DESCRIPTION
TDC2/TCC2 consolidation. EATM 15/07/2014. EN/EL. DC and control cable identification and cut completed Old light removal in TDC2 New AUG installed. Demin . circuit valve replacement. Remplacement des vannes terminé. Unités de ventilation. Travaux terminés. XTAX upgrade. - PowerPoint PPT PresentationTRANSCRIPT
TDC2/TCC2 consolidation
EATM 15/07/2014
EN/EL– DC and control cable identification and cut completed– Old light removal in TDC2– New AUG installed
Demin. circuit valve replacement
• Remplacement des vannes terminé
Unités de ventilation
• Travaux terminés.
XTAX upgrade
• 12/12 XTAX tables XTAX repaired• Still alignment issue for XTAX T4• This week: survey & test on XTAX T6 + roof closure
Magnet
• Manifolds re-installed
OTND (Onet nucleaire)
• Nettoyage 3 eme chateau XTAX OK• Démontage passerelle et chemins de câbles en
cours
OTND (Onet nucleaire)
Oculus porte
DoseMost critical activities Collective dose in uSv
47159 4186
XTAX table upgrade 4186
37405 2554
Removal, temporary storage and reinstall... 2554
19736 1705
TDC2/TCC2 replace valves 1705
43870 1630
Mesures topographiques TCC2 1630
44716 1526
Remplacement flexibles aimants TDC2 1526
48348 1104
démantèlement et nettoyage TDC2 1104
48664 1063
TDC2 Consolidation works EN/EL/CF - Phas... 1063
TOTAL 25000
PlanningJan'14 Feb'14 March 14 April 14 May 14 June 14 July 14 Aug' 14 Sep' 14 Oct' 14 Nov' 14
Date 6 13 20 27 3 10 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06 13 20 27 03 10 17week # 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47
Activities DurationCivil engineering 8w Vallier Dimens ione Mezz Peint
Cooling and ventilationChilled water 12w Remove pipes New pipes AHU coils
Demin. Water 5w valves
AHU control upgrade 12w
Handling 2w
Electricity NA NA physicsLV 10w startCabling 14+12w Cabling up
Magnets 12w
Vacuum 8w
Secondary beam lines 8 w Vacuum maintenance XTAX tables
Collimators and targets 2w
Beam instrumentationSurveyCleaning 4w