sri lanka’s power generation past, present and future › sites › cpf_new › files › 4...
TRANSCRIPT
CEYLON ELECTRICITY BOARD
Transmission DivisionCeylon Electricity Board
Sri Lanka
May 2016
Sri Lanka’s Power Generation
Past, Present and Future
Eng. Noel Priyantha- Chief Engineer (Renewable Energy)Eng. Buddhika Samarasekara- Chief Engineer (Generation Planning)
The average per capita electricity consumption in 2015 was 562 kWh/person.
Per Capita Electricity Consumption (2004-2015)
Installed Capacity and Peak Demand
2
Less significant relationship betweenGDP growth and Electricity demandgrowth in recent years
GDP Growth % & Elec. Demand Growth %
Country 2009 2010 2011 2012
Bangladesh 221 247 259 278
India 605 641 684 753
Japan 7838 8378 7848 5190
Malaysia 3934 4136 4246 3405
Pakistan 450 458 449 649
Singapore 7896 8438 8404 8595
Vietnam 917 1035 1073 907
Comparison with Regional Countries(kWh/person)
0
400
800
1200
1600
2000
2400
2800
3200
3600
4000
4400
1994
1995
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
Inst.
Capacity &
Peak D
em
and (
MW
)
Year
Installed capacity
Peak Demand
250
275
300
325
350
375
400
425
450
475
500
525
550
575
600
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
kWh
/pe
rso
n
Year
SRI LANKAN STATISTICS –POWER SECTOR
-10.0
-5.0
0.0
5.0
10.0
15.0
20.0
-2.0
0.0
2.0
4.0
6.0
8.0
10.0
199
4
199
5
199
6
199
7
199
8
199
9
200
0
200
1
200
2
200
3
200
4
200
5
200
6
200
7
200
8
200
9
201
0
201
1
201
2
201
3
201
4
201
5
Ele
c D
em
an
d G
row
th (
%)
GD
P G
row
th R
ate
(%
)
Year
GDP
Electricity
0
500
1000
1500
2000
2500
Load
(M
W)
Time
NCRE
CEB Hydro
IPP Thermal
CEB Thermal
TYPICAL LOAD CURVE OF SRI LANKA
4
CEB Hydro38%
CEB Thermal-
Coal34%
CEB Thermal-
Oil8%
IPP Thermal
9%
NCRE 11%
Energy Share in GWh- 2015
CEB Hydro36%
CEB Thermal -
Coal23%
CEB Thermal -
Oil14%
IPP Thermal
16%
NCRE 11%
Capacity Share in MW - 2015
1.48
6.64
16.83
27.55 31.62
-
5.00
10.00
15.00
20.00
25.00
30.00
35.00
CEB - Hydro CEB - Coal Renewable Energy CEB - Thermal IPP - Thermal
LKR
/kW
h
Generation Technology
Average Cost per Unit for Generation Technologies (For Year 2015)
PRESENT CAPACITY MIX AS AT DECEMBER 2015
Historical NCRE Contribution
5
Year
Energy Generation (GWh) Capacity (MW)
NCRE System
Total
NCRE Total System Installed
Capacity
2003 120 7612 39 2483
2004 206 8043 73 2499
2005 280 8769 88 2411
2006 346 9389 112 2434
2007 344 9814 119 2444
2008 433 9901 161 2645
2009 546 9882 181 2684
2010 724 10714 212 2818
2011 722 11528 227 3141
2012 730 11801 320 3312
2013 1178 11962 367 3355
2014 1215 12418 442 3932
6
Renewable Energy Contribution
0%
10%
20%
30%
40%
50%
60%
70%
0
1000
2000
3000
4000
5000
6000
7000
8000
2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015
Per
ece
nta
ge %
Ener
gy (
GW
h)
Year
NCRE Large Hydro Percentage of Renewable Energy from Total Energy
RENEWABLE ENERGY- PRESENT STATUS
0
1000
2000
3000
4000
5000
6000
7000
8000
0
5000
10000
15000
20000
25000
30000
35000
40000
45000
2000 2005 2010 2015 2020 2025 2030 2035
Pea
k D
em
and
(M
W)
Ener
gy D
eman
d (
GW
h)
Year
Energy
Peak
Actual Forecast
ACTUAL AND FORECAST ENERGY/PEAK DEMAND (AS PER DRAFT LTGEP 2015-2034)
FUTURE GENERATION OPTIONS - NON CONVENTIONAL
8
0.0%
5.0%
10.0%
15.0%
20.0%
25.0%
30.0%
0
500
1000
1500
2000
2500
3000
3500
4000
4500
20
15
20
16
20
17
20
18
20
19
20
20
20
21
20
22
20
23
20
24
20
25
20
26
20
27
20
28
20
29
20
30
20
31
20
32
20
33
20
34
20
35
20
36
20
37
20
38
20
39
20
40
20
41
Cap
acit
y (M
W)
Year
NCRE Additions
Solar (MW) Biomass (MW)
Wind (MW) Mini Hydro (MW)
PROJECTION ON COMPARSION OF CO2 SAVINGS
9
PRESENT STATUS OF NCRE TARIFF
10
PRINCIPLES OF TARIFF FIXING• Renewable energy, which is a natural resource, belongs to the
State.• Renewable energy should produce electricity in the long term
at prices below the cost of thermal power plants, using oil orcoal, or even gas.
• Developers are provided with a high tariff to cover theirexpenses and reasonable profits for an adequately long period(in this case fifteen years.) Cost based , technology specific andthree tiered or flat tariff
• Tier 1: Years 1- 8 ;Tier 2: Years 9 – 15; Tier 3: Years 16 – 20• (SPPA period – 20 years)• This tariff will be limited to small power producers ( Capacity
up to 10 MW)• This tariff has been designed to eliminate the problems of
negative cash flows experienced by many small powerproducers during the period of loan repayment.
11
NCRE TechnologyNo of
ProjectsCapacity (MW)
1 Mini Hydro Power 95 177
2Biomass - Agricultural & Industrial Waste
2 4.5
3 Biomass - Dendro Power 13 51
4 Biomass – Municipal Waste 1 10
5 Solar Power 4 40
6 Solar Thermal 3 30
7 Wind Power 1 1
Total 119 314
SPPA Signed NCRE Projects – Present Status
PROJECTS IN THE PIPELINE - NCRE
WHY CLIMATE FINANCE
• To reduce the Unit Generation Costs
12
7.027.95 9.63
12.97 13.73
16.61 17.8818.9
23.37
29.52
33.08
0
5
10
15
20
25
30
35
Trinco Coal250MW, 70%
New Coal300MW,70%
Wind 25MW,30%
LNG 300MW,70%
Dendro 5MW,70%
Solar 10MW,17%
CCY 300MW,70%
CCY 150MW,70%
Solar withbattery
10MW, 17%
GT 105MW,20%
GT 35MW,20%
Un
it g
en
era
tio
n c
ost
(U
Scts
/kW
h)
Power plant and typical plant factor (%)
Unit Generation Costs for Different Power Plants at Typical Plant Factors
• Sri Lanka seeks Climate Finance to reduce the present high cost of Renewable Energy – CPF support in this regard is highly welcome.
• Possibility of reducing the present feed in tariff payable to NCRE in future, sharing the carbon credits among stake holders including CEB, if appropriate.
• Overall Sector Development through use of carbon credits
Present Status : INDC
13
• TO ACHIVE EMISSION REDUCTION AT LEAST IDENTIFIED FROM INDCs
CHALLENGES TO OVERCOME & SOME SUGGESTONS TO EXPLORE
• If carbon markets revive, opportunity to get competitive prices for carboncredits may be lost by entering into long term agreements only with theWorld Bank Group.• Inclusion of some provisions in to ERPA to avoid such possibility
• Whether private sector will fully engage in to the CPF program and agree tosell credits to CEB as they may get better credits from competitive market.• Directive from the government, a long term proposition• Waive off credit rights as part of the SPPA that offers feed-in-tariffs
• According to present practice, all carbon credit programs should be directedby the Climate Change Secretariat (CCS).• Engaging CCS from the beginning and seeking their approvals as needed
• Understanding the impact on Intended Nationally Determined Contributions(INDCs), submitted by the Ministry of Mahaweli Development andEnvironment, Once CEB signs the SPA and ERPA, relevant carbon reductionwill be removed from the country and country cannot claim for any reductionof emissions.• Inclusion of ‘unconditional’ target in the baseline and credits from
‘conditional target’
14
THANK YOU
15
Additional slides
16
SRI LANKA Total Area : 65,610 km2
Land Area : 62,705 km2
Population : 20.97 million
Urban : 18.3% Rural : 81.7%
Population Density : 334 per/ sqkm
Labour Force : 8.973 million
Unemployment rate : 4.6%
Literacy rate : 93.3%
Life expectancy: 72 yrs (M), 78 yrs (F)
Monetary Unit : Sri Lankan Rupee
(1 USD = 146.19 LKR at 01.01.2016)
INTRODUCTION
Gross Domestic Product : 11,183 billion LKR
(Market Prices)
GDP per capita : 3,924 US$ (Market Prices)
GDP structure 2015
Agriculture – 7.85% Industry – 26.20%
Services – 56.61% Taxes less subsidies on products – 9.34%
FUTURE GENERATION OPTIONS - NON CONVENTIONALProjected NCRE capacity
18Based on Draft LTGEP 2017-2036
Year
Mini
Hydro
(MW)
Wind
(MW)
Biomass
(MW)
Solar
(MW)
Solar Net
Metering
(MW)
Total NCRE
Capacity
(MW)
Annual Total
NCRE
Generation
(GWh)
Share of NCRE
from Total
Generation %
2017 329 144 34 21 20 548 1782 12.1%
2018 344 244 39 121 26 774 2337 15.0%
2019 359 294 44 221 32 950 2720 16.4%
2020 374 464 49 371 39 1297 3530 20.3%
2021 384 539 54 371 44 1392 3840 21.1%
2022 394 609 59 471 50 1583 4277 22.4%
2023 404 669 64 571 55 1763 4663 23.2%
2024 414 714 69 571 60 1828 4875 23.1%
2025 424 799 74 671 64 2032 5339 24.1%
2026 434 799 79 771 69 2152 5553 23.9%
2027 444 824 84 771 74 2197 5702 23.4%
2028 454 869 89 871 79 2362 6051 23.6%
2029 464 894 94 871 83 2406 6200 23.1%
2030 474 964 99 971 88 2597 6619 23.5%
2031 484 999 104 971 93 2651 6785 23.0%
2032 494 1044 104 1071 98 2811 7099 23.0%
2033 504 1114 109 1071 102 2900 7378 22.9%
2034 514 1184 109 1171 107 3086 7763 23.0%
2035 524 1254 114 1271 112 3275 8186 23.2%
2036 534 1349 114 1271 117 3385 8506 23.1%
ENVIRONMENTAL ASPECTS
Comparison of CO2 Emissions from fuel combustion
19
Countrykg CO2/2005 US$ of GDP
kg CO2/2005 US$ of GDP Adjusted to
PPP
Tons of CO2
per CapitaGDP per capita (current US$)
Sri Lanka 0.33 0.08 0.67 3,280Pakistan 0.94 0.19 0.74 1,275
India 1.25 0.32 1.49 1,498Indonesia 0.94 0.21 1.70 3,475Thailand 1.07 0.30 3.69 5,779
China 1.85 0.64 6.60 6,807France 0.13 0.15 4.79 42,560Japan 0.26 0.30 9.70 38,634
Germany 0.24 0.26 9.25 46,251USA 0.35 0.35 16.18 53,042
World 0.57 0.37 4.52
IEA CO2 Emissions from Fuel Combustion (2014 Edition)-2013 data, World Bank website 2013 data
20
Present NCRE Projects Approval Process
Main Parameters
Debt equity ratio - 60:40
Loan repayment - 8 years
Construction period - 2 years
Return on equity (ROE) - 22 %
Plant factor and O & M percentages
Technology Plant Factor
O & M Percentage (Year 1-15)
O & M Percentage
Year (16 -20)
Mini Hydro 42 % 3 % 3 %
Mini Hydro – Local 42 % 3 % 3 %
Wind 32 % 1.5 % 1.5 %
Wind – Local 32 % 1.5 % 1.5 %
Biomass ( dendro) 80 % 4 % 5 %
Biomass (agricultural & industrial waste)
80 % 4 % 5 %
Waste Heat Recovery
67 % 1.33 % 1.33 %