Sneak Peak of Glumac Shanghai Office Sustainable Procurement Strategy At Green Drinks Shanghai Completion Date: June 31, 2014 Location: Shanghai, China Size: 600 sqm Owner: Glumac MEP Design: Glumac LEED & LBC Consultant: Glumac Energy Modeling: Glumac Commissioning: Glumac Interior Design: Gensler Contractor: Shimizu Material Consultant: GIGA

Upload: green-initiatives-

Post on 22-Nov-2014

79 views

Category:

Environment


0 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Sneak Peak of Glumac Shanghai Office Sustainable Procurement Strategy At Green Drinks Shanghai

Completion Date: June 31, 2014

Location: Shanghai, China Size: 600 sqm

Owner: Glumac

MEP Design: Glumac LEED & LBC Consultant: Glumac

Energy Modeling: Glumac Commissioning: Glumac Interior Design: Gensler

Contractor: Shimizu Material Consultant: GIGA

Page 2: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

ü  First Net Zero Energy/Water/Carbon Project in Asia ü  First Living Building Full Certification in Asia ü  First LEED V4 Platinum In Asia achieving 97 points ü  Multiple Latest Green Building Technologies

End  of  2014  

Page 3: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 4: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

GLUMAC OFFICE

Page 5: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Project  Partners:  

Page 6: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

 How  We  Process  the  Procurement  

Red  List  

Appropriate  Souring  

 Zero  Carbon  Footprint  

 

Life-­‐Cycle  Assessment  

 

ConstrucFon  ConservaFon    &  Reuse  

 Responsible  Industry  

•  Early  Planning  and  Scheduling  •  Reuse  and  ConservaFon  

•   Simplicity  &  MinimizaFon    

•  Life-­‐Cycle  Assessment  •  Sustainable  Criteria      

•  Cost-­‐efficiency      

•   Appropriate  applicaFon    

Planning  

Design  

SelecFon  

Procurement  

OperaFon  

Page 7: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Planning  

Page 8: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Planning  Note: text in red: first choice with Gensler. Text in blue: sourced from Declare. With Chinese means this product has potential vender or the production site in China

PROGRESS PLAN

# RADIUS (km) Vendor Contact

Responsible team

member

Letter Sent 13/12/23

Followed Up? Refused

Accepted, currently in

process

G/G Opts Review.

Selection &

Supporting Documents

Advocacy Letter Sent

Actions Complet

e

PRODUCT NAME

NEW PRODUCT / SALVAGED OR REUSED

COST (¥in RMB) NOTES NAME

LOCATION (city,

state/province,

DISTANCE FROM SITE (km) NAME PRIMARY

CONTENTS

CONTENT LOCATION

(city,

CONTENT DISTANCE

FROM MNFR

EXCEPTION APPLIED?

(yes/no)RED LIST (yes/no)

APP. SOURCING

(yes/no)

FSC CERTIFIED (yes/no)

MRc3.1 ENVIRONMENTAL PRODUCT

MRc3.2 MULTI-ATTRIBUTE

OPTIMIZATION

MRc4.1 RAW MATERIAL SOURING

MRc4.2 LEADERSHIP EXTRACTION

MRc5.1 MATERIAL

INGREDIENT

MRc5.2 MATERIAL

INGREDIENT

MRc5.3 PRODUCT

MANUFACTUR

EQc2 LOW EMITTING MATERIAL

3 Concrete 1 500 km

03 15 00Self Expanding Rubber Strip Waterstops 1 500 km New Material 2000 EXAMPLE!!! XYZ Corporation Shanghai 25

WATERSTOP - XYZ Concrete Hunan Province 350 no N/A Yes N/A No No

Self-declared reports No

Manufacturer Inventory No Yes Yes

03 35 19 Concrete Finishing Systems 5 1000 km

03 60 00 Grouting (confirm in scope)

opt 1 LaticreteDenny Yan Mkg Spe BZ

Co. Ltd in the Songjiang District of Shanghai, China

http://www.laticrete.com/portals/0/msds

opt 2 Ardex

David Jiang , [email protected]: 13916687096 BZ

http://www.ardexamericas.com/sp/Documents/MSDS_En_P

4 Masonry 1 500 kmopt 1 Reclaimed, Salvaged Brick AGopt 2opt 3

opt 4Coldspring Dimensional Limestone

Coldspring Dimensional Limestone

http://www.declareproducts.com/content/coldspring- Coldspring Cold Spring, USA Mankato, USA 147 km Yes No N/A

opt 5 Coldspring Dimensional GraniteColdspring Dimensional

http://www.declareproducts.com/content/ Coldspring

Raymond, Cold Spring, Au Sable USA Within 500 Miles Yes No N/A

4 Stone Pebble 1 500 km

opt 1 Zhejiang Weiguo Mining Co Ltd Qian Ming 15268175959 AGZhejiang Province, China

5 Metals 1 500 kmopt 1 BaoSteel AG

05 Stainless Steel Wang Fengguang 15167221022

opt 1 Shanghai Dong Guan Construction AG recycled metalShanghai Dong Guan

opt 2opt 3

05 50 00 Metal Fabrications 2 1000 km

05 70 00 Decorative Metals 2 1000 km AGopt 1 Raw steel plate Bao Steel AGopt 2opt 3

6 Wood, Plastics, Composites 2 1000 km

opt 1 Koshi Woods BZhttp://www.gigabase.org/en/manufacturer Osaka, Japan

opt 2 Baibio Old Wood Market Feng Hongtian 13515723782 BZOld Wood Market

Zhejiang Province, China

opt 3 EMCC Co. Ltd

Zhang Cheng Hua [email protected] PH: 138 6130 9610 M: 138 6130 9610 BZ

opt 4 Fujian Furniture Import & ExportChen Jian 8659187660386 87511553 BZ Fuzhou

opt 5 Intl wood ProductsXu Wei 51257673555 [email protected] BZ Kunshan

CSI MASTER FORMAT NUMBER

MATERIAL TITLE

ZONE PRODUCT GENERAL INFORMATION MANUFACTURER INFORMATION DETAIL CONTENT INFORMATION LBC LEED V4

Page 9: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Planning  

Page 10: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Planning  

Page 11: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Design  Decisions    

Page 12: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 13: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 14: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

SelecFon  Criteria  

   

Red  List  

Appropriate  Souring  

 Zero  Carbon  Footprint  

 

Life-­‐Cycle  Assessment  

 

ConstrucFon  ConservaFon    &  Reuse  

 Responsible  Industry  

Page 15: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Red List Free

 

No Red List materials or chemicals:

•  Asbestos •  Cadmium •  Chlorinated Polyethylene and

Chlorosulfonated Polyethylene •  Chlorofluorocarbons (CFCs) •  Chloroprene (Neoprene) •  Formaldehyde (added) •  Halogenated Flame Retardants •  Hydro-chlorofluorocarbons (HCFCs) •  Lead (added) •  Mercury •  Petrochemical Fertilizers and Pesticides •  Phthalates •  Polyvinyl Chloride (PVC) •  Wood treatments containing Creosote,

Arsenic or Pentachlorophenol

Page 16: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Responsible Industry

 

Advocate for the creation and adoption of third-party certified standards Sustainable resource extraction and fair labor practices.

Page 17: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Appropriate Sourcing

 

Raw materials & Manufacturing Zoning requirements

Page 18: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Embodied Carbon Footprint

 

total footprint of embodied carbon (tCO2e) from construction one-time carbon offset

Page 19: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Beauty  +  Spirit  

Each  Purchase  Has    a    Story    to    Tell  

Page 20: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 21: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Sustainable Material

Page 22: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

10mm (0.4 inch) with R-9.6/in (U-0.3Btu/h.ft2.f, K-1.5W/m2K) Flexible, thin, compression resistance, superb thermal resistance Perfect for hard to insulate spaces 8 to10 times thinner than Mineral Wool to deliver an equivalent R-value  

Dow Corning Building Insulation Blanket

Page 23: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

25 mm with R-40 5-10 times better thermal resistance than conventional insulation Maintain more than 80% of thermal performance after 30 years 95% recycled content  

Dow Corning Vacuum Incapsulated Panel

Page 24: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Smart Glass

Transparent when switch on and opaque when switch off SC=0.31 (on); SC=0.23 (off) Better acoustic  

Page 25: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Photovoltaic Panels

Capacity: 45 KW 187 panels Annual Electricity: 70,000 KWh Connected back to Campus and potentially back to the Grid with incentives  

Page 26: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Radiant Heating/Cooling Slab

 

High level of thermal comfort Fully passive system Maximize ceiling height Used for heating AND cooling Eliminates fan energy Utilizes thermal mass    

Page 27: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Lighting Fixture and Control

 

All fixtures are dimmable LED addressable High Efficient Locally sourced Full wireless control Vacancy Sensor vs Occupancy Sensor Peak power consumption = 2W/sm  

Page 28: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Healthy Air

• Floor grilles & patio brick slot - entryway dirt track-in system • Copy machine separately exhausted directly to outside • CO2 sensors • 3-Stage Air filtration - MERV 8 ~ ESP~ MERV15  

Cleaner  Outdoor  Air    Separate  Exhaust    

MERV15    Filter  

Ionizer   Collector  Polluted  Air Clean  Air  

PM2.5:200

PM2.5:50

MERV  8  Pre-­‐filter  

Page 29: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Net zero water Efficient fixtures with solar powered sensors Compositing toilet 100% recycle rainwater Purified without the use of chemicals.  

Annual  Rainwater  CollecFon  over  800m3  

ComposFng    Toilet  Efficient  fixtures  with  solar  powered  sensors  

Non-­‐chemical  FiltraFon  System  

Page 30: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Envirolet Composting Toilet

 

Compositing toilet: 0.2L/flush Regular low flush toilet: 4.5 L/flush 1st trial installment in China  

Page 31: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Purchasing for Ongoing Operations

Waste for Building Operations

OperaFon  

Page 32: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai

Green Cleaning Purchasing

Page 33: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 34: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 35: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai
Page 36: Sustainable Procurement Strategy for Glumac's LBC Office in Shanghai