state and local road project updates: part 3
DESCRIPTION
Mike Holder from the North Carolina Department of Transportation (NCDOT) Division 12 reports at the Charlotte Chamber 2011 Transportation Summit.TRANSCRIPT
Mike Holder Division 12
April 8th, 2011
2011 Charlotte Chamber
Transportation Summit
Highways:• Total identified needs (2015 – 2020) = $45 billion• About $9 billion in anticipated revenues for this timeframe
Non-highways:• Total identified needs (2015 – 2020) = $9 billion• About $1.5 billion in available revenue for this timeframe
Summary:• $54 billion in total identified transportation needs (2015 – 2020) • Estimated $10.5 billion in available revenue for this timeframe
Funding Snapshot
Strategic Prioritization Process
• Data-driven system created that evaluates all proposed TIP projects based on a list of quantitative data;
• Traffic counts• Congestion/capacity• Local support• Regional support• Safety
• Projects are scored individually and then ranked.
• Public meetings, aggressive community outreach
• Actively engaged local governments, MPO/RPOs and stakeholders
STIP Schedule
Sept. – Oct.2010 MPO/RPO review Draft STIP
Department requests feedback on initial process
March 2011 Public Meetings on Draft STIP
July 2011 BOT adopts Final STIP
Sept. 2011 NCDOT submits revised STIP to FHWA
December 2011 Draft NCSTP released
December 2011 Investment Strategy Process
May 2012 Draft Policy to Projects document released
State Transportation Improvement Program
Division 12:
STIP 12-18 $ 479 Million 6.27% Equity Share
Division 12 Ten Year Work Plan $864 Million
Maintain 13712 Lane Miles of Roadway
5,827,646 Square Feet of Bridge Deck
R-2206 – NC 16 Bypass
Lincoln and Catawba Counties
• Roadway is open to St James Church Road in Lincoln County
• Project scheduled for completion to NC 150 in Catawba County in Summer of 2011
• Turnkey $161 Million
R-3833 – Brawley School Road
Iredell County
• Widen to multi-lanes with new interchange at I-77
• Section from Chuckwood Road at “The Point” to I-77 under construction with completion fall 2012
• $124 million
I-3819 – Interchange Modifications
Iredell County
• Geometric improvements, widening and safety modifications to I-40/I-77 interchange and to US 21/I-40 interchange in Statesville
• Right of Way in progress
• Construction 2012 – 2015
• $100 million
I-2707 – US 74 Bypass
Cleveland County
• Right of Way purchase, Environmental Mitigation and Construction from 2011 to 2015
• $326 million
I-5000 – I-85/US 321 Interchange
Gaston County
• Geometric Safety Improvements to the existing interchange
• Right of Way in 2014
• Construction 2015
• $36 million
I-4750 – I-77 Widening
Iredell and Mecklenburg Counties
• Widen and reconstruct I-77 from NC 73 to I-40
• Right of Way 2016
• Construction 2019
• $526 million
R-3100 – NC 16 Widening
Catawba County
• Widening of Existing NC 16 from Tower Road to Claremont Road
• $52 million
R-2307 – NC 150 Widening
Iredell, Catawba, and Lincoln Counties
• Widening NC 150 from I-77 to Harvel Road in Catawba County
• Right of Way in 2017
• Construction in 2020
• $97 million
Questions?Questions?