Activity ID Activity Description UB Orig Dur g g e u % Early Start Early Finish Total Float Elementary & Middle School General 201 Notify Site Biologist 0 17JAN12A 10 Mobilization - Earthwork 3 02FEB12* 06FEB12 4 5 Construction Duration 411* 02FEB12 16SEP13 0 30 SWPPP Duration (calendar days) 593* 02FEB12 16SEP13 0 2 Notice of Award 0 28MAR12* 6 1 N.T.P. 0 09APR12* 0 20 Mobilization 10 09APR12 20APR12 0 99960 Substantial Completion - Middle School 0 13JUN13 25 99970 Punchlist 40 22JUL13 16SEP13 0 99950 Substantial Completion - Elementary School 0 19JUL13 0 99980 Project Contigency Time (Calendar Days) 0 17SEP13 16SEP13 0 Acceptance / Closeout 99990 Final Acceptance 0 16SEP13 0 99999 Project Closeout 40 19AUG13 14OCT13 0 100000 Project Complete 0 14OCT13 0 Submittals Procurements 99000 Start Critical Submittals 0 28MAR12 6 Structural Steel 99020 Prep/Sub Steel Shop Drawings 35 28MAR12 15MAY12 47 99022 Rev/Apv Steel Shop Drawings 10 16MAY12 30MAY12 47 99028 Fab/Del Structural Steel Embeds 30 31MAY12 12JUL12 47 Concrete Footing Embeds 99040 Prep/Sub Concrete Footing Embeds/Anchor Bolts 5 28MAR12 03APR12 6 99042 Rev/Apv Concrete Footing Embeds/Anchor Bolts 10 04APR12 17APR12 6 99048 Fab/Del Concrete Footing Embeds/Anchor Bolts 1 18APR12 18APR12 6 2012 2013 J F M A M J J A S O N D J F M A M J J A S O N D J FEB Notify Site Biologist Mobilization - Earthwork Construction Dur SWPPP Duration Notice of Award N.T.P. Mobilization Substantial Completion - Middle School Punchlist Substantial Completion - Elementary School Project Contigency Time (Calendar Days) Final Acceptance Project Closeout Project Complete Start Critical Submittals Prep/Sub Steel Shop Drawings Rev/Apv Steel Shop Drawings Fab/Del Structural Steel Embeds Prep/Sub Concrete Footing Embeds/Anchor Bolts Rev/Apv Concrete Footing Embeds/Anchor Bolts Fab/Del Concrete Footing Embeds/Anchor Bolts © Primavera Systems, Inc. Start Date 09JAN12 Finish Date 14OCT13 Data Date 09JAN12 Run Date 21FEB12 12:17 Early Bar Progress Bar Critical Activity BS07 Bakersfield City School District New Elementary & Middle School Bid Schedule Sheet 1 of 43 Lundgren Management 661-257-1805 Date Revision Checked Approved

Upload: others

Post on 25-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Elementary & Middle SchoolGeneral

201 Notify Site Biologist 0 17JAN12A

10 Mobilization - Earthwork 3 02FEB12* 06FEB12 4

5 Construction Duration 411* 02FEB12 16SEP13 0

30 SWPPP Duration (calendar days) 593* 02FEB12 16SEP13 0

2 Notice of Award 0 28MAR12* 6

1 N.T.P. 0 09APR12* 0

20 Mobilization 10 09APR12 20APR12 0

99960 Substantial Completion - Middle School 0 13JUN13 25

99970 Punchlist 40 22JUL13 16SEP13 0

99950 Substantial Completion - Elementary School 0 19JUL13 0

99980 Project Contigency Time (Calendar Days) 0 17SEP13 16SEP13 0

Acceptance / Closeout

99990 Final Acceptance 0 16SEP13 0

99999 Project Closeout 40 19AUG13 14OCT13 0

100000 Project Complete 0 14OCT13 0

SubmittalsProcurements 99000 Start Critical Submittals 0 28MAR12 6

Structural Steel 99020 Prep/Sub Steel Shop Drawings 35 28MAR12 15MAY12 47

99022 Rev/Apv Steel Shop Drawings 10 16MAY12 30MAY12 47

99028 Fab/Del Structural Steel Embeds 30 31MAY12 12JUL12 47

Concrete Footing Embeds 99040 Prep/Sub Concrete Footing Embeds/Anchor Bolts 5 28MAR12 03APR12 6

99042 Rev/Apv Concrete Footing Embeds/Anchor Bolts 10 04APR12 17APR12 6

99048 Fab/Del Concrete Footing Embeds/Anchor Bolts 1 18APR12 18APR12 6

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Notify Site Biologist

Mobilization - Earthwork

Construction Duration

SWPPP Duration (calendar days)

Notice of Award

N.T.P.

MobilizationSubstantial Completion - Middle School

PunchlistSubstantial Completion - Elementary School

Project Contigency Time (Calendar Days)

Final Acceptance

Project Closeout

Project Complete

Start Critical Submittals

Prep/Sub Steel Shop Drawings

Rev/Apv Steel Shop Drawings

Fab/Del Structural Steel Embeds

Prep/Sub Concrete Footing Embeds/Anchor Bolts

Rev/Apv Concrete Footing Embeds/Anchor Bolts

Fab/Del Concrete Footing Embeds/Anchor Bolts

© Primavera Systems, Inc.

Start Date 09JAN12Finish Date 14OCT13Data Date 09JAN12Run Date 21FEB12 12:17

Early Bar

Progress Bar

Critical Activity

BS07

Bakersfield City School District

New Elementary & Middle School

Bid Schedule

Sheet 1 of 43 Lundgren Management 661-257-1805Date Revision Checked Approved

Page 2: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 2 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Earthwork / Site UtilitiesEarthwork 1000 Start Earthwork 0 07FEB12 4

1020 Clear & Grub Site 3 07FEB12 09FEB12 6

1040 Survey Site 5 07FEB12 13FEB12 4

1060 Earthwork / Grade Site 30 14FEB12 26MAR12 4

1080 Construct Building Pads 10 20MAR12 02APR12 4

1100 EarthworkComplete 0 02APR12 4

Underground Utilities 1200 Install Site Main Storm Drainage 20 09APR12 04MAY12 167

1210 Install Site Sewer Mains 20 09APR12 04MAY12 167

1220 Install Site Water Mains 20 09APR12 04MAY12 170

1230 Install Main Fire Lines 20 12APR12 09MAY12 167

1240 Install Irrigation Mains 20 12APR12 09MAY12 167

1215 Install Site Sewer Laterals 10 07MAY12 18MAY12 211

1205 Install Site Storm Drainage Laterals 10 07MAY12 18MAY12 216

1225 Install Site Water Laterals 10 07MAY12 18MAY12 216

1235 Install Lateral Fire Lines 10 10MAY12 23MAY12 213

1245 Install Irrigation Laterals 10 10MAY12 23MAY12 213

1250 Install Site Main Electrical Conduits 20 10MAY12 07JUN12 167

1275 Install Grease Trap 5 21MAY12 25MAY12 211

1255 Install Site Lateral Electrical Conduits 20 08JUN12 06JUL12 183

1265 Install Site Drainage 10 12FEB13 25FEB13 60

Site Power 1400 Install Main Power Feeds 5 08JUN12 14JUN12 221

1420 F,R,P Transformer/Switchgear Pads 3 09JUL12 11JUL12 206

1440 Set Main Transformer / Switchgear 2 12JUL12 13JUL12 206

1460 Wire & Terminations 15 16JUL12 03AUG12 206

Retaining Wall @ N.E. Perimeter 1500 Excav. for Wall Ftg @ N. & E. Perimeter 3 23APR12 25APR12 11

1520 Form, Rebar Pour Wall Ftg @ N. & E. Perimeter 5 24APR12 30APR12 11

1540 Construct Retaining Wall @ N.& E. Perimeter 20 01MAY12 29MAY12 11

1560 Install Drainage & Waterproofing N.E. Retaining 4 30MAY12 04JUN12 11

1580 Bkfl @ N.E. Perimeter Retaining Wall 2 05JUN12 06JUN12 11

1600 Install Chain Link Fence @ N.E. Retaining Wall 5 07JUN12 13JUN12 33

Retaining Wall @ South Perimeter 1700 Excav. for Wall Ftg @ South Perimeter 3 07JUN12 11JUN12 11

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Start Earthwork

Clear & Grub Site

Survey Site

Earthwork / Grade Site

Construct Building Pads

EarthworkComplete

Install Site Main Storm Drainage

Install Site Sewer Mains

Install Site Water Mains

Install Main Fire Lines

Install Irrigation Mains

Install Site Sewer Laterals

Install Site Storm Drainage Laterals

Install Site Water Laterals

Install Lateral Fire Lines

Install Irrigation Laterals

Install Site Main Electrical Conduits

Install Grease Trap

Install Site Lateral Electrical Conduits

Install Site Drainage

Install Main Power Feeds

F,R,P Transformer/Switchgear Pads

Set Main Transformer / Switchgear

Wire & Terminations

Excav. for Wall Ftg @ N. & E. Perimeter

Form, Rebar Pour Wall Ftg @ N. & E. Perimeter

Construct Retaining Wall @ N.& E. Perimeter

Install Drainage & Waterproofing N.E. Retaining

Bkfl @ N.E. Perimeter Retaining Wall

Install Chain Link Fence @ N.E. Retaining Wall

Excav. for Wall Ftg @ South Perimeter

Sheet 2 of 43

Page 3: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 3 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

1720 Form, Rebar Pour Wall Ftg @ South Perimeter 5 08JUN12 14JUN12 11

1740 Construct Retaining Wall @ South Perimeter 15 15JUN12 06JUL12 11

1760 Install Drainage & Waterproofing South Retaining 3 09JUL12 11JUL12 11

1780 Bkfl @ South Perimeter Retaining Wall 2 12JUL12 13JUL12 11

1800 Install Chain Link Fence @ South Retaining Wall 5 16JUL12 20JUL12 11

Retaining Walls @ Bus Drop-off 1900 Excav. for Wall Ftgs @ Bus Drop-off 3 16JUL12 18JUL12 142

1920 Form, Rebar Pour Wall Ftgs @ Bus Drop-off 4 17JUL12 20JUL12 142

1940 Construct Retaining Walls @ Bus Drop-off 12 23JUL12 07AUG12 142

1960 Install Drainage & Waterproofing @ Bus Drop-off 3 08AUG12 10AUG12 142

1980 Bkfl @ Bus Drop-off Retaining Walls 2 13AUG12 14AUG12 142

Paving / Hardscape / Fence & ScreensPaving 2000 Final Grade @ Parking Lots 2 22MAR13 25MAR13 52

2120 Rough-in Site Lighting - Parking Lots 3 26MAR13 28MAR13 72

2020 Install Curbs & Gutters - Parking Lots 8 26MAR13 04APR13 52

2040 Install Base @ Parking Lots 3 05APR13 09APR13 57

2140 Install Site Lighting - Parking Lots 4 05APR13 10APR13 67

2160 Install Concrete Flatwork @ Parking Lots 5 05APR13 11APR13 66

2060 Initial Asphalt Course @ Parking Lots 2 10APR13 11APR13 57

2080 Final Asphalt Lift @ Parking Lots 2 12APR13 15APR13 64

2090 Final Asphalt Lift @ Offsite Roadways 2 16APR13 17APR13 65

2100 Wheel Stops, Striping & Signage @ Parking Lot 3 16APR13 18APR13 64

Bus Drop-off 2200 Final Grade for Bus Drop-off 2 26MAR13 27MAR13 58

2320 Rough-in Site Lighting - Bus Drop-off 2 26MAR13 27MAR13 75

2220 Install Curbs & Gutters @ Bus Drop-off 6 05APR13 12APR13 52

2240 Install Base @ Bus Drop-off 2 15APR13 16APR13 52

2340 Install Site Lighting - Bus Drop-off 3 15APR13 17APR13 63

2360 Install Concrete Flatwork @ Bus Drop-off 5 15APR13 19APR13 61

2260 Intial Asphalt Course @ Bus Drop-off 2 17APR13 18APR13 52

2280 Final Asphalt Lift @ Bus Drop-off 2 19APR13 22APR13 52

2300 Striping & Signage @ Bus Drop-off 2 23APR13 24APR13 60

Admin / Multipurpose Area 3000 Fine Grade for Hardscape - Admin/MP Area 5 05FEB13 11FEB13 39

3010 Install Flagpole Footing 3 12FEB13 14FEB13 75

3020 Ftgs for Planters & Decorative Walls - Admin/MP 8 12FEB13 21FEB13 39

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Form, Rebar Pour Wall Ftg @ South Perimeter

Construct Retaining Wall @ South Perimeter

Install Drainage & Waterproofing South Retaining

Bkfl @ South Perimeter Retaining Wall

Install Chain Link Fence @ South Retaining Wall

Excav. for Wall Ftgs @ Bus Drop-off

Form, Rebar Pour Wall Ftgs @ Bus Drop-off

Construct Retaining Walls @ Bus Drop-off

Install Drainage & Waterproofing @ Bus Drop-off

Bkfl @ Bus Drop-off Retaining Walls

Final Grade @ Parking Lots

Rough-in Site Lighting - Parking LotsInstall Curbs & Gutters - Parking Lots

Install Base @ Parking Lots

Install Site Lighting - Parking LotsInstall Concrete Flatwork @ Parking Lots

Initial Asphalt Course @ Parking Lots

Final Asphalt Lift @ Parking LotsFinal Asphalt Lift @ Offsite Roadways

Wheel Stops, Striping & Signage @ Parking Lot

Final Grade for Bus Drop-off

Rough-in Site Lighting - Bus Drop-offInstall Curbs & Gutters @ Bus Drop-off

Install Base @ Bus Drop-off

Install Site Lighting - Bus Drop-offInstall Concrete Flatwork @ Bus Drop-off

Intial Asphalt Course @ Bus Drop-off

Final Asphalt Lift @ Bus Drop-offStriping & Signage @ Bus Drop-off

Fine Grade for Hardscape - Admin/MP Area

Install Flagpole Footing

Ftgs for Planters & Decorative Walls - Admin/MP

Sheet 3 of 43

Page 4: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 4 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

3040 Construct Planters & Decorative Walls - Admin/MP 15 12FEB13 04MAR13 50

3030 Construct H/C Ramp & Stairs - Admin/MP Area 12 22FEB13 11MAR13 39

3060 Set Utility Screen Supports - Admin/MP Area 5 12MAR13 18MAR13 40

3050 Set Covered Walkway Supports - Admin/MP Area 6 12MAR13 19MAR13 39

3070 Concrete Flatwork - Admin/MP Area 12 20MAR13 04APR13 39

3090 Install Flagpole 2 05APR13 08APR13 40

3080 Install Handrails - Admin/MP Area 3 05APR13 09APR13 39

3130 Install School Signs/Monuments 5 05APR13 11APR13 77

3110 Install W-I Fencing & Gates - Admin/MP Area 12 10APR13 25APR13 39

Kindergaten / Elem Classroom Area 3200 Fine Grade for Hardscape - Elem Area 3 04APR13 08APR13 25

3230 Construct Planters Footings- Elem Area 5 09APR13 15APR13 25

3250 Set Covered Walkway Supports - Elem Area 5 09APR13 15APR13 37

3260 Set Utility Screen Supports - Elem Area 5 09APR13 15APR13 37

3240 Construct Planters - Elem Area 12 16APR13 01MAY13 25

3270 Concrete Flatwork - Elem Area 10 02MAY13 15MAY13 25

3280 Install Bike Rack 2 16MAY13 17MAY13 33

3310 Install W-I Fencing & Gates - Elem Area 10 16MAY13 30MAY13 25

Middle School Classroom Area 3400 Fine Grade for Hardscape - Middle School Area 5 14JAN13 18JAN13 50

3450 Set Covered Walkway Supports -Middle School Area 6 21JAN13 28JAN13 69

3460 Set Utility Screen Supports - Middle School Area 7 21JAN13 29JAN13 68

3430 Construct Planter Footings - Middle School Area 10 21JAN13 01FEB13 50

3440 Construct Planters - Middle School Area 15 04FEB13 22FEB13 50

3470 Concrete Flatwork - Middle School Area 12 25FEB13 12MAR13 50

3480 Install Bike Rack 2 13MAR13 14MAR13 89

3510 Install W-I Fencing & Gates - Middle School Area 10 31MAY13 13JUN13 25

Play Areas 3800 Fine Grade for Hardscape - Play Areas 3 13MAR13 15MAR13 50

3810 Construct Ball Wall Footings 5 18MAR13 22MAR13 60

3840 Install Footings for Playground Equipment 5 18MAR13 22MAR13 73

3820 Construct Ball Walls 15 18MAR13 05APR13 50

3870 Concrete Flatwork - Play Areas 10 08APR13 19APR13 50

3890 Asphalt Paving - Play Areas 3 22APR13 24APR13 50

3910 Install Playground Equipment 10 25APR13 08MAY13 50

Play Fields 4000 Fine Grade @ Play Fields 8 01FEB13* 12FEB13 41

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Construct Planters & Decorative Walls - Admin/MPConstruct H/C Ramp & Stairs - Admin/MP Area

Set Utility Screen Supports - Admin/MP Area

Set Covered Walkway Supports - Admin/MP Area

Concrete Flatwork - Admin/MP Area

Install Flagpole

Install Handrails - Admin/MP Area

Install School Signs/MonumentsInstall W-I Fencing & Gates - Admin/MP Area

Fine Grade for Hardscape - Elem Area

Construct Planters Footings- Elem Area

Set Covered Walkway Supports - Elem Area

Set Utility Screen Supports - Elem Area

Construct Planters - Elem Area

Concrete Flatwork - Elem Area

Install Bike RackInstall W-I Fencing & Gates - Elem Area

Fine Grade for Hardscape - Middle School Area

Set Covered Walkway Supports -Middle School Area

Set Utility Screen Supports - Middle School Area

Construct Planter Footings - Middle School Area

Construct Planters - Middle School AreaConcrete Flatwork - Middle School Area

Install Bike RackInstall W-I Fencing & Gates - Middle School Area

Fine Grade for Hardscape - Play Areas

Construct Ball Wall FootingsInstall Footings for Playground Equipment

Construct Ball Walls

Concrete Flatwork - Play Areas

Asphalt Paving - Play Areas

Install Playground Equipment

Fine Grade @ Play Fields

Sheet 4 of 43

Page 5: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 5 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

4040 Install Footings for Play Field Equipment 5 13FEB13 19FEB13 41

4020 Irrigation @ Play Fields 6 13FEB13 20FEB13 50

4070 Concrete Flatwork - Play Fields 10 13FEB13 26FEB13 46

4110 Install Play Field Equipment 10 20FEB13 05MAR13 41

4030 Seeding @ Play Fields 5 06MAR13 12MAR13 41

4050 Landscaping Maintenance @ Play Fields 90 13MAR13 18JUL13 41

4090 Plants & Trees @ Play Fields 8 15MAY13 24MAY13 78

Fencing, Irrigation & Landscaping 4200 Install Chain Link Fencing 10 12APR13 25APR13 79

4220 Install Irrigation @ Campus Areas 12 14JUN13 01JUL13 33

4240 Landscaping @ Campus Area 20 02JUL13 30JUL13 33

SignageSignage 4600 Signage - Buildings & Site 10 02MAY13 15MAY13 45

Bldg. A - MultipurposeMilestones 5000 Start Building A - Multipurpose 0 09APR12 0

5010 Building A - Multipurpose Duration 324* 09APR12 19JUL13 0

9990 Building A - Multipurpose Complete 0 19JUL13 0

Foundations / Underground 5100 Excavate Footings 6 09APR12 16APR12 0

5120 Rebar Footings & Stem Walls 12 11APR12 26APR12 0

5160 Form Footings & Stem Walls 10 17APR12 30APR12 3

5180 Install Electrical Sleeves & Stub-ups 5 24APR12 30APR12 4

5200 Install Plumbing Sleeves & Stub-ups 5 24APR12 30APR12 4

5320 Install Mechanical Sleeves & Stub-ups 5 24APR12 30APR12 4

5140 Layout / Install Anchor Bolts 6 27APR12 04MAY12 0

5220 Pour Footings & Stem Walls 5 07MAY12 11MAY12 0

5240 Strip Forms 5 14MAY12 18MAY12 0

5260 Install Underslab Plumbing 10 14MAY12 25MAY12 11

5280 Install Underslab Electrical Conduits 12 17MAY12 04JUN12 11

Structure / Slab-on-Grade 5500 Construct Initial CMU Courses for Slabs-on-Grade 15 21MAY12 11JUN12 0

5520 Bkfl/Compact at Initial CMU Courses 6 12JUN12 19JUN12 0

5540 Vapor Barrier & Sand @ Slabs-on-Grade 4 20JUN12 25JUN12 0

5560 Rebar for Slabs-on-grade 6 26JUN12 03JUL12 0

5580 Pour Slabs-on-Grade 3 05JUL12 09JUL12 0

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Footings for Play Field Equipment

Irrigation @ Play Fields

Concrete Flatwork - Play Fields

Install Play Field Equipment

Seeding @ Play FieldsLandscaping Maintenance @ Play Fields

Plants & Trees @ Play Fields

Install Chain Link FencingInstall Irrigation @ Campus Areas

Landscaping @ Campus Area

Signage - Buildings & Site

Start Building A - Multipurpose

Building A - Multipurpose DurationBuilding A - Multipurpose Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves & Stub-ups

Install Plumbing Sleeves & Stub-ups

Install Mechanical Sleeves & Stub-ups

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Construct Initial CMU Courses for Slabs-on-Grade

Bkfl/Compact at Initial CMU Courses

Vapor Barrier & Sand @ Slabs-on-Grade

Rebar for Slabs-on-grade

Pour Slabs-on-Grade

Sheet 5 of 43

Page 6: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 6 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

5600 Construct CMU Walls to Full Height 50 10JUL12 19SEP12 0

5620 Scaffolding for CMU 3 13JUL12 17JUL12 44

5640 Set Frames @ CMU Walls 5 13JUL12 19JUL12 42

5610 Install Steel in Masonry Walls 10 14AUG12 27AUG12 15

5650 Set Embeds @ CMU Walls 6 12SEP12 19SEP12 0

5660 Erect. Align & Weld-out Structural Steel 15 20SEP12 10OCT12 0

5680 Install & Weld Steel Decks 8 11OCT12 22OCT12 0

5720 Install Deck Penetrations 3 23OCT12 25OCT12 0

5700 Rebar & Pour @ Blockouts @ Structural Steel 3 23OCT12 25OCT12 32

5740 Install Plywood Roof Sheathing 5 26OCT12 01NOV12 0

Exterior 6000 Exterior Framing 20 26OCT12 27NOV12 32

6020 Set Roof Curbs 4 30OCT12 02NOV12 36

6060 Install Drain & Plumbing Risers 5 02NOV12 08NOV12 44

6040 Set HVAC Units 3 05NOV12 07NOV12 50

6080 Plywood Wall Sheathing 8 16NOV12 29NOV12 32

6100 Install Window Frames 8 28NOV12 07DEC12 43

6120 Install Storefronts 12 28NOV12 13DEC12 39

6160 Install Exterior Door Frames 4 30NOV12 05DEC12 45

6140 Insulation Board / Flashing 5 30NOV12 06DEC12 32

6180 Install Roofing System 5 07DEC12 13DEC12 32

6220 Flashings & Sealants 6 07DEC12 14DEC12 41

6200 Glazing 5 14DEC12 20DEC12 44

6240 Lath & Flashing for Plaster 10 14DEC12 28DEC12 39

6260 Install Metal Roof 10 14DEC12 28DEC12 32

6400 Install Solatubes / Flashing 8 31DEC12 10JAN13 89

6280 Plaster 25 31DEC12 04FEB13 39

6340 Paint @ Exterior 5 05FEB13 11FEB13 102

Rough-ins 6500 Install MEP Hangers 5 02NOV12 08NOV12 0

6520 Layout & Install Top Track 5 09NOV12 16NOV12 0

6540 Insulation @ Metal Decks 6 19NOV12 28NOV12 21

6560 Interior Framing 30 19NOV12 03JAN13 0

6580 Rough-in Fire Sprinkler Mains 10 29NOV12 12DEC12 21

6600 Rough-in Overhead Plumbing 5 13DEC12 19DEC12 21

6620 Rough-in Fire Suppression System 4 04JAN13 09JAN13 21

6640 Set Interior Door & Window Frames 6 04JAN13 11JAN13 23

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Construct CMU Walls to Full Height

Scaffolding for CMU

Set Frames @ CMU Walls

Install Steel in Masonry Walls

Set Embeds @ CMU Walls

Erect. Align & Weld-out Structural Steel

Install & Weld Steel Decks

Install Deck Penetrations

Rebar & Pour @ Blockouts @ Structural Steel

Install Plywood Roof Sheathing

Exterior Framing

Set Roof Curbs

Install Drain & Plumbing Risers

Set HVAC Units

Plywood Wall Sheathing

Install Window Frames

Install Storefronts

Install Exterior Door Frames

Insulation Board / Flashing

Install Roofing System

Flashings & Sealants

Glazing

Lath & Flashing for Plaster

Install Metal Roof

Install Solatubes / Flashing

Plaster

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Metal Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Rough-in Fire Suppression System

Set Interior Door & Window Frames

Sheet 6 of 43

Page 7: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 7 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

6660 Rough-in In-Wall Plumbing 12 04JAN13 21JAN13 13

6680 R-I Overhead Mechanical Units, Piping & Ducts 15 04JAN13 24JAN13 12

6700 Rough-in In-wall Electrical 25 04JAN13 07FEB13 0

6720 Rough-in Overhead Electrical Conduits 12 11JAN13 28JAN13 12

6740 Install In-wall Insulation 4 08FEB13 13FEB13 0

Interior Finishes 7000 Plywood @ Electrical Room 2 14FEB13 15FEB13 54

7020 Drywall 12 14FEB13 01MAR13 0

7040 Tape & Finish Drywall 20 15FEB13 14MAR13 0

7060 Install Cold Storage Room 10 04MAR13 15MAR13 28

7080 Ceramic Tile 15 04MAR13 22MAR13 65

7120 Set Panelboards 3 15MAR13 19MAR13 35

7140 Install Countertop Roll-up Doors 5 15MAR13 21MAR13 29

7050 Veneer Plaster @ Hard Lid Ceilings 10 15MAR13 28MAR13 0

7220 Pull wires & Terminate 10 20MAR13 02APR13 35

7100 Prime Paint 4 27MAR13 01APR13 0

7720 Grind, Seal & Stripe Concrete Floors 20 29MAR13 25APR13 36

7180 Install Stainless Steel Wall Panels @ Kitchen 4 02APR13 05APR13 10

7160 Install T-Bar Grid 4 02APR13 05APR13 32

7200 Install Platform Folding Panel 5 02APR13 08APR13 17

7240 Install Cabinetry & Casework 10 02APR13 15APR13 0

7260 Install Ventilation Hoods @ Kitchen 3 08APR13 10APR13 10

7840 Install Solatube Drops & Diffusers 4 08APR13 11APR13 44

7280 Install Fire Sprinkler Drops & Heads 5 08APR13 12APR13 43

7300 Install Mechanical Drops, Grills & Registers 6 08APR13 15APR13 42

7340 Install Lighting & L.V. Electrical Devices 12 08APR13 23APR13 32

7270 Finish Fire Suppression System 2 11APR13 12APR13 18

7320 Install Welded Seam Resilient Flooring @ Kitchen 10 11APR13 24APR13 10

7360 Install Fiberglass Reinforced Panels 2 16APR13 17APR13 10

7380 Install Tack Wall / Vinyl Wall Panels 3 16APR13 18APR13 9

7400 Hang Doors 7 16APR13 24APR13 0

7440 Install Acoustical Ceiling Panels 2 24APR13 25APR13 36

7460 Install Gynasium Equipment 6 24APR13 01MAY13 32

7420 Interior Glazing 5 25APR13 01MAY13 0

7450 Install Door Hardware 5 25APR13 01MAY13 42

7500 Install Acoustical Wall Panels 3 02MAY13 06MAY13 39

7480 Finish Paint 5 02MAY13 08MAY13 0

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Rough-in In-Wall Plumbing

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in In-wall Electrical

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Plywood @ Electrical Room

Drywall

Tape & Finish Drywall

Install Cold Storage Room

Ceramic Tile

Set Panelboards

Install Countertop Roll-up Doors

Veneer Plaster @ Hard Lid Ceilings

Pull wires & Terminate

Prime PaintGrind, Seal & Stripe Concrete Floors

Install Stainless Steel Wall Panels @ Kitchen

Install T-Bar Grid

Install Platform Folding Panel

Install Cabinetry & Casework

Install Ventilation Hoods @ Kitchen

Install Solatube Drops & DiffusersInstall Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Finish Fire Suppression SystemInstall Welded Seam Resilient Flooring @ Kitchen

Install Fiberglass Reinforced Panels

Install Tack Wall / Vinyl Wall Panels

Hang Doors

Install Acoustical Ceiling Panels

Install Gynasium Equipment

Interior Glazing

Install Door Hardware

Install Acoustical Wall Panels

Finish Paint

Sheet 7 of 43

Page 8: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 8 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

7820 Install Gynasium Bleachers 10 02MAY13 15MAY13 32

7540 Install Projection Screens / Projector Mounts 2 09MAY13 10MAY13 35

7740 Install Roof Ladder & Hatch 2 09MAY13 10MAY13 35

7560 Install Drinking Fountains 2 09MAY13 10MAY13 38

7580 Install Stage Curtain 4 09MAY13 14MAY13 36

7660 Finish Mechanical Controls 5 09MAY13 15MAY13 10

7680 Finish Electrical 5 09MAY13 15MAY13 10

7600 Install Handrails 5 09MAY13 15MAY13 32

7620 Install Plumbing Fixtures 6 09MAY13 16MAY13 32

7640 Install Flooring 10 09MAY13 22MAY13 27

7700 Install Kitchen & Serving Equipment 15 09MAY13 30MAY13 0

7760 Toilet Partitions & Accessories 2 17MAY13 20MAY13 32

7780 Touch-up Paint 3 23MAY13 28MAY13 27

Clean-up / Punchlist 9960 Clean-Up Bldg. A 3 29MAY13 31MAY13 27

9940 Start-up & Test Systems 10 31MAY13 13JUN13 0

9950 Commissioning 15 14JUN13 05JUL13 0

9980 Punchlist Bldg. A 10 08JUL13 19JUL13 0

Bldg. B - Administration - Middle SchoolMilestones 10000 Start Bldg. B - Middle School Administration 0 16APR12 25

10010 Bldg. B - Middle School Administration Duration 238* 16APR12 26MAR13 25

14990 Bldg. B - Middle School Administration Complete 0 26MAR13 25

Foundations / Underground 10100 Excavate Footings 5 16APR12 20APR12 25

10120 Rebar Footings & Stem Walls 10 17APR12 30APR12 25

10160 Form Footings & Stem Walls 8 26APR12 07MAY12 25

10140 Layout / Install Anchor Bolts 5 02MAY12 08MAY12 25

10180 Install Electrical Sleeves 2 04MAY12 07MAY12 26

10200 Install Plumbing Sleeves 2 04MAY12 07MAY12 26

10320 Install Mechanical Sleeves 2 04MAY12 07MAY12 26

10220 Pour Footings & Stem Walls 5 09MAY12 15MAY12 25

10240 Strip Forms 3 16MAY12 18MAY12 32

10260 Install Underslab Plumbing 10 16MAY12 30MAY12 25

10280 Install Underslab Electrical Conduits 12 21MAY12 06JUN12 25

Structure / Slab-on-Grade 10520 Bkfl/Compact at Stem Walls 5 21MAY12 25MAY12 32

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Gynasium BleachersInstall Projection Screens / Projector Mounts

Install Roof Ladder & Hatch

Install Drinking Fountains

Install Stage Curtain

Finish Mechanical Controls

Finish Electrical

Install Handrails

Install Plumbing Fixtures

Install FlooringInstall Kitchen & Serving Equipment

Toilet Partitions & Accessories

Touch-up Paint

Clean-Up Bldg. A

Start-up & Test Systems

Commissioning

Punchlist Bldg. A

Start Bldg. B - Middle School Administration

Bldg. B - Middle School Administration DurationBldg. B - Middle School Administration Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Layout / Install Anchor Bolts

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Sheet 8 of 43

Page 9: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 9 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

10540 Vapor Barrier & Sand @ Slabs-on-Grade 3 07JUN12 11JUN12 25

10560 Rebar for Slabs-on-grade 6 12JUN12 19JUN12 25

10580 Pour Slabs-on-Grade 3 20JUN12 22JUN12 25

10660 Erect. Align & Weld-out Structural Steel 15 25JUN12 16JUL12 25

10620 Wall Framing 18 17JUL12 09AUG12 25

10680 Roof Framing 12 02AUG12 17AUG12 25

10740 Install Plywood Roof Sheathing 8 20AUG12 29AUG12 25

Exterior 11050 Set Switchgear 2 25JUN12 26JUN12 106

11000 Exterior Framing 15 20AUG12 11SEP12 43

11020 Set Roof Curbs 4 22AUG12 27AUG12 40

11040 Set HVAC Units 2 28AUG12 29AUG12 55

11080 Plywood Wall Sheathing 10 29AUG12 13SEP12 43

11060 Install Drain & Plumbing Risers 2 30AUG12 31AUG12 50

11100 Install Window Frames 10 12SEP12 25SEP12 95

11120 Install Storefronts 10 12SEP12 25SEP12 95

11140 Insulation Board 3 14SEP12 18SEP12 43

11160 Install Exterior Door Frames 4 14SEP12 19SEP12 99

11180 Install Roofing System 6 19SEP12 26SEP12 43

11220 Flashings & Sealants 6 19SEP12 26SEP12 53

11200 Glazing 5 26SEP12 02OCT12 98

11240 Lath & Flashing for Plaster 8 26SEP12 05OCT12 95

11260 Install Metal Roof 10 27SEP12 10OCT12 43

11280 Plaster 25 08OCT12 09NOV12 95

11400 Install Solatubes 4 11OCT12 16OCT12 100

11340 Paint @ Exterior 4 13NOV12 16NOV12 103

Rough-ins 11500 Install MEP Hangers 3 30AUG12 03SEP12 25

11520 Layout & Install Top Track 4 04SEP12 11SEP12 25

11540 Insulation @ Metal Decks 4 12SEP12 17SEP12 27

11560 Interior Framing 20 12SEP12 09OCT12 25

11580 Rough-in Fire Sprinkler Mains 10 18SEP12 01OCT12 27

11600 Rough-in Overhead Plumbing 6 02OCT12 09OCT12 27

11640 Set Interior Door & Window Frames 8 10OCT12 19OCT12 36

11680 R-I Overhead Mechanical Units, Piping & Ducts 12 10OCT12 25OCT12 27

11660 Rough-in In-wall Plumbing 12 10OCT12 25OCT12 28

11700 Rough-in In-wall Electrical 15 10OCT12 30OCT12 25

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Vapor Barrier & Sand @ Slabs-on-Grade

Rebar for Slabs-on-grade

Pour Slabs-on-Grade

Erect. Align & Weld-out Structural Steel

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Set Switchgear

Exterior Framing

Set Roof Curbs

Set HVAC Units

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Install Storefronts

Insulation Board

Install Exterior Door Frames

Install Roofing System

Flashings & Sealants

Glazing

Lath & Flashing for Plaster

Install Metal Roof

Plaster

Install Solatubes

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Metal Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Set Interior Door & Window Frames

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in In-wall Plumbing

Rough-in In-wall Electrical

Sheet 9 of 43

Page 10: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 10 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

11720 Rough-in Overhead Electrical Conduits 12 17OCT12 01NOV12 27

11740 Install In-wall Insulation 4 31OCT12 05NOV12 25

Interior Finishes 12000 Plywood @ Electrical Room 2 06NOV12 07NOV12 64

12020 Drywall 12 06NOV12 26NOV12 25

12040 Tape & Finish Drywall 15 09NOV12 04DEC12 25

12080 Ceramic Tile 12 27NOV12 12DEC12 80

12120 Set Panelboards 2 05DEC12 06DEC12 48

12100 Prime Paint 4 05DEC12 10DEC12 25

12220 Pull wires & Terminate 10 07DEC12 20DEC12 48

12160 Install T-Bar Grid 4 11DEC12 14DEC12 64

12240 Install Cabinetry & Casework 15 11DEC12 02JAN13 25

12280 Install Fire Sprinkler Drops & Heads 6 17DEC12 24DEC12 68

12300 Install Mechanical Drops, Grills & Registers 6 17DEC12 24DEC12 68

12840 Install Solatube Drops & Diffusers 6 17DEC12 24DEC12 68

12340 Install Lighting & L.V. Electrical Devices 10 21DEC12 07JAN13 60

12380 Install Tack Wall / Vinyl Wall Panels 3 03JAN13 07JAN13 33

12400 Hang Doors 6 03JAN13 10JAN13 25

12440 Install Acoustical Ceiling Panels 2 08JAN13 09JAN13 60

12420 Interior Glazing 5 11JAN13 17JAN13 25

12450 Install Door Hardware 6 11JAN13 18JAN13 59

12480 Finish Paint 5 18JAN13 24JAN13 25

12560 Install Drinking Fountains 2 25JAN13 28JAN13 56

12540 Install Projection Screens / Projector Mounts 3 25JAN13 29JAN13 52

12740 Install Roof Ladder & Hatch 4 25JAN13 30JAN13 51

12620 Install Plumbing Fixtures 5 25JAN13 31JAN13 51

12660 Finish Mechanical Controls 6 25JAN13 01FEB13 27

12640 Install Flooring 6 25JAN13 01FEB13 49

12680 Finish Electrical 8 25JAN13 05FEB13 25

12760 Toilet Partitions & Accessories 2 01FEB13 04FEB13 51

12780 Touch-up Paint 3 06FEB13 08FEB13 47

Clean-up / Punchlist 14940 Start-up & Test Systems 10 06FEB13 19FEB13 25

14960 Clean-Up Bldg. B 3 11FEB13 13FEB13 47

14950 Commissioning 15 20FEB13 12MAR13 25

14980 Punchlist Bldg. B 10 13MAR13 26MAR13 25

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Plywood @ Electrical Room

Drywall

Tape & Finish Drywall

Ceramic Tile

Set Panelboards

Prime Paint

Pull wires & Terminate

Install T-Bar Grid

Install Cabinetry & Casework

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Solatube Drops & Diffusers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Hang Doors

Install Acoustical Ceiling Panels

Interior Glazing

Install Door Hardware

Finish Paint

Install Drinking Fountains

Install Projection Screens / Projector Mounts

Install Roof Ladder & Hatch

Install Plumbing Fixtures

Finish Mechanical Controls

Install Flooring

Finish Electrical

Toilet Partitions & Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. B

Commissioning

Punchlist Bldg. B

Sheet 10 of 43

Page 11: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 11 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Bldg. C - ClassroomMilestones 15000 Start Bldg. C Middle School Classroom 0 30APR12 45

15010 Bldg. C Middle School Classroom Duration 193* 30APR12 05FEB13 38

19990 Bldg. C - Middle School Classroom Complete 0 05FEB13 38

Foundations / Underground 15100 Excavate Footings 4 30APR12 03MAY12 70

15120 Rebar Footings & Stem Walls 8 01MAY12 10MAY12 70

15160 Form Footings & Stem Walls 5 08MAY12 14MAY12 71

15180 Install Electrical Sleeves 2 11MAY12 14MAY12 72

15200 Install Plumbing Sleeves 2 11MAY12 14MAY12 72

15320 Install Mechanical Sleeves 2 11MAY12 14MAY12 72

15140 Layout / Install Anchor Bolts 4 11MAY12 16MAY12 70

15220 Pour Footings & Stem Walls 4 17MAY12 22MAY12 70

15240 Strip Forms 2 23MAY12 24MAY12 74

15260 Install Underslab Plumbing 3 23MAY12 25MAY12 70

15300 Install Underslab Mechanical Piping 3 23MAY12 25MAY12 76

15280 Install Underslab Electrical Conduits 6 29MAY12 05JUN12 70

Structure / Slab-on-Grade 15520 Bkfl/Compact at Stem Walls 3 25MAY12 30MAY12 74

15540 Vapor Barrier & Sand @ Slab-on-Grade 2 06JUN12 07JUN12 70

15560 Rebar for Slab-on-grade 4 08JUN12 13JUN12 70

15580 Pour Slab-on-Grade 3 14JUN12 18JUN12 70

15620 Wall Framing 12 19JUN12 05JUL12 70

15680 Roof Framing 6 03JUL12 11JUL12 70

15740 Install Plywood Roof Sheathing 5 12JUL12 18JUL12 70

15600 Form & Pour Mechanical & Electrical Pads 3 26JUL12 30JUL12 80

Exterior 16000 Exterior Framing 8 12JUL12 23JUL12 80

16020 Set Solatube Curbs 2 16JUL12 17JUL12 80

16080 Plywood Wall Sheathing 6 18JUL12 25JUL12 80

16060 Install Drain & Plumbing Risers 2 19JUL12 20JUL12 92

16100 Install Window Frames 12 24JUL12 08AUG12 106

16140 Insulation Board 3 26JUL12 30JUL12 89

16160 Install Exterior Door Frames 4 26JUL12 31JUL12 112

16220 Flashings & Sealants 6 26JUL12 02AUG12 90

16040 Set HVAC Units 2 31JUL12 01AUG12 80

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Start Bldg. C Middle School Classroom

Bldg. C Middle School Classroom Duration

Bldg. C - Middle School Classroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Mechanical Piping

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Solatube Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Sheet 11 of 43

Page 12: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 12 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

16050 Set Switchgear 2 31JUL12 01AUG12 81

16260 Install Metal Roof 4 31JUL12 03AUG12 89

16400 Install Solatubes 4 06AUG12 09AUG12 127

16200 Glazing 5 09AUG12 15AUG12 107

16240 Lath & Flashing for Plaster 6 09AUG12 16AUG12 106

16280 Plaster 25 17AUG12 24SEP12 106

16380 Construct Mechanical / Electrical Enclosures 8 25SEP12 04OCT12 106

16340 Paint @ Exterior 5 05OCT12 11OCT12 106

Rough-ins 16500 Install MEP Hangers 3 19JUL12 23JUL12 70

16520 Layout & Install Top Track 2 24JUL12 25JUL12 70

16540 Insulation @ Roof Decks 4 26JUL12 31JUL12 70

16560 Interior Framing 10 26JUL12 08AUG12 73

16580 Rough-in Fire Sprinkler Mains 6 01AUG12 08AUG12 70

16600 Rough-in Overhead Plumbing 3 09AUG12 13AUG12 70

16660 Rough-in In-wall Plumbing 4 09AUG12 14AUG12 80

16640 Set Interior Door & Window Frames 6 09AUG12 16AUG12 80

16700 Rough-in In-wall Electrical 10 09AUG12 22AUG12 74

16680 R-I Overhead Mechanical Units, Piping & Ducts 12 14AUG12 29AUG12 70

16720 Rough-in Overhead Electrical Conduits 8 21AUG12 30AUG12 70

16740 Install In-wall Insulation 2 23AUG12 24AUG12 74

Interior Finishes 17020 Drywall 5 31AUG12 10SEP12 70

17040 Tape & Finish Drywall 8 03SEP12 14SEP12 70

17100 Prime Paint 4 13SEP12 18SEP12 70

17120 Set Panelboards 2 17SEP12 18SEP12 85

17160 Install T-Bar Grid 4 19SEP12 24SEP12 101

17220 Pull wires & Terminate 8 19SEP12 28SEP12 85

17240 Install Cabinetry & Casework 10 19SEP12 02OCT12 70

17840 Install Solatube Drops & Diffusers 4 25SEP12 28SEP12 105

17280 Install Fire Sprinkler Drops & Heads 5 25SEP12 01OCT12 104

17300 Install Mechanical Drops, Grills & Registers 6 25SEP12 02OCT12 103

17340 Install Lighting & L.V. Electrical Devices 8 01OCT12 10OCT12 97

17380 Install Tack Wall / Vinyl Wall Panels 3 03OCT12 05OCT12 75

17620 Install Sinks 4 03OCT12 08OCT12 109

17400 Hang Doors 5 03OCT12 09OCT12 70

17420 Interior Glazing 3 10OCT12 12OCT12 70

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Rough-in In-wall Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Prime Paint

Set Panelboards

Install T-Bar Grid

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Interior Glazing

Sheet 12 of 43

Page 13: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 13 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

17440 Install Acoustical Ceiling Panels 2 11OCT12 12OCT12 97

17480 Finish Paint 5 15OCT12 19OCT12 70

17540 Install Projection Screens / Projector Mounts 2 22OCT12 23OCT12 95

17560 Install Markerboards 2 22OCT12 23OCT12 95

17660 Finish Mechanical Controls 5 22OCT12 26OCT12 70

17680 Finish Electrical 5 22OCT12 26OCT12 70

17640 Polish Concrete Floor 5 22OCT12 26OCT12 92

17450 Install Door Hardware 5 11JAN13 17JAN13 38

17780 Touch-up Paint 3 18JAN13 22JAN13 38

Clean-up / Punchlist 19940 Start-up & Test Systems 10 29OCT12 09NOV12 70

19950 Commissioning 15 13NOV12 05DEC12 70

19960 Clean-Up Bldg. C 3 23JAN13 25JAN13 38

19980 Punchlist Bldg. C 10 23JAN13 05FEB13 38

Bldg. D - ClassroomMilestones 20000 Start Bldg. D Middle School Classroom 0 07MAY12 45

20010 Bldg. D Middle School Classroom Duration 161* 07MAY12 27DEC12 60

24990 Bldg. D - Middle School Classroom Complete 0 27DEC12 60

Foundations / Underground 20100 Excavate Footings 4 07MAY12 10MAY12 60

20120 Rebar Footings & Stem Walls 8 08MAY12 17MAY12 60

20160 Form Footings & Stem Walls 5 15MAY12 21MAY12 61

20180 Install Electrical Sleeves 2 18MAY12 21MAY12 62

20200 Install Plumbing Sleeves 2 18MAY12 21MAY12 62

20320 Install Mechanical Sleeves 2 18MAY12 21MAY12 62

20140 Layout / Install Anchor Bolts 4 18MAY12 23MAY12 60

20220 Pour Footings & Stem Walls 4 24MAY12 30MAY12 60

20240 Strip Forms 2 31MAY12 01JUN12 64

20300 Install Underslab Mechanical Piping 3 31MAY12 04JUN12 66

20260 Install Underslab Plumbing 5 31MAY12 06JUN12 60

20280 Install Underslab Electrical Conduits 6 05JUN12 12JUN12 60

Structure / Slab-on-Grade 20520 Bkfl/Compact at Stem Walls 3 04JUN12 06JUN12 64

20540 Vapor Barrier & Sand @ Slab-on-Grade 2 13JUN12 14JUN12 60

20560 Rebar for Slab-on-grade 4 15JUN12 20JUN12 60

20580 Pour Slab-on-Grade 3 21JUN12 25JUN12 60

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Acoustical Ceiling Panels

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Finish Mechanical Controls

Finish Electrical

Polish Concrete Floor

Install Door Hardware

Touch-up Paint

Start-up & Test Systems

Commissioning

Clean-Up Bldg. C

Punchlist Bldg. C

Start Bldg. D Middle School Classroom

Bldg. D Middle School Classroom Duration

Bldg. D - Middle School Classroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Mechanical Piping

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Sheet 13 of 43

Page 14: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 14 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

20660 Wall Framing 12 26JUN12 12JUL12 60

20680 Roof Framing 6 11JUL12 18JUL12 60

20740 Install Plywood Roof Sheathing 5 19JUL12 25JUL12 60

20600 Form & Pour Mechanical & Electrical Pads 3 02AUG12 06AUG12 70

Exterior 21000 Exterior Framing 8 19JUL12 30JUL12 70

21020 Set Solatube Curbs 2 23JUL12 24JUL12 70

21080 Plywood Wall Sheathing 6 25JUL12 01AUG12 70

21060 Install Drain & Plumbing Risers 2 26JUL12 27JUL12 82

21100 Install Window Frames 12 31JUL12 15AUG12 96

21140 Insulation Board 3 02AUG12 06AUG12 79

21160 Install Exterior Door Frames 4 02AUG12 07AUG12 102

21220 Flashings & Sealants 6 02AUG12 09AUG12 80

21040 Set HVAC Units 2 07AUG12 08AUG12 70

21050 Set Switchgear 2 07AUG12 08AUG12 71

21260 Install Metal Roof 4 07AUG12 10AUG12 79

21400 Install Solatubes 4 13AUG12 16AUG12 117

21200 Glazing 5 16AUG12 22AUG12 97

21240 Lath & Flashing for Plaster 6 16AUG12 23AUG12 96

21280 Plaster 25 24AUG12 01OCT12 96

21380 Construct Mechanical / Electrical Enclosures 8 02OCT12 11OCT12 96

21340 Paint @ Exterior 5 12OCT12 18OCT12 96

Rough-ins 21500 Install MEP Hangers 3 26JUL12 30JUL12 60

21520 Layout & Install Top Track 2 31JUL12 01AUG12 60

21540 Insulation @ Roof Decks 4 02AUG12 07AUG12 60

21560 Interior Framing 10 02AUG12 15AUG12 63

21580 Rough-in Fire Sprinkler Mains 6 08AUG12 15AUG12 60

21600 Rough-in Overhead Plumbing 3 16AUG12 20AUG12 60

21640 Set Interior Door & Window Frames 6 16AUG12 23AUG12 70

21660 Rough-in In-wall Plumbing 8 16AUG12 27AUG12 66

21700 Rough-in In-wall Electrical 10 16AUG12 29AUG12 64

21680 R-I Overhead Mechanical Units, Piping & Ducts 12 21AUG12 07SEP12 60

21720 Rough-in Overhead Electrical Conduits 8 28AUG12 10SEP12 60

21740 Install In-wall Insulation 2 30AUG12 31AUG12 64

Interior Finishes 22020 Drywall 5 11SEP12 17SEP12 60

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Solatube Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Plumbing

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Sheet 14 of 43

Page 15: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 15 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

22040 Tape & Finish Drywall 8 12SEP12 21SEP12 60

22080 Ceramic Tile 6 18SEP12 25SEP12 107

22100 Prime Paint 4 20SEP12 25SEP12 60

22120 Set Panelboards 2 24SEP12 25SEP12 75

22160 Install T-Bar Grid 4 26SEP12 01OCT12 91

22220 Pull wires & Terminate 8 26SEP12 05OCT12 75

22240 Install Cabinetry & Casework 10 26SEP12 09OCT12 60

22840 Install Solatube Drops & Diffusers 4 02OCT12 05OCT12 95

22280 Install Fire Sprinkler Drops & Heads 5 02OCT12 08OCT12 94

22300 Install Mechanical Drops, Grills & Registers 6 02OCT12 09OCT12 93

22340 Install Lighting & L.V. Electrical Devices 8 08OCT12 17OCT12 87

22380 Install Tack Wall / Vinyl Wall Panels 3 10OCT12 12OCT12 65

22260 Install Sinks 3 10OCT12 12OCT12 100

22400 Hang Doors 5 10OCT12 16OCT12 60

22420 Interior Glazing 3 17OCT12 19OCT12 60

22450 Install Door Hardware 5 17OCT12 23OCT12 90

22440 Install Acoustical Ceiling Panels 2 18OCT12 19OCT12 87

22480 Finish Paint 5 22OCT12 26OCT12 60

22540 Install Projection Screens / Projector Mounts 2 29OCT12 30OCT12 85

22560 Install Markerboards 2 29OCT12 30OCT12 85

22620 Install Plumbing Fixtures 4 29OCT12 01NOV12 84

22660 Finish Mechanical Controls 5 29OCT12 02NOV12 60

22680 Finish Electrical 5 29OCT12 02NOV12 60

22640 Polish Concrete Floor 5 29OCT12 02NOV12 82

22760 Toilet Accessories 2 02NOV12 05NOV12 84

22780 Touch-up Paint 3 05NOV12 07NOV12 82

Clean-up / Punchlist 24940 Start-up & Test Systems 10 05NOV12 19NOV12 60

24960 Clean-Up Bldg. D 3 08NOV12 13NOV12 82

24950 Commissioning 15 20NOV12 12DEC12 60

24980 Punchlist Bldg. D 10 13DEC12 27DEC12 60

Bldg. E - ClassroomMilestones 25000 Start Bldg. E Middle School Classroom 0 07MAY12 45

25010 Bldg. E Middle School Classroom Duration 161* 07MAY12 27DEC12 60

29990 Bldg. E - Middle School Classroom Complete 0 27DEC12 60

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Set Panelboards

Install T-Bar Grid

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Interior Glazing

Install Door Hardware

Install Acoustical Ceiling Panels

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Install Plumbing Fixtures

Finish Mechanical Controls

Finish Electrical

Polish Concrete Floor

Toilet Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. D

Commissioning

Punchlist Bldg. D

Start Bldg. E Middle School Classroom

Bldg. E Middle School Classroom Duration

Bldg. E - Middle School Classroom Complete

Sheet 15 of 43

Page 16: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 16 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Foundations / Underground 25100 Excavate Footings 4 07MAY12 10MAY12 60

25120 Rebar Footings & Stem Walls 8 08MAY12 17MAY12 60

25160 Form Footings & Stem Walls 5 15MAY12 21MAY12 61

25180 Install Electrical Sleeves 2 18MAY12 21MAY12 62

25200 Install Plumbing Sleeves 2 18MAY12 21MAY12 62

25320 Install Mechanical Sleeves 2 18MAY12 21MAY12 62

25140 Layout / Install Anchor Bolts 4 18MAY12 23MAY12 60

25220 Pour Footings & Stem Walls 4 24MAY12 30MAY12 60

25240 Strip Forms 2 31MAY12 01JUN12 64

25260 Install Underslab Plumbing 3 31MAY12 04JUN12 60

25300 Install Underslab Mechanical Piping 3 31MAY12 04JUN12 66

25280 Install Underslab Electrical Conduits 6 05JUN12 12JUN12 60

Structure / Slab-on-Grade 25520 Bkfl/Compact at Stem Walls 3 04JUN12 06JUN12 64

25540 Vapor Barrier & Sand @ Slab-on-Grade 2 13JUN12 14JUN12 60

25560 Rebar for Slab-on-grade 4 15JUN12 20JUN12 60

25580 Pour Slab-on-Grade 3 21JUN12 25JUN12 60

25660 Wall Framing 12 26JUN12 12JUL12 60

25680 Roof Framing 6 11JUL12 18JUL12 60

25740 Install Plywood Roof Sheathing 5 19JUL12 25JUL12 60

25600 Form & Pour Mechanical & Electrical Pads 3 02AUG12 06AUG12 70

Exterior 26000 Exterior Framing 8 19JUL12 30JUL12 70

26020 Set Solatube Curbs 2 23JUL12 24JUL12 70

26080 Plywood Wall Sheathing 6 25JUL12 01AUG12 70

26060 Install Drain & Plumbing Risers 2 26JUL12 27JUL12 82

26100 Install Window Frames 12 31JUL12 15AUG12 96

26140 Insulation Board 3 02AUG12 06AUG12 79

26160 Install Exterior Door Frames 4 02AUG12 07AUG12 102

26220 Flashings & Sealants 6 02AUG12 09AUG12 80

26040 Set HVAC Units 2 07AUG12 08AUG12 70

26050 Set Switchgear 2 07AUG12 08AUG12 71

26260 Install Metal Roof 4 07AUG12 10AUG12 79

26400 Install Solatubes 4 13AUG12 16AUG12 117

26200 Glazing 5 16AUG12 22AUG12 97

26240 Lath & Flashing for Plaster 6 16AUG12 23AUG12 96

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Mechanical Piping

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Solatube Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Sheet 16 of 43

Page 17: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 17 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

26280 Plaster 25 24AUG12 01OCT12 96

26380 Construct Mechanical / Electrical Enclosures 8 02OCT12 11OCT12 96

26340 Paint @ Exterior 5 12OCT12 18OCT12 96

Rough-ins 26500 Install MEP Hangers 3 26JUL12 30JUL12 60

26520 Layout & Install Top Track 2 31JUL12 01AUG12 60

26540 Insulation @ Roof Decks 4 02AUG12 07AUG12 60

26560 Interior Framing 10 02AUG12 15AUG12 63

26580 Rough-in Fire Sprinkler Mains 6 08AUG12 15AUG12 60

26600 Rough-in Overhead Plumbing 3 16AUG12 20AUG12 60

26660 Rough-in In-wall Plumbing 4 16AUG12 21AUG12 70

26640 Set Interior Door & Window Frames 6 16AUG12 23AUG12 70

26700 Rough-in In-wall Electrical 10 16AUG12 29AUG12 64

26680 R-I Overhead Mechanical Units, Piping & Ducts 12 21AUG12 07SEP12 60

26720 Rough-in Overhead Electrical Conduits 8 28AUG12 10SEP12 60

26740 Install In-wall Insulation 2 30AUG12 31AUG12 64

Interior Finishes 27020 Drywall 5 11SEP12 17SEP12 60

27040 Tape & Finish Drywall 8 12SEP12 21SEP12 60

27100 Prime Paint 4 20SEP12 25SEP12 60

27120 Set Panelboards 2 24SEP12 25SEP12 75

27160 Install T-Bar Grid 4 26SEP12 01OCT12 91

27220 Pull wires & Terminate 8 26SEP12 05OCT12 75

27240 Install Cabinetry & Casework 10 26SEP12 09OCT12 60

27840 Install Solatube Drops & Diffusers 4 02OCT12 05OCT12 95

27280 Install Fire Sprinkler Drops & Heads 5 02OCT12 08OCT12 94

27300 Install Mechanical Drops, Grills & Registers 6 02OCT12 09OCT12 93

27340 Install Lighting & L.V. Electrical Devices 8 08OCT12 17OCT12 87

27380 Install Tack Wall / Vinyl Wall Panels 3 10OCT12 12OCT12 65

27620 Install Sinks 4 10OCT12 15OCT12 99

27400 Hang Doors 5 10OCT12 16OCT12 60

27420 Interior Glazing 3 17OCT12 19OCT12 60

27450 Install Door Hardware 5 17OCT12 23OCT12 90

27440 Install Acoustical Ceiling Panels 2 18OCT12 19OCT12 87

27480 Finish Paint 5 22OCT12 26OCT12 60

27540 Install Projection Screens / Projector Mounts 2 29OCT12 30OCT12 85

27560 Install Markerboards 2 29OCT12 30OCT12 85

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Rough-in In-wall Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Prime Paint

Set Panelboards

Install T-Bar Grid

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Interior Glazing

Install Door Hardware

Install Acoustical Ceiling Panels

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Sheet 17 of 43

Page 18: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 18 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

27660 Finish Mechanical Controls 5 29OCT12 02NOV12 60

27680 Finish Electrical 5 29OCT12 02NOV12 60

27640 Polish Concrete Floor 5 29OCT12 02NOV12 82

27780 Touch-up Paint 3 05NOV12 07NOV12 82

Clean-up / Punchlist 29940 Start-up & Test Systems 10 05NOV12 19NOV12 60

29960 Clean-Up Bldg. E 3 08NOV12 13NOV12 82

29950 Commissioning 15 20NOV12 12DEC12 60

29980 Punchlist Bldg. E 10 13DEC12 27DEC12 60

Bldg. F - ClassroomMilestones 30000 Start Bldg. F Middle School Classroom 0 14MAY12 45

30010 Bldg. F Middle School Classroom Duration 161* 14MAY12 04JAN13 55

34990 Bldg. F - Middle School Classroom Complete 0 04JAN13 55

Foundations / Underground 30100 Excavate Footings 4 14MAY12 17MAY12 55

30120 Rebar Footings & Stem Walls 8 15MAY12 24MAY12 55

30160 Form Footings & Stem Walls 5 22MAY12 29MAY12 56

30180 Install Electrical Sleeves 2 25MAY12 29MAY12 57

30200 Install Plumbing Sleeves 2 25MAY12 29MAY12 57

30320 Install Mechanical Sleeves 2 25MAY12 29MAY12 57

30140 Layout / Install Anchor Bolts 4 25MAY12 31MAY12 55

30220 Pour Footings & Stem Walls 4 01JUN12 06JUN12 55

30240 Strip Forms 2 07JUN12 08JUN12 59

30260 Install Underslab Plumbing 3 07JUN12 11JUN12 55

30300 Install Underslab Mechanical Piping 3 07JUN12 11JUN12 61

30280 Install Underslab Electrical Conduits 6 12JUN12 19JUN12 55

Structure / Slab-on-Grade 30520 Bkfl/Compact at Stem Walls 3 11JUN12 13JUN12 59

30540 Vapor Barrier & Sand @ Slab-on-Grade 2 20JUN12 21JUN12 55

30560 Rebar for Slab-on-grade 4 22JUN12 27JUN12 55

30580 Pour Slab-on-Grade 3 28JUN12 02JUL12 55

30660 Wall Framing 12 03JUL12 19JUL12 55

30680 Roof Framing 6 18JUL12 25JUL12 55

30740 Install Plywood Roof Sheathing 5 26JUL12 01AUG12 55

30600 Form & Pour Mechanical & Electrical Pads 3 09AUG12 13AUG12 65

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Finish Mechanical Controls

Finish Electrical

Polish Concrete Floor

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. E

Commissioning

Punchlist Bldg. E

Start Bldg. F Middle School Classroom

Bldg. F Middle School Classroom Duration

Bldg. F - Middle School Classroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Mechanical Piping

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Sheet 18 of 43

Page 19: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 19 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Exterior 31000 Exterior Framing 8 26JUL12 06AUG12 65

31020 Set Solatube Curbs 2 30JUL12 31JUL12 65

31080 Plywood Wall Sheathing 6 01AUG12 08AUG12 65

31060 Install Drain & Plumbing Risers 2 02AUG12 03AUG12 77

31100 Install Window Frames 12 07AUG12 22AUG12 91

31140 Insulation Board 3 09AUG12 13AUG12 74

31160 Install Exterior Door Frames 4 09AUG12 14AUG12 97

31220 Flashings & Sealants 6 09AUG12 16AUG12 75

31040 Set HVAC Units 2 14AUG12 15AUG12 65

31050 Set Switchgear 2 14AUG12 15AUG12 66

31260 Install Metal Roof 4 14AUG12 17AUG12 74

31400 Install Solatubes 4 20AUG12 23AUG12 112

31200 Glazing 5 23AUG12 29AUG12 92

31240 Lath & Flashing for Plaster 6 23AUG12 30AUG12 91

31280 Plaster 25 31AUG12 08OCT12 91

31380 Construct Mechanical / Electrical Enclosures 8 09OCT12 18OCT12 91

31340 Paint @ Exterior 5 19OCT12 25OCT12 91

Rough-ins 31500 Install MEP Hangers 3 02AUG12 06AUG12 55

31520 Layout & Install Top Track 2 07AUG12 08AUG12 55

31540 Insulation @ Roof Decks 4 09AUG12 14AUG12 55

31560 Interior Framing 10 09AUG12 22AUG12 58

31580 Rough-in Fire Sprinkler Mains 6 15AUG12 22AUG12 55

31600 Rough-in Overhead Plumbing 3 23AUG12 27AUG12 55

31660 Rough-in In-wall Plumbing 4 23AUG12 28AUG12 65

31640 Set Interior Door & Window Frames 6 23AUG12 30AUG12 65

31700 Rough-in In-wall Electrical 10 23AUG12 07SEP12 59

31680 R-I Overhead Mechanical Units, Piping & Ducts 12 28AUG12 14SEP12 55

31720 Rough-in Overhead Electrical Conduits 8 04SEP12 17SEP12 55

31740 Install In-wall Insulation 2 10SEP12 11SEP12 59

Interior Finishes 32020 Drywall 5 18SEP12 24SEP12 55

32040 Tape & Finish Drywall 8 19SEP12 28SEP12 55

32100 Prime Paint 4 27SEP12 02OCT12 55

32120 Set Panelboards 2 01OCT12 02OCT12 70

32160 Install T-Bar Grid 4 03OCT12 08OCT12 86

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Exterior Framing

Set Solatube Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Rough-in In-wall Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Prime Paint

Set Panelboards

Install T-Bar Grid

Sheet 19 of 43

Page 20: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 20 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

32220 Pull wires & Terminate 8 03OCT12 12OCT12 70

32240 Install Cabinetry & Casework 10 03OCT12 16OCT12 55

32840 Install Solatube Drops & Diffusers 4 09OCT12 12OCT12 90

32280 Install Fire Sprinkler Drops & Heads 5 09OCT12 15OCT12 89

32300 Install Mechanical Drops, Grills & Registers 6 09OCT12 16OCT12 88

32340 Install Lighting & L.V. Electrical Devices 8 15OCT12 24OCT12 82

32380 Install Tack Wall / Vinyl Wall Panels 3 17OCT12 19OCT12 60

32620 Install Sinks 4 17OCT12 22OCT12 94

32400 Hang Doors 5 17OCT12 23OCT12 55

32420 Interior Glazing 3 24OCT12 26OCT12 55

32450 Install Door Hardware 5 24OCT12 30OCT12 85

32440 Install Acoustical Ceiling Panels 2 25OCT12 26OCT12 82

32480 Finish Paint 5 29OCT12 02NOV12 55

32540 Install Projection Screens / Projector Mounts 2 05NOV12 06NOV12 80

32560 Install Markerboards 2 05NOV12 06NOV12 80

32660 Finish Mechanical Controls 5 05NOV12 09NOV12 55

32680 Finish Electrical 5 05NOV12 09NOV12 55

32640 Polish Concrete Floor 5 05NOV12 09NOV12 77

32780 Touch-up Paint 3 13NOV12 15NOV12 77

Clean-up / Punchlist 34940 Start-up & Test Systems 10 13NOV12 28NOV12 55

34960 Clean-Up Bldg. F 3 16NOV12 20NOV12 77

34950 Commissioning 15 29NOV12 19DEC12 55

34980 Punchlist Bldg. F 10 20DEC12 04JAN13 55

Bldg. G- ClassroomMilestones 35000 Start Bldg. G Middle School Classroom 0 21MAY12 45

35010 Bldg. G Middle School Classroom Duration 161* 21MAY12 11JAN13 50

39990 Bldg. G - Middle School Classroom Complete 0 11JAN13 50

Foundations / Underground 35100 Excavate Footings 4 21MAY12 24MAY12 50

35120 Rebar Footings & Stem Walls 8 22MAY12 01JUN12 50

35160 Form Footings & Stem Walls 5 30MAY12 05JUN12 51

35180 Install Electrical Sleeves 2 04JUN12 05JUN12 52

35200 Install Plumbing Sleeves 2 04JUN12 05JUN12 52

35320 Install Mechanical Sleeves 2 04JUN12 05JUN12 52

35140 Layout / Install Anchor Bolts 4 04JUN12 07JUN12 50

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Interior Glazing

Install Door Hardware

Install Acoustical Ceiling Panels

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Finish Mechanical Controls

Finish Electrical

Polish Concrete Floor

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. F

Commissioning

Punchlist Bldg. F

Start Bldg. G Middle School Classroom

Bldg. G Middle School Classroom Duration

Bldg. G - Middle School Classroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Sheet 20 of 43

Page 21: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 21 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

35220 Pour Footings & Stem Walls 4 08JUN12 13JUN12 50

35240 Strip Forms 2 14JUN12 15JUN12 54

35300 Install Underslab Mechanical Piping 3 14JUN12 18JUN12 56

35260 Install Underslab Plumbing 5 14JUN12 20JUN12 50

35280 Install Underslab Electrical Conduits 6 19JUN12 26JUN12 50

Structure / Slab-on-Grade 35520 Bkfl/Compact at Stem Walls 3 18JUN12 20JUN12 54

35540 Vapor Barrier & Sand @ Slab-on-Grade 2 27JUN12 28JUN12 50

35560 Rebar for Slab-on-grade 4 29JUN12 05JUL12 50

35580 Pour Slab-on-Grade 3 06JUL12 10JUL12 50

35660 Wall Framing 12 11JUL12 26JUL12 50

35680 Roof Framing 6 25JUL12 01AUG12 50

35740 Install Plywood Roof Sheathing 5 02AUG12 08AUG12 50

35600 Form & Pour Mechanical & Electrical Pads 3 16AUG12 20AUG12 60

Exterior 36000 Exterior Framing 8 02AUG12 13AUG12 60

36020 Set Solatube Curbs 2 06AUG12 07AUG12 60

36080 Plywood Wall Sheathing 6 08AUG12 15AUG12 60

36060 Install Drain & Plumbing Risers 2 09AUG12 10AUG12 72

36100 Install Window Frames 12 14AUG12 29AUG12 86

36140 Insulation Board 3 16AUG12 20AUG12 69

36160 Install Exterior Door Frames 4 16AUG12 21AUG12 92

36220 Flashings & Sealants 6 16AUG12 23AUG12 70

36040 Set HVAC Units 2 21AUG12 22AUG12 60

36050 Set Switchgear 2 21AUG12 22AUG12 61

36260 Install Metal Roof 4 21AUG12 24AUG12 69

36400 Install Solatubes 4 27AUG12 30AUG12 107

36200 Glazing 5 30AUG12 07SEP12 87

36240 Lath & Flashing for Plaster 6 30AUG12 10SEP12 86

36280 Plaster 25 11SEP12 15OCT12 86

36380 Construct Mechanical / Electrical Enclosures 8 16OCT12 25OCT12 86

36340 Paint @ Exterior 5 26OCT12 01NOV12 86

Rough-ins 36500 Install MEP Hangers 3 09AUG12 13AUG12 50

36520 Layout & Install Top Track 2 14AUG12 15AUG12 50

36540 Insulation @ Roof Decks 4 16AUG12 21AUG12 50

36560 Interior Framing 10 16AUG12 29AUG12 53

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Pour Footings & Stem Walls

Strip Forms

Install Underslab Mechanical Piping

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Solatube Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Sheet 21 of 43

Page 22: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 22 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

36580 Rough-in Fire Sprinkler Mains 6 22AUG12 29AUG12 50

36600 Rough-in Overhead Plumbing 3 30AUG12 03SEP12 50

36640 Set Interior Door & Window Frames 6 30AUG12 10SEP12 60

36660 Rough-in In-wall Plumbing 8 30AUG12 12SEP12 56

36700 Rough-in In-wall Electrical 10 30AUG12 14SEP12 54

36680 R-I Overhead Mechanical Units, Piping & Ducts 12 04SEP12 21SEP12 50

36720 Rough-in Overhead Electrical Conduits 8 13SEP12 24SEP12 50

36740 Install In-wall Insulation 2 17SEP12 18SEP12 54

Interior Finishes 37020 Drywall 5 25SEP12 01OCT12 50

37040 Tape & Finish Drywall 8 26SEP12 05OCT12 50

37080 Ceramic Tile 6 02OCT12 09OCT12 97

37100 Prime Paint 4 04OCT12 09OCT12 50

37120 Set Panelboards 2 08OCT12 09OCT12 65

37160 Install T-Bar Grid 4 10OCT12 15OCT12 81

37220 Pull wires & Terminate 8 10OCT12 19OCT12 65

37240 Install Cabinetry & Casework 10 10OCT12 23OCT12 50

37840 Install Solatube Drops & Diffusers 4 16OCT12 19OCT12 85

37280 Install Fire Sprinkler Drops & Heads 5 16OCT12 22OCT12 84

37300 Install Mechanical Drops, Grills & Registers 6 16OCT12 23OCT12 83

37340 Install Lighting & L.V. Electrical Devices 8 22OCT12 31OCT12 77

37380 Install Tack Wall / Vinyl Wall Panels 3 24OCT12 26OCT12 55

37260 Install Sinks 3 24OCT12 26OCT12 90

37400 Hang Doors 5 24OCT12 30OCT12 50

37420 Interior Glazing 3 31OCT12 02NOV12 50

37450 Install Door Hardware 5 31OCT12 06NOV12 80

37440 Install Acoustical Ceiling Panels 2 01NOV12 02NOV12 77

37480 Finish Paint 5 05NOV12 09NOV12 50

37540 Install Projection Screens / Projector Mounts 2 13NOV12 14NOV12 75

37560 Install Markerboards 2 13NOV12 14NOV12 75

37620 Install Plumbing Fixtures 4 13NOV12 16NOV12 74

37660 Finish Mechanical Controls 5 13NOV12 19NOV12 50

37680 Finish Electrical 5 13NOV12 19NOV12 50

37640 Polish Concrete Floor 5 13NOV12 19NOV12 72

37760 Toilet Accessories 2 19NOV12 20NOV12 74

37780 Touch-up Paint 3 20NOV12 26NOV12 72

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Plumbing

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Set Panelboards

Install T-Bar Grid

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Interior Glazing

Install Door Hardware

Install Acoustical Ceiling Panels

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Install Plumbing Fixtures

Finish Mechanical Controls

Finish Electrical

Polish Concrete Floor

Toilet Accessories

Touch-up Paint

Sheet 22 of 43

Page 23: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 23 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Clean-up / Punchlist 39940 Start-up & Test Systems 10 20NOV12 05DEC12 50

39960 Clean-Up Bldg. G 3 27NOV12 29NOV12 72

39950 Commissioning 15 06DEC12 27DEC12 50

39980 Punchlist Bldg. G 10 28DEC12 11JAN13 50

Bldg. H - Exercise RoomsMilestones 40000 Start Bldg. H - Excercise Rooms 0 29MAY12 45

40010 Bldg. H - Excercise Rooms Duration 234* 29MAY12 01MAY13 45

44990 Bldg. H - Excercise Rooms Complete 0 01MAY13 45

Foundations / Underground 40100 Excavate Footings 5 29MAY12 04JUN12 45

40120 Rebar Footings & Stem Walls 12 08JUN12 25JUN12 45

40160 Form Footings & Stem Walls 10 18JUN12 29JUN12 45

40180 Install Electrical Sleeves 2 28JUN12 29JUN12 46

40200 Install Plumbing Sleeves 2 28JUN12 29JUN12 46

40320 Install Mechanical Sleeves 2 28JUN12 29JUN12 46

40140 Layout / Install Anchor Bolts 3 28JUN12 02JUL12 45

40220 Pour Footings & Stem Walls 5 03JUL12 10JUL12 45

40240 Strip Forms 2 11JUL12 12JUL12 56

40260 Install Underslab Plumbing 10 11JUL12 24JUL12 45

40280 Install Underslab Electrical Conduits 12 18JUL12 02AUG12 45

Structure / Slab-on-Grade 40520 Bkfl/Compact at Stem Walls 4 13JUL12 18JUL12 56

40540 Vapor Barrier & Sand @ Slabs-on-Grade 3 03AUG12 07AUG12 45

40560 Rebar for Slabs-on-grade 6 08AUG12 15AUG12 45

40580 Pour Slabs-on-Grade 3 16AUG12 20AUG12 45

40660 Erect. Align & Weld-out Structural Steel 12 21AUG12 07SEP12 45

40620 Wall Framing 18 10SEP12 03OCT12 45

40680 Roof Framing 15 26SEP12 16OCT12 45

40740 Install Plywood Roof Sheathing 7 17OCT12 25OCT12 45

Exterior 41000 Exterior Framing 12 17OCT12 01NOV12 53

41020 Set Roof Curbs 2 19OCT12 22OCT12 62

41040 Set HVAC Units 2 23OCT12 24OCT12 71

41080 Plywood Wall Sheathing 8 25OCT12 05NOV12 57

41060 Install Drain & Plumbing Risers 3 26OCT12 30OCT12 64

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Start-up & Test Systems

Clean-Up Bldg. G

Commissioning

Punchlist Bldg. G

Start Bldg. H - Excercise Rooms

Bldg. H - Excercise Rooms DurationBldg. H - Excercise Rooms Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slabs-on-Grade

Rebar for Slabs-on-grade

Pour Slabs-on-Grade

Erect. Align & Weld-out Structural Steel

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Exterior Framing

Set Roof Curbs

Set HVAC Units

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Sheet 23 of 43

Page 24: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 24 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

41100 Install Window Frames 8 02NOV12 14NOV12 55

41120 Install Storefronts 10 02NOV12 16NOV12 53

41140 Insulation Board 3 06NOV12 08NOV12 60

41160 Install Exterior Door Frames 4 06NOV12 09NOV12 57

41180 Install Roofing System 5 09NOV12 16NOV12 60

41220 Flashings & Sealants 6 09NOV12 19NOV12 67

41400 Install Solatubes 2 19NOV12 20NOV12 112

41200 Glazing 8 19NOV12 30NOV12 53

41240 Lath & Flashing for Plaster 8 19NOV12 30NOV12 53

41260 Install Metal Roof 8 19NOV12 30NOV12 60

41280 Plaster 25 03DEC12 08JAN13 53

41340 Paint @ Exterior 4 09JAN13 14JAN13 97

Rough-ins 41620 Rough-in Partition Track 3 10SEP12 12SEP12 97

41500 Install MEP Hangers 3 26OCT12 30OCT12 45

41520 Layout & Install Top Track 3 31OCT12 02NOV12 45

41540 Insulation @ Metal Decks 4 05NOV12 08NOV12 49

41560 Interior Framing 15 05NOV12 28NOV12 45

41580 Rough-in Fire Sprinkler Mains 6 09NOV12 19NOV12 49

41600 Rough-in Overhead Plumbing 3 20NOV12 26NOV12 49

41640 Set Interior Door & Window Frames 6 29NOV12 06DEC12 56

41660 Rough-in In-wall Plumbing 10 29NOV12 12DEC12 50

41680 R-I Overhead Mechanical Units, Piping & Ducts 12 29NOV12 14DEC12 47

41700 Rough-in In-wall Electrical 15 29NOV12 19DEC12 45

41720 Rough-in Overhead Electrical Conduits 10 06DEC12 19DEC12 47

41740 Install In-wall Insulation 2 20DEC12 21DEC12 45

Interior Finishes 42000 Plywood @ Electrical Room 2 24DEC12 26DEC12 77

42020 Drywall 10 24DEC12 08JAN13 45

42040 Tape & Finish Drywall 15 28DEC12 18JAN13 45

42080 Ceramic Tile 18 09JAN13 01FEB13 75

42100 Prime Paint 4 17JAN13 22JAN13 45

42120 Set Panelboards 2 21JAN13 22JAN13 61

42060 Install Moveable Partition Wall 2 21JAN13 22JAN13 65

42050 Veneer Plaster @ Hard Lid Ceilings 8 21JAN13 30JAN13 59

42160 Install T-Bar Grid 2 23JAN13 24JAN13 71

42240 Install Cabinetry & Casework 10 23JAN13 05FEB13 45

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Window Frames

Install Storefronts

Insulation Board

Install Exterior Door Frames

Install Roofing System

Flashings & Sealants

Install Solatubes

Glazing

Lath & Flashing for Plaster

Install Metal Roof

Plaster

Paint @ Exterior

Rough-in Partition Track

Install MEP Hangers

Layout & Install Top Track

Insulation @ Metal Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Plumbing

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in In-wall Electrical

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Plywood @ Electrical Room

Drywall

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Set Panelboards

Install Moveable Partition Wall

Veneer Plaster @ Hard Lid Ceilings

Install T-Bar Grid

Install Cabinetry & Casework

Sheet 24 of 43

Page 25: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 25 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

42220 Pull wires & Terminate 10 23JAN13 05FEB13 61

42840 Install Solatube Drops & Diffusers 4 25JAN13 30JAN13 75

42280 Install Fire Sprinkler Drops & Heads 5 25JAN13 31JAN13 74

42300 Install Mechanical Drops, Grills & Registers 5 25JAN13 31JAN13 74

42400 Hang Doors 6 06FEB13 13FEB13 45

42340 Install Lighting & L.V. Electrical Devices 8 06FEB13 15FEB13 63

42420 Interior Glazing 4 14FEB13 19FEB13 45

42450 Install Door Hardware 6 14FEB13 21FEB13 66

42440 Install Acoustical Ceiling Panels 2 18FEB13 19FEB13 63

42480 Finish Paint 6 20FEB13 27FEB13 45

42540 Install Markerboards 2 28FEB13 01MAR13 60

42740 Install Roof Ladder & Hatch 2 28FEB13 01MAR13 60

42560 Install Drinking Fountains 2 28FEB13 01MAR13 63

42640 Polish Concrete Floor 5 28FEB13 06MAR13 57

42620 Install Plumbing Fixtures 6 28FEB13 07MAR13 57

42660 Finish Mechanical Controls 7 28FEB13 08MAR13 48

42680 Finish Electrical 10 28FEB13 13MAR13 45

42760 Toilet Partitions & Accessories 2 08MAR13 11MAR13 57

42780 Touch-up Paint 3 14MAR13 18MAR13 52

Clean-up / Punchlist 44940 Start-up & Test Systems 10 14MAR13 27MAR13 45

44960 Clean-Up Bldg. H 3 19MAR13 21MAR13 52

44950 Commissioning 15 28MAR13 17APR13 45

44980 Punchlist Bldg. H 10 18APR13 01MAY13 45

Bldg. J - RestroomsMilestones 50000 Start Bldg. J Middle School Restroom 0 30APR12 89

50010 Bldg. J Middle School Restroom Duration 118* 30APR12 16OCT12 108

54990 Bldg. J - Middle School Restroom Complete 0 16OCT12 108

Foundations / Underground 50100 Excavate Footings 3 30APR12 02MAY12 89

50120 Rebar Footings & Stem Walls 4 03MAY12 08MAY12 89

50160 Form Footings & Stem Walls 3 08MAY12 10MAY12 89

50180 Install Electrical Sleeves 2 09MAY12 10MAY12 90

50200 Install Plumbing Sleeves 2 09MAY12 10MAY12 90

50320 Install Mechanical Sleeves 2 09MAY12 10MAY12 90

50140 Layout / Install Anchor Bolts 2 10MAY12 11MAY12 89

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Pull wires & Terminate

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & HeadsInstall Mechanical Drops, Grills & Registers

Hang Doors

Install Lighting & L.V. Electrical Devices

Interior Glazing

Install Door Hardware

Install Acoustical Ceiling Panels

Finish Paint

Install Markerboards

Install Roof Ladder & Hatch

Install Drinking Fountains

Polish Concrete Floor

Install Plumbing Fixtures

Finish Mechanical Controls

Finish Electrical

Toilet Partitions & Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. H

Commissioning

Punchlist Bldg. H

Start Bldg. J Middle School Restroom

Bldg. J Middle School Restroom Duration

Bldg. J - Middle School Restroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Sheet 25 of 43

Page 26: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 26 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

50220 Pour Footings & Stem Walls 3 14MAY12 16MAY12 89

50240 Strip Forms 2 17MAY12 18MAY12 94

50260 Install Underslab Plumbing 5 17MAY12 23MAY12 89

50280 Install Underslab Electrical Conduits 6 22MAY12 30MAY12 89

Structure / Slab-on-Grade 50520 Bkfl/Compact at Stem Walls 2 21MAY12 22MAY12 94

50540 Vapor Barrier & Sand @ Slab-on-Grade 2 31MAY12 01JUN12 89

50560 Rebar for Slab-on-grade 2 04JUN12 05JUN12 89

50580 Pour Slab-on-Grade 3 06JUN12 08JUN12 89

50660 Wall Framing 6 11JUN12 18JUN12 89

50680 Roof Framing 4 25JUN12 28JUN12 89

50740 Install Plywood Roof Sheathing 3 29JUN12 03JUL12 89

Exterior 51060 Install Drain & Plumbing Risers 2 19JUN12 20JUN12 119

51080 Plywood Wall Sheathing 2 29JUN12 02JUL12 111

51100 Install Window Frames 2 03JUL12 05JUL12 136

51160 Install Exterior Door Frames 2 03JUL12 05JUL12 138

51020 Set Solatube Curbs & Roof Hatch Curb 2 05JUL12 06JUL12 89

51240 Lath & Flashing for Plaster 3 06JUL12 10JUL12 138

51200 Glazing 5 06JUL12 12JUL12 136

51140 Insulation Board 2 09JUL12 10JUL12 108

51220 Flashings & Sealants 2 11JUL12 12JUL12 114

51180 Install Roofing System 4 11JUL12 16JUL12 108

51280 Plaster 25 13JUL12 16AUG12 136

51400 Install Solatubes 2 17JUL12 18JUL12 110

51260 Install Metal Roof 4 17JUL12 20JUL12 108

51380 Tile @ Drinking Fountains 4 20JUL12 25JUL12 153

51420 Install Drinking Fountains 2 17AUG12 20AUG12 137

51340 Paint @ Exterior 3 17AUG12 21AUG12 136

Rough-ins 51540 Insulation @ Roof Decks 2 05JUL12 06JUL12 89

51560 Interior Framing 3 05JUL12 09JUL12 90

51580 Rough-in Fire Sprinkler 2 09JUL12 10JUL12 89

51700 Rough-in In-wall Electrical 2 10JUL12 11JUL12 113

51660 Rough-in In-wall Plumbing 6 10JUL12 17JUL12 109

51680 R-I Overhead Mechanical Units & Ducts 3 11JUL12 13JUL12 89

51740 Install In-wall Insulation 2 18JUL12 19JUL12 109

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Install Drain & Plumbing Risers

Plywood Wall Sheathing

Install Window Frames

Install Exterior Door Frames

Set Solatube Curbs & Roof Hatch Curb

Lath & Flashing for Plaster

Glazing

Insulation Board

Flashings & Sealants

Install Roofing System

Plaster

Install Solatubes

Install Metal Roof

Tile @ Drinking Fountains

Install Drinking Fountains

Paint @ Exterior

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler

Rough-in In-wall Electrical

Rough-in In-wall Plumbing

R-I Overhead Mechanical Units & Ducts

Install In-wall Insulation

Sheet 26 of 43

Page 27: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 27 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Interior Finishes 52020 Drywall 3 23JUL12 25JUL12 108

52040 Tape & Finish Drywall 5 24JUL12 30JUL12 113

52080 Ceramic Tile 10 26JUL12 08AUG12 108

52100 Prime Paint 2 31JUL12 01AUG12 113

52220 Pull wires & Terminate 3 31JUL12 02AUG12 119

52280 Install Fire Sprinkler Heads 2 02AUG12 03AUG12 145

52600 Install Solatube Diffusers 2 02AUG12 03AUG12 145

52340 Install Lighting & L.V. Electrical Devices 3 03AUG12 07AUG12 143

52400 Hang Doors 2 09AUG12 10AUG12 108

52450 Install Door Hardware 2 13AUG12 14AUG12 138

52480 Finish Paint 5 13AUG12 17AUG12 108

52740 Install Roof Ladder & Hatch 2 20AUG12 21AUG12 133

52660 Finish Mechanical Controls 5 20AUG12 24AUG12 108

52680 Finish Electrical 5 20AUG12 24AUG12 108

52620 Install Plumbing Fixtures 6 20AUG12 27AUG12 125

52760 Toilet Accessories 4 28AUG12 31AUG12 125

52780 Touch-up Paint 3 03SEP12 07SEP12 125

Clean-up / Punchlist 54940 Start-up & Test Systems 10 27AUG12 11SEP12 108

54960 Clean-Up Bldg. J 3 10SEP12 12SEP12 125

54950 Commissioning 15 12SEP12 02OCT12 108

54980 Punchlist Bldg. J 10 03OCT12 16OCT12 108

Bldg. K - RestroomsMilestones 55000 Start Bldg. K Middle School Restroom 0 14MAY12 79

55010 Bldg. K Middle School Restroom Duration 118* 14MAY12 30OCT12 98

59990 Bldg. K - Middle School Restroom Complete 0 30OCT12 98

Foundations / Underground 55100 Excavate Footings 3 14MAY12 16MAY12 79

55120 Rebar Footings & Stem Walls 4 17MAY12 22MAY12 79

55160 Form Footings & Stem Walls 3 22MAY12 24MAY12 79

55180 Install Electrical Sleeves 2 23MAY12 24MAY12 80

55200 Install Plumbing Sleeves 2 23MAY12 24MAY12 80

55320 Install Mechanical Sleeves 2 23MAY12 24MAY12 80

55140 Layout / Install Anchor Bolts 2 24MAY12 25MAY12 79

55220 Pour Footings & Stem Walls 3 29MAY12 31MAY12 79

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Drywall

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Pull wires & Terminate

Install Fire Sprinkler Heads

Install Solatube Diffusers

Install Lighting & L.V. Electrical Devices

Hang Doors

Install Door Hardware

Finish Paint

Install Roof Ladder & Hatch

Finish Mechanical Controls

Finish Electrical

Install Plumbing Fixtures

Toilet Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. J

Commissioning

Punchlist Bldg. J

Start Bldg. K Middle School Restroom

Bldg. K Middle School Restroom Duration

Bldg. K - Middle School Restroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Sheet 27 of 43

Page 28: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 28 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

55240 Strip Forms 2 01JUN12 04JUN12 84

55260 Install Underslab Plumbing 5 01JUN12 07JUN12 79

55280 Install Underslab Electrical Conduits 6 06JUN12 13JUN12 79

Structure / Slab-on-Grade 55520 Bkfl/Compact at Stem Walls 2 05JUN12 06JUN12 84

55540 Vapor Barrier & Sand @ Slab-on-Grade 2 14JUN12 15JUN12 79

55560 Rebar for Slab-on-grade 2 18JUN12 19JUN12 79

55580 Pour Slab-on-Grade 3 20JUN12 22JUN12 79

55660 Wall Framing 6 25JUN12 02JUL12 79

55680 Roof Framing 4 10JUL12 13JUL12 79

55740 Install Plywood Roof Sheathing 3 16JUL12 18JUL12 79

Exterior 56060 Install Drain & Plumbing Risers 2 03JUL12 05JUL12 109

56080 Plywood Wall Sheathing 2 16JUL12 17JUL12 101

56100 Install Window Frames 2 18JUL12 19JUL12 126

56160 Install Exterior Door Frames 2 18JUL12 19JUL12 128

56020 Set Solatube Mounts & Roof Hatch Curb 2 19JUL12 20JUL12 79

56240 Lath & Flashing for Plaster 3 20JUL12 24JUL12 128

56200 Glazing 5 20JUL12 26JUL12 126

56140 Insulation Board 2 23JUL12 24JUL12 98

56220 Flashings & Sealants 2 25JUL12 26JUL12 104

56180 Install Roofing System 4 25JUL12 30JUL12 98

56280 Plaster 25 27JUL12 30AUG12 126

56400 Install Solatubes 2 31JUL12 01AUG12 100

56260 Install Metal Roof 4 31JUL12 03AUG12 98

56380 Tile @ Drinking Fountains 4 03AUG12 08AUG12 143

56420 Install Drinking Fountains 2 31AUG12 03SEP12 127

56340 Paint @ Exterior 3 31AUG12 04SEP12 126

Rough-ins 56540 Insulation @ Roof Decks 2 19JUL12 20JUL12 79

56560 Interior Framing 3 19JUL12 23JUL12 80

56580 Rough-in Fire Sprinkler 2 23JUL12 24JUL12 79

56700 Rough-in In-wall Electrical 2 24JUL12 25JUL12 103

56660 Rough-in In-wall Plumbing 6 24JUL12 31JUL12 99

56680 R-I Overhead Mechanical Units & Ducts 3 25JUL12 27JUL12 79

56740 Install In-wall Insulation 2 01AUG12 02AUG12 99

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Install Drain & Plumbing Risers

Plywood Wall Sheathing

Install Window Frames

Install Exterior Door Frames

Set Solatube Mounts & Roof Hatch Curb

Lath & Flashing for Plaster

Glazing

Insulation Board

Flashings & Sealants

Install Roofing System

Plaster

Install Solatubes

Install Metal Roof

Tile @ Drinking Fountains

Install Drinking Fountains

Paint @ Exterior

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler

Rough-in In-wall Electrical

Rough-in In-wall Plumbing

R-I Overhead Mechanical Units & Ducts

Install In-wall Insulation

Sheet 28 of 43

Page 29: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 29 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Interior Finishes 57020 Drywall 3 06AUG12 08AUG12 98

57040 Tape & Finish Drywall 5 07AUG12 13AUG12 103

57080 Ceramic Tile 10 09AUG12 22AUG12 98

57100 Prime Paint 2 14AUG12 15AUG12 103

57220 Pull wires & Terminate 3 14AUG12 16AUG12 109

57280 Install Fire Sprinkler Heads 2 16AUG12 17AUG12 135

57600 Install Solatube Diffusers 2 16AUG12 17AUG12 135

57340 Install Lighting & L.V. Electrical Devices 3 17AUG12 21AUG12 133

57400 Hang Doors 2 23AUG12 24AUG12 98

57450 Install Door Hardware 2 27AUG12 28AUG12 128

57480 Finish Paint 5 27AUG12 31AUG12 98

57740 Install Roof Ladder & Hatch 2 03SEP12 04SEP12 123

57660 Finish Mechanical Controls 5 03SEP12 11SEP12 98

57680 Finish Electrical 5 03SEP12 11SEP12 98

57620 Install Plumbing Fixtures 6 03SEP12 12SEP12 115

57760 Toilet Accessories 4 13SEP12 18SEP12 115

57780 Touch-up Paint 3 19SEP12 21SEP12 115

Clean-up / Punchlist 59940 Start-up & Test Systems 10 12SEP12 25SEP12 98

59960 Clean-Up Bldg. K 3 24SEP12 26SEP12 115

59950 Commissioning 15 26SEP12 16OCT12 98

59980 Punchlist Bldg. K 10 17OCT12 30OCT12 98

Bldg. L - Administration - Elementary SchoolMilestones 60000 Start Bldg. L - Elementary School Administration 0 16APR12 25

60010 Bldg. L - Elementary School Admin. Duration 238* 16APR12 26MAR13 81

64990 Bldg. L - Elementary School Admin. Complete 0 26MAR13 81

Foundations / Underground 60100 Excavate Footings 5 16APR12 20APR12 81

60120 Rebar Footings & Stem Walls 10 17APR12 30APR12 81

60160 Form Footings & Stem Walls 8 26APR12 07MAY12 81

60140 Layout / Install Anchor Bolts 5 02MAY12 08MAY12 81

60180 Install Electrical Sleeves 2 04MAY12 07MAY12 82

60200 Install Plumbing Sleeves 2 04MAY12 07MAY12 82

60320 Install Mechanical Sleeves 2 04MAY12 07MAY12 82

60220 Pour Footings & Stem Walls 5 09MAY12 15MAY12 81

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Drywall

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Pull wires & Terminate

Install Fire Sprinkler Heads

Install Solatube Diffusers

Install Lighting & L.V. Electrical Devices

Hang Doors

Install Door Hardware

Finish Paint

Install Roof Ladder & Hatch

Finish Mechanical Controls

Finish Electrical

Install Plumbing Fixtures

Toilet Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. K

Commissioning

Punchlist Bldg. K

Start Bldg. L - Elementary School Administration

Bldg. L - Elementary School Admin. DurationBldg. L - Elementary School Admin. Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Layout / Install Anchor Bolts

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Pour Footings & Stem Walls

Sheet 29 of 43

Page 30: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 30 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

60240 Strip Forms 3 16MAY12 18MAY12 88

60260 Install Underslab Plumbing 10 16MAY12 30MAY12 81

60280 Install Underslab Electrical Conduits 12 21MAY12 06JUN12 81

Structure / Slab-on-Grade 60520 Bkfl/Compact at Stem Walls 5 21MAY12 25MAY12 88

60540 Vapor Barrier & Sand @ Slabs-on-Grade 3 07JUN12 11JUN12 81

60560 Rebar for Slabs-on-grade 6 12JUN12 19JUN12 81

60580 Pour Slabs-on-Grade 3 20JUN12 22JUN12 81

60660 Erect. Align & Weld-out Structural Steel 15 25JUN12 16JUL12 81

60620 Wall Framing 18 17JUL12 09AUG12 81

60680 Roof Framing 12 02AUG12 17AUG12 81

60740 Install Plywood Roof Sheathing 8 20AUG12 29AUG12 81

Exterior 61050 Set Switchgear 2 25JUN12 26JUN12 106

61000 Exterior Framing 15 20AUG12 11SEP12 95

61020 Set Roof Curbs 4 22AUG12 27AUG12 96

61040 Set HVAC Units 2 28AUG12 29AUG12 111

61080 Plywood Wall Sheathing 10 29AUG12 13SEP12 99

61060 Install Drain & Plumbing Risers 2 30AUG12 31AUG12 106

61100 Install Window Frames 10 12SEP12 25SEP12 95

61120 Install Storefronts 10 12SEP12 25SEP12 95

61140 Insulation Board 3 14SEP12 18SEP12 99

61160 Install Exterior Door Frames 4 14SEP12 19SEP12 99

61180 Install Roofing System 6 19SEP12 26SEP12 99

61220 Flashings & Sealants 6 19SEP12 26SEP12 109

61200 Glazing 5 26SEP12 02OCT12 98

61240 Lath & Flashing for Plaster 8 26SEP12 05OCT12 95

61260 Install Metal Roof 10 27SEP12 10OCT12 99

61280 Plaster 25 08OCT12 09NOV12 95

61400 Install Solatubes 4 11OCT12 16OCT12 156

61340 Paint @ Exterior 4 13NOV12 16NOV12 159

Rough-ins 61500 Install MEP Hangers 3 30AUG12 03SEP12 81

61520 Layout & Install Top Track 4 04SEP12 11SEP12 81

61540 Insulation @ Metal Decks 4 12SEP12 17SEP12 83

61560 Interior Framing 20 12SEP12 09OCT12 81

61580 Rough-in Fire Sprinkler Mains 10 18SEP12 01OCT12 83

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slabs-on-Grade

Rebar for Slabs-on-grade

Pour Slabs-on-Grade

Erect. Align & Weld-out Structural Steel

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Set Switchgear

Exterior Framing

Set Roof Curbs

Set HVAC Units

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Install Window Frames

Install Storefronts

Insulation Board

Install Exterior Door Frames

Install Roofing System

Flashings & Sealants

Glazing

Lath & Flashing for Plaster

Install Metal Roof

Plaster

Install Solatubes

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Metal Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Sheet 30 of 43

Page 31: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 31 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

61600 Rough-in Overhead Plumbing 6 02OCT12 09OCT12 83

61640 Set Interior Door & Window Frames 8 10OCT12 19OCT12 92

61680 R-I Overhead Mechanical Units, Piping & Ducts 12 10OCT12 25OCT12 83

61660 Rough-in In-wall Plumbing 12 10OCT12 25OCT12 84

61700 Rough-in In-wall Electrical 15 10OCT12 30OCT12 81

61720 Rough-in Overhead Electrical Conduits 12 17OCT12 01NOV12 83

61740 Install In-wall Insulation 4 31OCT12 05NOV12 81

Interior Finishes 62000 Plywood @ Electrical Room 2 06NOV12 07NOV12 120

62020 Drywall 12 06NOV12 26NOV12 81

62040 Tape & Finish Drywall 15 09NOV12 04DEC12 81

62080 Ceramic Tile 12 27NOV12 12DEC12 136

62120 Set Panelboards 2 05DEC12 06DEC12 104

62100 Prime Paint 4 05DEC12 10DEC12 81

62220 Pull wires & Terminate 10 07DEC12 20DEC12 104

62160 Install T-Bar Grid 4 11DEC12 14DEC12 120

62240 Install Cabinetry & Casework 15 11DEC12 02JAN13 81

62280 Install Fire Sprinkler Drops & Heads 6 17DEC12 24DEC12 124

62300 Install Mechanical Drops, Grills & Registers 6 17DEC12 24DEC12 124

62840 Install Solatube Drops & Diffusers 6 17DEC12 24DEC12 124

62340 Install Lighting & L.V. Electrical Devices 10 21DEC12 07JAN13 116

62380 Install Tack Wall / Vinyl Wall Panels 3 03JAN13 07JAN13 89

62400 Hang Doors 6 03JAN13 10JAN13 81

62440 Install Acoustical Ceiling Panels 2 08JAN13 09JAN13 116

62420 Interior Glazing 5 11JAN13 17JAN13 81

62450 Install Door Hardware 6 11JAN13 18JAN13 115

62480 Finish Paint 5 18JAN13 24JAN13 81

62560 Install Drinking Fountains 2 25JAN13 28JAN13 112

62540 Install Projection Screens / Projector Mounts 3 25JAN13 29JAN13 108

62740 Install Roof Ladder & Hatch 4 25JAN13 30JAN13 107

62620 Install Plumbing Fixtures 5 25JAN13 31JAN13 107

62660 Finish Mechanical Controls 6 25JAN13 01FEB13 83

62640 Install Flooring 6 25JAN13 01FEB13 105

62680 Finish Electrical 8 25JAN13 05FEB13 81

62760 Toilet Partitions & Accessories 2 01FEB13 04FEB13 107

62780 Touch-up Paint 3 06FEB13 08FEB13 103

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Rough-in Overhead Plumbing

Set Interior Door & Window Frames

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in In-wall Plumbing

Rough-in In-wall Electrical

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Plywood @ Electrical Room

Drywall

Tape & Finish Drywall

Ceramic Tile

Set Panelboards

Prime Paint

Pull wires & Terminate

Install T-Bar Grid

Install Cabinetry & Casework

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Solatube Drops & Diffusers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Hang Doors

Install Acoustical Ceiling Panels

Interior Glazing

Install Door Hardware

Finish Paint

Install Drinking Fountains

Install Projection Screens / Projector Mounts

Install Roof Ladder & Hatch

Install Plumbing Fixtures

Finish Mechanical Controls

Install Flooring

Finish Electrical

Toilet Partitions & Accessories

Touch-up Paint

Sheet 31 of 43

Page 32: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 32 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Clean-up / Punchlist 64940 Start-up & Test Systems 10 06FEB13 19FEB13 81

64960 Clean-Up Bldg. L 3 11FEB13 13FEB13 103

64950 Commissioning 15 20FEB13 12MAR13 81

64980 Punchlist Bldg. L 10 13MAR13 26MAR13 81

Bldg. M - KindergartenMilestones 65000 Start Bldg. M - Kindergarten 0 23APR12 25

65010 Bldg. M - Kindergarten Duration 239* 23APR12 03APR13 25

69990 Bldg. M - Kindergarten Complete 0 03APR13 25

Foundations / Underground 65100 Excavate Footings 5 23APR12 27APR12 25

65120 Rebar Footings & Stem Walls 10 26APR12 09MAY12 25

65160 Form Footings & Stem Walls 8 02MAY12 11MAY12 27

65180 Install Electrical Sleeves 2 10MAY12 11MAY12 28

65200 Install Plumbing Sleeves 2 10MAY12 11MAY12 28

65320 Install Mechanical Sleeves 2 10MAY12 11MAY12 28

65140 Layout / Install Anchor Bolts 5 10MAY12 16MAY12 25

65220 Pour Footings & Stem Walls 5 17MAY12 23MAY12 25

65240 Strip Forms 2 24MAY12 25MAY12 35

65260 Install Underslab Plumbing 10 24MAY12 07JUN12 25

65280 Install Underslab Electrical Conduits 12 01JUN12 18JUN12 25

Structure / Slab-on-Grade 65520 Bkfl/Compact at Stem Walls 5 29MAY12 04JUN12 35

65540 Vapor Barrier & Sand @ Slabs-on-Grade 3 19JUN12 21JUN12 25

65560 Rebar for Slabs-on-grade 5 22JUN12 28JUN12 25

65580 Pour Slabs-on-Grade 3 29JUN12 03JUL12 25

65660 Erect. Align & Weld-out Structural Steel 15 05JUL12 25JUL12 25

65620 Wall Framing 18 26JUL12 20AUG12 25

65680 Roof Framing 12 13AUG12 28AUG12 25

65740 Install Plywood Roof Sheathing 10 29AUG12 13SEP12 25

65600 Form & Pour Mechanical & Electrical Pads 3 25SEP12 27SEP12 33

Exterior 66000 Exterior Framing 15 29AUG12 20SEP12 33

66020 Set Roof Curbs 2 31AUG12 03SEP12 44

66080 Plywood Wall Sheathing 8 13SEP12 24SEP12 33

66060 Install Drain & Plumbing Risers 2 14SEP12 17SEP12 54

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Start-up & Test Systems

Clean-Up Bldg. L

Commissioning

Punchlist Bldg. L

Start Bldg. M - Kindergarten

Bldg. M - Kindergarten Duration

Bldg. M - Kindergarten Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slabs-on-Grade

Rebar for Slabs-on-grade

Pour Slabs-on-Grade

Erect. Align & Weld-out Structural Steel

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Roof Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Sheet 32 of 43

Page 33: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 33 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

66120 Install Storefronts 5 21SEP12 27SEP12 88

66100 Install Window Frames 6 21SEP12 28SEP12 87

66140 Insulation Board 3 25SEP12 27SEP12 49

66160 Install Exterior Door Frames 4 25SEP12 28SEP12 87

66050 Set Switchgear 2 28SEP12 01OCT12 33

66040 Set HVAC Units 2 28SEP12 01OCT12 40

66180 Install Roofing System 6 28SEP12 05OCT12 49

66220 Flashings & Sealants 6 28SEP12 05OCT12 133

66200 Glazing 5 01OCT12 05OCT12 90

66240 Lath & Flashing for Plaster 8 01OCT12 10OCT12 87

66400 Install Solatubes 6 08OCT12 15OCT12 109

66280 Plaster 25 11OCT12 15NOV12 87

66380 Construct Mechanical / Electrical Enclosures 8 16NOV12 29NOV12 97

66340 Paint @ Exterior 5 30NOV12 06DEC12 97

Rough-ins 66500 Install MEP Hangers 3 14SEP12 18SEP12 25

66520 Layout & Install Top Track 5 19SEP12 25SEP12 25

66540 Insulation @ Metal Decks 4 26SEP12 01OCT12 26

66560 Interior Framing 10 26SEP12 09OCT12 25

66580 Rough-in Fire Sprinkler Mains 8 02OCT12 11OCT12 26

66640 Set Interior Door & Window Frames 6 10OCT12 17OCT12 41

66660 Rough-in In-wall Plumbing 12 10OCT12 25OCT12 33

66700 Rough-in In-wall Electrical 20 10OCT12 06NOV12 25

66600 Rough-in Overhead Plumbing 6 12OCT12 19OCT12 26

66680 R-I Overhead Mechanical Units, Piping & Ducts 12 22OCT12 06NOV12 26

66720 Rough-in Overhead Electrical Conduits 8 29OCT12 07NOV12 26

66740 Install In-wall Insulation 2 07NOV12 08NOV12 25

Interior Finishes 67000 Plywood @ Electrical Room 2 09NOV12 13NOV12 67

67020 Drywall 12 09NOV12 29NOV12 25

67040 Tape & Finish Drywall 20 15NOV12 14DEC12 25

67080 Ceramic Tile 12 30NOV12 17DEC12 84

67120 Set Panelboards 2 17DEC12 18DEC12 46

67100 Prime Paint 4 17DEC12 20DEC12 25

67220 Pull wires & Terminate 8 19DEC12 31DEC12 46

67160 Install T-Bar Grid 4 21DEC12 27DEC12 64

67240 Install Cabinetry & Casework 12 21DEC12 09JAN13 25

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Storefronts

Install Window Frames

Insulation Board

Install Exterior Door Frames

Set Switchgear

Set HVAC Units

Install Roofing System

Flashings & Sealants

Glazing

Lath & Flashing for Plaster

Install Solatubes

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Metal Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Set Interior Door & Window Frames

Rough-in In-wall Plumbing

Rough-in In-wall Electrical

Rough-in Overhead Plumbing

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Plywood @ Electrical Room

Drywall

Tape & Finish Drywall

Ceramic Tile

Set Panelboards

Prime Paint

Pull wires & Terminate

Install T-Bar Grid

Install Cabinetry & Casework

Sheet 33 of 43

Page 34: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 34 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

67280 Install Fire Sprinkler Drops & Heads 5 28DEC12 04JAN13 67

67840 Install Solatube Drops & Diffusers 7 28DEC12 08JAN13 65

67300 Install Mechanical Drops, Grills & Registers 8 28DEC12 09JAN13 64

67340 Install Lighting & L.V. Electrical Devices 8 02JAN13 11JAN13 62

67380 Install Tack Wall / Vinyl Wall Panels 3 10JAN13 14JAN13 32

67400 Hang Doors 6 10JAN13 17JAN13 25

67440 Install Acoustical Ceiling Panels 2 14JAN13 15JAN13 62

67420 Interior Glazing 4 18JAN13 23JAN13 25

67450 Install Door Hardware 5 18JAN13 24JAN13 61

67480 Finish Paint 5 24JAN13 30JAN13 25

67540 Install Projection Screens / Projector Mounts 2 31JAN13 01FEB13 55

67740 Install Roof Ladder & Hatch 2 31JAN13 01FEB13 55

67560 Install Drinking Fountains 2 31JAN13 01FEB13 58

67620 Install Plumbing Fixtures 4 31JAN13 05FEB13 54

67640 Install Flooring 6 31JAN13 07FEB13 51

67660 Finish Mechanical Controls 8 31JAN13 11FEB13 27

67680 Finish Electrical 10 31JAN13 13FEB13 25

67760 Toilet Partitions & Accessories 2 06FEB13 07FEB13 54

67780 Touch-up Paint 3 14FEB13 18FEB13 47

Clean-up / Punchlist 69940 Start-up & Test Systems 10 14FEB13 27FEB13 25

69960 Clean-Up Bldg. M 3 19FEB13 21FEB13 47

69950 Commissioning 15 28FEB13 20MAR13 25

69980 Punchlist Bldg. M 10 21MAR13 03APR13 25

Bldg. N - ClassroomMilestones 70000 Start Bldg. N - Elem. School Classroom 0 05JUN12 45

70010 Bldg. N - Elem. School Classroom Duration 172* 05JUN12 11FEB13 62

74990 Bldg. N - Elem. School Classroom Complete 0 11FEB13 62

Foundations / Underground 70100 Excavate Footings 5 05JUN12 11JUN12 62

70120 Rebar Footings & Stem Walls 10 06JUN12 19JUN12 62

70160 Form Footings & Stem Walls 6 14JUN12 21JUN12 63

70180 Install Electrical Sleeves 2 20JUN12 21JUN12 64

70200 Install Plumbing Sleeves 2 20JUN12 21JUN12 64

70320 Install Mechanical Sleeves 2 20JUN12 21JUN12 64

70140 Layout / Install Anchor Bolts 4 20JUN12 25JUN12 62

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Fire Sprinkler Drops & Heads

Install Solatube Drops & Diffusers

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Hang Doors

Install Acoustical Ceiling Panels

Interior Glazing

Install Door Hardware

Finish Paint

Install Projection Screens / Projector Mounts

Install Roof Ladder & Hatch

Install Drinking Fountains

Install Plumbing Fixtures

Install Flooring

Finish Mechanical Controls

Finish Electrical

Toilet Partitions & Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. M

Commissioning

Punchlist Bldg. M

Start Bldg. N - Elem. School Classroom

Bldg. N - Elem. School Classroom DurationBldg. N - Elem. School Classroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Sheet 34 of 43

Page 35: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 35 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

70220 Pour Footings & Stem Walls 4 26JUN12 29JUN12 62

70240 Strip Forms 2 02JUL12 03JUL12 66

70300 Install Underslab Mechanical Piping 3 02JUL12 05JUL12 68

70260 Install Underslab Plumbing 5 02JUL12 09JUL12 62

70280 Install Underslab Electrical Conduits 6 06JUL12 13JUL12 62

Structure / Slab-on-Grade 70520 Bkfl/Compact at Stem Walls 3 05JUL12 09JUL12 66

70540 Vapor Barrier & Sand @ Slab-on-Grade 4 16JUL12 19JUL12 62

70560 Rebar for Slab-on-grade 5 20JUL12 26JUL12 62

70580 Pour Slab-on-Grade 3 27JUL12 31JUL12 62

70660 Wall Framing 15 01AUG12 21AUG12 62

70680 Roof Framing 8 15AUG12 24AUG12 62

70740 Install Plywood Roof Sheathing 5 27AUG12 31AUG12 62

70600 Form & Pour Mechanical & Electrical Pads 3 14SEP12 18SEP12 72

Exterior 71000 Exterior Framing 10 27AUG12 11SEP12 72

71020 Set Solatube Curbs 3 29AUG12 31AUG12 73

71060 Install Drain & Plumbing Risers 2 03SEP12 04SEP12 86

71080 Plywood Wall Sheathing 6 04SEP12 13SEP12 72

71100 Install Window Frames 12 12SEP12 27SEP12 98

71140 Insulation Board 3 14SEP12 18SEP12 81

71160 Install Exterior Door Frames 4 14SEP12 19SEP12 104

71220 Flashings & Sealants 6 14SEP12 21SEP12 82

71040 Set HVAC Units 2 19SEP12 20SEP12 72

71050 Set Switchgear 2 19SEP12 20SEP12 73

71260 Install Metal Roof 4 19SEP12 24SEP12 81

71400 Install Solatubes 4 25SEP12 28SEP12 121

71200 Glazing 5 28SEP12 04OCT12 101

71240 Lath & Flashing for Plaster 8 28SEP12 09OCT12 98

71280 Plaster 25 10OCT12 14NOV12 98

71380 Construct Mechanical / Electrical Enclosures 8 15NOV12 28NOV12 98

71340 Paint @ Exterior 5 29NOV12 05DEC12 98

Rough-ins 71500 Install MEP Hangers 4 03SEP12 10SEP12 62

71520 Layout & Install Top Track 3 11SEP12 13SEP12 62

71540 Insulation @ Roof Decks 4 14SEP12 19SEP12 62

71560 Interior Framing 10 14SEP12 27SEP12 65

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Pour Footings & Stem Walls

Strip Forms

Install Underslab Mechanical Piping

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Solatube Curbs

Install Drain & Plumbing Risers

Plywood Wall Sheathing

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Sheet 35 of 43

Page 36: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 36 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

71580 Rough-in Fire Sprinkler Mains 6 20SEP12 27SEP12 62

71600 Rough-in Overhead Plumbing 3 28SEP12 02OCT12 62

71640 Set Interior Door & Window Frames 6 28SEP12 05OCT12 72

71660 Rough-in In-wall Plumbing 8 28SEP12 09OCT12 68

71700 Rough-in In-wall Electrical 10 28SEP12 11OCT12 66

71680 R-I Overhead Mechanical Units, Piping & Ducts 12 03OCT12 18OCT12 62

71720 Rough-in Overhead Electrical Conduits 8 10OCT12 19OCT12 62

71740 Install In-wall Insulation 2 12OCT12 15OCT12 66

Interior Finishes 72020 Drywall 5 22OCT12 26OCT12 62

72040 Tape & Finish Drywall 8 23OCT12 01NOV12 62

72080 Ceramic Tile 6 29OCT12 05NOV12 113

72100 Prime Paint 4 31OCT12 05NOV12 62

72120 Set Panelboards 2 02NOV12 05NOV12 79

72160 Install T-Bar Grid 4 06NOV12 09NOV12 95

72220 Pull wires & Terminate 8 06NOV12 16NOV12 79

72240 Install Cabinetry & Casework 12 06NOV12 26NOV12 62

72840 Install Solatube Drops & Diffusers 4 13NOV12 16NOV12 99

72280 Install Fire Sprinkler Drops & Heads 5 13NOV12 19NOV12 98

72300 Install Mechanical Drops, Grills & Registers 6 13NOV12 20NOV12 97

72340 Install Lighting & L.V. Electrical Devices 8 19NOV12 30NOV12 91

72380 Install Tack Wall / Vinyl Wall Panels 3 27NOV12 29NOV12 67

72260 Install Sinks 3 27NOV12 29NOV12 102

72400 Hang Doors 5 27NOV12 03DEC12 62

72440 Install Acoustical Ceiling Panels 2 03DEC12 04DEC12 91

72420 Interior Glazing 3 04DEC12 06DEC12 62

72450 Install Door Hardware 5 04DEC12 10DEC12 92

72480 Finish Paint 5 07DEC12 13DEC12 62

72540 Install Projection Screens / Projector Mounts 2 14DEC12 17DEC12 87

72560 Install Markerboards 2 14DEC12 17DEC12 87

72620 Install Plumbing Fixtures 2 14DEC12 17DEC12 88

72660 Finish Mechanical Controls 5 14DEC12 20DEC12 62

72680 Finish Electrical 5 14DEC12 20DEC12 62

72640 Install Flooring 5 14DEC12 20DEC12 84

72760 Toilet Accessories 2 18DEC12 19DEC12 88

72780 Touch-up Paint 3 21DEC12 26DEC12 84

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Plumbing

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Set Panelboards

Install T-Bar Grid

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Install Acoustical Ceiling Panels

Interior Glazing

Install Door Hardware

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Install Plumbing Fixtures

Finish Mechanical Controls

Finish Electrical

Install Flooring

Toilet Accessories

Touch-up Paint

Sheet 36 of 43

Page 37: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 37 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

Clean-up / Punchlist 74940 Start-up & Test Systems 10 21DEC12 07JAN13 62

74960 Clean-Up Bldg. N 3 27DEC12 31DEC12 84

74950 Commissioning 15 08JAN13 28JAN13 62

74980 Punchlist Bldg. N 10 29JAN13 11FEB13 62

Bldg. P - ClassroomMilestones 80000 Start Bldg. P - Elem. School Classroom 0 05JUN12 45

80010 Bldg. P - Elem. School Classroom Duration 161* 05JUN12 25JAN13 45

84990 Bldg. P - Elem. School Classroom Complete 0 25JAN13 45

Foundations / Underground 80100 Excavate Footings 4 05JUN12 08JUN12 45

80120 Rebar Footings & Stem Walls 8 06JUN12 15JUN12 45

80160 Form Footings & Stem Walls 5 13JUN12 19JUN12 46

80180 Install Electrical Sleeves 2 18JUN12 19JUN12 47

80200 Install Plumbing Sleeves 2 18JUN12 19JUN12 47

80320 Install Mechanical Sleeves 2 18JUN12 19JUN12 47

80140 Layout / Install Anchor Bolts 4 18JUN12 21JUN12 45

80220 Pour Footings & Stem Walls 4 22JUN12 27JUN12 45

80240 Strip Forms 2 28JUN12 29JUN12 49

80300 Install Underslab Mechanical Piping 3 28JUN12 02JUL12 51

80260 Install Underslab Plumbing 5 28JUN12 05JUL12 45

80280 Install Underslab Electrical Conduits 6 03JUL12 11JUL12 45

Structure / Slab-on-Grade 80520 Bkfl/Compact at Stem Walls 3 02JUL12 05JUL12 49

80540 Vapor Barrier & Sand @ Slab-on-Grade 2 12JUL12 13JUL12 45

80560 Rebar for Slab-on-grade 4 16JUL12 19JUL12 45

80580 Pour Slab-on-Grade 3 20JUL12 24JUL12 45

80660 Wall Framing 10 25JUL12 07AUG12 45

80680 Roof Framing 6 08AUG12 15AUG12 45

80740 Install Plywood Roof Sheathing 5 16AUG12 22AUG12 45

80600 Form & Pour Mechanical & Electrical Pads 3 30AUG12 03SEP12 55

Exterior 81000 Exterior Framing 8 16AUG12 27AUG12 55

81020 Set Solatube Curbs 2 20AUG12 21AUG12 55

81080 Plywood Wall Sheathing 6 22AUG12 29AUG12 55

81060 Install Drain & Plumbing Risers 2 23AUG12 24AUG12 67

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Start-up & Test Systems

Clean-Up Bldg. N

Commissioning

Punchlist Bldg. N

Start Bldg. P - Elem. School Classroom

Bldg. P - Elem. School Classroom Duration

Bldg. P - Elem. School Classroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Mechanical Piping

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Form & Pour Mechanical & Electrical Pads

Exterior Framing

Set Solatube Curbs

Plywood Wall Sheathing

Install Drain & Plumbing Risers

Sheet 37 of 43

Page 38: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 38 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

81100 Install Window Frames 12 28AUG12 14SEP12 81

81140 Insulation Board 3 30AUG12 03SEP12 64

81160 Install Exterior Door Frames 4 30AUG12 04SEP12 87

81220 Flashings & Sealants 6 30AUG12 10SEP12 65

81040 Set HVAC Units 2 04SEP12 07SEP12 55

81050 Set Switchgear 2 04SEP12 07SEP12 56

81260 Install Metal Roof 4 04SEP12 11SEP12 64

81400 Install Solatubes 4 12SEP12 17SEP12 102

81200 Glazing 5 17SEP12 21SEP12 82

81240 Lath & Flashing for Plaster 6 17SEP12 24SEP12 81

81280 Plaster 25 25SEP12 29OCT12 81

81380 Construct Mechanical / Electrical Enclosures 8 30OCT12 08NOV12 81

81340 Paint @ Exterior 5 09NOV12 16NOV12 81

Rough-ins 81500 Install MEP Hangers 3 23AUG12 27AUG12 45

81520 Layout & Install Top Track 2 28AUG12 29AUG12 45

81540 Insulation @ Roof Decks 4 30AUG12 04SEP12 45

81560 Interior Framing 10 30AUG12 14SEP12 48

81580 Rough-in Fire Sprinkler Mains 6 07SEP12 14SEP12 45

81600 Rough-in Overhead Plumbing 3 17SEP12 19SEP12 45

81660 Rough-in In-wall Plumbing 5 17SEP12 21SEP12 54

81640 Set Interior Door & Window Frames 6 17SEP12 24SEP12 55

81700 Rough-in In-wall Electrical 10 17SEP12 28SEP12 49

81680 R-I Overhead Mechanical Units, Piping & Ducts 12 20SEP12 05OCT12 45

81720 Rough-in Overhead Electrical Conduits 8 27SEP12 08OCT12 45

81740 Install In-wall Insulation 2 01OCT12 02OCT12 49

Interior Finishes 82020 Drywall 5 09OCT12 15OCT12 45

82040 Tape & Finish Drywall 8 10OCT12 19OCT12 45

82080 Ceramic Tile 6 16OCT12 23OCT12 92

82100 Prime Paint 4 18OCT12 23OCT12 45

82120 Set Panelboards 2 22OCT12 23OCT12 60

82160 Install T-Bar Grid 4 24OCT12 29OCT12 76

82220 Pull wires & Terminate 8 24OCT12 02NOV12 60

82240 Install Cabinetry & Casework 10 24OCT12 06NOV12 45

82840 Install Solatube Drops & Diffusers 4 30OCT12 02NOV12 80

82280 Install Fire Sprinkler Drops & Heads 5 30OCT12 05NOV12 79

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Window Frames

Insulation Board

Install Exterior Door Frames

Flashings & Sealants

Set HVAC Units

Set Switchgear

Install Metal Roof

Install Solatubes

Glazing

Lath & Flashing for Plaster

Plaster

Construct Mechanical / Electrical Enclosures

Paint @ Exterior

Install MEP Hangers

Layout & Install Top Track

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler Mains

Rough-in Overhead Plumbing

Rough-in In-wall Plumbing

Set Interior Door & Window Frames

Rough-in In-wall Electrical

R-I Overhead Mechanical Units, Piping & Ducts

Rough-in Overhead Electrical Conduits

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Set Panelboards

Install T-Bar Grid

Pull wires & Terminate

Install Cabinetry & Casework

Install Solatube Drops & Diffusers

Install Fire Sprinkler Drops & Heads

Sheet 38 of 43

Page 39: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 39 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

82300 Install Mechanical Drops, Grills & Registers 6 30OCT12 06NOV12 78

82340 Install Lighting & L.V. Electrical Devices 8 05NOV12 15NOV12 72

82380 Install Tack Wall / Vinyl Wall Panels 3 07NOV12 09NOV12 50

82260 Install Sinks 3 07NOV12 09NOV12 85

82400 Hang Doors 5 07NOV12 14NOV12 45

82420 Interior Glazing 3 15NOV12 19NOV12 45

82450 Install Door Hardware 5 15NOV12 21NOV12 75

82440 Install Acoustical Ceiling Panels 2 16NOV12 19NOV12 72

82480 Finish Paint 5 20NOV12 28NOV12 45

82540 Install Projection Screens / Projector Mounts 2 29NOV12 30NOV12 70

82560 Install Markerboards 2 29NOV12 30NOV12 70

82620 Install Plumbing Fixtures 4 29NOV12 04DEC12 69

82660 Finish Mechanical Controls 5 29NOV12 05DEC12 45

82680 Finish Electrical 5 29NOV12 05DEC12 45

82640 Install Flooring 5 29NOV12 05DEC12 67

82760 Toilet Accessories 2 05DEC12 06DEC12 69

82780 Touch-up Paint 3 06DEC12 10DEC12 67

Clean-up / Punchlist 84940 Start-up & Test Systems 10 06DEC12 19DEC12 45

84960 Clean-Up Bldg. P 3 11DEC12 13DEC12 67

84950 Commissioning 15 20DEC12 11JAN13 45

84980 Punchlist Bldg. P 10 14JAN13 25JAN13 45

Bldg. Q - RestroomsMilestones 85000 Start Bldg. Q Elem. School Restroom 0 05JUN12 64

85010 Bldg. Q Elem. School Restroom Duration 118* 05JUN12 21NOV12 88

89990 Bldg. Q - Elem. School Restroom Complete 0 21NOV12 88

Foundations / Underground 85100 Excavate Footings 3 05JUN12 07JUN12 64

85120 Rebar Footings & Stem Walls 4 08JUN12 13JUN12 64

85160 Form Footings & Stem Walls 3 13JUN12 15JUN12 64

85180 Install Electrical Sleeves 2 14JUN12 15JUN12 65

85200 Install Plumbing Sleeves 2 14JUN12 15JUN12 65

85320 Install Mechanical Sleeves 2 14JUN12 15JUN12 65

85140 Layout / Install Anchor Bolts 2 15JUN12 18JUN12 64

85220 Pour Footings & Stem Walls 3 19JUN12 21JUN12 64

85240 Strip Forms 2 22JUN12 25JUN12 69

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Mechanical Drops, Grills & Registers

Install Lighting & L.V. Electrical Devices

Install Tack Wall / Vinyl Wall Panels

Install Sinks

Hang Doors

Interior Glazing

Install Door Hardware

Install Acoustical Ceiling Panels

Finish Paint

Install Projection Screens / Projector Mounts

Install Markerboards

Install Plumbing Fixtures

Finish Mechanical Controls

Finish Electrical

Install Flooring

Toilet Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. P

Commissioning

Punchlist Bldg. P

Start Bldg. Q Elem. School Restroom

Bldg. Q Elem. School Restroom Duration

Bldg. Q - Elem. School Restroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Sheet 39 of 43

Page 40: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 40 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

85260 Install Underslab Plumbing 5 22JUN12 28JUN12 64

85280 Install Underslab Electrical Conduits 6 27JUN12 05JUL12 64

Structure / Slab-on-Grade 85520 Bkfl/Compact at Stem Walls 2 26JUN12 27JUN12 69

85540 Vapor Barrier & Sand @ Slab-on-Grade 2 06JUL12 09JUL12 64

85560 Rebar for Slab-on-grade 2 10JUL12 11JUL12 64

85580 Pour Slab-on-Grade 3 12JUL12 16JUL12 64

85660 Wall Framing 6 17JUL12 24JUL12 64

85680 Roof Framing 4 31JUL12 03AUG12 64

85740 Install Plywood Roof Sheathing 3 06AUG12 08AUG12 64

Exterior 86060 Install Drain & Plumbing Risers 2 25JUL12 26JUL12 99

86080 Plywood Wall Sheathing 2 06AUG12 07AUG12 91

86100 Install Window Frames 2 08AUG12 09AUG12 116

86160 Install Exterior Door Frames 2 08AUG12 09AUG12 118

86020 Set Solatube Mounts & Roof Hatch Curb 2 09AUG12 10AUG12 64

86240 Lath & Flashing for Plaster 3 10AUG12 14AUG12 118

86200 Glazing 5 10AUG12 16AUG12 116

86140 Insulation Board 2 13AUG12 14AUG12 88

86220 Flashings & Sealants 2 15AUG12 16AUG12 94

86180 Install Roofing System 4 15AUG12 20AUG12 88

86280 Plaster 25 17AUG12 24SEP12 116

86400 Install Solatubes 2 21AUG12 22AUG12 90

86260 Install Metal Roof 4 21AUG12 24AUG12 88

86380 Tile @ Drinking Fountains 4 24AUG12 29AUG12 133

86420 Install Drinking Fountains 2 25SEP12 26SEP12 117

86340 Paint @ Exterior 3 25SEP12 27SEP12 116

Rough-ins 86540 Insulation @ Roof Decks 2 09AUG12 10AUG12 64

86560 Interior Framing 3 09AUG12 13AUG12 65

86580 Rough-in Fire Sprinkler 2 13AUG12 14AUG12 64

86700 Rough-in In-wall Electrical 2 14AUG12 15AUG12 93

86660 Rough-in In-wall Plumbing 6 14AUG12 21AUG12 89

86680 R-I Overhead Mechanical Units & Ducts 3 15AUG12 17AUG12 64

86740 Install In-wall Insulation 2 22AUG12 23AUG12 89

Interior Finishes 87020 Drywall 3 27AUG12 29AUG12 88

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Underslab Plumbing

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Install Drain & Plumbing Risers

Plywood Wall Sheathing

Install Window Frames

Install Exterior Door Frames

Set Solatube Mounts & Roof Hatch Curb

Lath & Flashing for Plaster

Glazing

Insulation Board

Flashings & Sealants

Install Roofing System

Plaster

Install Solatubes

Install Metal Roof

Tile @ Drinking Fountains

Install Drinking Fountains

Paint @ Exterior

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler

Rough-in In-wall Electrical

Rough-in In-wall Plumbing

R-I Overhead Mechanical Units & Ducts

Install In-wall Insulation

Drywall

Sheet 40 of 43

Page 41: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 41 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

87040 Tape & Finish Drywall 5 28AUG12 03SEP12 93

87080 Ceramic Tile 10 30AUG12 14SEP12 88

87100 Prime Paint 2 04SEP12 07SEP12 93

87220 Pull wires & Terminate 3 04SEP12 10SEP12 99

87280 Install Fire Sprinkler Heads 2 10SEP12 11SEP12 125

87600 Install Solatube Diffusers 2 10SEP12 11SEP12 125

87340 Install Lighting & L.V. Electrical Devices 3 11SEP12 13SEP12 123

87400 Hang Doors 2 17SEP12 18SEP12 88

87450 Install Door Hardware 2 19SEP12 20SEP12 118

87480 Finish Paint 5 19SEP12 25SEP12 88

87740 Install Roof Ladder & Hatch 2 26SEP12 27SEP12 113

87660 Finish Mechanical Controls 5 26SEP12 02OCT12 88

87680 Finish Electrical 5 26SEP12 02OCT12 88

87620 Install Plumbing Fixtures 6 26SEP12 03OCT12 105

87760 Toilet Accessories 4 04OCT12 09OCT12 105

87780 Touch-up Paint 3 10OCT12 12OCT12 105

Clean-up / Punchlist 89940 Start-up & Test Systems 10 03OCT12 16OCT12 88

89960 Clean-Up Bldg. Q 3 15OCT12 17OCT12 105

89950 Commissioning 15 17OCT12 06NOV12 88

89980 Punchlist Bldg. Q 10 07NOV12 21NOV12 88

Bldg. R - RestroomsMilestones 90000 Start Bldg. R Elem. School Restroom 0 05JUN12 64

90010 Bldg. R Elem. School Restroom Duration 118* 05JUN12 21NOV12 88

94990 Bldg. R - Elem. School Restroom Complete 0 21NOV12 88

Foundations / Underground 90100 Excavate Footings 3 05JUN12 07JUN12 64

90120 Rebar Footings & Stem Walls 4 08JUN12 13JUN12 64

90160 Form Footings & Stem Walls 3 13JUN12 15JUN12 64

90180 Install Electrical Sleeves 2 14JUN12 15JUN12 65

90200 Install Plumbing Sleeves 2 14JUN12 15JUN12 65

90320 Install Mechanical Sleeves 2 14JUN12 15JUN12 65

90140 Layout / Install Anchor Bolts 2 15JUN12 18JUN12 64

90220 Pour Footings & Stem Walls 3 19JUN12 21JUN12 64

90240 Strip Forms 2 22JUN12 25JUN12 69

90260 Install Underslab Plumbing 5 22JUN12 28JUN12 64

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Tape & Finish Drywall

Ceramic Tile

Prime Paint

Pull wires & Terminate

Install Fire Sprinkler Heads

Install Solatube Diffusers

Install Lighting & L.V. Electrical Devices

Hang Doors

Install Door Hardware

Finish Paint

Install Roof Ladder & Hatch

Finish Mechanical Controls

Finish Electrical

Install Plumbing Fixtures

Toilet Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. Q

Commissioning

Punchlist Bldg. Q

Start Bldg. R Elem. School Restroom

Bldg. R Elem. School Restroom Duration

Bldg. R - Elem. School Restroom Complete

Excavate Footings

Rebar Footings & Stem Walls

Form Footings & Stem Walls

Install Electrical Sleeves

Install Plumbing Sleeves

Install Mechanical Sleeves

Layout / Install Anchor Bolts

Pour Footings & Stem Walls

Strip Forms

Install Underslab Plumbing

Sheet 41 of 43

Page 42: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 42 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

90280 Install Underslab Electrical Conduits 6 27JUN12 05JUL12 64

Structure / Slab-on-Grade 90520 Bkfl/Compact at Stem Walls 2 26JUN12 27JUN12 69

90540 Vapor Barrier & Sand @ Slab-on-Grade 2 06JUL12 09JUL12 64

90560 Rebar for Slab-on-grade 2 10JUL12 11JUL12 64

90580 Pour Slab-on-Grade 3 12JUL12 16JUL12 64

90660 Wall Framing 6 17JUL12 24JUL12 64

90680 Roof Framing 4 31JUL12 03AUG12 64

90740 Install Plywood Roof Sheathing 3 06AUG12 08AUG12 64

Exterior 91060 Install Drain & Plumbing Risers 2 25JUL12 26JUL12 99

91080 Plywood Wall Sheathing 2 06AUG12 07AUG12 91

91100 Install Window Frames 2 08AUG12 09AUG12 116

91160 Install Exterior Door Frames 2 08AUG12 09AUG12 118

91020 Set Solatube Mounts & Roof Hatch Curb 2 09AUG12 10AUG12 64

91240 Lath & Flashing for Plaster 3 10AUG12 14AUG12 118

91200 Glazing 5 10AUG12 16AUG12 116

91140 Insulation Board 2 13AUG12 14AUG12 88

91220 Flashings & Sealants 2 15AUG12 16AUG12 94

91180 Install Roofing System 4 15AUG12 20AUG12 88

91280 Plaster 25 17AUG12 24SEP12 116

91400 Install Solatubes 2 21AUG12 22AUG12 90

91260 Install Metal Roof 4 21AUG12 24AUG12 88

91380 Tile @ Drinking Fountains 4 24AUG12 29AUG12 133

91420 Install Drinking Fountains 2 25SEP12 26SEP12 117

91340 Paint @ Exterior 3 25SEP12 27SEP12 116

Rough-ins 91540 Insulation @ Roof Decks 2 09AUG12 10AUG12 64

91560 Interior Framing 3 09AUG12 13AUG12 65

91580 Rough-in Fire Sprinkler 2 13AUG12 14AUG12 64

91700 Rough-in In-wall Electrical 2 14AUG12 15AUG12 93

91660 Rough-in In-wall Plumbing 6 14AUG12 21AUG12 89

91680 R-I Overhead Mechanical Units & Ducts 3 15AUG12 17AUG12 64

91740 Install In-wall Insulation 2 22AUG12 23AUG12 89

Interior Finishes 92020 Drywall 3 27AUG12 29AUG12 88

92040 Tape & Finish Drywall 5 28AUG12 03SEP12 93

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Install Underslab Electrical Conduits

Bkfl/Compact at Stem Walls

Vapor Barrier & Sand @ Slab-on-Grade

Rebar for Slab-on-grade

Pour Slab-on-Grade

Wall Framing

Roof Framing

Install Plywood Roof Sheathing

Install Drain & Plumbing Risers

Plywood Wall Sheathing

Install Window Frames

Install Exterior Door Frames

Set Solatube Mounts & Roof Hatch Curb

Lath & Flashing for Plaster

Glazing

Insulation Board

Flashings & Sealants

Install Roofing System

Plaster

Install Solatubes

Install Metal Roof

Tile @ Drinking Fountains

Install Drinking Fountains

Paint @ Exterior

Insulation @ Roof Decks

Interior Framing

Rough-in Fire Sprinkler

Rough-in In-wall Electrical

Rough-in In-wall Plumbing

R-I Overhead Mechanical Units & Ducts

Install In-wall Insulation

Drywall

Tape & Finish Drywall

Sheet 42 of 43

Page 43: SUBAOrig Target 1 % Early 2012 2013 J F M A M J J A S O N ...departments.bcsd.com/mot/addendums/Addendum 1/01-08... · Activity ID Activity Description SUBAOrig Dur Target 1 Orig

Sheet 43 of 43

ActivityID

ActivityDescription

SUBAOrigDurTarget 1Orig Dur

RemDur% Early

StartEarlyFinish

TotalFloat

92080 Ceramic Tile 10 30AUG12 14SEP12 88

92100 Prime Paint 2 04SEP12 07SEP12 93

92220 Pull wires & Terminate 3 04SEP12 10SEP12 99

92280 Install Fire Sprinkler Heads 2 10SEP12 11SEP12 125

92600 Install Solatube Diffusers 2 10SEP12 11SEP12 125

92340 Install Lighting & L.V. Electrical Devices 3 11SEP12 13SEP12 123

92400 Hang Doors 2 17SEP12 18SEP12 88

92450 Install Door Hardware 2 19SEP12 20SEP12 118

92480 Finish Paint 5 19SEP12 25SEP12 88

92740 Install Roof Ladder & Hatch 2 26SEP12 27SEP12 113

92660 Finish Mechanical Controls 5 26SEP12 02OCT12 88

92680 Finish Electrical 5 26SEP12 02OCT12 88

92620 Install Plumbing Fixtures 6 26SEP12 03OCT12 105

92760 Toilet Accessories 4 04OCT12 09OCT12 105

92780 Touch-up Paint 3 10OCT12 12OCT12 105

Clean-up / Punchlist 94940 Start-up & Test Systems 10 03OCT12 16OCT12 88

94960 Clean-Up Bldg. R 3 15OCT12 17OCT12 105

94950 Commissioning 15 17OCT12 06NOV12 88

94980 Punchlist Bldg. R 10 07NOV12 21NOV12 88

2012 2013J F M A M J J A S O N D J F M A M J J A S O N D JFEB

Ceramic Tile

Prime Paint

Pull wires & Terminate

Install Fire Sprinkler Heads

Install Solatube Diffusers

Install Lighting & L.V. Electrical Devices

Hang Doors

Install Door Hardware

Finish Paint

Install Roof Ladder & Hatch

Finish Mechanical Controls

Finish Electrical

Install Plumbing Fixtures

Toilet Accessories

Touch-up Paint

Start-up & Test Systems

Clean-Up Bldg. R

Commissioning

Punchlist Bldg. R