t#.* · the study team shall conduct capacity building workshops on the vea/a process that it will...
TRANSCRIPT
'-i..i " -(.t,1 .' i
l; ,-r
-I
'f;"tEd't#.*I([PUBLIC OF THE I'HILIPPINES
NATIONAL ECONOMIC AND DEVELOPMENT AUTHORITY
BID BULLETIN NO. 1
CONDUCT OF VALUE ENGTNEERTNG / VALUE ANALYSTS (VE/VA) FORINFRASTRUCTURE DEVELOPMENT PROJECTS _ PANAY RIVER BASIN
INTEGRATED DEVELOPMENT PROJECT (PRBIDP)
TO : PROSPECTM BIDDEWS
Please be informed of the following clarifications/amendments for the subject procurement:
IiEDA sa P.lsig, l: Saint tosctn.lrir Escrivf f)riv{, Ortigts Cenler, plrsig Ctty 16051,,0, llox ill9, Grenhilh . ltls. 611,094!, ro 68
wwu'.ncda.gov.ph
REFERENCE / ITEM CLARIFICATION / AMENDMENT
Bid Document page 95:
Conduct of Study Tour / Site Wsit
The Study Tour / Site Visit shall also include atleast two (2) counterpart technical personneleach from the National Economic andDevelopment Authority (NEDA), NationalIrrigation Administration (NIA) and/or otherstakeholders as will be determined bv NEDA.
Bid Document page 98-99:
I'imelin es an d D el iv erah les
Interim VE/VA ReportThe Interim VE/VA Report shall provide morein depth findings based on the DevelopmentPhase, or os appropriate under a similarmethodolopgt.
Capacity Building WorkshopThe Study Team shall conduct capacity buildingworkshops on the VEA/A process that it willadopt in the conduct of the VE/VA Study onPRBIDP for selected govemment technicalpersonnel, supervisors/managers and/or offrcialswhich will be identifed/determined by NEDA.
Presentation toNEDA/NIA/ICC/INFRACOMThe Consulting Firm / Study Team will presentthe results of the VE/VA Study, findings andrecommendations to NEDA. NIA and/or otherstakeholders for comments. The Study Teammay also be called to present the same to theInvestment Coordination Committee (ICC),Committee on ln&astructure (INFRACOM),and/or other inter-agency committees, asnecessary.
Final VE/VA ReportThe Study Team shall incorporate any
applicable comment and recommendation
received from NEDA/NIA/ICC/INFRACOM,and/or other stakeholders. after the submission
of the Draft Final VE/VA Report. The FinalVE/VA Report shall be accompanied by the
Workshop Reports based on the capacity
building activities undertaken.
Notes:2. The Consulting Firm shall submit, together
with the VE/VA Work and Financial Plan
(WFP), its estimated man-month
requirements based on the timelines ofdeliverables and Annex B of the Terms ofReference (TOR). The Certified Value
Specialist (CVS) shall be engaged for a
minimum of 2.I man-months.
3. The Study Team may prepare a canned five(5)-minute audio-visual presentation (AVP)for ease of presentation toNEDA/NIA/ICCiINFRACOM. and/or other
stakeholders.
Bid Document page l0l-105:
Qu o lifi c at i o n Re q u ir e men t s forExperts/Consultants
For Experts/Consultants requiring professional
licenses, the Consulting Firm shall submit, as
part of its Technical Proposal, certified true
copies of the licenses of the Experts nominatedby the Firm for the Study.
Bid Document page 107:
Tech nical Ev u lu ation Criteria
The work experiences of the nominated Expertsshould be indicated in man-months. Workexperience shall also include similar and/orrelevant trainings/lectures conducted within thelast 20 years. Trainings acquired should be
indicated in terms of number of hours. Nott-indication thereof shall have zero (0)
rating/score forexperience/training.
that particular
The Project Manager / Team Leader, and theDeputy Team Leader, may only be nominatedby one (l) Consulting Firm for each particularposition. As such, firms nominating the same
Project Leader / Team Leader, or the same
Deputy Team Leader, shall have zero (0)
rating/score for that particular position.
Bid Document page 109:
Responsibilities of the Consulting Firm
The Consulting Firm shall shoulder all expensesrequired in the conduct of the Study, includingall costs related to the on-the-job capacltybuilding and training workshops, as well as the
study tour/site visit. However, the ConsultingFirm shall not provide "per diem" allowances
to any of the government personnel involved orparticipating in the StudY.
Bid Document page I l0:
Breakdown of Approved Budgetfor theContract (ABC)
Items TotalA. Remuneration 9,769,425.00
B. Reimbursable 2,229,010.28(includes meetings,workshop/trainingcosts, office spacerental, materials,accommodations,airfares/travelexpenses, etc.)Tax on Remuneration(r2%vATlTotal I1.999.010.28
Change to:
Items TotalC. Remuneration 9.769.425.00D. Reimbursable 2-230.575.00(includes meetings,workshop/trainingcosts, offtce spacerental, materials,accommodations,airfares/travelexpenses, etc.)Tax on Remuneration(Tz%VAT\Total 12.000.000.00
On the BDS :
TABLE OF RATING FOR SELECTIONTechnical Proposal - 70 points
Financial Proposal - 30 points
Change to :
TABLE OF RATING FOR SELECTIONTechnical Proposal - 80 pointsFinancial Proposal - 20 points
Issued on 16 July 2018, Pasig City.