stevens creek steelhead passage improvement …...stevens creek steelhead passage improvement...
TRANSCRIPT
Stevens Creek Steelhead Passage Improvement Project Feasibility Report
Prepared for:
Friends of Stevens Creek Trail
Prepared By:
DOMENICHELLI & ASSOCIATES
CIVIL ENGINEERING
1101 Investment Blvd., Suite 115
El Dorado Hills, CA 95762
November, 2017
Friends of Stevens Creek Trail PAGE i DOMENICHELLI & ASSOCIATES, INC.
TABLE OF CONTENTS
Table of Contents ............................................................................................................................. i
Table of Figures .............................................................................................................................. ii
Table of Tables .............................................................................................................................. iii
Section 1 – Background .................................................................................................................. 1
Introduction and Purpose ............................................................................................................ 1
Barrier Mitigation Projects ......................................................................................................... 1
Hydraulic Analyses ..................................................................................................................... 4
Flood Control Impacts ............................................................................................................ 5
Fish Passage Hydraulics ......................................................................................................... 5
Alternatives Analysis .................................................................................................................. 6
Preliminary Designs and Recommendations .............................................................................. 6
Section 2 – Detailed Project Analyses ............................................................................................ 7
Moffett Drop Structure and Downstream Channel – HL01 & HB 02 ........................................ 7
Alternative Identified for Drop Structure and Downstream Channel ..................................... 9
Hydraulic Considerations...................................................................................................... 10
Costs and Constructability Considerations ........................................................................... 12
Conclusions – Moffett Drop Structure and Downstream Channel – HL01/HB02 ............... 13
Hetch Hetchy Pipeline Drop Structure – HB 05/06 .................................................................. 14
Conclusions – Hetch Hetchy Drop Structure – HB05/06 ..................................................... 17
Highway 85 crossing (un-numbered) ........................................................................................ 18
Conclusions – Un-Numbered Crossing for Highway 85 ...................................................... 20
El Camino Real Crossing – HB 13 ........................................................................................... 21
Conclusions – El Camino Real – HB13 ................................................................................ 23
Highway 85 Crossing near Village Court – HB 15 .................................................................. 24
Conclusion – Highway 85 near Village Court – HB15 ........................................................ 26
Highway 280 Crossing– HB 20 ................................................................................................ 27
Conclusion – Highway 280 Crossing– HB20 ....................................................................... 30
Deep Cliff Golf Course – HB 28 .............................................................................................. 31
Conclusion – Deep Cliff Golf Course – HB28 ..................................................................... 33
Gauge Station Weir (HB 32) ..................................................................................................... 34
Friends of Stevens Creek Trail PAGE ii DOMENICHELLI & ASSOCIATES, INC.
Conclusion – Gauge Station Weir – HB32 ........................................................................... 35
Section 3 – Summary of Project Conclusions and Recommendations ......................................... 36
References ..................................................................................................................................... 37
Appendix A – Conceptual Design Drawings ................................................................................ 38
Appendix B – Hydraulic Calculations .......................................................................................... 38
Appendix C – Cost Estimates ....................................................................................................... 38
TABLE OF FIGURES
Figure 1. Project Location Map ..................................................................................................... 2
Figure 2. Existing Drop Structure and Fish Ladder ....................................................................... 8
Figure 3. Downstream Concrete Channel (approx. 800 lineal feet) .............................................. 8
Figure 4. Step at Downstream end of Channel past Highway 101 ................................................ 9
Figure 5. New Concrete Fish Ladder Option with Existing Denil Ladder Shown ........................ 9
Figure 6. Moffett Drop Downstream Channel Alternatives ........................................................ 10
Figure 7. Hetch Hetchy Drop (PWA, 2005) ................................................................................. 14
Figure 8. Rendering Taken from PWA Report (2005) ................................................................. 15
Figure 9. Drop Structure Option 2, Above Grade Concrete Fish Ladder ..................................... 16
Figure 10. Drop Structure Option 3, Cut-in and Baffle Weirs...................................................... 16
Figure 11. Highway 85 Crossing with no flow ............................................................................. 18
Figure 12. Highway 85 Crossing at 40 to 50 cfs........................................................................... 19
Figure 13. Existing Baffles Upstream of Highway 85 Crossing .................................................. 20
Figure 14. Culvert at El Camino Real .......................................................................................... 21
Figure 15. Baffle Option from (PWA, 2005) ............................................................................... 22
Figure 16. Rock Baffle Option..................................................................................................... 23
Figure 17. Existing Conditions at Highway 85 Crossing (PWA 2005) ....................................... 24
Figure 18. Proposed Rendering of Rock Baffles ......................................................................... 25
Figure 19. Proposed Rock Placement within Culvert .................................................................. 26
Figure 20. Highway 280 Culvert Crossing .................................................................................. 27
Figure 21. Highway 280 Culvert Crossing, Low Flow in the Arch Culvert ................................ 27
Figure 22. Highway 280 Culvert Crossing .................................................................................. 28
Figure 23. Proposed Low Flow Culvert Rock Baffles ................................................................. 29
Figure 24. Existing Golf Course Low Water Crossing ................................................................ 31
Figure 25. Rendering of Proposed Rock Baffles ......................................................................... 32
Friends of Stevens Creek Trail PAGE iii DOMENICHELLI & ASSOCIATES, INC.
Figure 26. Golf Course Rock Baffle Schematic .......................................................................... 32
Figure 27. Existing Conditions of Gauge Station Weir ............................................................... 34
Figure 28. Rendering of Proposed Rock Weirs at Gauge Station ................................................ 35
TABLE OF TABLES
Table 1. List of Projects ................................................................................................................. 3
Table 2. Fish Passage Criteria ........................................................................................................ 5
Table 3. Moffett Drop Alternatives HL01/HB02 – Flood Hydraulic Analysis Results ............... 11
Table 4. Hydraulic Results for Adult Fish Passage – Moffett Drop Structure HL01/HB02 ....... 11
Table 5. Opinion of Probable Construction Costs – Moffett Drop Structure – HL01/HB02 ....... 12
Table 6. Constructability & Permitting Issues .............................................................................. 13
Table 7. Opinion of Probable Construction Costs – Hetch Hetchy Drop Structure – HB05/06 . 17
Table 8. Opinion of Probable Construction Costs – Un-Numbered Crossing for Highway 85.... 20
Table 9. Opinion of Probable Construction Costs – El Camino Real – HB13 ............................. 23
Table 10. Opinion of Probable Construction Costs – Highway 85 near Village Court – HB15 .. 26
Table 11. Opinion of Probable Construction Costs – Highway 280 Crossing– HB20 ................. 30
Table 12. Opinion of Probable Construction Costs – Deep Cliff Golf Course – HB28 .............. 33
Table 13. Opinion of Probable Construction Costs – Gauge Station Weir – HB32 .................... 35
Table 14. Summary of Findings and Recommendations .............................................................. 37
Friends of Stevens Creek Trail PAGE 1 DOMENICHELLI & ASSOCIATES, INC.
SECTION 1 – BACKGROUND
Introduction and Purpose
Stevens Creek has been identified as a priority for steelhead population restoration by the Fisheries
and Aquatic Habitat Collaborative Effort (FAHCE), which includes federal, state and local
stakeholders. The FAHCE is in the process of developing a Fish Habitat Conservation Plan for
three local watersheds including Stevens Creek for the purpose of seeking to balance and integrate
all beneficial uses of the local water source including drinking water, flood protection, recreation
and fisheries. The Santa Clara County Creeks Coalition (SCCCC) is a local organization involved
in advancing the goals of the FAHCE and has administered the efforts involved in this study on
behalf of the Friends of Stevens Creek Trail organization.
This Study is funded by a grant from the Santa Clara Valley Water District (District), with
additional funding from the City of Mountain View, City of Cupertino, City of Sunnyvale, Mid-
Peninsula Regional Open Space District, and Friends of Stevens Creek Trail.
Since the development of the FAHCE program, significant fish passage enhancement on Stevens
Creek have been completed, however, there are still several barriers that have been identified in
past studies that are considered features that can potentially hinder steelhead migration. Studies
used as primary sources for this report include:
1. Santa Clara Valley Water District (SCVWD), Stewardship Initiative: Stevens Creek Fish
Barrier Assessment, Philip Williams & Associates, Ltd., May 19, 2005. (PWA, 2005)
2. Stevens Creek Fish Passage Assessment, Highway 101 to Moffett Drop Structure, Michael
Love & Associates, Inc., April 28, 2016. (LOVE, 2016)
Other sources gathered by SCCCC and referenced in this feasibility analysis are listed at the end
of this report.
To continue efforts to enhance steelhead passage in Steven Creek, Domenichelli & Associates Inc.
(D&A) was contracted by the SCCCC to prepare a Feasibility Report to develop preferred
alternatives at eight (8) locations on Stevens Creek chosen by the SCCCC to remediate steelhead
migration impediments. The project scope was focused on solutions that meet standard fish
passage criteria for the selected barriers. The severity of the passage impediments and a
quantitative analysis of the benefits of solutions to the overall stream system was not requested by
the SCCCC and would be beyond the scope of this study. This report provides hydraulic analyses,
conceptual drawings and opinions of probable costs for preferred projects at the selected locations.
Other alternatives identified at each location are also addressed in this report and are compared to
the selected options.
Barrier Mitigation Projects
Figure 1 provides a map of the eight locations selected for further analysis by the SCCCC. These
projects begin near the Stevens Creek stream crossing of Highway 101, and extend upstream to a
gauging station just downstream from Stevens Creek Reservoir.
Friends of Stevens Creek Trail PAGE 2 DOMENICHELLI & ASSOCIATES, INC.
Figure 1. Project Location Map
The projects include concrete channels with significant drops and shallow depths at lower flows,
major culvert crossings with flat wide bottoms creating shallow depths at low flows and a low
water (concrete) vehicular crossing. A short description of each site is provided below in Table 1.
Moffett Federal Airfield Mountain View, CA
Stevens Creek Reservoir
Friends of Stevens Creek Trail PAGE 3 DOMENICHELLI & ASSOCIATES, INC.
Table 1. List of Projects
Barrier
Number * Name
Barrier
Classification Proposed Alternatives
HL01, HB 02
Moffett Blvd Drop
Structure and
Downstream
Channel
Drop Structure
& Concrete
Channel
1. Retain existing fish ladder with low flow
channel downstream
2. New vertical slot fish ladder with low flow
channel downstream
3. Rock weirs and scour pools with low flow
channel downstream
4. Replace west concrete bank with vertical wall
and cut wider natural low flow channel
HB 05/06
Hetch Hetchy
Pipeline
Encasement
Drop Structure
& upstream
Concrete
Channel
1. Stepped rock weirs & pools
2. Fish ladder at drop
Unnumbered
Highway 85
Crossing near
Central Ave.
Box Culvert 1. Cut low flow channel into floor of culvert
2. Add upstream weir
HB 13 El Camino Real
Crossing Arch Culvert
1. Add vanes or baffles
2. Cut low flow channel into floor of culvert
HB 15
Highway 85
Crossing near
Village Court
Box Culvert 1. Add vanes or baffles
2. Cut low flow channel into floor of culvert
HB 20 Highway 280
Crossing Arch Culvert
1. Add vanes or baffles
2. Cut Low flow channel
HB 28 Deep Cliff Golf
Course
Low Flow
Vehicle
Crossing
1. Remove crossing
2. Replace with stepped rock weir and pool ladder
HB 32 Stevens Creek
Park Stream Gauge Gauging Weir 1. Add stepped rock weir and pool fish ladder
2. Deepen pool above weir
*Source of Numbering and Barrier Identifications – 1) SCVWD 2002 Draft List of Fish Passage
Impediments, 2) PWA Report 2005.
Friends of Stevens Creek Trail PAGE 4 DOMENICHELLI & ASSOCIATES, INC.
The SCVWD list referenced above as a source of the numbering, includes all eight barriers except
the Highway 85 crossing labeled “Unnumbered”. The SCVWD list described the barriers in this
study as partial barriers with low “constraint ratings” with the exception of the Moffett Drop
(ladder) and downstream channel. These were given a low to moderate rating for the drop and
ladder, and a high constraint rating for the downstream channel.
The Moffett Drop Structure and Downstream Channel is considered a higher constraint to fish
migration due to the drop height, sedimentation issues with the existing Denil ladder and the
inadequate depths of flows in the downstream trapezoidal concrete channel. These combined
issues result in a significant impediment to both migrating adult and juvenile steelhead at this reach
of Stevens Creek.
As mentioned above, the remaining seven projects are listed as barriers of varied and lesser degree
of constraints to passage, when compared to the Moffett reach. For example, the drops are all
smaller in height, from 2 to 3 feet at the Hetch Hetchy site to approximately 1 to 1.5 feet at the
Deep Cliff Golf Course and the Stevens Creek Park Gauging Station. The two structures with less
than 2 foot drops are classified as juvenile migration impediments only. These barriers are located
in the upper stream reaches where good rearing habitat exists. The Hetch Hetchy and Moffett
reaches are located farther downstream in less suitable habitat, with focus on upstream migrating
adult passage.
Of the remaining structures, four (4) are large culvert/bridge crossings where flat channel bottoms
with very little gradient create long, relatively shallow flow profiles as the stream flows recede.
Due to these hydraulic conditions, most of these culverts have a significant amount of sediment
deposition. This limits the ability to add features to direct and concentrate flow, such as baffles as
describe in previous studies (PWA 2005). Such in-stream structures would decrease flood
conveyance. In fact, at some locations, the current flood models rely on sediment transport during
high flows that would scour out the sediment down to the original culvert bottoms. Therefore,
constructing any permanent structures at the existing (observed) channel bottom elevations would
create excessive flood flow obstruction. Addressing these sites with their dynamic geomorphic
conditions are hydraulically the more challenging projects.
Although the Moffett Drop and Downstream Channel project is described as the greatest fish
passage impediment of the eight (8) selected projects discussed in this report, some of the others
are more easily mitigated relative to permitting, constructability and costs. Therefore, the ability
to address multiple lower priority barriers initially should be considered.
Hydraulic Analyses
In order for the study projects to be considered feasible, they must pass hydraulic analysis for both
fish passage criteria as well as flood conveyance neutrality. Hydraulic modeling of alternatives
for this study requires flood flow conveyance analysis as an initial check to assure that flooding
potential is not increased due to the proposed improvements. Once it is determined that the project
will not increase flood elevations (flood neutral), then a more focused hydraulic analysis of the
project features is necessary to show that the solution is effective to pass fish at lower (than flood
stage) flows per standard fish passage criteria.
Friends of Stevens Creek Trail PAGE 5 DOMENICHELLI & ASSOCIATES, INC.
Flood Control Impacts
To assess flood flow impacts, detailed HEC-RAS models were created for each site from the latest
flood control model provided by the District. These separate focused models were extracted from
the District flood model with end conditions calibrated to mirror results of the District’s overall
existing conditions model results. Some alternatives will clearly create flood impacts due to
significant obstructions to flow or increased channel roughness. Detailed modeling for these
alternatives are not presented, where the impacts can be simply identified and discussed.
Fish Passage Hydraulics
Each project alternative considered must meet a minimum requirement for fish passage to be
deemed feasible. For conventional fish ladder alternatives, standard equations are used (with
spreadsheets) to establish hydraulics to meet passage criteria. Low flow channels cut into concrete
channel bottoms can utilize the same HEC-RAS models used for the flood control analysis. When
using rock weir and pool ladder arrangements, simple weir calculations can approximate water
levels to establish surface profiles through the proposed system. For baffle systems through
culverts to concentrate low flows, the HEC-RAS models can again be used to show the
effectiveness of these features to meet depth and velocity requirements.
Criteria for steelhead fish passage are provided below in Table 2 (LOVE, 2016). The minimum
and maximum flow rates were established for the Moffett Drop and Downstream Channel project
reach in the 2016 (LOVE) study. These values were also used for the Hetch Hetchy project just
upstream for this study. The other criteria in Table 2 originated from standard criteria established
by the State Department of Fish and Wildlife.
Table 2. Fish Passage Criteria
Criteria (established by SCVWD) Juvenile
Steelhead
Adult
Steelhead
Minimum Flow Depth (feet) 0.3 ft 0.8 ft
Minimum Flow Rate (cubic feet/second) 8 cfs 16 cfs
Maximum Flow Rate (cubic feet/second) 14 cfs 70 cfs
Maximum flow velocity for sustained
swimming (feet per second) 1.5 fps 6.0 fps
Maximum flow velocity for short duration
bursts (feet per second) 3.0 fps 10.0 fps
Maximum water surface drop (feet) 0.5 ft 1.0 ft
In addition to the criteria listed above, duration for sustained and burst swimming without rest are
also important criteria. The duration is the same for both adults and juveniles; 30 minutes for
sustained swimming and 5 seconds for short bursts.
Regarding fish passage criteria, reference has been made in previous studies for providing passage
for both adult and juvenile steelhead. From review of the Stevens Creek stream conditions relative
to the location of the barrier projects, further assessment has been made to consider the practicality
of solutions relative to the benefit of meeting juvenile passage criteria. Spawning and rearing
habitat is less suitable in the lower reaches of the creek where there is more concrete lining, less
cover, anticipated higher water temperatures (farther from the cold-water source), and less coarse
Friends of Stevens Creek Trail PAGE 6 DOMENICHELLI & ASSOCIATES, INC.
gravel materials for spawning. The lower reaches also contain the more difficult passage
challenges and costly solutions such as the Moffett Drop reach and the Hetch Hetchy Crossing.
With upstream juvenile passage criteria requiring lower velocities and smaller jump heights, much
longer and complex features are required. Given the limited benefit at significantly higher costs,
this study does not provide improvements for upstream juvenile passage in the lower reaches,
downstream of the El Camino Real Crossing.
Alternatives Analysis
After defining each project alternative and completing analyses of the hydraulics relative to flood
control and fish passage feasibility, alternatives were ranked based on ability to meet hydraulic
criteria goals, preliminary costs, permit-ability, and to a lesser degree aesthetic value. Some
alternatives were eliminated for hydraulic reasons or by inspection, where an option of similar
hydraulic feasibility could be constructed at significantly less cost. Therefore, cost estimates were
not prepared for all alternatives. Preferred projects were selected from viable alternatives for each
project location. Some sites have only one option and some have several.
Preliminary Designs and Recommendations
Preliminary design drawings are provided for each preferred project. These drawings include
conceptual plans and profiles adequate to describe the features and to refine cost estimates.
A summary of recommendations including overall project costs for each site is provide at the
conclusion of this report.
Friends of Stevens Creek Trail PAGE 7 DOMENICHELLI & ASSOCIATES, INC.
SECTION 2 – DETAILED PROJECT ANALYSES
Moffett Drop Structure and Downstream Channel – HL01 & HB 02
Figures 2 and 3 provide photos of the existing Moffett Drop Structure and downstream channel.
The project barrier is comprised of: 1) the drop structure (approximately 6 feet high) with an
existing Denil fish ladder, 2) approximately 800 feet of trapezoidal concrete channel, 3) the
Highway 101 culvert crossing and 4) a second drop of approximately 2.5 feet downstream from
the Highway 101 crossing.
A previous study (LOVE 2016) indicates that the Denil ladder at the drop structure can pass adult
steelhead for approximately 60% of the target fish passage flows when the ladder and tail pool are
clear of sediment. This is a good passage total, however, in a 2010 study by the District’s Capitol
Program Service Division (FAHCE Stevens Creek Fish Passage Enhancement), it was pointed out
that the Denil type ladder is obsolete based on current fish passage standards and are now
considered partial barriers primarily due to sediment and debris blockage that can occur within the
steel weir structures of the fish ladder. As seen in Figure 2 below, the ladder is passing minimal
flow and the tailwater pool is completely filled with sediment.
The downstream concrete channel has two distinct reaches, one upstream of Highway 101 and one
downstream. The upstream reach is a trapezoidal channel where flow depths are the main issue
when the flows are less than 70cfs. The reach downstream of Highway 101 to the concrete apron
drop is a wider channel which results in shallower depth than the upstream reach. Per the 2016
LOVE report, there are no (fish passage) flows that meet the adult passage depth criteria for this
reach.
The Highway 101 culvert crossing provides a narrower flow path than the adjacent open channel
reaches, therefore the depth criteria is met once flow exceeds 40cfs. Lower flows will still result
in a depth issue for passage through the culvert.
The water surface drop at the downstream end of the concrete channel is slightly greater than the
one-foot criteria, up to approximately 60cfs. In addition, the downstream pool is relatively shallow
making the jump onto the concrete apron more difficult at lower flows.
As stated previously, mitigation for this project will include features to pass adult steelhead only.
Upstream movement of juveniles will not be addressed due to extensive costs resulting in nominal
benefit.
Friends of Stevens Creek Trail PAGE 8 DOMENICHELLI & ASSOCIATES, INC.
Figure 2. Existing Drop Structure and Fish Ladder
Figure 3. Downstream Concrete Channel (approx. 800 lineal feet)
Friends of Stevens Creek Trail PAGE 9 DOMENICHELLI & ASSOCIATES, INC.
Figure 4. Step at Downstream end of Channel past Highway 101
Alternative Identified for Drop Structure and Downstream Channel
Drop Structure Alternative- Three basic options have been identified to assist fish migration past
the drop structure. These options include:1) use the existing Denil ladder, 2) replace the Denil
ladder with an improved concrete ladder or 3) provide a (grouted) rock weir and pool ladder.
Figure 5 below shows the new fish ladder (Option 2) superimposed over the existing ladder.
Figure 5. New Concrete Fish Ladder Option with Existing Denil Ladder Shown
Concrete Channel- For the concrete channel downstream of the drop structure, all options include
a new low flow channel to maintain passage flow depths and acceptable velocities. Variations on
the type of downstream low flow channel are presented in Figure 6. Each variation could be used
with any of the three options presented above for the drop structure passage.
Friends of Stevens Creek Trail PAGE 10 DOMENICHELLI & ASSOCIATES, INC.
Figure 6. Moffett Drop Downstream Channel Alternatives
Hydraulic Considerations
The above fish passage alternatives for the Moffett drop structure and downstream concrete
channel were analyzed for flood flow impacts in this study. The proposed alternative conditions
are compared to the existing conditions to show potential impacts.
The existing conditions HEC-RAS model begins downstream of the Highway 101 bridge crossing
and extends upstream above the Moffett drop. At a 100-yr event flow of 5,500cfs, water surface
elevations reach near the top of the existing channel banks and show breach potential at several
locations. Any increase in flood elevations caused by fish passage mitigation alternative would be
considered significant impacts.
Model runs with Alternative 3 (rock weir ladder) and/or Option B (rock weir channel) were found
to be unacceptable due to increased water surface elevations during major storm events.. This was
a result of adding rocks that increased surface roughness and conveyance constraints within the
concrete channel. Therefore, the alternatives containing these features were no longer considered.
The following Table 3 summarizes results of multiple HEC-RAS models to assess the flood
impacts of the hydraulically viable alternatives. These alternatives provide combinations of the
drop structure options with appropriate downstream channel improvement options. Detailed model
output is provided in Appendix B for the preferred project and other alternatives of interest.
Friends of Stevens Creek Trail PAGE 11 DOMENICHELLI & ASSOCIATES, INC.
Table 3. Moffett Drop Alternatives HL01/HB02 – Flood Hydraulic Analysis Results
Alternative 100-yr Flow
(cfs)
Change in
100yr WSE
Meets Flood Flow
Criteria
Existing Conditions 5,500 Baseline yes
1A. Use Existing Ladder with new
Concrete low flow channel 5,500 None yes
2A. New Wider, Longer Ladder with
Concrete low flow channel 5,500 None yes
1C. Use Existing Ladder & Cut Wide
Vegetated Low Flow with vertical wall
to add conveyance
5,500 None Yes, but requires on-going
vegetation maintenance
2C. New Wider, Longer Ladder & Cut
Wide Vegetated Low Flow with vertical
wall to add conveyance
5,500 None Yes, but requires on-going
vegetation maintenance
As seen above these four alternatives listed show insignificant potential impact to flood
conveyance. However, options including the wide vegetative low flow channel would require
ongoing maintenance to assure that vegetation growth does not choke off the added conveyance.
This would result in a condition that will not meet flood flow criteria.
Relative to adult fish passage criteria, the existing drop and downstream channel do not adequately
meet depth and velocity requirements as presented previously. The Denil ladder has limitations
due to reoccurring sediment blockage. Table 4 summarizes the effectiveness of the four
alternatives to meet adult steelhead passage criteria.
Table 4. Hydraulic Results for Adult Fish Passage – Moffett Drop Structure HL01/HB02
Alternative
Channel
Meets
Minimum
Depth
Channel Meets
Velocity
Criteria
Meets Ladder flow,
jump and slope criteria
Existing Conditions Only portions at
higher flows Most flows
Ladder blockage issues
limit flows
1A. Use Existing Ladder with new
Concrete low flow channel yes yes
Ladder blockage issues
limit flows
2A. New Wider, Longer Ladder with
Concrete low flow channel yes yes yes
1C. Use Existing Ladder & Cut Wide
Vegetated Low Flow with vertical wall
to add conveyance
yes yes Ladder blockage issues
limit flows
2C. New Wider, Longer Ladder & Cut
Wide Vegetated Low Flow with vertical
wall to add conveyance
yes yes yes
From Tables 3 and 4, Alternatives 2A and 2C meet all the hydraulic criteria (flood protection and
fish passage), with Alternative 2C requiring more extensive maintenance. Alternative 1A can also
meet all the passage criteria if sediment build up could be avoided.
Friends of Stevens Creek Trail PAGE 12 DOMENICHELLI & ASSOCIATES, INC.
Sedimentation Considerations
As previously stated, sedimentation and debris build up in the Denil ladder has been an ongoing
issue. Replacement with a wider ladder, with less baffles and slotted openings will improve this
condition, however, a detailed sediment analysis is recommended to show the degree of improved
operations and maintenance before proceeding with design. This would also be the case for the
low flow channel. The slope of the proposed low flow channel is steeper than the main channel
by providing a continuous grade eliminating two drops. This will provide higher velocity than in
the main channel and more energy to carry sediment downstream. However, a detailed sediment
analysis would also demonstrate the effectiveness of this feature.
Costs and Constructability Considerations
The lowest cost alternative would be to use the existing ladder and cut a low flow channel
(Alternative 1A). All others will require significant demolition and construction of major in-
channel improvements.
Table 5 below lists preliminary opinions of probable construction costs for Alternatives 1A, 2A,
1C & 2C. Detailed cost information is provided in Appendix C. Total project costs for the
preferred projects are summarized in the Conclusion of this report.
Table 5. Opinion of Probable Construction Costs – Moffett Drop Structure – HL01/HB02
Alternative
Mob/ Site
Prep and
Demolition
costs
Low Flow
Channel
costs
Fish
Ladder
costs
Total Construction
Cost with a 25%
Contingency
1A. Use Existing Ladder with new
Concrete low flow channel $307,000 $560,000 15,000 $1,103,000
2A. New Wider, Longer Ladder with
Concrete low flow channel $342,000 $560,000 $260,000 $1,453,000
1C. Use Existing Ladder & Cut Wide
Vegetated Low Flow with vertical wall
to add conveyance
$479,000 $2,040,000 $15,000 $3,352,000
2C. New Wider, Longer Ladder & Cut
Wide Vegetated Low Flow with
vertical wall to add conveyance
$499,000 $2,040,000 $260,000 $3,682,000
25% contingency includes: unknowns at this conceptual level of design
When considering constructability, it is important to understand that construction issues may
increase costs over current estimates, may create obstacles that will require a different approach
or may create a permitting problem that will be difficult to overcome. Table 6 presents some
constructability issues that are identified for the three alternatives brought forward in this analysis.
Friends of Stevens Creek Trail PAGE 13 DOMENICHELLI & ASSOCIATES, INC.
Table 6. Constructability & Permitting Issues
Alternative Constructability Issues Ability to Permit
Cut Low Flow Channel &
Use Existing Ladder Channel access & dewatering
In-stream water quality
permitting issues
Moderate difficulty
Cut Low Flow Channel &
New Wider, Longer Ladder
Channel access & dewatering,
Shoring needed to stabilize
removal of existing ladder.
In-stream water quality
permitting issues
Moderate difficulty
Cut Wide Vegetated Low
Flow with vertical wall to
add conveyance & new
rock ladder
Channel access & dewatering
Removing existing channel wall
will create significant bank
stability issues, extensive haul out
of materials
In-stream water quality
permitting issues, State and
local flood control permitting
High difficulty
Permitting and Environmental Compliance
There are several permits that would be required to implement any of the alternatives. Work
performed within a streambed will require at a minimum: 1) a California Department of Fish and
Wildlife, Streambed Alteration Permit, 2) a State Regional Water Quality Control Board Permit
for addressing and monitoring water quality during construction and 3) review and approvals from
state and local agencies including the District for flood control. In addition, appropriate
encroachment permitting for work in associated rights of way will be required. Depending on the
presence of any listed species, permits could also extend to the federal level involving the US Fish
and Wildlife Service and the Army Corps of Engineers.
To comply with permitting and environmental regulatory processes will be time consuming and
costly. This project will at a minimum require a Mitigated Negative Declaration (MND) or
depending on preliminary environmental findings a complete Environmental Impact Report/ Study
(EIR/EIS).
Conclusions – Moffett Drop Structure and Downstream Channel – HL01/HB02
Based on the analyses presented above, Alternative 2A with a concrete low flow channel and a
new wider and longer conventional fish ladder best meets of all the fish passage objectives at the
least overall cost for this reach. Appendix A contains conceptual design drawings for the preferred
project. The plans show a vertical slotted ladder type for the new fishway. This type of ladder
allows for a less obstructed pathway (than the existing ladder) at a wide range of flows for fish
passage as well as for downstream flowing sediment. Other ladders such as a pool and weir type
ladder may be considered during final design.
Friends of Stevens Creek Trail PAGE 14 DOMENICHELLI & ASSOCIATES, INC.
Hetch Hetchy Pipeline Drop Structure – HB 05/06
The Hetch Hetchy Drop Structure is located approximately 1,900 feet upstream from the Moffett
Drop. This feature is comprised of a concrete structure acting as a channel grade control to protect
an existing 72-inch pipeline crossing beneath Stevens Creek. The encasement creates a 4.4 foot
drop in the channel bottom which creates a barrier for fish migration. This barrier is not as
pronounced as the Moffett Drop and includes a downstream weir that reduces the jump to between
2.3 and 2.5 feet during most migratory flows.
Similar to the Moffett Drop project, this barrier is in the lower reaches where much of the channel
is lined and upstream migration of adult steelhead is more critical. To meet the 1-foot maximum
jump, a new fish ladder with 2 or 3 jumps will be adequate. Previous analysis (PWA, 2005)
recommends a ladder that would cut into the existing structure. Figure 7 provides a photo of the
existing drop and Figure 8 is a rendering of the cut in ladder from the PWA report.
Figure 7. Hetch Hetchy Drop (PWA, 2005)
Friends of Stevens Creek Trail PAGE 15 DOMENICHELLI & ASSOCIATES, INC.
Figure 8. Rendering Taken from PWA Report (2005)
This approach would solve the barrier issue at this location with no hydraulic impact for flood flow
passage. Concerns with this alternative would be costs associated with cutting down to the
required foundation depth for the new ladder and the potential to conflict with the 72-inch pipeline
or other utilities crossing at this location. A retaining wall will also be required to support the bank
lining along the ladder, but this can be incorporated into the ladder construction. Regarding the
72-inch Hetch Hetchy pipeline, the crossing location is difficult to determine from as-built plans.
If it is close to the drop, then the cut-in ladder would not be feasible. If it is farther upstream (at
least 40 to 50 feet), then the cut-in ladder may be constructed as shown above. In fact, the ladder
shown from the PWA report is providing juvenile passage with 5 to 6-inch steps. A ladder
providing 1-foot steps would be much shorter and require less modification to the drop structure.
In any case, the San Francisco Public Utilities Commission (SFPUC), owner of the pipeline would
have to approve the modification. A properly designed concrete ladder structure that provides the
same level of protection for the pipe will be necessary. An option to the cut-in ladder would be to
construct an above grade ladder starting downstream and ending at the drop. Figure 9 below shows
this concept. This construction would be less costly and not require cutting into the drop structure,
but does protrude into the channel flow. Modeling of this alternative relative to flood flows
showed that the minor obstruction of the above grade features would cause a slight increase in the
flood water surface elevations just upstream of the drop. Given the increased water surface
elevation result, this alternative would not be considered feasible.
A third option that uses the cut in ladder approach would be to raise the existing downstream baffle
slightly and provide just one cut-in ladder step and a second short upstream baffle to provide added
upstream depth. This option shown in Figure 10 is less of an obstruction resulting in no net
increase in flood elevations, maintains structural integrity of the pipeline protection and is less
costly to construct than the other options presented. For these reasons, this third option is the
current preferred alternative. Appendix A shows a more detailed design layout for this alternative.
Friends of Stevens Creek Trail PAGE 16 DOMENICHELLI & ASSOCIATES, INC.
Figure 9. Drop Structure Option 2, Above Grade Concrete Fish Ladder
Figure 10. Drop Structure Option 3, Cut-in and Baffle Weirs
To confirm that the configuration for the preferred alternative will work properly for a wide range
of flows, detailed surveying of the downstream and upstream channel will be necessary during the
final design. Based on the photo above (Figure 7), the existing downstream baffle is submerged
with very little jump to cross into the upstream plunge pool. This is due to a raise in the
downstream channel (as shown on the as-built drawings) that is approximately 2 to 6-inches below
the top of the baffle. This allows for a raise in the baffle height as suggested for this design without
exceeding adult 1-foot step parameter. Per the PWA report, there is another critical riffle farther
upstream close to where the channel returns to an earthen bottom. Some minor grading to create
a low flow channel and one additional short baffle weir may be necessary. This can be determined
after detailed surveying during final design.
Another option to use a series of rock weirs as the ladder was also considered for this site.
However, this option would require means to anchor the rock into the existing concrete and bagged
(concrete) banks and grouting of the rock to assure they will remain during high flows. The
construction of a conventional ladder would be more reliable and use less material for significant
cost savings. Therefore, the rock system was not considered further.
Below is a summary of anticipated construction costs for the ladder installation alternatives at this
site.
Friends of Stevens Creek Trail PAGE 17 DOMENICHELLI & ASSOCIATES, INC.
Table 7. Opinion of Probable Construction Costs – Hetch Hetchy Drop Structure – HB05/06
Alternative
Mob/ Site Prep
and Demolition
costs
Ladder
Construction
costs
Fish Ladder costs
1. Cut -in ladder with 3 steps $81,300 $69,700 $189,000
2. Above grade ladder (not
Preferred due to flood flow) $69,700 $70,600 $176,000
3. Raise existing baffle and
shorter cut-in ladder $69,800 $49,000 $149,000
25% contingency includes: unknowns at this conceptual level of design
Conclusions – Hetch Hetchy Drop Structure – HB05/06
Based on the analyses presented above, Alternative 3 with a raised downstream baffle and a 2-
step cut-in ladder will be the preferred alternative for the Hetch Hetchy Drop Structure. Permits
for this project would be similar to those discussed for the Moffett Drop and Downstream Channel
Project. However, due to the reduced amount of work in the channel, the permit process and
environmental documentation should be less complex and time consuming. Obtaining approval
by the SFPUC for this project will be an added challenge.
Friends of Stevens Creek Trail PAGE 18 DOMENICHELLI & ASSOCIATES, INC.
Highway 85 crossing (un-numbered)
The Highway 85 crossing near Central Avenue is shown below and consists of a downstream weir
preceded by a drop of approximately 3 feet into a plunge pool created by the weir. This leads
upstream to a concrete box culvert under the highway. The main concerns described in previous
reports are the potential to strand fish in the plunge pool and the height of the drop. As seen in
Figure 12, the drop creates a jump greater than 1 foot (measured at 1.5 feet) during optimum
migratory flows. Relative to stranding, any time there is a plunge pool arrangement like this,
juvenile fish can be stranded and would need a means to move out of this local impediment.
Another issue observed in the field and considered a greater impediment by our study team was
the shallow depth in the culvert.
The goals for this site will be to provide a smaller jump at the drop and provide deeper water in
the upstream channel for fish to move past this location.
Figure 11. Highway 85 Crossing with no flow
Friends of Stevens Creek Trail PAGE 19 DOMENICHELLI & ASSOCIATES, INC.
Figure 12. Highway 85 Crossing at 40 to 50 cfs
The higher priority for adult passage is to provide depth upstream. In Figure 12 above, it is evident
that the wide flat bottom of the culvert creates a uniform shallow depth through the culvert even
when the flows are in the 40 to 50cfs range. At low flows, the depth would be well below
acceptable criteria.
Similar to the drop downstream of Highway 101 at the Moffett site, cutting in a low flow channel
will provide greater depth for migration at the same time reducing the jump from the plunge pool.
This will also provide more opportunity for juvenile fish to escape this location during lower flows.
The low flow channel would be in the center of the culvert and need only be approximately 0.8-
feet deep and 4-foot top width. This will add enough depth for passage and because it is a cut
section, will have no impact on flood water elevations. With this in mind, flood flow modeling
was not included for this site.
At the upstream end of the culvert, a series of baffles for fish passage exist. These baffles are not
shown on the as-built drawings and therefore, the tie in from the proposed low flow channel will
have to be determined with detailed surveying at a later date. Below is a photo of the upstream
baffle system.
Friends of Stevens Creek Trail PAGE 20 DOMENICHELLI & ASSOCIATES, INC.
Figure 13. Existing Baffles Upstream of Highway 85 Crossing
During final design, the drop structure, weir and entire culvert up to the upstream baffles will need
to be surveyed. From the field review, it appears that there is a considerable slope in the channel
through the culvert. By introducing a low flow channel, the jump at the first upstream baffle could
become higher. An intermediate jump (weir) within the low flow channel with flatter slope may
be necessary to mitigate for any passage problems within the upstream system.
Appendix A provides a schematic design for the low flow improvements for this site. No other
alternatives were considered for this location due to the limitations on what modifications would
be acceptable within the culvert relative to conveyance of flood flows.
Table 8 below provides an opinion of probable costs for the preferred project including the
additional upstream weir as described previously.
Table 8. Opinion of Probable Construction Costs – Un-Numbered Crossing for Highway 85
Description
Mob/ Site Prep/
& Demolition
costs
Low Flow
Channel
costs
Total Construction
Cost with a 25%
Contingency
Low flow Channel
(including upstream weir) $155,000 $153,000 $385,000
25% contingency includes unknowns at this conceptual level of design
Conclusions – Un-Numbered Crossing for Highway 85
Based on the analyses presented above, a cut in low flow channel with a potential for an upstream
0.8-foot weir back to existing grade will be the preferred alternative for this crossing of Highway
85. This project requires minimal streambed alterations and should result in less costly and time
Friends of Stevens Creek Trail PAGE 21 DOMENICHELLI & ASSOCIATES, INC.
consuming environmental permitting than the Moffett or Hetch Hetchy projects. However, as this
project is entirely within the Caltrans Right of Way, an encroachment permit and project design
approvals must be obtained from Caltrans.
El Camino Real Crossing – HB 13
The El Camino Crossing of Steven Creek consists of a single arch bridge opening (approximately
30 feet wide by 23 feet high). The slope through the opening is relatively flat and the bottom cross
slope is also flat, resulting in wide relatively shallow flow through the crossing. As-built drawings
provided as well as field review did not indicate a concrete bottom. However, due to sediment
build-up, a bottom apron could exist and be submerged in sediment. The photo below, Figure 14
shows the crossing from the downstream end looking upstream.
Figure 14. Culvert at El Camino Real
The concern at this crossing is that the wide flat bottom results in shallow flow, especially as flows
recede. HEC-RAS modeling results show that the minimum depth criteria is no longer met at
flows less than 40cfs for this culvert. Solutions to remedy this situation have been limited to
creating a low flow channel that is much narrower and deeper. To create the low flow channel
there are basically two approaches: 1) dredge out a narrow channel and carry the slope downstream
far enough to maintain high scour velocity or 2) create a baffle system to direct flow to one side
of the crossing to create a narrower deeper flow path. Approach 1 would be less reliable because
the low flow channel could fill back in with sediment during larger flow events. Grade control
would be necessary to maintain the desired shape of the channel; therefore, the use of a baffle
system would be more desirable.
Figure 15 shows a baffle option suggested in a previous report (PWA 2005). This arrangement
would concentrate flow to one side creating deeper channel flow through the culvert. This would
achieve the fish passage objective of deeper channel flow however, constructing baffles above the
Friends of Stevens Creek Trail PAGE 22 DOMENICHELLI & ASSOCIATES, INC.
channel invert will be an obstruction of flood flows. HEC-RAS modeling of the existing
conditions show that during a 100-year event, the culvert does not flow full and upstream water
surface elevations are not near the top of banks. When running the proposed condition with the
baffles, an increase of 0.9-feet in the 100-year water surface elevations (WSEs) occur (see
Appendix B results). This increase in WSEs does not meet the flood control criteria, therefore the
use of above grade permanent baffles will not be feasible.
Figure 15. Baffle Option from (PWA, 2005)
Another concern with the baffle option is the ability to anchor the baffles in place. If the culvert
has no concrete bottom or if it is well below the surface of the sediment, anchoring the baffles
would require deep and costly foundations.
Upon further consideration, two modifications of the baffle arrangement have been analyzed. The
first modification uses a combination of cutting a low flow channel in conjunction with
construction of a smaller (shallower) baffle. The low flow channel would counteract flow
obstruction of the baffles by adding conveyance area. The second modification would be to create
the baffles with rock to stay in place during typical winter high flow events (approximately a 2-yr
event). The rocks could be sized so that during a larger (10yr or greater) event, the rocks would
be swept downstream removing any obstruction to the flood conveyance through the culvert. The
rock baffle option is shown below in Figure 16.
Friends of Stevens Creek Trail PAGE 23 DOMENICHELLI & ASSOCIATES, INC.
Figure 16. Rock Baffle Option
The low flow channel will be designed to extend downstream beyond the end of the culvert to
maintain a positive and adequate slope to help transport sediment, while maintaining fish passage
velocities and depths. Appendix A shows a typical design for this and other culverts addressed in
this study. The maximum rock size will be approximately 12-inch diameter rock.
Table 9 provides an opinion of probable costs for the rock baffle/ low flow channel option. It
should be noted that the above rock size can be hand placed and the low flow channel could be
dug with hand tools. This could be the ongoing maintenance program in late summer when larger
storm events from the previous winter wash away the rocks. It has been suggested by local stream
stewardship groups that this could be done by volunteers.
Table 9. Opinion of Probable Construction Costs – El Camino Real – HB13
Alternative
Mob/ Site Prep/
& Excavation
costs
Baffle
Construction
costs
Total
Construction
Cost with a 25%
Contingency
Rock Baffles and low flow channel $72,200 $40,000 $130,000
25% contingency includes unknowns at this conceptual level of design
Conclusions – El Camino Real – HB13
Based on the analyses presented above, a rock baffle system will be the preferred alternative for
the El Camino Real crossing. Permitting requirements for the initial construction would be similar
stream alteration and water quality permits as described for the all of the projects in this report.
Caltrans permitting process will also be included for this culvert. On-going maintenance
Friends of Stevens Creek Trail PAGE 24 DOMENICHELLI & ASSOCIATES, INC.
potentially by volunteers would likely require permitting.
Highway 85 Crossing near Village Court – HB 15
The Highway 85 crossing of Stevens Creek near Village Court consists of an approximate 24-foot-
wide by 20-foot-high box culvert. The 110-foot-long culvert was built with a curved alignment,
which concentrates the lower flows to the outside of the curve as would be anticipated due to forces
of the channel flows and resulting scour of sediment. Similar to the El Camino Real crossing, this
culvert either is an earthen bottom or sediment build up has created a condition where any concrete
channel bottom could not be found with hand tools. Figure 17 show this crossing looking
upstream. Note that curved alignment already creates a low flow channel to the outside of the
curve. This condition creates depths adequate for fish passage at lower flows than at the El Camino
Real crossing. As seen in the photo below, the depth is low at the critical riffle. Without detailed
surveying, no precise hydraulic modeling was performed at this location. However, based on field
review, we anticipate that adequate depth would be present at a flow closer to 30cfs at this culvert.
Figure 17. Existing Conditions at Highway 85 Crossing (PWA 2005)
For this culvert, the same fish passage solutions as at El Camino Real would apply to enhance
passage at lower flows. Although the culvert already has low flow concentrated to one side,
creating a better defined low flow channel that continues downstream of the culvert is desirable.
The use of rock baffles similar to the El Camino Real crossing to enhance the low flow channel
condition is proposed. Unlike the El Camino Real site, this culvert does not currently pass the
100-year flow with freeboard. The existing conditions modeling shows that the 100-year water
surface is above the soffit of the culvert which causes water surface elevations closer to the top of
bank. Again, by adding permanent baffles obstructing the flow path in the culvert, the water
surface will rise significantly (up to several feet) depending on the height of the baffles. The option
to lower the baffles and cut into the low flow to balance the conveyance area as in the proposed El
Friends of Stevens Creek Trail PAGE 25 DOMENICHELLI & ASSOCIATES, INC.
Camino Real project, would improve this condition. However, where to set the baffles relative to
anticipated sediment levels during and after major storm events is difficult to determine. In fact,
the District’s current flood model contains culvert (and bridge) openings with inverts consistently
deeper than what has been measured during site visits at low flows. This supports the premise that
during higher flows, the sediment will be scoured down closer to the levels of the channels
surveyed at the time of the original design of the system.
Due to the flood concerns addressed above and the costs related to constructing permanent baffles,
the permanent baffle option within culvert crossings is no longer considered in this study. Rock
baffles sized to be transported (scoured out and conveyed) downstream during major flood events
are recommended at this crossing. Placing the rock baffles and shaping a deeper low flow channel
along the outside of the curved culvert would not obstruct flow conveyance under current
conditions (see Figures 18 and 19 below). Keeping in mind that a major flood event will likely
remove the baffle system and the rock will need to be recovered and/or replaced. As mentioned
for the El Camino Real crossing, the rock will be sized to remain in place up to approximately the
10-yr flood event.
Figure 18. Proposed Rendering of Rock Baffles
Friends of Stevens Creek Trail PAGE 26 DOMENICHELLI & ASSOCIATES, INC.
Figure 19. Proposed Rock Placement within Culvert
Fortunately, this site already has the formation of a low flow channel due to the culvert curvature.
Enhancing the low flow channel to meet passage criteria will require less channel work than other
culvert crossings. Table 10 provides an opinion of probable costs for the rock baffle system at
this site.
Table 10. Opinion of Probable Construction Costs – Highway 85 near Village Court – HB15
Alternative
Mob/ Site Prep/
& Excavation
costs
Baffle
Construction
costs
Total
Construction
Cost with a
25%
Contingency
Rock baffles and low flow channel $56,000 $32,500 $111,000
25% contingency includes unknowns at this conceptual level of design
Conclusion – Highway 85 near Village Court – HB15
Based on the analyses presented above, a rock baffle system will be the preferred alternative for
the Highway 85 crossing near Village Court. Permit requirements and environmental
documentation will be similar to the El Camino Real culvert project.
Friends of Stevens Creek Trail PAGE 27 DOMENICHELLI & ASSOCIATES, INC.
Highway 280 Crossing– HB 20
The Highway 280 crossing is another crossing where flat longitudinal channel slope as well as a
flat bottom across the channel section creates shallow flow during low flow conditions. The
crossing consists of two side by side culverts, one is a concrete arch culvert and the other is a
circular shaped concrete culvert. Figures 20 and 21 below show the upstream entrance to the dual
culvert crossing.
Figure 20. Highway 280 Culvert Crossing
Figure 21. Highway 280 Culvert Crossing, Low Flow in the Arch Culvert
Friends of Stevens Creek Trail PAGE 28 DOMENICHELLI & ASSOCIATES, INC.
For this crossing, note that the circular culvert to the right in Figure 20 has no flow and that all low
flow is conveyed through the arch culvert. This is due to the configuration (alignment) of the
culverts relative to the stream alignment. Although the culverts are straight, the stream enters the
culverts at an abrupt right turn (looking downstream). This directs the flow to the left side of the
arch culvert and drops sediment to the inside of the curve in front of the right culvert, creating a
significantly lower invert in the arch culvert along the left edge (wall).
In contrast to the entrance, at the exit of the culverts, the stream takes an abrupt left turn. This
shifts the low flow in the arch culvert to the opposite side of the culvert as shown in Figure 22
looking upstream at the exit.
Figure 22. Highway 280 Culvert Crossing
Therefore, in the arch culvert the low flow channel shifts from one side to the other from the
entrance to the exit. The problem for fish passage is that in the middle section of this long flat
sloped culvert, the invert flattens and the low flow becomes shallow and flat across the entire cross-
section. See Figure 23 for the channel configuration at this crossing.
Friends of Stevens Creek Trail PAGE 29 DOMENICHELLI & ASSOCIATES, INC.
Figure 23. Proposed Low Flow Culvert Rock Baffles
The solution is similar to the previous two culverts where baffles would concentrate flow to one
side or the other within the middle section of the culvert. The difference is that the baffles would
have the most beneficial affect if they switch from the left side to the right (looking upstream) with
a transition in the middle. Figure 23 shows this configuration. Appendix A shows a more detailed
view of the recommended layout of the low flow channel with rock baffles.
Again, the 100-yr water surface elevations are a concern for this crossing. The current District
model shows the upstream flood elevations near the top of bank. This is with both culverts flowing
with no sediment. These culverts are shown with concrete bottoms in the as-built drawings and in
the HEC-RAS model. Given the shape of the culverts, this indicates a minimum of 5 feet of
sediment in the photos above. A model run with the inverts at the top of the sediment as shown in
the photos, created upstream flood levels several feet higher in an area where the 100-yr flood
flows already overtop the banks farther upstream. If any obstructions are introduced to channelize
low flow at the current sediment elevations, then the obstruction must be removed with the
sediment at the higher flows.
Friends of Stevens Creek Trail PAGE 30 DOMENICHELLI & ASSOCIATES, INC.
Rock baffles as discussed for the previous culverts are again a viable solution. Due to damaging
flood potential, the baffle rocks must be sized to move out of the arch (low flow) culvert. A
smaller size rock for this more critical flood conveyance feature is recommended to assure that
flood velocities will adequately scour out the entire culvert. Using smaller rocks sized to remain
for between a 5 to 10-year event may be appropriate. This would require inspecting the site and
replacement of rock more often to ensure effective fish passage is maintained.
Other options such as collapsing or hinged baffles, or even inflatable baffles have been discussed.
However, initial construction and ongoing maintenance costs for such features that would have
uncertain reliability were deemed infeasible at this time.
Table 11 provides an opinion of probable costs for the rock baffle system at this site.
Table 11. Opinion of Probable Construction Costs – Highway 280 Crossing– HB20
Alternative
Mob/ Site Prep/
& Excavation
costs
Baffle
Construction
costs
Total Construction
Cost with a 25%
Contingency
Rock baffles and low flow channel $79,000 $37,500 $146,000
25% contingency includes unknowns at this conceptual level of design
Conclusion – Highway 280 Crossing– HB20
Based on the analyses presented above, a rock baffle system will be the preferred alternative for
the Highway 280 crossing. Permitting and environmental documentation will be the same for all
of the highway culverts.
Friends of Stevens Creek Trail PAGE 31 DOMENICHELLI & ASSOCIATES, INC.
Deep Cliff Golf Course – HB 28
The Deep Cliff Golf Course is located farther upstream in the watershed and provides a greater
opportunity for spawning and rearing with much of the channel in its natural or semi-natural state.
For this location, movement of juvenile steelhead is more desirable than in the lower reaches where
upstream passage for juveniles will be difficult during most flow conditions, and rescue and
transport would likely be most effective for juvenile survival.
The crossing in question is an abandoned low water vehicular crossing. The crossing is concrete
paved and creates a jump that although not severe enough for adult passage under most flows, it
is restrictive for juvenile passage. Figure 24 shows the crossing, which has scoured away to a
degree over time, leaving the mild hydraulic jump. At lower flows, this drop is more pronounced
and measures approximately 1.5 feet high.
Figure 24. Existing Golf Course Low Water Crossing
Downstream of the drop is a plunge pool with a tail out invert elevation approximately 1.5 feet
lower than the paved surface low point. The solution for this site begins with a straight forward
approach which is to remove the concrete crossing. However, to completely remove the crossing
down to original grade would have some impact farther upstream. Over time, the upstream section
of the stream has created valuable habitat with deeper water and large trees growing at the bank’s
edge. If the jump were completely removed, lowering the water levels, potential for bank
undercutting is a concern.
A solution to remove the concrete from the center of the stream, while maintaining the overall
gradient would be to construct a rock weir stepped ladder configuration. For juvenile passage, this
would require three 6-inch steps to overcome the maximum drop of 1.5 feet at low flows. Figure
Friends of Stevens Creek Trail PAGE 32 DOMENICHELLI & ASSOCIATES, INC.
25 below shows a rendering of the design concept for this crossing. Appendix A shows a plan and
profile for the preliminary design.
Figure 25. Rendering of Proposed Rock Baffles
Figure 26. Golf Course Rock Baffle Schematic
This site design would include three rock weir structures using rock sized adequately as a base that
will not be washed away, with intermediate sized rocks to fill most of the voids. Because this
feature will replace the existing barrier to flow, no measurable impact to flood flow is anticipated
for this design. With properly sized and placed rock at this location, grouting of the rock will not
be necessary. Maintenance of the weir will likely require annual inspection and replacement of
intermediate sized rocks.
Table 12 provides an opinion of probable costs for the rock weir system at this site.
Friends of Stevens Creek Trail PAGE 33 DOMENICHELLI & ASSOCIATES, INC.
Table 12. Opinion of Probable Construction Costs – Deep Cliff Golf Course – HB28
Alternative
Mob./ Site
Prep/
Excavation/De
mob. costs
Weir &
Pool Rock
Placement
costs
Total Construction
Cost with a 25%
Contingency
Rock Weir and Pool Steps $50,100 $18,000 $88,000
25% contingency includes unknowns at this conceptual level of design
Conclusion – Deep Cliff Golf Course – HB28
Based on the analyses presented above, a rock weir and pool system will be the preferred
alternative for the Deep Creek Golf Course crossing. Although in-stream alteration permitting
through the State Department of Fish and Wildlife will be required, this feature is located on
private land, therefore approvals and encroachment permitting from state and local agencies will
not be required.
Friends of Stevens Creek Trail PAGE 34 DOMENICHELLI & ASSOCIATES, INC.
Gauge Station Weir (HB 32)
Near the upper reach of the study limits is an existing gaging station. This station is located
approximately ½ mile downstream of the Stevens Creek Reservoir within a park setting. As with
the Deep Cliff Golf Course, the stream is closer to its natural state and habitat is reasonably good
for spawning and rearing of steelhead. The station consists of a drop structure with a control weir
at the top of the structure for calibrating flow at variable depths passing over the weir. The drop
provides a free weir flow condition with no backwater affect from the downstream channel.
Checking records for this station, the station appears to have been out of operation for many years.
However, given potential for future use, fish passage solution will not cut into the weir structure.
Figure 27 shows the gauge station features.
Figure 27. Existing Conditions of Gauge Station Weir
The drop at the gauge to the downstream plunge pool was measured to be between 1.5 to 1.8 feet.
To reduce the maximum jump to 6-inches for juvenile migration would require a minimum of
three jumps. Installing a fish ladder at this location would be costly, due to the fact that the plunge
pool is nearly 8 feet deep at the drop. This would require a high ladder to overcome a relatively
small lift. A more economical solution would be to construct a series of two rock weirs near the
tail out of the plunge pool (three weir jumps total). The pool is relatively long and could
accommodate two weirs, with the first weir closest to the existing drop to be constructed at
approximately 4 feet high as the pool begins to shallow and one shorter weir to follow downstream
closer to the tail out. Figure 28 shows a rendering for the weir installations. Appendix A provides
a plan and profile for this preliminary design.
Friends of Stevens Creek Trail PAGE 35 DOMENICHELLI & ASSOCIATES, INC.
Figure 28. Rendering of Proposed Rock Weirs at Gauge Station
Table 13 provides an opinion of probable costs for the rock weir system at this site.
Table 13. Opinion of Probable Construction Costs – Gauge Station Weir – HB32
Alternative
Channel
Excavation/
Restoration
costs
Rock Weir
Construction
costs
Total
Construction Cost
with a 25%
Contingency
Rock Weir Ladder $35,200 $30,000 $85,000
25% contingency includes unknowns at this conceptual level of design
Conclusion – Gauge Station Weir – HB32
Based on the analyses presented above, a rock weir and pool system will be the preferred
alternative. In-stream alteration permitting through the State Department of Fish and Wildlife and
State water quality permitting will be required for this project. The project is located within a
public park, therefore encroachment permitting will also be required.
Friends of Stevens Creek Trail PAGE 36 DOMENICHELLI & ASSOCIATES, INC.
SECTION 3 – SUMMARY OF PROJECT CONCLUSIONS AND RECOMMENDATIONS
The following Table 14 summarizes the recommendations for the preferred projects for the eight
sites analyzed in this study. Cost presented below include the construction estimates from the
individual projects opinion of probable costs, as well as non-construction related cost anticipated
for each project. The percentage of construction cost for the non-construction items vary with the
size and complexity of the project. Typically, the lower the construction cost, the larger the non-
construction percentage. Engineering and Construction Management commonly varies from 25%
to 40% of the construction. We anticipate that permitting and administration costs may vary from
as low as 25% to over 50% of construction. The wide variation depends on potential
environmental impacts (currently unknown), the size and complexity of the project and the
ownership of the property and facility where the improvements are proposed. A more complex
project like the Moffett Drop and Downstream Channel is a long linear project with potentially
more impacts. It also has a crossing of a State highway. In the permitting and administration cost
estimate, this project is given a relatively high percentage even though construction costs are high.
For the Deep Cliff Golf Course project, there are no public encroachments and the potential
environmental impacts are less, resulting in lower permitting and environmental cost allocations.
As mentioned previously, although the Moffett Drop and Downstream Channel project is the
apparent greatest barrier to fish passage of the eight selected projects, it has the highest costs and
has the longest duration to implement. Completion of construction documents followed by
implementation of some of the less critical sites would be easier to fund and to complete much
faster. The SCCCC and the District can move forward with one or more projects of choice as
funding becomes available.
One of the unknown variables that can impact the long-term maintenance and overall feasibility
of the proposed projects is the sediment loading and transport within the Stevens Creek system. A
detailed sediment transport analysis of the stream system is recommended before final design of
any new constructed features, especially in the downstream reaches. This would be important not
only for fish passage enhancement but also to address impacts to flood control.
Friends of Stevens Creek Trail PAGE 37 DOMENICHELLI & ASSOCIATES, INC.
Table 14. Summary of Findings and Recommendations
Project Site
Preferred
Alternative
Estimated
Construction
Costs
Engineering
&
Construction
Management
Permitting and
Administration
Costs
TOTAL
Opinion of
Probable
Project Cost
Moffett Blvd Drop
Structure
Cut in concrete low
flow channel & new
wider, longer
conventional ladder
$1,453,000 $435,900 $435,900 $2,325,000
Hetch Hetchy
Pipeline
Encasement
Raised downstream
baffle and a 2- step
cut in ladder
$176,000 $70,400 $88,000 $344,400
Highway 85
Crossing near
Central Ave.
Cut in concrete low
flow channel with an
upstream weir jump
$385,000 $115,500 $96,250 $596,800
El Camino Real
Crossing
Rock baffles and low
flow channel $130,000 $45,500 $65,000 $240,000
Highway 85
Crossing near
Village Court
Rock baffles and low
flow channel $111,000 $38,850 $55,500 $205,400,
Highway 280
Crossing
Rock baffles and low
flow channel $146,000 $51,100 $65,700 $262,800
Deep Cliff Golf
Coarse
Rock weir and pool
system $88,000 $30,800 $26,400 $145,200
Stevens Creek Park
Stream Gauge
Rock weir and pool
system $85,000 $29,750 $29,750 $144,500
REFERENCES
1. Santa Clara Valley Water District (SCVWD), Stewardship Initiative: Stevens Creek Fish
Barrier Assessment, Philip Williams & Associates, Ltd., May 19, 2005. (PWA, 2005)
2. Stevens Creek Fish Passage Assessment, Highway 101 to Moffett Drop Structure, Michael
Love & Associates, Inc., April 28, 2016. (LOVE, 2016)
3. FAHCE Stevens Creek Fish Passage Enhancement, Project No. 00294001, Final Planning
Study Report, Capital Program Services Division, January 2010
4. California Department of Fish and Wildlife, CALIFORNIA SALMONID STREAM
HABITAT RESTORATION MANUAL, Forth Addition, 1996 Volume 1 and 2
5. Various As-Built Plan sets, Steven Creek Channel Improvements, provided by Santa Clara
Valley Water District.
Santa Clara County Creeks Coalition DOMENICHELLI & ASSOCIATES, INC.
APPENDIX A – CONCEPTUAL DESIGN DRAWINGS
APPENDIX B – HYDRAULIC CALCULATIONS
APPENDIX C – COST ESTIMATES
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
APPENDIX A
CONCEPTUAL DESIGN DRAWINGS
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Moffett Drop Structure & Channel
EXISTING WEIR
EXISTING FISH LADDER
PROPOSED FISH LADDER
EXISTING DROP STRUCTURE
EXISTING BAFFLES
NEW LOW FLOW
CHANNEL
NEW TAIL POOL
8' O.C.
5'
TOP OF DROPTOE OF DROP
REMOVE PORTION
OF EXISTING WEIR
5' 8' O.C.
3'
4'
EXISTING DROP
STRUCTURE
EXISTING WEIR
EXISTING TAIL POOL
NEW TAIL POOL
NEW FISH LADDER
EXISTING
DENIL LADDER
EXISTING MAIN
CHANNEL BOTTOM
BOTTOM OF NEW
LOW FLOW CHANNEL
1.2' DEEP
1.2
'
MOFFETT DROP & CHANNEL
APPENDIX A SHEET 1 of 3
3+00 3+50 4+004+50 5+00 5+50 6+00
22
24
26
28
30
32
20
0+00 0+50 1+00 2+00 2+50 3+00
0+00
1+00
2+00
3+00
2+00
34
22
24
26
28
20
30
32
33
34
3+00
4+00
5+006+00
HWY 101 OVERPASS
22
24
26
28
20
22
24
26
28
20
MA
TC
HL
IN
E:
SE
E B
EL
OW
MA
TC
HL
IN
E: S
HE
ET
3
MA
TC
HL
IN
E:
SE
E A
BO
VE
MOFFETT DROP & CHANNEL
APPENDIX A SHEET 2 of 3
TOP OF FISH
LADDER
EXISTING
POOL AT
FISH LADDER
EXTENT OF
CONCRETE REMOVAL
NEW CHANNELRESTING
POOL, TYP
RESTING
POOL
EXISTING SLOPED
WALLS
OUTSIDE EDGEOF
EXISTING CHANNEL
NEW CHANNEL
FLOOR
EXISTING
CHANNEL FLOOR
NEW CHANNEL
FLOOR
EXISTING
CHANNEL FLOOR
EXISTING
CHANNEL STEP
PROPOSED
POOL AT
FISH LADDER
PROPOSED
FISH LADDER
EXISTING
FISH LADDER
DR
OP
PROPOSED
FISH LADDER
EXISTING
FISH LADDER
S = 0.0013
6+00 6+50 7+00 7+50 8+00 8+50
22
24
26
28
20
HWY 101 OVERPASS
6+00
7+00
8+008+50
22
24
26
28
20
RESTING POOL
VERTICAL SIDEWALLS
SLOPED SIDEWALLS, TYP
IN TRAVEL CHANNELS
EXTENT OF
DEMOLITION & NEW
CONSTRUCTION
8.0'
2.0' 2.0'1.0'
SIDEWALLS SLOPE WILL VARY
3.5
'
EXISTING CHANNELL
FLOOR & SLOPED
SIDEWALLS, TYP
DEPTH = 1.2' TO 2.0'
2.0
'
6.0'
EMBEDDED CONCRETE LOGS (TYP)
MA
TC
HL
IN
E: S
HE
ET
2
EXTENT OF
CONCRETE REMOVAL
NEW CHANNEL
EXISTING SLOPED
WALLS
OUTSIDE EDGEOF
EXISTING CHANNEL
NEW CHANNEL
FLOOR
EXISTING
CHANNEL FLOOR
EXISTING
CHANNEL STEP
BEGINNING OF DEMO
& NEW CHANNEL
EXISTING OVERPASS
SUPPORT
VERTICAL SIDEWALLS
UNDER OVERPASS
MOFFETT DROP & CHANNEL
APPENDIX A SHEET 3 of 3
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Hetch Hetchy Pipeline Drop Structure Options 2 & 3
Top of Drop
38.00
Toe of Drop
33.60
Top of New Weir
39.25
Top of Slope
37.50
40'
45'
50'
35'
30'
55'
60'
Bottom of Pool
33.50
Existing Channel Bottom
35.50
New Fish Ladder
5.0
'
8' O.C.
Lower Center 4"
New Weir
Existing Concrete
Existing Bagged Concrete
Remove Existing Baffle Weir
HETCH HETCHY CROSSING
APPENDIX A DROP STRUCTURE - OPTION 2
Top of New Weir
37.50
Toe of Drop
33.60
40'
45'
50'
35'
30'
55'
60'
Bottom of Pool
33.50
Existing Channel Bottom
35.50
Top of New Weir
38.5
Top of New Weir
36.50
Top of Existing Weir
Toe of Drop
36.00
5.0
'
Lower Center 3"
New Weir
Existing Concrete
Existing Bagged Concrete
5.0
'
1.0
'
5.0'
1.0' 1.0'
EXISTING CONCRETE SLAB
VA
RIE
S
HETCH HETCHY CROSSING
APPENDIX A DROP STRUCTURE - OPTION 3
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Highway 85 Crossing (Un-numbered) Plan & Profile
40'
50'
EXISTING BAFFLES
NEW WEIR
(IF NEEDED)
NEW TOP OF DROP
CUT LOW-FLOW CHANNEL, S=0.0015
EXISTING BAFFLES
NEW WEIR
(IF NEEDED)
CUT LOW FLOW CHANNEL
CUT LOW FLOW CHANNEL
END LOW FLOW
CHANNEL AT DROP
EXISTING WEIR
EXISTING WEIR
48.6'
55'
60'
65'
70'
75'
45'
40'
EXISTING CHANNEL BOTTOM EXISTING CHANNEL BOTTOM
45'
50'
55'
60'
65'
70'
75'
APPROX. 200 LF
HIGHWAY 85 CROSSING (UN-NUMBERED)
APPENDIX A
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Typical Box Culvert Plan & Section View
ROCK BAFFLE
LOW FLOW CHANNEL
EXISTING BOX CULVERT
MAX 1.0'
DIA ROCK
NEW ROCK BAFFLES
(ABOVE GRADE)
EMBED ROCK IN LOW
FLOW CHANNEL
LOW FLOW
CHANNEL ℄TYPICAL BOX CULVERT
APPROXIMATE LOW
FLOW CHANNEL BANK
F
L
O
W
LOW FLOW ROCK TAILOUT
GRADE CONTROL
TYPICAL BOX CULVERT PLAN & SECTION
APPENDIX A EL CAMINO REAL & HIGHWAY 85 NEAR VILLAGE CT.
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Highway 280 Crossing near Village Court Plan & Section View
GRAVEL BAR
GRAVEL
BAR
LOW FLOW
CHANNEL ℄
ROCK
BAFFLES
(TYP)
HW
Y 2
80
HW
Y 2
80
F
L
O
W
F
L
O
W
22' WIDE
ARCH CULVERT
22' DIAMETER
CIRCULAR CULVERT
EXISTING WALL
FLOW TRANSITION
ROCK BARRIER
EXISTING WALL
LOW FLOW ROCK TAILOUT
GRADE CONTROL
ROCK BAFFLE
1.0' MAX
DIA ROCK
LOW FLOW CHANNEL
EXISTING ARCH CULVERT
EXISTING CIRCULAR
CULVERT
EXISTING GRADE OF
SEDIMENT (TYP)
HIGHWAY 280 CROSSING (HB 20)
APPENDIX A
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Deep Cliff Golf Course Plan & Profile
FLOW
REMOVE CONCRETE
CROSSING
ROCK WEIRS
(TYP)
REMOVE CONCRETE CROSSING
6" DROP (TYP)
ROCK WEIRS
10' 15'
1.5' DIA. MAX
ROCK SIZE (TYP)
DEEP CLIFF GOLF COURSE (HB 28)
APPENDIX A
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix A
Drawings
Gauge Station Weir Plan & Profile
FLOW
NEW ROCK
WEIRS
EXISTING GAUGE
STATION WEIR
NEW ROCK
WEIRS
EXISTING GAUGE
STATION WEIR
EXISTING
BRIDGE
BR
ID
GE
STREAM
GAUGE
10' ≈ 20'
≈ 25'
1' MIN
1.5' TO 2.0'
3.5' TO 4.0'
1.5' TO 2.0'
MAX DIA ROCK
6' TO 8'
1' MIN
GAUGE STATION WEIR (HB 32)
APPENDIX A
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
APPENDIX B
HYDRAULIC CALCULATIONS
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix B
Hydraulic Modeling Results
Moffett Drop Structure
0 200 400 600 800 1000 1200 140015
20
25
30
35
40
45
50
Steven's Creek Barriers Plan: Existing Moffet 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Ex Moffet River: RIVER-1 Reach: Reach-1 Profile: 100yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 15283.5 100yr 5750.00 31.25 44.72 41.93 46.37 0.005288 10.29 558.76 67.16 0.63
Reach-1 15183.5 100yr 5750.00 31.15 41.94 41.92 45.38 0.014097 14.86 386.83 55.77 0.99
Reach-1 15082.5 100yr 5750.00 31.05 41.90 40.72 44.49 0.003525 12.90 445.76 57.14 0.81
Reach-1 15042.5 100yr 5750.00 30.75 39.81 39.81 44.12 0.007291 16.65 345.38 40.00 1.00
Reach-1 15035 100yr 5750.00 24.75 39.28 34.28 41.00 0.002006 10.55 544.90 40.00 0.50
Reach-1 14984 100yr 5750.00 24.75 39.26 33.80 40.88 0.001798 10.21 563.02 40.00 0.48
Reach-1 14959 100yr 5750.00 24.65 39.07 35.14 40.82 0.001831 10.61 542.07 51.18 0.57
Reach-1 14883 100yr 5750.00 24.78 38.51 35.68 40.62 0.002400 11.65 493.58 50.83 0.66
Reach-1 14799 100yr 5750.00 24.75 38.31 35.65 40.39 0.002846 11.59 496.06 60.33 0.71
Reach-1 14698 100yr 5750.00 24.67 38.24 35.61 40.05 0.002286 10.80 532.33 61.59 0.65
Reach-1 14601 100yr 5750.00 24.49 38.24 34.92 39.77 0.001794 9.92 579.62 64.12 0.58
Reach-1 14587 100yr 5750.00 24.48 38.23 34.88 39.74 0.001772 9.85 584.03 65.00 0.58
Reach-1 14569 100yr 5750.00 24.46 38.21 34.86 39.70 0.001790 9.80 586.96 71.21 0.58
Reach-1 14563 100yr 5750.00 23.72 38.28 34.31 39.66 0.001618 9.40 611.53 68.15 0.55
Reach-1 14549 100yr 5750.00 23.55 37.84 33.11 39.60 0.001091 10.65 539.92 66.71 0.52
Reach-1 14400 Bridge
Reach-1 14323 100yr 5750.00 23.40 35.99 33.29 38.45 0.000676 12.59 456.70 46.99 0.66
Reach-1 14315 100yr 5750.00 23.40 35.68 38.42 0.001681 13.28 433.11 39.66 0.71
Reach-1 14300 100yr 5750.00 23.41 35.68 38.38 0.001659 13.18 436.17 40.11 0.70
Reach-1 14250 100yr 5750.00 23.38 33.73 33.73 38.10 0.003349 16.78 342.67 40.09 1.01
Reach-1 14222 100yr 5750.00 23.30 33.63 33.63 37.60 0.003184 15.99 359.55 45.64 1.00
Reach-1 14217 100yr 5750.00 21.58 33.53 33.53 37.42 0.003246 15.83 363.28 46.67 1.00
Reach-1 14213 100yr 5750.00 21.18 33.43 36.28 0.032441 13.54 424.67 49.81 0.81
Reach-1 14209.5* 100yr 5750.00 21.10 33.52 36.09 0.026367 12.86 447.23 52.96 0.76
Reach-1 14206 100yr 5750.00 21.03 33.77 35.86 0.019203 11.60 495.59 57.12 0.67
Reach-1 14202 100yr 5750.00 21.03 33.61 35.77 0.020250 11.80 487.28 56.98 0.68
Reach-1 14193 100yr 5750.00 21.34 33.64 35.54 0.016494 11.06 519.84 70.76 0.65
Reach-1 14182 100yr 5750.00 20.28 33.49 35.33 0.018017 10.91 527.07 79.73 0.68
Reach-1 14168 100yr 5750.00 20.04 33.30 35.05 0.017635 10.61 541.96 84.64 0.67
Reach-1 14155 100yr 5750.00 19.61 33.22 34.79 0.014213 10.06 571.66 83.03 0.61
Reach-1 14137 100yr 5750.00 18.92 33.18 34.49 0.011300 9.17 626.88 78.18 0.54
Reach-1 14124 100yr 5750.00 18.45 33.06 34.32 0.011821 8.98 640.09 79.11 0.52
Reach-1 14096 100yr 5750.00 18.47 32.97 33.93 0.009428 7.87 730.85 82.02 0.46
Reach-1 14032 100yr 5750.00 17.92 29.73 29.73 32.58 0.049990 13.53 424.90 74.61 1.00
0 200 400 600 800 1000 1200 140015
20
25
30
35
40
45
50
Steven's Creek Barriers Plan: Proposed Moffet Fish Ladder 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Pro Moffet Ladde River: RIVER-1 Reach: Reach-1 Profile: 100yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 15283.5 100yr 5750.00 31.25 44.64 41.93 46.32 0.005428 10.39 553.33 66.84 0.64
Reach-1 15183.5 100yr 5750.00 31.15 42.54 41.92 45.44 0.011251 13.67 420.63 58.05 0.89
Reach-1 15082.5 100yr 5750.00 31.05 42.49 40.72 44.72 0.002878 11.98 479.90 58.88 0.74
Reach-1 15042.5 100yr 5750.00 30.75 40.02 40.02 44.33 0.007389 16.67 344.96 40.00 1.00
Reach-1 15035 100yr 5750.00 24.75 40.03 34.73 41.69 0.001918 10.32 557.17 40.00 0.49
Reach-1 14979 100yr 5750.00 24.75 40.05 34.02 41.54 0.001621 9.81 586.06 40.00 0.45
Reach-1 14974 100yr 5750.00 23.26 40.15 33.26 41.49 0.001385 9.27 620.55 40.00 0.41
Reach-1 14972 Inl Struct
Reach-1 14959 100yr 5750.00 23.21 39.47 35.03 41.07 0.001706 10.14 567.06 53.30 0.55
Reach-1 14957 Inl Struct
Reach-1 14883 100yr 5750.00 23.01 38.51 35.54 40.58 0.002423 11.53 498.81 50.82 0.65
Reach-1 14799 100yr 5750.00 22.80 38.31 35.50 40.34 0.002858 11.45 502.05 60.34 0.70
Reach-1 14698 100yr 5750.00 22.54 38.23 35.47 40.01 0.002315 10.68 538.41 61.57 0.64
Reach-1 14601 100yr 5750.00 22.29 38.23 34.79 39.73 0.001827 9.83 585.14 64.07 0.57
Reach-1 14587 100yr 5750.00 22.26 38.21 34.74 39.69 0.001805 9.76 589.30 64.89 0.57
Reach-1 14569 100yr 5750.00 22.21 38.19 34.71 39.65 0.001825 9.71 592.41 71.02 0.57
Reach-1 14563 100yr 5750.00 22.20 38.25 34.21 39.61 0.001640 9.37 613.96 67.71 0.54
Reach-1 14549 100yr 5750.00 22.16 37.83 32.98 39.56 0.001105 10.55 544.85 66.54 0.51
Reach-1 14400 Bridge
Reach-1 14323 100yr 5750.00 21.59 35.83 33.14 38.30 0.000733 12.61 455.85 45.98 0.66
Reach-1 14315 100yr 5750.00 21.57 35.51 38.26 0.001761 13.29 432.51 39.65 0.71
Reach-1 14300 100yr 5750.00 21.53 35.51 38.22 0.001749 13.22 435.06 40.10 0.71
Reach-1 14250 100yr 5750.00 21.40 33.58 33.58 37.94 0.003508 16.74 343.39 40.08 1.01
Reach-1 14222 100yr 5750.00 21.33 33.49 33.49 37.46 0.003345 16.00 359.29 45.64 1.01
Reach-1 14217 100yr 5750.00 21.30 33.51 33.51 37.40 0.003278 15.83 363.28 46.67 1.00
Reach-1 14213 100yr 5750.00 21.18 33.44 36.28 0.032397 13.53 424.85 49.81 0.81
Reach-1 14209.5* 100yr 5750.00 21.10 33.52 36.09 0.026332 12.85 447.42 52.96 0.76
Reach-1 14206 100yr 5750.00 21.03 33.77 35.86 0.019181 11.60 495.77 57.12 0.67
Reach-1 14202 100yr 5750.00 21.03 33.61 35.77 0.020224 11.80 487.47 56.98 0.68
Reach-1 14193 100yr 5750.00 21.34 33.64 35.54 0.016471 11.06 520.06 70.76 0.65
Reach-1 14182 100yr 5750.00 20.28 33.49 35.33 0.018006 10.91 527.19 79.73 0.68
Reach-1 14168 100yr 5750.00 20.04 33.30 35.05 0.017623 10.61 542.10 84.65 0.67
Reach-1 14155 100yr 5750.00 19.61 33.22 34.79 0.014208 10.06 571.73 83.04 0.61
Reach-1 14137 100yr 5750.00 18.92 33.18 34.49 0.011304 9.17 626.80 78.18 0.54
Reach-1 14124 100yr 5750.00 18.45 33.06 34.32 0.011817 8.98 640.15 79.11 0.52
Reach-1 14096 100yr 5750.00 18.47 32.97 33.93 0.009426 7.87 730.92 82.03 0.46
Reach-1 14032 100yr 5750.00 17.92 29.73 29.73 32.58 0.050070 13.54 424.65 74.58 1.00
0 200 400 600 800 1000 1200 140015
20
25
30
35
40
45
50
Steven's Creek Barriers Plan: Existing Moffet 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 16 CFS
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Ex Moffet River: RIVER-1 Reach: Reach-1 Profile: 16 CFS
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 15283.5 16 CFS 16.00 31.25 31.98 31.52 32.00 0.001315 1.05 15.21 21.41 0.22
Reach-1 15183.5 16 CFS 16.00 31.15 31.79 31.47 31.82 0.002678 1.31 12.20 21.13 0.30
Reach-1 15082.5 16 CFS 16.00 31.05 31.35 31.28 31.42 0.006494 2.11 7.60 25.88 0.68
Reach-1 15042.5 16 CFS 16.00 30.75 30.93 30.93 31.02 0.016046 2.42 6.62 36.00 0.99
Reach-1 15035 16 CFS 16.00 24.75 25.48 24.93 25.48 0.000171 0.61 26.14 36.00 0.13
Reach-1 14984 16 CFS 16.00 24.75 25.47 24.93 25.47 0.000179 0.62 25.81 36.00 0.13
Reach-1 14959 16 CFS 16.00 24.65 25.46 24.89 25.47 0.000260 0.80 19.99 25.52 0.16
Reach-1 14883 16 CFS 16.00 24.78 25.41 25.06 25.43 0.000837 1.20 13.38 22.58 0.27
Reach-1 14799 16 CFS 16.00 24.75 25.33 25.02 25.36 0.001038 1.28 12.47 22.29 0.30
Reach-1 14698 16 CFS 16.00 24.67 25.18 24.96 25.22 0.001892 1.53 10.47 22.65 0.40
Reach-1 14601 16 CFS 16.00 24.49 24.99 24.78 25.03 0.002030 1.58 10.16 22.16 0.41
Reach-1 14587 16 CFS 16.00 24.48 24.96 24.75 25.00 0.002156 1.61 9.92 21.87 0.42
Reach-1 14569 16 CFS 16.00 24.46 24.78 24.78 24.91 0.013913 2.86 5.60 21.29 0.98
Reach-1 14563 16 CFS 16.00 23.72 24.10 24.00 24.16 0.004351 1.93 8.31 23.75 0.57
Reach-1 14549 16 CFS 16.00 23.55 24.10 23.85 24.12 0.001175 1.19 13.46 30.84 0.31
Reach-1 14400 Bridge
Reach-1 14323 16 CFS 16.00 23.40 23.67 20.87 23.74 0.005901 2.07 7.73 26.01 0.67
Reach-1 14315 16 CFS 16.00 23.40 23.61 23.68 0.008407 2.24 7.14 26.05 0.75
Reach-1 14300 16 CFS 16.00 0.00 23.41 23.53 0.012748 2.87 5.58 1.30 0.24
Reach-1 14250 16 CFS 16.00 0.00 22.53 22.72 0.020669 3.57 4.48 1.30 0.34
Reach-1 14222 16 CFS 16.00 0.00 20.67 20.67 21.51 0.107807 7.35 2.18 1.30 1.00
Reach-1 14217 16 CFS 16.00 0.00 20.36 20.61 0.026508 3.99 4.01 1.30 0.40
Reach-1 14213 16 CFS 16.00 0.00 20.32 20.52 0.020766 3.58 4.47 1.30 0.34
Reach-1 14209.5* 16 CFS 16.00 0.00 20.24 20.44 0.020811 3.58 4.47 1.30 0.34
Reach-1 14206 16 CFS 16.00 0.00 20.16 20.36 0.020863 3.59 4.46 1.30 0.34
Reach-1 14202 16 CFS 16.00 0.00 20.06 20.27 0.022276 3.69 4.33 1.30 0.36
Reach-1 14193 16 CFS 16.00 0.00 19.68 20.02 0.037409 4.66 3.44 1.30 0.50
Reach-1 14182 16 CFS 16.00 0.00 19.49 19.68 0.019802 3.50 4.57 1.30 0.33
Reach-1 14168 16 CFS 16.00 0.00 19.20 19.39 0.020532 3.56 4.49 1.30 0.34
Reach-1 14155 16 CFS 16.00 0.00 18.96 19.14 0.018195 3.37 4.75 1.30 0.31
Reach-1 14137 16 CFS 16.00 0.00 18.70 18.84 0.014251 3.02 5.31 1.30 0.26
Reach-1 14124 16 CFS 16.00 18.45 18.53 18.66 0.012695 2.83 5.65 2.66 0.34
Reach-1 14096 16 CFS 16.00 0.00 18.11 18.26 0.015377 3.12 5.12 1.30 0.28
Reach-1 14032 16 CFS 16.00 0.00 15.29 15.29 16.13 0.107816 7.35 2.18 1.30 1.00
0 200 400 600 800 1000 1200 140015
20
25
30
35
40
45
50
Steven's Creek Barriers Plan: Proposed Moffet Fish Ladder 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 16 CFS
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Pro Moffet Ladde River: RIVER-1 Reach: Reach-1 Profile: 16 CFS
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 15283.5 16 CFS 16.00 31.25 31.98 31.52 32.00 0.001319 1.05 15.20 21.41 0.22
Reach-1 15183.5 16 CFS 16.00 31.15 31.79 31.47 31.82 0.002705 1.32 12.16 21.13 0.31
Reach-1 15082.5 16 CFS 16.00 31.05 31.35 31.28 31.42 0.006320 2.09 7.66 25.89 0.68
Reach-1 15042.5 16 CFS 16.00 30.75 30.94 30.94 31.04 0.015824 2.46 6.50 34.00 0.99
Reach-1 15035 16 CFS 16.00 24.75 25.32 24.94 25.33 0.000428 0.83 19.36 34.00 0.19
Reach-1 14979 16 CFS 16.00 24.75 25.29 24.94 25.30 0.000503 0.87 18.43 34.00 0.21
Reach-1 14974 16 CFS 16.00 23.26 25.29 24.37 25.30 0.000201 0.61 26.26 40.00 0.13
Reach-1 14972 Inl Struct
Reach-1 14959 16 CFS 16.00 23.21 25.19 24.31 25.20 0.000418 0.91 17.54 25.02 0.19
Reach-1 14957 Inl Struct
Reach-1 14883 16 CFS 16.00 23.01 25.09 24.14 25.12 0.001439 1.38 11.60 21.89 0.33
Reach-1 14799 16 CFS 16.00 22.80 24.86 23.93 24.92 0.004413 1.95 8.22 21.28 0.55
Reach-1 14698 16 CFS 16.00 22.54 24.39 23.69 24.53 0.003173 3.04 5.26 3.70 0.45
Reach-1 14601 16 CFS 16.00 22.29 23.99 23.44 24.17 0.004243 3.40 4.71 3.53 0.52
Reach-1 14587 16 CFS 16.00 22.26 23.92 23.41 24.11 0.004641 3.51 4.56 3.49 0.54
Reach-1 14569 16 CFS 16.00 22.21 23.80 23.36 24.02 0.005475 3.74 4.28 3.38 0.59
Reach-1 14563 16 CFS 16.00 22.20 23.87 23.31 23.94 0.006865 2.17 7.37 23.37 0.68
Reach-1 14549 16 CFS 16.00 22.16 23.85 23.25 23.88 0.002255 1.43 11.22 30.54 0.41
Reach-1 14400 Bridge
Reach-1 14323 16 CFS 16.00 21.59 23.08 22.73 23.31 0.002239 3.92 4.08 3.49 0.64
Reach-1 14315 16 CFS 16.00 21.57 23.06 23.29 0.002729 3.85 4.16 3.58 0.63
Reach-1 14300 16 CFS 16.00 21.53 23.01 23.25 0.002873 3.92 4.08 3.50 0.64
Reach-1 14250 16 CFS 16.00 21.40 22.80 23.08 0.003595 4.26 3.75 3.35 0.71
Reach-1 14222 16 CFS 16.00 21.33 22.52 22.46 22.94 0.006139 5.20 3.08 3.19 0.93
Reach-1 14217 16 CFS 16.00 21.30 22.49 22.49 22.90 0.007144 5.16 3.10 3.70 0.99
Reach-1 14213 16 CFS 16.00 21.18 22.26 22.28 0.005974 1.03 15.61 30.40 0.25
Reach-1 14209.5* 16 CFS 16.00 21.10 22.25 22.26 0.002607 0.82 19.51 28.54 0.17
Reach-1 14206 16 CFS 16.00 21.03 22.25 22.25 0.001009 0.59 27.03 32.23 0.11
Reach-1 14202 16 CFS 16.00 21.03 22.25 22.25 0.001025 0.59 26.89 32.23 0.11
Reach-1 14193 16 CFS 16.00 21.34 22.12 22.22 0.048027 2.49 6.43 16.37 0.70
Reach-1 14182 16 CFS 16.00 20.28 21.88 21.93 0.015149 1.81 8.84 14.79 0.41
Reach-1 14168 16 CFS 16.00 20.04 21.56 21.63 0.030380 2.11 7.58 17.10 0.56
Reach-1 14155 16 CFS 16.00 19.61 21.11 20.82 21.24 0.029580 2.87 5.58 7.43 0.58
Reach-1 14137 16 CFS 16.00 18.92 20.07 20.07 20.36 0.094201 4.33 3.70 6.43 1.01
Reach-1 14124 16 CFS 16.00 18.45 19.74 19.78 0.009786 1.55 10.33 14.43 0.32
Reach-1 14096 16 CFS 16.00 18.47 19.58 19.59 0.004473 1.07 15.00 20.56 0.22
Reach-1 14032 16 CFS 16.00 17.92 18.57 18.57 18.78 0.113419 3.64 4.40 10.72 1.00
0 200 400 600 800 1000 1200 140015
20
25
30
35
40
45
50
Steven's Creek Barriers Plan: 1) Ex Moffet 8/8/2017 2) Pro Moffet Ladde 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100yr - Ex Moffet
WS 100yr - Pro Moffet Ladde
WS 16 CFS - Pro Moffet Ladde
WS 16 CFS - Ex Moffet
Ground
ROB
Ground
RIVER-1 Reach-1
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix B
Hydraulic Modeling Results
Hetch Hetchy Pipeline Drop Structure
0 100 200 300 400 500 600 70035
40
45
50
55
60
Steven's Creek Barriers Plan: Existing Hetch-Hetchy 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Ex HH River: RIVER-1 Reach: Reach-1 Profile: 100yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 17283.5 100yr 5750.00 42.25 57.81 58.86 0.007097 8.25 697.32 72.21 0.47
Reach-1 17083.5 100yr 5750.00 41.65 55.47 57.03 0.011584 10.02 573.95 63.89 0.59
Reach-1 17057.5 100yr 5750.00 40.95 55.14 56.90 0.001971 10.65 539.95 58.05 0.62
Reach-1 16984 100yr 5750.00 40.85 53.53 52.49 56.58 0.004055 14.01 410.52 49.16 0.85
Reach-1 16972 100yr 5750.00 40.85 52.49 52.49 56.43 0.005734 15.93 360.99 46.41 1.01
Reach-1 16971.* 100yr 5750.00 39.70 53.55 55.79 0.002685 12.03 477.88 52.44 0.70
Reach-1 16970.* 100yr 5750.00 38.55 54.03 55.58 0.001621 9.98 575.94 56.84 0.55
Reach-1 16969.* 100yr 5750.00 37.40 54.31 55.46 0.001080 8.59 669.01 60.59 0.46
Reach-1 16968 100yr 5750.00 36.25 54.49 55.38 0.000760 7.55 761.62 63.99 0.39
Reach-1 16958 100yr 5750.00 36.25 54.49 47.25 55.37 0.000762 7.56 761.05 63.97 0.39
Reach-1 16956 Inl Struct
Reach-1 16938 100yr 5750.00 36.25 54.07 55.02 0.000838 7.83 734.41 62.95 0.40
Reach-1 16923.5 100yr 5750.00 36.25 54.11 46.70 54.98 0.000732 7.47 769.84 62.45 0.37
Reach-1 16921.5 100yr 5750.00 38.25 53.76 48.56 54.95 0.001155 8.75 657.19 61.28 0.47
Reach-1 16783.5 100yr 5750.00 38.25 53.33 48.70 54.60 0.007892 9.07 633.78 63.67 0.51
Reach-1 16583.5 100yr 5750.00 36.75 47.61 47.61 51.45 0.034924 15.71 365.89 47.76 1.00
0 100 200 300 400 500 600 70035
40
45
50
55
60
Steven's Creek Barriers Plan: Proposed HH Cut 8/15/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Pro HH Cut River: RIVER-1 Reach: Reach-1 Profile: 100yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 17283.5 100yr 5750.00 42.25 57.31 58.46 0.007934 8.59 669.48 70.62 0.49
Reach-1 17183.5* 100yr 5750.00 41.95 56.50 57.84 0.004728 9.26 620.74 67.59 0.54
Reach-1 17083.5 100yr 5750.00 41.65 55.49 57.09 0.012133 10.16 566.10 63.95 0.60
Reach-1 17078.5 100yr 5750.00 41.00 55.52 57.00 0.011011 9.75 589.63 64.22 0.57
Reach-1 17057.5 100yr 5750.00 40.70 55.13 56.89 0.001960 10.63 540.87 58.02 0.61
Reach-1 16996 100yr 5750.00 40.60 53.68 56.61 0.003844 13.73 418.76 49.56 0.83
Reach-1 16984 100yr 5750.00 40.35 53.48 52.48 56.54 0.004087 14.03 409.80 49.04 0.86
Reach-1 16972 100yr 5750.00 40.35 52.48 52.48 56.40 0.005717 15.89 361.82 46.37 1.00
Reach-1 16968 100yr 5750.00 36.25 54.39 55.29 0.000779 7.62 754.96 63.74 0.39
Reach-1 16958 100yr 5750.00 36.25 54.38 47.22 55.28 0.000780 7.62 754.39 63.71 0.39
Reach-1 16956 Inl Struct
Reach-1 16938 100yr 5750.00 36.25 54.06 55.01 0.000840 7.83 733.98 62.93 0.40
Reach-1 16923.5 100yr 5750.00 36.25 54.13 46.43 54.97 0.000694 7.35 782.28 62.48 0.37
Reach-1 16921.5 100yr 5750.00 38.25 53.79 48.29 54.93 0.001078 8.57 671.06 61.37 0.46
Reach-1 16783.5 100yr 5750.00 38.25 53.33 48.70 54.60 0.007893 9.07 633.76 63.67 0.51
Reach-1 16583.5 100yr 5750.00 36.75 47.61 47.61 51.45 0.034924 15.71 365.89 47.76 1.00
HEC-RAS Plan: Ex HH River: RIVER-1 Reach: Reach-1 Profile: 16 CFS
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 17283.5 16 CFS 16.00 42.25 43.34 43.37 0.006585 1.41 11.37 17.20 0.30
Reach-1 17183.5* 16 CFS 16.00 41.95 42.93 42.96 0.002835 1.40 11.44 15.78 0.29
Reach-1 17083.5 16 CFS 16.00 41.65 41.97 41.97 42.13 0.090576 3.15 5.08 16.62 1.00
Reach-1 17057.5 16 CFS 16.00 40.95 41.54 41.59 0.002062 1.79 8.95 16.34 0.43
Reach-1 16984 16 CFS 16.00 40.85 41.34 41.40 0.003247 2.02 7.92 16.89 0.52
Reach-1 16972 16 CFS 16.00 40.85 41.17 41.17 41.32 0.013792 3.16 5.07 16.44 1.00
Reach-1 16971.* 16 CFS 16.00 39.70 40.00 40.00 40.15 0.014015 3.11 5.15 17.37 1.00
Reach-1 16970.* 16 CFS 16.00 38.55 39.35 39.37 0.000484 1.07 14.93 19.59 0.22
Reach-1 16969.* 16 CFS 16.00 37.40 39.36 39.37 0.000022 0.39 41.19 23.41 0.05
Reach-1 16968 16 CFS 16.00 36.25 39.37 39.37 0.000004 0.22 72.60 27.10 0.02
Reach-1 16958 16 CFS 16.00 36.25 39.37 36.52 39.37 0.000004 0.22 72.60 27.10 0.02
Reach-1 16956 Inl Struct
Reach-1 16938 16 CFS 16.00 36.25 39.36 39.36 0.000004 0.22 72.36 27.08 0.02
Reach-1 16923.5 16 CFS 16.00 36.25 39.36 36.94 39.36 0.000005 0.21 74.57 31.78 0.02
Reach-1 16921.5 16 CFS 16.00 38.25 39.34 38.93 39.36 0.000803 1.08 14.77 27.82 0.26
Reach-1 16783.5 16 CFS 16.00 38.25 39.14 38.74 39.15 0.003520 1.04 15.44 24.94 0.23
Reach-1 16583.5 16 CFS 16.00 36.75 37.03 37.03 37.18 0.087973 3.03 5.28 19.29 1.02
0 100 200 300 400 500 600 70035
40
45
50
55
60
Steven's Creek Barriers Plan: Existing Hetch-Hetchy 8/15/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 16 CFS
Ground
ROB
RIVER-1 Reach-1
0 100 200 300 400 500 600 70035
40
45
50
55
60
Steven's Creek Barriers Plan: Proposed HH Cut 8/15/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 16 CFS
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Pro HH Cut River: RIVER-1 Reach: Reach-1 Profile: 16 CFS
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 17283.5 16 CFS 16.00 42.25 43.27 43.28 0.001931 0.95 16.78 17.92 0.17
Reach-1 17183.5* 16 CFS 16.00 41.95 43.09 43.11 0.001531 1.21 13.21 14.01 0.22
Reach-1 17083.5 16 CFS 16.00 41.65 42.48 42.48 42.62 0.090062 2.97 5.40 19.11 0.98
Reach-1 17078.5 16 CFS 16.00 41.00 41.86 41.86 42.01 0.115387 3.11 5.15 19.20 1.06
Reach-1 17057.5 16 CFS 16.00 40.70 41.46 41.51 0.001940 1.77 9.05 16.01 0.41
Reach-1 16996 16 CFS 16.00 40.60 41.28 41.35 0.003461 2.06 7.75 16.75 0.53
Reach-1 16984 16 CFS 16.00 40.35 41.24 41.08 41.31 0.003360 2.04 7.83 16.64 0.52
Reach-1 16972 16 CFS 16.00 40.35 41.08 41.08 41.23 0.012400 3.06 5.23 16.22 0.95
Reach-1 16968 16 CFS 16.00 36.25 40.07 40.07 0.000002 0.17 92.18 28.81 0.02
Reach-1 16958 16 CFS 16.00 36.25 40.07 36.52 40.07 0.000002 0.17 92.18 28.81 0.02
Reach-1 16956 Inl Struct
Reach-1 16938 16 CFS 16.00 36.25 39.22 39.22 0.000005 0.23 68.72 26.75 0.03
Reach-1 16923.5 16 CFS 16.00 36.25 39.22 36.57 39.22 0.000003 0.20 81.89 31.50 0.02
Reach-1 16921.5 16 CFS 16.00 38.25 39.21 38.58 39.22 0.000181 0.70 22.94 27.53 0.13
Reach-1 16783.5 16 CFS 16.00 38.25 39.14 38.74 39.15 0.003520 1.04 15.44 24.94 0.23
Reach-1 16583.5 16 CFS 16.00 36.75 37.03 37.03 37.18 0.087973 3.03 5.28 19.29 1.02
0 100 200 300 400 500 600 70035
40
45
50
55
60
Steven's Creek Barriers Plan: 1) Pro HH Cut 8/15/2017 2) Ex HH 8/15/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100yr - Pro HH Cut
WS 100yr - Ex HH
WS 16 CFS - Pro HH Cut
WS 16 CFS - Ex HH
Ground
ROB
Ground
RIVER-1 Reach-1
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix B
Hydraulic Modeling Results
Bridge Crossings
0 100 200 300 400 500 600 70090
100
110
120
130
140
Steven's Creek Barriers Plan: Existing El Camino 5/15/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Existing El River: RIVER-1 Reach: Reach-1 Profile: 100-yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 25951 100-yr 5750.00 100.40 116.06 117.78 0.008794 10.51 547.34 50.52 0.56
Reach-1 25871 100-yr 5750.00 100.10 115.34 117.05 0.009377 10.49 547.90 36.01 0.47
Reach-1 25746 100-yr 5750.00 99.40 113.88 108.67 115.77 0.010790 11.05 520.47 35.99 0.51
Reach-1 25621.1 Culvert
Reach-1 25621 100-yr 5750.00 98.70 110.72 113.47 0.019414 13.32 431.80 35.98 0.68
Reach-1 25600 100-yr 5750.00 98.60 111.31 112.81 0.009472 9.83 584.70 68.07 0.59
Reach-1 25551 100-yr 5750.00 97.60 111.35 112.31 0.005344 7.85 732.20 77.55 0.45
Reach-1 25422 100-yr 5750.00 95.70 106.64 106.64 110.63 0.031254 16.03 358.73 45.06 1.00
Reach-1 25307 100-yr 5750.00 91.40 101.65 101.65 105.12 0.029621 14.95 384.73 56.19 1.01
0 100 200 300 400 500 600 70090
100
110
120
130
140
Steven's Creek Barriers Plan: Pro El Camino Baffles - HB13 8/3/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: HB-13 Baffles River: RIVER-1 Reach: Reach-1 Profile: 100-yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 25951 100-yr 5750.00 100.40 117.02 118.46 0.006974 9.64 596.45 52.33 0.50
Reach-1 25871 100-yr 5750.00 100.10 116.36 117.86 0.007861 9.83 584.71 36.02 0.43
Reach-1 25746 100-yr 5750.00 99.40 113.77 110.67 116.37 0.016749 12.93 444.71 35.98 0.65
Reach-1 25621.1 Culvert
Reach-1 25621 100-yr 5750.00 98.70 109.96 109.96 114.60 0.040914 17.28 332.75 35.96 1.00
Reach-1 25600 100-yr 5750.00 98.60 111.31 112.81 0.009472 9.83 584.70 68.07 0.59
Reach-1 25551 100-yr 5750.00 97.60 111.35 112.31 0.005344 7.85 732.20 77.55 0.45
Reach-1 25422 100-yr 5750.00 95.70 106.64 106.64 110.63 0.031254 16.03 358.73 45.06 1.00
Reach-1 25307 100-yr 5750.00 91.40 101.65 101.65 105.12 0.029621 14.95 384.73 56.19 1.01
0 100 200 300 400 500 600 70090
100
110
120
130
140
Steven's Creek Barriers Plan: 1) Existing El 5/15/2017 2) HB-13 Baffles 8/3/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr - Existing El
WS 100-yr - HB-13 Baffles
WS 20 CFS - Existing El
WS 15 CFS - HB-13 Baffles
Ground
ROB
RIVER-1 Reach-1
0 200 400 600 800 1000120
130
140
150
160
170
Steven's Creek Barriers Plan: Existing Hwy 85 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Existing Hwy River: RIVER-1 Reach: Reach-1 Profile: 100-yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 31131 100-yr 5750.00 134.00 150.02 149.10 154.15 0.041406 16.30 352.76 34.03 0.89
Reach-1 30831 100-yr 5750.00 133.10 151.00 151.76 0.001647 7.03 818.22 69.82 0.36
Reach-1 30731 100-yr 5750.00 132.80 148.43 144.01 151.32 0.003513 13.63 421.85 58.45 0.61
Reach-1 30646 Bridge
Reach-1 30561 100-yr 5750.00 132.00 143.22 143.22 148.82 0.010652 19.00 302.56 48.43 1.00
Reach-1 30371 100-yr 5750.00 128.80 140.55 141.58 0.003543 8.16 704.52 95.22 0.53
Reach-1 30271 100-yr 5750.00 127.80 137.03 137.03 140.47 0.013842 14.89 386.29 56.27 1.00
0 200 400 600 800 1000120
130
140
150
160
170
Steven's Creek Barriers Plan: Pro Baffles Hwy 85 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Pro Baffles Hwy8 River: RIVER-1 Reach: Reach-1 Profile: 100-yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 31131 100-yr 5750.00 134.00 154.73 156.57 0.014183 10.88 528.30 40.62 0.53
Reach-1 30831 100-yr 5750.00 133.10 155.18 155.58 0.000688 5.07 1135.19 81.68 0.24
Reach-1 30731 100-yr 5750.00 132.80 153.76 144.01 155.36 0.001321 10.16 565.68 69.50 0.39
Reach-1 30646 Bridge
Reach-1 30561 100-yr 5750.00 132.00 143.22 143.22 148.82 0.010650 19.00 302.57 48.43 1.00
Reach-1 30371 100-yr 5750.00 128.80 140.55 141.59 0.003538 8.16 704.96 95.27 0.53
Reach-1 30271 100-yr 5750.00 127.80 137.01 137.01 140.47 0.013957 14.93 385.18 56.22 1.01
0 200 400 600 800 1000120
130
140
150
160
170
Steven's Creek Barriers Plan: 1) Existing Hwy 8/8/2017 2) Pro Baffles Hwy8 8/8/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr - Existing Hwy
WS 100-yr - Pro Baffles Hwy8
WS 16 CFS - Existing Hwy
WS 16 CFS - Pro Baffles Hwy8
Ground
ROB
RIVER-1 Reach-1
0 200 400 600 800 1000 1200240
250
260
270
280
290
Steven's Creek Barriers Plan: Existing Hwy 280 5/9/2017
Main Channel Distance (ft)
Ele
vation (
ft)
Legend
WS 100-yr
Ground
ROB
RIVER-1 Reach-1
HEC-RAS Plan: Ex 280 River: RIVER-1 Reach: Reach-1 Profile: 100-yr
Reach River Sta Profile Q Total Min Ch El W.S. Elev Crit W.S. E.G. Elev E.G. Slope Vel Chnl Flow Area Top Width Froude # Chl
(cfs) (ft) (ft) (ft) (ft) (ft/ft) (ft/s) (sq ft) (ft)
Reach-1 46125 100-yr 5460.00 252.80 265.43 266.27 0.003431 7.55 886.48 301.03 0.51
Reach-1 45979 100-yr 5460.00 250.00 264.11 265.31 0.003094 9.16 719.03 119.52 0.51
Reach-1 45915 100-yr 5460.00 249.00 264.39 264.94 0.001112 6.05 1009.91 113.87 0.27
Reach-1 45885 100-yr 5460.00 248.80 263.10 258.20 264.56 0.004503 9.69 563.70 56.64 0.48
Reach-1 45715 Culvert
Reach-1 45546 100-yr 5460.00 247.80 257.66 257.30 261.27 0.016360 15.23 358.44 54.60 0.94
Reach-1 45545 100-yr 5460.00 246.80 260.12 253.55 260.99 0.002162 7.46 731.86 54.97 0.36
Reach-1 45445 100-yr 5460.00 246.80 259.81 260.72 0.003028 7.65 713.66 93.84 0.49
Reach-1 45065 100-yr 5460.00 246.50 254.96 254.96 257.87 0.021790 13.71 398.38 69.13 1.01
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
Appendix B
Hydraulic Modeling Results
Fish Ladder Hydraulic Calculations
MOFFETT FISH LADDER
Slotted Fish Ladder
Slot equation: Q= Cd(Ws*Y)* (2GH)^.5
Cd=orifice constant for slot at wall=0.58
Ws= slot width =1.5 ft slot height =2.5ft
Y= depth upstream of slot < Lfish >
H= change in WSE u/s pool to d/s pool-target =1 foot
G= 32.2 Ws > <
Q= Cw*Lfish*(H)^ 1.5 ladder section
Cw=weir constant= 3.1
Lfish = width of ladder weir above slot=3.5 ft
Headworks (ladder) Inlet : Q= Cw*Linlet*(H)^1.5 = Y HLinlet=width of the ladder opening = 5 ft =
Q= Cw*Ldrop(H)^1.5 ladder profileLdrop=width of the drop structure weir= 29.5ft
LOW FLOW (set H to 1 and vary Y until equations provides Q low)Q low= 14 to 16cfs
Q (cfs) 14.0 Q 0
Ws 1.5 L-fish 3.5
Y 2 h 0 Q 15.5 Q 0
G 32.2 L-inlet 5 L -drop 29.5
H 1 h 1 h 0
1 ft high sill weir
Total ladder Q= 14.0 cfs
Ladder % of total
14.0 cfs 100.0% OK
1
2.5 slot height
FULL LADDER FLOW (Y=4ft)
Q (cfs) 27.9 Q 19.9
Ws 1.5 L-fish 3.5
Y 4 h 1.5 Q 83.1 Q 258.7
G 32.2 L 5 L 29.5
H 1 h 3 h 2
1 ft high sill weir
Total Ladder Q 47.9 cfs
306.5 cfs 15.6% OK
3
2.5
Drop Structure Spill
Total Flow
ladder Weir bottom=
Fish Ladder Weir equation:
Drop Structure Spill
Total Stream Flow =
Upstream inlet Depth
Fish Ladder Weir
Ladder inlet capacity
Fish Ladder Slot
Upstream Depth
Ladder Weir Height
Fish Ladder Slot Fish Ladder Weir
Ladder inlet capacity
Hetch Hetchy Drop
Above Grade Slotted Fish Ladder Option
with 1 foot sill weir across top of drop
LOW FLOW
Percent of total flow in Ladder
14.0 cfs 100.0%
1
2.5
Q cfs 14.0 Q cfs 0.0 Q cfs 16.0 Q cfs 0
Ws 1.5 L 3.5 L 5 L 16
Y 2.0 h 0.0 h 1 h 0
G 32.2
h 1
Total Fish Q 14.0 cfs
Ladder Full Flow
Percent of total flow in Ladder
183.0 cfs 25.8%
3
2.5
Q cfs 27.9 Q cfs 19.3 Q cfs 83.1 Q cfs 135.8
Ws 1.5 L 3.5 L 5 L 16
Y 4.0 h 1.5 h 3 h 2
G 32.2
h 1
Total Fish Q 47.2 cfs
ladder inlet capacity Main Spill
Total Flow
Upstream Depth
Ladder Weir Height
Fish Ladder Slot flow Fish Ladder Weir flow
Main Spill
Total Flow
Upstream Depth
Ladder Weir Height
Fish Ladder Slot flow Fish Ladder Weir flow ladder inlet capacity
Friends of Stevens Creek Trail DOMENICHELLI & ASSOCIATES, INC.
APPENDIX C
COST ESTIMATES
Moffett Drop Structure Project
Alternative 1A Use Existing Ladder and Construction of New Concrete Low Flow Channel
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 75,000$ 75,000$
Saw Cut Concrete Channel 1600 LF 32.00$ 51,200$
Concrete Demolition and Removal 8,400 CF 12.00$ 100,800$
Construct Concrete Low flow Channel 700 CY 800$ 560,000$
Clean and repair Denil Ladder 1 LS 15,000$ 15,000$
Subtotal: 817,000$
Mobilization, Bonds, Insurance (8%) 8% LS 65,360$ 65,360.00$
882,360$
Construction Contingency 25% LS 220,590$ 220,590$
TOTAL CONSTRUCTION COSTS 1,103,000$
Subtotal Construction:
Domenichelli and Associates 11/20/2017
Moffett Drop Structure Project
Alternative 2A New Ladder and Construction of New Concrete Low Flow Channel
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 75,000$ 75,000$
Saw Cut Concrete Channel 1800 LF 32.00$ 57,600$
Concrete Demolition and Removal 9,000 CF 12.00$ 108,000$
Construct Concrete Low flow Channel 700 CY 800$ 560,000$
Construct New Fish Ladder 200 CY 1,300$ 260,000$
Subtotal: 1,075,600$
Mobilization, Bonds, Insurance (8%) 8% LS 86,048$ 86,048.00$
1,161,648$
Construction Contingency 25% LS 290,412$ 290,412$
TOTAL CONSTRUCTION COSTS 1,453,000$
Subtotal Construction:
Domenichelli and Associates 11/20/2017
Moffett Drop Structure Project
Alternative 1C - Use Existing Ladder and Construction of New Natural Channel Downstream
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 75,000$ 75,000$
Saw Cut Concrete Channel 1000 LF 32.00$ 32,000$
Concrete Demolition and Removal 13,200 CF 12.00$ 158,400$
Earthwork 3,200 CY 45.00$ 144,000$
Construct Retaining Wall 1,540 CY 1,200.00$ 1,848,000$
Construct Natural Low flow Channel (rock and plantings) 780 CY 250$ 195,000$
Clean and repair Denil Ladder 1 LS 15,000$ 15,000$
Subtotal: 2,482,400$
Mobilization, Bonds, Insurance (8%) 8% LS 198,592$ 198,592.00$
2,680,992$
Construction Contingency 25% LS 670,248$ 670,248$
TOTAL CONSTRUCTION COSTS 3,352,000$
Subtotal Construction:
Domenichelli and Associates 11/20/2017
Moffett Drop Structure Project
Alternative 2C - New Ladder and Construction of New Natural Channel Downstream
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 75,000$ 75,000$
Saw Cut Concrete Channel 1000 LF 32.00$ 32,000$
Concrete Demolition and Removal 13,200 CF 12.00$ 158,400$
Earthwork 3,200 CY 45.00$ 144,000$
Construct Retaining Wall 1,540 CY 1,200.00$ 1,848,000$
Construct Natural Low flow Channel (rock and plantings) 780 CY 250$ 195,000$
Construct New Fish Ladder 200 CY 1,300$ 260,000$
Subtotal: 2,727,400$
Mobilization, Bonds, Insurance (8%) 8% LS 218,192$ 218,192.00$
2,945,592$
Construction Contingency 25% LS 736,398$ 736,398$
TOTAL CONSTRUCTION COSTS 3,682,000$
Subtotal Construction:
Domenichelli and Associates 11/20/2017
Hetch Hetchy Drop Structure Project
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 40,000$ 40,000$
Saw Cut Concrete Channel 140 LF 36.00$ 5,040$
Concrete Demolition and Removal 670 CF 15.00$ 10,050$
Concrete Channel Replacement (upstream low flow) 14 CY 800.00$ 11,200$
Construct Retaining Wall 15 CY 1,500$ 22,500$
Construct New Fish Ladder 20 CY 1,800$ 36,000$ Subtotal: 139,790$
Mobilization, Bonds, Insurance (8%) 8% LS 11,183$ 11,183.20$
150,973$
Construction Contingency 25% LS 37,743$ 37,743$
TOTAL CONSTRUCTION COSTS 189,000$
Cut in Concrete Fish Ladder
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Hetch Hetchy Drop Structure Project
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 35,000$ 35,000$
Saw Cut Concrete 100 LF 36.00$ 3,600$
Concrete Demolition and Removal 380 CF 15.00$ 5,700$
Concrete Channel Replacement (upstream low flow) 14 CY 800.00$ 11,200$
Raise baffle & Construct New Fish Ladder 33 CY 1,800$ 59,400$ Subtotal: 129,900$
Mobilization, Bonds, Insurance (8%) 8% LS 10,392$ 10,392.00$
140,292$
Construction Contingency 25% LS 35,073$ 35,073$
TOTAL CONSTRUCTION COSTS 176,000$
Above Grade Concrete Fish Ladder
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Hetch Hetchy Drop Structure Project
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 35,000$ 35,000$
Saw Cut Concrete 100 LF 36.00$ 3,600$
Concrete Demolition and Removal 495 CF 15.00$ 7,425$
Concrete Channel Replacement (upstream low flow) 16 CY 800.00$ 12,800$
Construct New Fish Ladder 20 CY 1,800$ 36,000$ Subtotal: 109,825$
Mobilization, Bonds, Insurance (8%) 8% LS 8,786$ 8,786.00$
118,611$
Construction Contingency 25% LS 29,653$ 29,653$
TOTAL CONSTRUCTION COSTS 149,000$
Raise baffle and cut in 2 Step Concrete Fish Ladder
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Un-Numbered Crossing for Highway 85
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Stream Diversion and Dewatering 1 LS 45,000$ 45,000$
Saw Cut Concrete 400 LF 36.00$ 14,400$
Concrete Demolition and Removal 3,850 CF 15.00$ 57,750$
Construct Concrete Low Flow Channel 180 CY 800.00$ 144,000$
Upstream Weir (if needed for grade control) 5 CY 1,800$ 9,000$ Subtotal: 285,150$
Mobilization, Bonds, Insurance (8%) 8% LS 22,812$ 22,812.00$
307,962$
Construction Contingency 25% LS 76,991$ 76,991$
TOTAL CONSTRUCTION COSTS 385,000$
Cut in Low Flow Channel
Subtotal Construction:
Domenichelli and Associates 8/23/2017
El Camino Real Culvert
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Access, Stream Diversion and Dewatering 1 LS 55,000$ 55,000$
Channel Excavation (assume 4 ft to scour resistant material) 200 CY 75.00$ 15,000$
Foundation and achors to Culvert 40 CY 1,200.00$ 48,000$
Baffle Construction 20 CY 1,500.00$ 30,000$
Subtotal: 163,000$
Mobilization, Bonds, Insurance (8%) 8% LS 13,040$ 13,040.00$
176,040$
Construction Contingency 25% LS 44,010$ 44,010$
TOTAL CONSTRUCTION COSTS 221,000$
Concrete Baffles
Subtotal Construction:
Domenichelli and Associates 8/23/2017
El Camino Real Culvert
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Access, Stream Diversion and Dewatering 1 LS 35,000$ 35,000$
Channel Excavation 75 CY 75.00$ 5,625$
Rock Baffle Construction 80 CY 500.00$ 40,000$
Subtotal: 95,625$
Mobilization, Bonds, Insurance (8%) 8% LS 7,650$ 7,650.00$
103,275$
Construction Contingency 25% LS 25,819$ 25,819$
TOTAL CONSTRUCTION COSTS 130,000$
Rock Baffles
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Highway 85 Near Village Court
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Access, Stream Diversion and Dewatering 1 LS 30,000$ 30,000$
Channel Excavation 60 CY 75.00$ 4,500$
Rock Baffle Construction 65 CY 500.00$ 32,500$
Subtotal: 82,000$
Mobilization, Bonds, Insurance (8%) 8% LS 6,560$ 6,560.00$
88,560$
Construction Contingency 25% LS 22,140$ 22,140$
TOTAL CONSTRUCTION COSTS 111,000$
Rock Baffles
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Highway 280 Culvert
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 15,000$ 15,000$
Temporary Access, Stream Diversion and Dewatering 1 LS 50,000$ 50,000$
Channel Excavation 70 CY 75.00$ 5,250$
Rock Baffle Construction 75 CY 500.00$ 37,500$
Subtotal: 107,750$
Mobilization, Bonds, Insurance (8%) 8% LS 8,620$ 8,620.00$
116,370$
Construction Contingency 25% LS 29,093$ 29,093$
TOTAL CONSTRUCTION COSTS 146,000$
Rock Baffles
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Deep Cliff Golf Course
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 10,000$ 10,000$
Temporary Access, Stream Diversion and Dewatering 1 LS 15,000$ 15,000$
Demo Crossing & Clearing 1 LS 18,000$ 18,000$
Channel Excavation 10 CY 150.00$ 1,500$
Rock Weir Construction (hand placed) 18 CY 1,000.00$ 18,000$
Subtotal: 62,500$
Mobilization, Bonds, Insurance (12%) smaller job higher percentage 12% LS 7,500$ 7,500.00$
70,000$
Construction Contingency 25% LS 17,500$ 17,500$
TOTAL CONSTRUCTION COSTS 88,000$
Rock Weir and Pool Ladder
Subtotal Construction:
Domenichelli and Associates 8/23/2017
Gauge Station Weir
Engineer's Opinion of Probable Costs
Element Description
Estimated
Quantity Units Unit Price Estimated Amount
Storm Water Pollution Prevention Plan 1 LS 10,000$ 10,000$
Temporary Access, Stream Diversion and Dewatering 1 LS 18,000$ 18,000$
Channel Excavation 15 CY 150.00$ 2,250$
Rock Weir Construction (hand placed) 30 CY 1,000.00$ 30,000$
Subtotal: 60,250$
Mobilization, Bonds, Insurance (12%) smaller job higher percentage 12% LS 7,230$ 7,230.00$
67,480$
Construction Contingency 25% LS 16,870$ 16,870$
TOTAL CONSTRUCTION COSTS 85,000$
Rock Weir and Pool Ladder
Subtotal Construction:
Domenichelli and Associates 8/23/2017