SRF Cryomodule Assembly Facility Plans
Tug Arkan
AAC, May 10-12, 2005
2
Outline
Introduction Cryomodule Assembly Workflow Infrastructure Plans Procurement Plans Summary
3
Introduction
A plan is being developed to assemble 1.3 GHz Elliptical cryomodules at Fermilab.
Current plan involves two1.3 GHz (β=1) cryomodules to be assembled in FY06 and FY07.
High power RF and Beam testing of these cryomodules will be done on the Fermilab site in the proposed Meson Lab test facility (HPTF)
MP9 building will be used to setup the infrastructure to assemble these cryomodules.
4
Cryomodule Assembly Workflow Plans in FY06 & FY07
Assumptions for the assembly of two 1.3 GHz Elliptical cryomodules in FY06 & FY07: (R&D production rate)
SRF bare cavities are fabricated in industry. (Form/machine parts, electron beam welding)
Cavities are processed (tuned for field flatness, baked, chemical etched {BCP and/or electro-polished}, high pressure water rinsed and vertical dewar tested).
Cavities are outfitted with helium vessel and input power coupler and further dressed (tuner, magnetic shielding) for the horizontal dewar test.
It is assumed that these steps (processing & dressing) are carried out elsewhere (collaborating laboratories, universities).
After passing horizontal dewar test, the cavity with helium vessel and cold part of the input coupler is shipped sealed to the MP9 facility.
The sealed cavities with cold input coupler are received at the MP9 facility for incorporation into cryomodules. 8 dressed cavities are assembled into a string at MP9 facility clean rooms. The cavity string is then assembled into cold mass. Cold mass is then inserted into vacuum vessel and the cryomodule assembly is complete.
5
Receive dressed Cavities
Receive peripheral (vacuum vessel, cryogenic pipes, super-insulation
etc.) Cryomodule Parts
Assemble dressed Cavities to form a
String in the Cavity String
Assembly Area (Clean Room)
Work Flow at MP9 FacilityWork Flow at MP9 Facility
Install String Assembly to Cold Mass in the Cold Mass
Assembly Area
6
Cryomodule Testing at HPTF
Ship completed cryomodules to
HPTF
Install the String assembly with the cold mass into the Vacuum vessel in the Vacuum Vessel
Assembly area
Cavity Repair
fail
Cryomodule Repair (assumes one or more cavities must be replaced)
-Disassemble the module
-Disassemble the string in the Clean Room
-Install a new dressed cavity to the string
pass
Cyomodule production is successful
Send the Cryomodule
back for repair
Work Flow at MP9 FacilityWork Flow at MP9 Facility
7
Infrastructure Plans at MP91.3 GHz Elliptical Cryomodules Assembly Infrastructure at MP9 in FY06 & FY07
8
Cryomodule Assembly Workflow Model for Small Scale Mass Production Rate Assumptions for a production rate of 1~2 cryomodules per month: (small
scale mass production rate) SRF bare cavities are fabricated in industry. (Form/machine parts, electron beam welding).
The bare cavities arrive to FNAL. Cavities are processed (tuned for field flatness, baked, chemical etched {BCP and/or
electro-polished}, high pressure water rinsed and vertical dewar tested) at Fermilab. Cavities are outfitted with helium vessel and input power coupler and further dressed (tuner,
magnetic shielding) for the horizontal dewar test at Fermilab. After passing the horizontal dewar test, the cavity with helium vessel and cold part of the
input coupler is shipped sealed to the MP9 facility. The sealed cavities with cold input coupler are received at the MP9 facility for incorporation
into strings. 8 dressed cavities are assembled into a string at MP9 facility clean rooms. The cavity string is then transported to another assembly facility to be assembled into cold
mass. Cold mass is then inserted into vacuum vessel and the cryomodule assembly will be completed. (1~2 cryomodules per month in two ~ three cold mass and vacuum vessel assembly lines.
9
Receive bare Cavities
Receive peripheral parts to dress cavities & assemble a string
Chemical Etch Cavity (BCP and/or Electropolish)
Dress cavity-Weld Helium vessel
-Install input power coupler-Assemble Tuner,
-Assemble magnetic shielding
Assemble Dressed Cavities to form a String in the Cavity
String Assembly Area (Clean Room)
Horizontal Dewar Test Dressed
CavityPass
Pass
FailHigh Pressure Water Rinse (HPWR) Cavity
Vertical Dewar Test Processed Cavity
Fail
Transport String Assembly to
another Facility
10
Receive String Assembly
Receive peripheral (vacuum vessel, cryogenic pipes, super-
insulation etc.) Cryomodule Parts
Install String Assembly to Cold Mass in the Cold Mass
Assembly Area
Ship completed cryomodules to HPTF
Install the String assembly with the cold mass to the Vacuum vessel in the Vacuum Vessel
Assembly area
Cryomodule Testing at HPTF
Cryomodule Repair (assumes one or more cavities must be replaced)
-Disassemble the module
-Disassemble the string in the Clean Room
-Install a new dressed cavity to the string
Fail
Send the Cryomodule back for repair
Pass
Cyomodule production is successful
Cavity Repair
11
MP9 Building & MP9 Building & Meson AreaMeson Area
12
MP9 Building MP9 Building inside viewsinside views
Beam Separator work at MP9 will be completed by the end of November 2006
13
Procurement Plans
FY05: Elliptical cavity string assembly clean
rooms 1.3 GHz elliptical cryomodules cold mass
and vacuum vessel assembly fixtures FY06:
Elliptical cavities string assembly fixtures Clean room equipment Portable clean rooms Miscellaneous fixtures
14
Summary
In FY06 and FY07, MP9 building will be used for the infrastructure to assemble two 1.3 GHz (β = 1) elliptical cryomodules.
3~4 FTE’s are needed to assemble the strings in the cavity string assembly clean rooms.
6~8 FTE’s are needed for string to cold mass and vacuum vessel assembly outside of the clean rooms.
MP9 has no cryogenics capabilities, testing of cavities and completed cryomodules needs to be done at proposed HPTF areas.
To assemble cryomodules with a small scale mass production rate (1~2 cryomodules per month), MP9 facility could be used only for the cavity string assembly infrastructure and another facility could be setup for the string to cold mass and vacuum vessel assembly infrastructure (non clean room, multiple assembly lines).
This production rate will require ~50 FTE to work in multiple production assembly lines.