or more personal and
/organization which is enforceable at Law. This is an agreement, whereby one party
agrees to perform work or services for the other party within the contractual agreement.
To manage the contracts ,organizations have their own department to manage the various
contracts effectively. The department will play the major role on execution of any kind
of projects from initiation to closure. The main functionality of Contracts Management
department is to initiate the contracts, Planning, Exection, Control and closure upon
satisfactory completion of projects. As you know the phase will interact each other or in
some projects all the phases will not exist due to the nature of projects. The projects may
be subdivided into many phases in accordance with the nature of project and each phase
will be managed through the contracts department throughout the project cycle . There
are several types of contracts which will be applied to the projects based on the inherent
in nature of Statement of Works ( SOW). It is very useful in the construction industry,
especially in Engineering ,procurement and construction (EPC)project ;since these
projects will have many phases each will be managed thro sub contractor while it
requires to have a very close monitoring in scope verification and control. Meanwhile, it
creates a record system that will be useful as templates to other upcoming projects in the
same organization for similar projects .This will help the organization to eliminate the
Inaccuracies which had occurred in the previous projects. Contracts administration
ensures that both parties meet their contractual obligation and protect the legal rights
Page # 3 of 13
ABOUT MY TECHNICAL PAPER
I am qualified degree holder in Engineering with the elective subject in contracts
management. I have been working with various companies as Contract Administrator the
last 17 years. I have selected to submit my Technical Paper on Contract Management
and I hope the input shall justify my selection.
Presently I am working with EPC Contractor M/s. SNC Lavalin International Inc., as
Contracts Administrator for their BeAAT Project (Central Environment Protection
Facilities) our Company is one of the third largest EPC CONTRACTOR in the world in
the field of Oil and Gas, Power and Aluminum smelters. The organization has a system to
manage the different contracts regardless of type of projects. The objective is to achieve
the project completion within the budget and time schedule. In my projects, we are highly
involved in all the areas such as initiation to project closure due to the nature of
projects .The project has been subdivided into many phases to manage and control
effectively. I have experienced in this project the effectiveness of the contract
management in fulfilling the obligation of Main contractor and sub contractor
successfully. As we are aware that, EPC contracts will have several changes on project
life cycle. Due to the nature of project, we have stumble upon changes in design which
creates the several impacts in scope and schedule. In this instant, I would like to brief
how we managed the Lump sum contract in EPC construction in this particular project
especially handling variations ,claim and payment systems.
Page # 4 of 13
ROLES AND RESPONSIBILTIES OF CONTRACTS ADMINISTRATOR
(PROJECTS)
Formulate contract plan
Contractor Pre qualification
Prepare Tenderers lists
Prepare tender Packages
Receive tenders
Prepare Evaluation and recommendation
Award contracts
Execute contracts
Process progress payments
Negotiate and issue contract change notices and amendments to contacts
Evaluate and negotiate claims from the contractors
Maintain contract files
Close –out all contracts and
Maintain performance records
Page # 5 of 13
ABOUT MY PROJECT:
The project had been initiated by the UN environmental department to facilitate the
treatment of waste generated from the oil sectors to protect the environment. This is a
UNIQUE project in the world which contains all the treatment facilities are
interconnected to neutralizing the contaminated waste. The client has awarded the Lump
Sum EPC Contract (Engineering, Procurement and Construction) to my company. The
EPC contract is most valuable for the complex design and procurement and where the
buyer desires to contract with a single party. In this scenario, I would like to brief about
my project and what are the major complex units are designed and under
procurement/construction which are as follows;
Incinerator
Solidification
Thermal descorption
Centrifugation
Chemical treatment
Mercury distillation
Tank farms
Landfills
To manage the Lump sum EPC contract effectively, we have considered the following
phases and each phase had been awarded as sub contract.
Site preparation ,earthwork and civil works
Mechanical and piping works
Electrical and instrumentation
Land Fills
Page # 6 of 13
CONTRACT PLAN:
Since we decided the phases and execute the project by sub contracting, we are now in
the process to select that type of contract for different packages. The contract selection is
basically affected by how extensive we have the project Scope of work (SOW). Since the
customer had transferred the risk to EPC contractor vide Lump sum Contract, we also
determined to manage the phases through the Lump sum contract for better execution,
monitoring and control.
REFERENCE CONTRACTUAL DOCUMENTS:
As an EPC contractor and decided to execute the contract through sub contracts, we have
prepared the set of contractual documents which will make a legal agreement between the
parties to fulfill the obligation that has been given to sub contractors thro Request for Bid.
Since, my paper is based on contracts administration for the particular project, I would
like to highlight what are contractual documents which we are referring to manage the
Lump sum contract .The documents are listed as per the order of precedence. Incase of
any discrepancies in any of the documents which is not resolved between the parties, the
documents shall be referred as in order to solve the issues
SIGNATURE AGREEMENT
ARTICLE OF AGREEMENT
PARTICULAR SPECIFICATION
SCOPE OF WORK
BILL OF QUANITIES
Upon review of contract awarded and evaluations of various requirements as per section,
due to changes during execution in the areas as listed below could occur which leads to
variation, claim and schedule delays that are affecting the cost and completion date of the
Page # 7 of 13
project. I wish to elaborate all functions in the variation, claim and schedule delay areas
in detail.
VARIATIONS AND CLAIM:
Eventhough, the design criteria is well defined, EPC contracts allows client changes or
variation during the project life cycle. In principle this is not a problem, rather the
problem rises when there is a question who is responsible for the cost and time impact
associated with change. For illustration, a change in process may have little cost and time
impact if it is made during the basic design. But if any changes occur during the
construction, the impact shall be significant.
In this project life cycle the changes occurred in both the phases of design and
construction. Since the design changes pertinent to client and Prime EPC contractor , I
would like to share how we have managed the critical changes in Scope of work occurred
while construction in progress.
In my project, I have managed the changes through design change authorization (DCA)
and contract trend notice (CTN). Since we are discussing the subject between the EPC
contractor and sub contractor perspective the DCA procedure is not applicable, because
we are designing and instruct the sub contractor to construct as per drawings and
applicable specifications. How ever, I would like to brief about DCA. While we are in
detail design or construction if we decided to change the specification or equipment
which should be addressed to customers through DCA that shall contain the reasons why
to have the specific change to process or any form and shall mention that this will have
an impact in schedule and /or cost with all relevant back ups to review and comments. If
there is any impact in cost or schedule, the EPC contractor shall be advised accordingly
Page # 8 of 13
to submit the CTN .The DCA shall be applicable if there is no potential change in cost
and schedule.
Only those potential changes that falls outside the Contract and could be construed to
impact cost, quality and /or schedule should be considered for a Contract Trend
notice(CTN) .CTN should accompany with the detailed supporting documentation such
as reference letters, vendor confirmation and cost and time estimation. All CTN’s are
documented & monitored for its status.
According to contract, both the parties can able to initiate the changes when and
wherever require to fulfill the requirement of customers. In EPC contracts, the EPC
contractor is designing the project and or phases and will be issuing to sub contractor to
execute in accordance to the applicable specification and issued for construction
drawings. After receiving the drawings, sub contracts may verify with the scope of work
which is stipulated in contract and if find that any changes, the contractor will be
notifying the EPC contractor accordingly. On the other hand, EPC contractor itself will
generate the changes which occurred in my project most of the project life cycle.
The changes are formulized vide formal letters stating the items to be considered while
contraction that shall be implemented unilaterally since my contractual clause states
that” Not withstanding any dispute and or any changes either in drawing or
specification ,upon request contractor shall be perform the same without affecting the
progress”.
In this project, we have set sub clause in Article of Agreement stating that how to process
the variations and implement the same. To conclude the lump sum price of the changes
either positive or negative variation to Scope of Work, the sub contactors were instructed
Page # 9 of 13
to include the various unit rates in the form of appendix to BOQ which will be utilizing
to compute the Lump sum value of the requested changes.
Now, the changes have occurred and the contractor is advised to execute the changes in
accordance with contract. The contractor has informed the EPC contractor that due to
these changes there will be cost and time impact in the contract. Subsequently, contractor
has been advised to submit the back ups for the variations so that the request will be
evaluated and revert to contractor all in terms and conditions of contract. Upon receipt of
the requested documents, EPC contractor will be reviewing the request with the Scope of
Work and if requires, will be organizing a meeting to discuss the varies items incurred in
the changes, and accordingly the contractor to be informed either the requested changes
are within the contract or not.
If the changes are legitimate and not in scope of work, the contractor will be advised to
proceed further and subsequently the cost and time impact shall be estimated. In case the
stipulated unit rates are not covered the items involved in the changes, new rate will be
established and agreed to utilize to compute the lump sum price.
When the cost is finalized, contractor will be informed that the changes are approved and
advise them to proceed to implement the changes. Consequently to include the approved
changes, the amendment to contract will be issued and that to be signed by both the
parties and thereafter the approved changes are becoming the integral part of scope of
work. We were maintaining the register to track the approved and unapproved variations
in which we can able to monitor the scope changes and what impact we had due to this.
Besides, we have come across several variations are not mutually agreed due to inherent
nature of variations. Those are called claim against the contract. The disputed claims will
be resolved amicably with terms and conditions of contract. If not the claim shall be
Page # 10 of 13
reference to third party, that is called arbitration. In this, common personals those who
are not connected to either parties will be reviewing the request from both the parties as
the international law and given the verdict to abide on. If the verdict is not fulfilling any
one party, then that party can refer to court and the settlement will be as per the court
decision which is firm and final.
SCHEDULE DELAY:
Construction contracts frequently require schedule or program for tracking the progress
and delay. To determine the delay, the submitted Base line schedule can be monitored
and updated regularly to find the schedule variations. We have used the Primavera for
tracking the same. In deed, any party claiming against the time should demonstrate that
the other party actually delayed work on the CRITICAL PATH of the project. As you
know, if any changes and /or delay occurred on critical activities, this will affect the
project duration which will have an impact.
In my project, the schedule had a high impact since the changes occurred in detailed
design and also in construction phase. For example, for incinerator facility, we have
signed the contract with vendor to design and supply the kiln with in the agreed duration.
During the design phase, the vendor advised that the requirement which had been given
to consider for detail design is not sufficient to fulfill the project requirement. Due to this
the delivery of the kiln is delayed substantially which is in critical path of the project. So
the project duration has been extended for several months. Since the delay is not incurred
by the contractor, they issued a delay notice to main EPC contractor and further requested
EOT (extension of time) and cost related to maintain the construction teams in project.
Another major case of delay noted on this project was due to failure in meeting
hydrostatic testing requirement of under ground GRE Pipe upon installation. Although
Page # 11 of 13
these pipes were inspected at vendors works at random (10%) prior to delivery to site.
Due to this failure, we had to remove all installed underground GRE pipes and replace
with new pipes supplied by another vendor. A substantial delay occurred due to this
incidence.
As Contract Manager I had put in all my effort to expedite the early placement of order
and prioritized an early delivery from vendor and negotiated with sub-contractor to
increase manpower to reinstall these pipes on war footing plan.
As a contract administrator, I have evaluated the request and estimated how many days
this delay will affect the contraction period which will be executed by others. On the
other hand, if we increase the recourses upon receiving the equipments what will be the
impact of schedule? In this particular example, I have taken a decision to crash the
duration which will allow us to complete the installation of all related activities .To
conclude that I have compared the time versus cost and selected the lowest cost impact to
project and time as well ,so that the delay could be reduced substantially. Since the delay
is not occurred by sub contractor, I have recommended compensating the cost incurring
to execute the work beyond the contractual period.
PROGRESS MEASUREMENT and PAYMENT SYSTEM:
Due to the nature of the project, we have decided to measure the process by incremental
mile stone method. What is the meaning of Mile stone? Milestone is an important activity
that must occur when scheduled in the project in order to achieve the project objective.
Incremental milestone means that the particular milestone activity has been broken into
manageable intermediate milestones. Each and every sub divided milestone will have the
weightage which will be using to compute the total progress in terms of cost incurred in
that particular period. In every cut of dates, the physical progress is computed as the
Page # 12 of 13
actual work executed at site and that to be compared with the mile stones. The completed
milestone shall be considered for progress and payment.
Since it is an incremental milestone measurement system which is comparatively simply
than other methods to achieve this, a milestone lists were prepared for which suitable
percentages were allotted. Accordingly, we have entered the completed activities and
obtain the cumulative value of work done until the cut-off date. To submit the invoice
for that particular period we should have to take into account the retention amount as per
contract and previously invoiced amounts to obtain from payment retrieve system. In my
project, the approved invoice shall be payable to sub contractor within 60 days from the
approved date or 7 days from receiving the payment from the customers which is coming
earlier. Once I completed this process, I am updating the PM+ System which is computer
aided record system that is implemented to track the entire document in this project.
CONCLUSION:
In my personal opinion for my project although the intent of programming, planning and
scheduling is to ensure completion of the project within the budgeted cost and contractual
time and fulfilling the requirements as per contract. But in practice due to so many
unforeseen facts related to change in detailed design, could creep in thereby cost and time
could be affected. I personally recommend all the organization should have to follow in
this kind of system which is highly effective. So as a contract administrator, it is of high
importance that from day one the project process is monitored, evaluated and corrective
action and reactions shall be the ultimate responsibility of contracts administrator.
Page # 13 of 13