student: bingjie liu supervisor: dr. pedro ferreira msc ... · pdf fileprograms, midas has...
TRANSCRIPT
Figure 7: Open and Braced Excavation Problem
(Crisp manual)
Retaining wall
Numerical Analysis of A Novel Form of Underground ConstructionStudent: Bingjie Liu
Introduction
Aim
Methodology
Comparisons from three examples between CRISP and MIDAS
GTS/NX have been carried out as a benchmark process.
Terzaghi Consolidation
Figure 1: Proposed Cable
Stayed Cavern Design, Created
by Professor Anthony Swain
Nowadays due to the rapid growth of urban development, large
underground caverns,which can be used for transport systems and
water supply etc. have been popularly demanded in urban areas. [1] A
innovative construction method for underground caverns ,‘Cable
Stayed Cavern’ (Figure1), has been proposed by Professor Anthony
Swain. However, the ground movements, one of the most obvious
challenges caused by the excavation have to be predicted to prevent
any damages from the surrounding structures.
1. To provide the methods of setting up
consolidation analysis problems in
MIDAS GTS/NX to other users and
validate the use of MIDAS in
consolidation analysis as well.
2. To model the 3D underground cavern
with corresponding excavation
sequences in MIDAS GTS/NX to find the
resulting ground movements.
The methodology of this project contained the benchmarks between
CRISP and MIDAS GTS/MX to validate the use of MIDAS, which is
being new (a few month) to the department of geotechnical problems.
Three same examples were applied in both programs and the results
were compared to verify MIDAS. After benchmarking these two
programs, MIDAS has been used to model the 3D cavern with
corresponding excavation sequences.
Benchmarks
Supervisor: Dr. Pedro Ferreira
Msc Civil Engineering
-0.100
-0.090
-0.080
-0.070
-0.060
-0.050
-0.040
-0.030
-0.020
-0.010
0.000
0 10 20 30 40 50 60 70 80 90 100 110
Vertical disp.(MIDAS)
Vertical disp. (CRISP)
Time (Nodal value) (Day)
Ver
tica
l d
isp
lace
men
t (
Nod
al
valu
e)
(m)
-1
-0.9
-0.8
-0.7
-0.6
-0.5
-0.4
-0.3
-0.2
-0.1
0
0 10 20 30 40 50 60 70 80 90 100 110
Exce
ss P
ore
Pre
ssu
re (
kN
*m
-2)
Excess pore pressure (MIDAS)
Excess pore pressure (CRISP)
Normalized excess pore pressure(Hand)
Time (Nodal value) (Day)
Open and Braced Excavation
This one-dimensional Terzaghi
consolidation problem has been chosen
and is represent in Figure 2. The
pressure on the top surface was kept
constant during the consolidation
process and the drainage constraint is
only applied at the top, i.e. set to zero
pressure, while other edges were
undrained to allow excess pore pressure
to build up then dissipate to the surface.
Figure 2: Terzaghi
Consolidation Problem
(Midas manual)
Figure 3: Mesh
example for
MIDAS
Figure 4: Mesh
example for
CRISP
Figure 8: Mesh example for MIDAS
Figure 9: Mesh example for CRISP
Figure 5: Vertical Displacement against Time for Corresponding
nodes in CRISP and MIDAS
Vertical Displacement
Excess pore pressure
Figure 6: Excess pore pressure against Time for corresponding nodes
in CRISP and MIDAS
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
0 1 2 3 4
Ve
rtic
al d
isp
lace
me
nt
(No
de
Val
ue
) (m
)
X Coordinate (Node value) (m)
MIDAS (super imposed element method)(4-node- element)MIDAS (change property method)(4-node-element)CRISP
Basement Heave
0.000
0.010
0.020
0.030
0.040
0.050
0.060
0.070
0.080
0.090
0.100
0 1 2 3 4
Ve
rtic
al d
isp
lace
me
nt
(No
de
Val
ue
) (m
)
X Coordinate (Node value) (m)
MIDAS (super imposed element method)(8-node- element)MIDAS (change property method)(8-node-element)CRISP
Basement Heave
7
7.4
7.8
8.2
8.6
9
9.4
9.8
10.2
-0.070 -0.066 -0.062 -0.058 -0.054 -0.050 -0.046 -0.042 -0.038
Y C
oo
rdin
ate
(N
od
al V
alu
e)
(m)
Horizontal displacment (Nodal value) (m)
MIDAS (super imposed elementmethod)(4-node- element)MIDAS (change property method)(4-node- element)CRISP
Wall Deflection
7
7.4
7.8
8.2
8.6
9
9.4
9.8
10.2
-0.070 -0.066 -0.062 -0.058 -0.054 -0.050 -0.046 -0.042 -0.038
Y C
oo
rdin
ate
(N
od
al V
alu
e)
(m)
Horizontal displacment (Nodal value) (m)
MIDAS (super imposed elementmethod)(8-node- element)MIDAS (change propertymethod)(8-node- element)CRISP
Wall Deflection
2D Embankment Consolidation
Vertical Displacement Vertical Displacement
10m
1.4m
20m
Figure 14: 2D Embankment Consolidation (MIDAS manual)
Figure 10: Vertical Displacement against X Coordinate for
Corresponding Nodes in CRISP and MIDAS (4-node-element)
Figure 11: Vertical Displacement against X Coordinate for
Corresponding Nodes in CRISP and MIDAS (8-node-element)
Figure 12: Y Coordinate against Horizontal Displacement for
Corresponding Nodes in CRISP and MIDAS (4-node-element)
Figure 13: Y Coordinate against Horizontal Displacement for
Corresponding Nodes in CRISP and MIDAS (-node-element)
Figure 15: Mesh example for MIDAS Figure 16: Mesh example for CRISP
-0.70
-0.60
-0.50
-0.40
-0.30
-0.20
-0.10
0.00
0 250 500 750 1000 1250 1500 1750 2000 2250 2500 2750 3000 3250
Ve
rtic
al D
isp
lace
me
nt
(m)
Time (day)
CRISP (Elastic) MIDAS (Elastic)
Vertical Displacement
-0.18
-0.16
-0.14
-0.12
-0.1
-0.08
-0.06
-0.04
-0.02
0
0 250 500 750 1000 1250 1500 1750 2000 2250 2500 2750 3000 3250V
erti
cal D
isp
lacm
ent
(m)
Time (day)
MIDAS (Modified Cam Clay)
CRISP(Modified Cam Clay)
MIDAS (Modified Cam Clay,input pc)
Vertical Displacement
3D Cavern in MIDAS
Figure 17: Vertical Displacement against Time for Corresponding
Nodes in CRISP and MIDAS (Elastic) Figure 18: Vertical Displacement against Time for Corresponding
Nodes in CRISP and MIDAS (Plastic)
Figure 19: Assembled Structures with Cables Figure 20: All Geometry Parts
Figure 21:Effective Vertical Stress Distribution at
In-situ Stage
1. Good agreement between CRISP and MIDAS in elastic analysis.
2. The differences of results between CRISP and MIDAS can be
decreased by increasing the number of nodes per element.
3. Bad agreement between CRISP and MIDAS in plastic analysis
perhaps because of input pre-consolidation pressure 𝑝𝑐′ and initial
void ratio𝑒0.
4. The vertical effective stress redistributed during the 3D cavern
excavation, with decreases after excavation and increases after the
following concrete lining installation.
Conclusions
Reference:
1. Attewell, P.B., Yeates, J., and Selby, A.R. (1986). Soil movements
induced by tunnelling and their effects on pipelines and structures,
Blackie, Glasgow, Scotland, p.325.
Figure 23:Vertical Stress after Soil
excavation
Figure 22:Vertical Stress at
In-situ Stage
Figure 24:Vertical Stress after Shaft
Installation