Page 1: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

TCC2-TDC2 working group

Handling means for the TAX repairs

21th September 2011

Page 2: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Handling means for the TAX repairs

• Simple rotative hook• Double rotative hooks• Modification of the crane• Vision system• Radiation measurement mobile platform• Standard transport means

Page 3: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Simple rotative hook

• Adaptation of the hook used for HiRadMat• Lifting capacity 4t• Will be operated with a remote controlProduction finishedNeed to be testedMounting on the craneneed some adaptations(installation of a cableRealer, and a power plug)

Page 4: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Double rotative hooks

• Two rotative hooks mounted on a motorized pivot• Lifting capacity 8t• Will be operated with a remote controlProduction and procurement started-> ready end of DecemberMounting on the craneneed some adaptations(installation of a cableRealer, and a power plug)

Page 5: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Modification of the crane

• Installation of remote control• Installation of a cable realer for the supply and

the control of the different ‘’handling tools’’• Remote control ordered delivery by December• Modification of the crane will be done at the

beginning of the Christmas shutdown (to agreed with the planning of the area)

Page 6: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Vision system

• Will used same equipment as used for HiRadMat

• Regarding the return of experience at HiRadMat it make sense to install an optical fiber on the crane

• Fix Cameras might be needed

Page 7: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Radiation measurement mobile platform

• Mostly finished someextra modifications need to be done (longer arm, flexible fitting for the probe, lighting)-> completely finishedat the end of October

Page 8: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Radiation measurement mobile platform

Page 9: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Standard transport means

• Repairs of the TA Boggies on going

• A cleaning of the bottom of the shaft shall be done a lot of dust, concrete is on the floor

Page 10: TCC2-TDC2 working group Handling means for the TAX repairs JL GRENARD EN-HE 21th September 2011

JL GRENARD EN-HE

Any questions?