technical considerations getting to “microgrid–ready”

40
Technical Considerations Getting to “Microgrid–Ready” What does it take to put together a well-performing Microgrid? By: Michael Higginson November 6, 2017 1

Upload: others

Post on 28-May-2022

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Technical Considerations Getting to “Microgrid–Ready”

Technical Considerations Getting to “Microgrid–Ready”

What does it take to put together a well-performing Microgrid?

By: Michael Higginson

November 6, 2017

1

Page 2: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Building Blocks

Distributed Energy Resources (DERs)

Switching and Protection Devices

Microgrid Control

2

Page 3: Technical Considerations Getting to “Microgrid–Ready”

Distributed Energy Resources (DERs)

3

Page 4: Technical Considerations Getting to “Microgrid–Ready”

DERs: Considerations

Power and energy capabilities

Response to system events

Paralleling and interconnection limitations

4

Page 5: Technical Considerations Getting to “Microgrid–Ready”

Conventional Generation: Power and Energy Capabilities

5

Power output • Minimum output • Maximum output

Energy • Fuel availability

Efficiency • Typically ~30% • Can be increased to ~80% with CHP

Page 6: Technical Considerations Getting to “Microgrid–Ready”

Battery Energy Storage: Power and Energy Capabilities

6

Power output •Minimum output (charging) •Maximum output (discharging)

Energy • Battery capacity

Efficiency • 80-90+% round trip efficiency

Page 7: Technical Considerations Getting to “Microgrid–Ready”

Renewable Resources: Power and Energy Capabilities

7

Power output • Minimum output • Maximum output

Energy

Intermittency

Page 8: Technical Considerations Getting to “Microgrid–Ready”

8

Page 9: Technical Considerations Getting to “Microgrid–Ready”

9

Generators: Frequency Response

Load Acceptance Droop and Isochronous Controls

Page 10: Technical Considerations Getting to “Microgrid–Ready”

Decrement Curves • Current decreases with time • Machine will respond to events on

utility system

10

Generators: Fault Response

Page 11: Technical Considerations Getting to “Microgrid–Ready”

Inverter-Interconnected Resources: Fault Response

11

Ride-through • Voltage and frequency

tripping

Limited output current

Fast response

Page 12: Technical Considerations Getting to “Microgrid–Ready”

12

Page 13: Technical Considerations Getting to “Microgrid–Ready”

Paralleling and Interconnection Considerations

13

System grounding while islanded

Synchronization

Generator pitch and harmonics

Page 14: Technical Considerations Getting to “Microgrid–Ready”

14

Page 15: Technical Considerations Getting to “Microgrid–Ready”

Activity: Select DERs

• Critical load: 20-250 kW • Evaluate the advantages and disadvantages of each of the following generation

options:

15

Option 1 Option 2 Option 3 Option 4

250 kW Battery

300 kW Conventional Generator

300 kW Conventional Generator

250 kW Battery

100 kW Solar PV

100 kW Solar PV

300 kW Conventional Generator

100 kW Solar PV

Page 16: Technical Considerations Getting to “Microgrid–Ready”

DERs: Key Takeaway

16

Power and energy capabilities • Ensuring sufficient capacity • Optimizing DER performance under expected load

Response to system events • Accepting load • Local and remote fault response

Paralleling and interconnection limitations • Can resources parallel?

Distributed energy resources must be carefully selected weighing advantages and disadvantages

Page 17: Technical Considerations Getting to “Microgrid–Ready”

© S&C Electric Company 2017, all rights reserved 17

Page 18: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Switching and Protection

18

Page 19: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Protection Challenges

• System topology changes: – Complex power flow, instead of from remote generation to load – Opening and closing switches – DER fault behavior

19

Page 20: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Protection: Key Ideas

Differentiate between load, inrush, and fault

current through all scenarios

Directionality in microgrid protection is necessary to achieve

selective coordination

Coordinate with downstream

overcurrent devices

20

Page 21: Technical Considerations Getting to “Microgrid–Ready”

Fault Current from Inverters

• Limited fault current availability • Ride-through capabilities

21

Page 22: Technical Considerations Getting to “Microgrid–Ready”

Generator Fault Decrement

22

Page 23: Technical Considerations Getting to “Microgrid–Ready”

Example Microgrid Scenarios

• 12.47 kV System • 250 kW BESS • 1 MW Natural Gas Generator • Renewable resources

23

Grid-Tied Fault

Current (kA)

Islanded Max Fault

Current (kA)

Islanded Min Fault Current

(kA)

Max Load Current

(kA)

5.0 0.5 0.02 0.05

Page 24: Technical Considerations Getting to “Microgrid–Ready”

24

Page 25: Technical Considerations Getting to “Microgrid–Ready”

Need for Protection Directionality

25

Page 26: Technical Considerations Getting to “Microgrid–Ready”

Example Fault Scenario

26

52 52 52

Load BESS Generator

Page 27: Technical Considerations Getting to “Microgrid–Ready”

Example Fault Scenario

27

52 52 52

Load BESS Generator

Page 28: Technical Considerations Getting to “Microgrid–Ready”

Challenges in Identifying Direction

• Delay in relay • System frequency changes • Inverter output waveforms • CT saturation

28

Page 29: Technical Considerations Getting to “Microgrid–Ready”

29

Page 30: Technical Considerations Getting to “Microgrid–Ready”

Coordinating with Existing Devices

30

• Existing devices on system are likely overcurrent protection

• Lateral and transformer fuses • Low-voltage breakers • Generator + inverter breakers

• Some devices may not operate while

islanded

• If selected carefully, breakers can be coordinated for many fault scenarios

Page 31: Technical Considerations Getting to “Microgrid–Ready”

31

Page 32: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Protection: Key Takeaways

Differentiate between load, inrush, and fault current through all scenarios

Directionality in microgrid protection is necessary to achieve selective coordination

Coordinate with downstream overcurrent devices

32

Page 33: Technical Considerations Getting to “Microgrid–Ready”

© S&C Electric Company 2017, all rights reserved 33

Page 34: Technical Considerations Getting to “Microgrid–Ready”

Control Level Temporal Requirement

Typical Functions Control Components

Tertiary Minutes • Forecasting • Advanced Optimization • Modeling

Software

Secondary Seconds • SCADA • Load Control • Generation Control

Hardware/Software

Primary Microseconds to Milliseconds

• Switching Logic • Protection

• Inverter Controllers • Generator Governor and

Exciter • Protection Relays

Microgrid Control: Hierarchy 34

34

Page 35: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Control: Architecture

35

SINGLE CENTRAL CONTROL DISTRIBUTED CONTROLS

Page 36: Technical Considerations Getting to “Microgrid–Ready”

36

36

Microgrid Control: Cybersecurity

Primary Guidelines

NIST 800-52, Security and Privacy for Federal Information Systems

NIST IR 7628, Guidelines for Smart Grid Cybersecurity

NERC CIP v5, Critical Infrastructure Protection

NIST 800-53, Risk Management Framework

Cybersecurity is needed in microgrids

Page 37: Technical Considerations Getting to “Microgrid–Ready”

Microgrid Control: Key Takeaway

The microgrid controller is an important part of the microgrid. Getting it wrong can leave your customers in the dark.

37

Page 38: Technical Considerations Getting to “Microgrid–Ready”

© S&C Electric Company 2017, all rights reserved 38

Page 39: Technical Considerations Getting to “Microgrid–Ready”

Conclusions

39

Distributed energy resources must be carefully selected weighing advantages and disadvantages

Effective microgrid protection involves use of sophisticated communication-assisted schemes and adaptive relay settings

The microgrid controller is an important part of the microgrid. Getting it wrong can leave your customers in the dark.

Page 40: Technical Considerations Getting to “Microgrid–Ready”

Questions ?

Contact Us [email protected]

40