Software Verification and Validation Plan (SVVP) Template
Items that are intended to stay in as part of your document are in bold;
explanatory comments are in italic text. Plain text is used where you
might insert wording about your project.
This document is an annotated outline for a Software Verification and
Validation Plan, adapted from the IEEE Standard for Software
Verification and Validation Plans (Standard 1012), and the IEEE Guide
for Software Verification and Validation Plans (Guide 1059).
Tailor as appropriate. Where you decide to omit a section, you might
keep the header, but insert a comment saying why you omit the
element (e.g., This section is not applicable to the plan.)
-
8/2/2019 SVVPLAN
2/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 2 01/17/01
(Agency)
(Project)
Software Verification and Validation Plan
Version: (n) Date: (mm/dd/yyyy)
-
8/2/2019 SVVPLAN
3/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 1 01/17/01
TABLE OF CONTENTS
1. PURPOSE 3
2. REFERENCED DOCUMENTS 4
3. DEFINITIONS 5
4. VERIFICATION AND VALIDATION OVERVIEW 5
4.1 Organization 5
4.2 Master Schedule 6
4.3 Resource Summary 6
4.4 Responsibilities 7
4.5 Tools, Techniques, and Methodologies 7
5. LIFECYCLE VERIFICATION AND VALIDATION 7
5.1 Management of V&V 7
5.2 Concept Phase 8
5.3 Requirements Phase 9
5.4 Design Phase 9
5.5 Implementation Phase 10
5.6 Test Phase 11
5.7 Installation and Checkout Phase 11
5.8 Operation and Maintenance Phase 12
6. Reporting 12
-
8/2/2019 SVVPLAN
4/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 2 01/17/01
TABLE OF CONTENTS (CONTINUED)
7. Administrative Procedures 13
7.1 Anomaly Reporting and Resolution 13
7.2 Task Iteration Policy 13
7.3 Deviation Policy 13
7.4 Control Procedures 14
7.5 Standards, Practices, and Conventions 14
8. Plan Approvals 14
-
8/2/2019 SVVPLAN
5/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 3 01/17/01
1. PURPOSE
(NOTE 1: THE SOFTWARE VERIFICATION AND VALIDATION PLAN GUIDELINES WERE
DERIVED AND DEVELOPED FROM IEEE STANDARD FOR SOFTWARE VERIFICATION ANDVALIDATION (STANDARD 1012) AND THE IEEE GUIDE FOR SOFTWARE VERIFICATION ANDVALIDATION PLANS (GUIDE 1059)).
(Note 2: The ordering of Software Verification and Validation Plan (SVVP) elements
is not meant to imply that the sections or subsections must be developed or
presented in that order. The order of presentation is intended for ease of use, not as a
guide to preparing the various elements of the Software Verification and Validation
Plan. If some or all of the content of a section is in another document, then a
reference to that material may be listed in place of the corresponding content.)
(The Purpose section of the Software Verification and Validation Plan defines the purpose,
scope, and goals of the plan. The software project must be identified and the specific
software product items, covered by the plan, must be identified. The specific goals of the
verification and validation effort must be specified.
The SVVP purpose section provides the highest level description of verification and
validation efforts. The following topics must be addressed:
Project identification, Plan goals,
Summary of verification and validation efforts,
Responsibilities conveyed with the plan,
Software to be verified and validated,
Identification of waivers and changes to organization standards, and
SVVP assumptions.)
Software verification and validation (V&V) is a disciplined approach to assessing software
products throughout the software development life cycle. Verification and validation strives toensure that quality is built into the software and that the software satisfies business functional
requirements.
Software verification and validation employs review, analysis, and testing techniques to
determine whether a software product and its intermediate deliverables comply with
requirements. These requirements include both business functional capabilities and quality
attributes.
-
8/2/2019 SVVPLAN
6/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 4 01/17/01
The objectives of the V&V effort are to find defects and to determine if required functions and
attributes are built into the software system. V&V activities are designed to support:1. Verification that the products of each software life cycle phase:
- Comply with previous life cycle phase requirements and products for
correctness, completeness, consistency, and accuracy,
- Satisfy the standards, policies, practices, procedures, and conventions of the
phase, and
- Establish the proper basis for initiating the next life cycle phase.
2. Validate that the completed end product complies with established software and
system requirements.
Verification and validation provide management with insights into the state of the project and
the software products, allowing for timely change in the products or in the software
development life cycle approach.
(Verification and validation effort is typically applied in parallel with software development and
support activities. Verification and validation planning may be broken down into the following
steps:
- Identify the V&V scope,
- Establish specific objectives from the general project scope,
- Analyze the project input prior to selecting V&V tools and techniques,
- Select tools and techniques, and
- Develop the Software Verification and Validation Plan (SVVP)).
2. REFERENCE DOCUMENTS
(This section shall identify the binding compliance documents, documents referenced in the
plan, and any supporting documents required to implement, or supplement, the SVVP.
Ensure that the reference document list is consistent with other project documentation.
Ensure that all documents listed in the plan are referenced. Specify documents completely
-
8/2/2019 SVVPLAN
7/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 5 01/17/01
including the version and date reference.)
-
8/2/2019 SVVPLAN
8/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 6 01/17/01
3. Definitions
(The definition section provides a reference to the definition of all terms required to properlyinterpret the SVVP. This section also notes acronyms and notations used in the plan. Include
only terms necessary for understanding the SVVP. Refer to other project documentation for a
comprehensive list of project definitions (e.g., Software Project Management Plan, Software
Quality Assurance Plan). For SVVP purposes, the following definitions apply:)
SVVP Software Verification and Validation Plan.
Validation The process of evaluating software at the end of the software development
process to ensure compliance to software requirements.
Verification The process of determining whether or not products of a given phase of the
software development process fulfill the requirements established during the previous phase.
V&V Verification and validation.
4. VERIFICATION AND VALIDATION OVERVIEW
(Describe the organization, schedule, resources, responsibilities, tools, techniques, and
methodologies to be deployed in order to perform the verification and validation activities.)
4.1 Organization
(Define the relationship of verification and validation to other efforts such as
development, project management, quality assurance, and configuration
management. Define the lines of communication within the verification and
validation effort, the authority for resolving issues, and the authority for
approving verification and validation deliverables.)
-
8/2/2019 SVVPLAN
9/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 7 01/17/01
(The specific organization structure of the V&V effort will depend on the nature
of the system under development, the developing organizations, and any
contractual arrangements.)
4.2 Master Schedule
(The master schedule summarizes the various verification and validation tasks
and their relationship to the overall project.)
(Describe the project life cycle and project milestones including completion dates.
Summarize the schedule of verification and validation tasks and how verification
and validation results provide feedback to the development process to support
overall project management functions.)
(The objective of this section is to define an orderly flow of material between
project activities and verification and validation tasks. Use reference to PERT,
CPM, and Gantt Charts to define the relationship of activities.)
(If the life cycle used in the SVVP differs from the life cycle model defined in IEEE
Standard 1012, this section must show how all requirements of the Standard will
be satisfied. The summary of tasks may be in narrative, tabular, or graphic form.)
4.3 Resource Summary
(This section summarizes the resources needed to perform verification and
validation tasks, including staffing, facilities, tools, finances, and special
procedural requirements such as security, access rights, and documentation
control. In this section:
Use graphs and tables to present resource utilization,
Include equipment and laboratory resources required,
Summarize the purpose and cost of hardware and software tools to be
employed, and
Take all resources into account and allow for additional time and money to
cope with contingencies.)
-
8/2/2019 SVVPLAN
10/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 8 01/17/01
4.4 Responsibilities
(Identify the organization responsible for performing verification and validation
tasks. There are two levels of responsibility general responsibilities assigned to
different organizations and specific responsibilities for the V&V tasks to be
performed should be assigned to individuals. General responsibilities should be
supplemented with specific responsibility for each task in the verification and
validation plan.)
4.5 Tools, Techniques, and Methodology
(Identify the special software tools, techniques, and methodologies to be employed
by the verification and validation team. The purpose of each should be defined
and plans for the acquisition, training, support, and qualification of each shall be
described in this section. This section may be in narrative or graphic format. A
separate tool plan may be developed for software tool acquisition, development,
or modification. In this case, a separate Tool Plan section may be added to the
plan.)
5. LIFECYCLE VERIFICATION AND VALIDATION
(This section of the SVVP provides the detailed plan for the verification and validation
tasks throughout the project life cycle. Please refer to IEEE Standard 1012 and IEEE
Guide 1059 for detailed descriptions of lifecycle verification and validation activities.)
5.1 Management of V & V
This section shall address the following general topics:
Verification and validation tasks,
Methods and criteria,
Inputs and outputs,
Schedule,
Resources,
-
8/2/2019 SVVPLAN
11/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 9 01/17/01
Risks and assumptions, and
Roles and responsibilities.
(In addition, all sub-sections of this major heading (5) must specifically address all
seven of the topics noted above.)
(For all software projects, the Management of Verification and Validation section
must include the following minimum tasks:
Software Verification and Validation Plan Generation,
Baseline Change Assessment,
Management Review of V&V, and
Review Support.)
(Initiate the Software Verification and Validation Plan during the Concept phase
of the project life cycle. However, verification and validation planning may be
dependent on things outside of your control. Therefore, V&V planning may be
most effectively performed in conjunction with the overall software development
planning effort. The SVVP is often best developed incrementally.)
(Evaluate proposed software changes for effects on previously completed V&V
tasks. The request for baseline change assessment should be formally documented
in a change proposal.)
(Conduct periodic reviews of V&V efforts, technical accomplishments, resource
utilization, future planning, and risk management. Management review comprises
all of the general responsibilities of management for monitoring, controlling,
reporting, and managing the plan.)
(Identify key review support milestones. Correlate V&V task results to support
project management and technical reviews.)
5.2 Concept Phase
(This section of the plan shall address the seven topics identified in section 5.1 of
this document. Evaluate concept documentation to determine if the proposed
project concept satisfies user needs and project objectives. Identify major
constraints of interfacing systems and limitations of the proposed approach.
Assess the criticality of each software item.)
(The concept phase establishes the reason for the system. Evaluation in the
-
8/2/2019 SVVPLAN
12/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 10 01/17/01
concept phase should establish that the objectives of the system define the user
needs to be addressed and the technical and business advantages to be expected.)
5.3 Requirements Phase
(The requirements phase is when the functional and technical capabilities of the
software product are defined and documented. The product from the
requirements phase (Software Requirements Specification) should accurately state
the software mission and what the software is intended to do. Requirements must
be traceable to user needs and the system concept.)
(This section of the plan shall address the seven topics identified in section 5.1 of
this document. For critical software, Requirements Phase Verification and
Validation must include the following tasks:
Software requirements traceability analysis, (Trace SRS requirements tosystem requirements in concept documentation. Analyze identified
relationships for correctness, consistency, completeness, and accuracy. Do the
requirements completely satisfy the capabilities specified in the concept
document?)
Software requirements evaluation, (Evaluate SRS requirements forcorrectness, consistency, completeness, accuracy, readability, and testability.
Assess the technical merits of the requirements.)
Software requirements interface analysis, (Evaluate the SRS with hardware,user, operator, and software interface requirements documentation for
correctness, consistency, completeness, accuracy, and readability Ensure that
all external interfaces to the software and internal interfaces between
software functions are complete and correctly specified.) and
Test plan analysis for- System test, and- Acceptance test.)
5.4 Design Phase
(The design phase in the software life cycle involves the designs for architecture,
software components, interfaces, and data creation, documentation, and
verification. Design must trace back to requirements.)
-
8/2/2019 SVVPLAN
13/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 11 01/17/01
(This section of the plan shall address the seven topics identified in section 5.1 of
this document. For critical software, design phase V&V will include the following
tasks:
Software design traceability analysis (Trace design documentation torequirements. Analyze identified relationships for correctness, consistency,
completeness, and accuracy.),
Software design evaluation (Evaluate design for correctness, consistency,completeness, accuracy, readability, and testability. Assess the technical
merits of the requirements and compliance to organization standards.),
Software design interface analysis, (Evaluate design with hardware, operator,and software interface requirements documentation for correctness,
consistency, completeness, accuracy, and readability At a minimum, analyze
data elements at each interface.) and
Test design generation
- Component test plan, and
- Integration test plan.)
5.5 Implementation Phase
(This section of the plan shall address the seven topics identified in section 5.1 of
this document. Implementation phase V&V must include the following tasks:
Source code traceability analysis (Trace source code to design specificationand assess correctness, consistency, completeness, and accuracy.),
Source code evaluation (evaluate source code for correctness, consistency,completeness, accuracy, and testability. Assess code quality and compliance to
organization standards.),
Source code interface evaluation (Evaluate source code with hardware,operator, and design documentation for correctness, consistency,
completeness, and accuracy.),
Source code documentation evaluation (Evaluate draft code-relateddocuments with source code to ensure completeness, correctness, and
consistency.),
Test case generation for:
-
8/2/2019 SVVPLAN
14/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 12 01/17/01
- Component test- Integration test- System test and- Acceptance test,
Test procedure generation for:- Component test
- Integration test and
- System test,
Component test execution.)
5.6 Test Phase(This section of the plan shall address the seven topics identified in section 5.1 of
this document. The following tasks must be included in this section:
Acceptance test procedure generation, (Develop test procedures foracceptance test) and
Test execution- Integration test,- System test, and
- Acceptance test.)
5.7 Installation and Checkout Phase
(This section of the plan shall address the seven topics identified in section 5.1 of
this document. The following verification and validation tasks must be included in
this section:
Installation configuration audit, (Audit installation package to determine thatall software products required to correctly install and operate the system arepresent and correct), and
Final V&V report generation, (Summarize all V&V activities and resultsincluding the status and disposition of anomalies in the V&V final report).)
-
8/2/2019 SVVPLAN
15/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 13 01/17/01
5.8 Operation and Maintenance Phase
(This section of the plan shall address the seven topics identified in section 5.1 of
this document. Any modifications, enhancements, or additions to software during
this phase shall be treated as development activity and shall be verified and
validated. If the original software was verified and validated under this standard,
the standard must continue to be followed in the Operations and Maintenance
phase. The minimum V&V tasks to include:
- Software verification and validation plan revision,- Anomaly Evaluation,- Proposed change assessment, and
- Phase task iteration.)
(The operation and maintenance phase is the period of time in the software life
cycle during which the software product is employed in an operational
environment, monitored for satisfactory performance, and modified to correct
problems or respond to changing requirements. Operation and maintenance may
not be a phase but a sequence of repetitions or subsets of the software
development life cycle.)
6. Reporting
(This section describes how the results of implementing the SVVP will be documented.
Verification and validation reporting will occur throughout the software life cycle.
Specify the content, format, and timing of all verification and validation reports.
The required V&V reports include:
- Anomaly reports,
- Task reporting,
- Phase summary reports, and
- Final report.)
-
8/2/2019 SVVPLAN
16/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 14 01/17/01
7. Administrative Procedures
(This section should identify any existing administrative procedures that are to be
implemented as part of the SVVP. Verification and validation efforts consist of both
management and technical tasks. At least three audiences should be identified for the V&V
information personnel performing the V&V tasks, personnel performing development tasks,
and management.)
7.1 Anomaly Reporting and Resolution
(Identify the method of reporting and resolving anomalies including the criteria
for reporting an anomaly, anomaly report distribution, and the authority and time
line for resolving anomalies. This section should have the following sub-sections:
- Methods and criteria for reporting,
- Report distribution,
- Methods and criteria for anomaly resolution,
- Anomaly criticality scheme,
- Resolution timing.)
7.2 Task Iteration Policy
(Describe the criteria used to determine when V&V tasks must be re-performed
because input has changed. These criteria include assessments of change,
criticality, cost, schedule, and effects on product quality.)
7.3 Deviation Policy
(Describe the procedures and forms used to request a deviation from the SVVP.
The information required for deviation must include task identification, deviation
rationale, and effect on software quality. Authority for approving deviations from
-
8/2/2019 SVVPLAN
17/17
Software Verification and Validation Plan
Q:\IRM\PRIVATE\INITIATI\QA\QAPLAN\SVVPLAN.doc 15 01/17/01
the plan must also be identified.)
7.4 Control Procedures
(Identify all control procedures applied to the verification and validation effort.
At a minimum, control procedures should be identified for:
- Configuration management,
- Archive and retrieval,
- Security, and
- Access control.)
7.5 Standards, Practices, and Conventions
(This section identifies the standards, practices, and conventions that govern the
performance of verification and validation tasks. Include IEEE, IRMC, and
organizational standards, policies, procedures, and guidelines.)
8. Plan Approvals
(Identify the plan approvers. List the name, signature and date of plan approval.)